ID Task Task Name Duration Start Finish Predecessors 30 Sep '18 07 Oct '18 14 Oct '18 21 Oct '18

h Predecessors 30 Sep '18 07 Oct '18 14 Oct '18 21 Oct '18 28 Oct '18 04 Nov '18 11 Nov '18 18 Nov '18 25 Nov '18 02 Dec '18 09 Dec '18 16 Dec '18 23 Dec '18 30 Dec '18 06 Jan '19 13 Jan '19 20 Jan '19 27 Jan '19 03 Feb '19 10 Feb '19 17 Feb '19 24 Feb '19 03 Mar '19 10 Mar '19 17 Mar '19 24 Mar '19 31 Mar '19 07 Apr '19 14 Apr '19 21 Apr '19 28 Apr '19 05 May '19 12 May '19 19 May '19 26 May '19 02 Jun '19 09 Jun '19
Mode MTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SM
1 PRELIMINARIES: 6 days Mon 22/10/18 Sat 27/10/18

2 START 0 days Mon 22/10/18 Mon 22/10/18 22/10

3 Mobilization (Manpower/Equipment) 1 day Mon 22/10/18 Mon 22/10/18 2

4 Health and Safety (PPE & medicines) 1 day Tue 23/10/18 Tue 23/10/18 3

5 Temporary Facilities (Bunkhouse/Field Office/Storage) 5 days Tue 23/10/18 Sat 27/10/18 3

6 SITE WORKS: 119 days Sat 03/11/18 Wed 27/03/19

7 Lay-out and staking 1 day Sat 03/11/18 Sat 03/11/18 5

8 Excavation for foundation 6 days Mon 05/11/18 Sat 10/11/18 7

9 Backfilling 7 days Mon 11/03/19 Mon 18/03/19 8,53

10 Spreadng/levelling/compaction 7 days Tue 19/03/19 Tue 26/03/19 9

11 Soil treatment/Termite Proofing 1 day Wed 27/03/19 Wed 27/03/19 10

12 CONCRETE & MASONRY WORKS: 140 days Mon 05/11/18 Mon 22/04/19

13 FORMWORKS: Columns 7 days Mon 05/11/18 Mon 12/11/18 7

14 REBARWORKS: Cutting>Footings 15 days Mon 05/11/18 Wed 21/11/18 7

15 REBARWORKS: Installation of Footing 8 days Thu 22/11/18 Sat 01/12/18 14

16 REBARWORKS: Cutting>Columns>Ground floor 15 days Mon 05/11/18 Wed 21/11/18 7

17 REBARWORKS: Installation>Columns>Ground Floor 15 days Thu 22/11/18 Mon 10/12/18 16

18 CONCRETEWORKS: Footings 6 days Tue 11/12/18 Mon 17/12/18 13,17,15

19 FORMWORKS: Installation of Column Forms 4 days Wed 19/12/18 Sat 22/12/18

20 CONCRETEWORKS: Columns>Ground Floor 18 days Wed 26/12/18 Thu 17/01/19 19

21 FORMWORKS/SCAFFOLDING: 2nd Floor 21 days Tue 18/12/18 Tue 15/01/19 18

22 REBARWORKS: Installation>Floor Beams and Slabs 12 days Wed 16/01/19 Tue 29/01/19 21

23 REBARWORKS: Cutting>Columns> 2nd floor 15 days Mon 26/11/18 Thu 13/12/18 16

24 CONCRETEWORKS: 2nd Floor Beams and Slabs 2 days Wed 30/01/19 Thu 31/01/19 22

25 REBARWORKS: Installation>Columns> 2nd floor 15 days Fri 01/02/19 Mon 18/02/19 24,23

26 FORMWORKS/SCAFFOLDING: Columns> 2nd Floor 15 days Fri 15/02/19 Mon 04/03/19 24

27 CONCRETEWORKS: 2nd Floor Columns 15 days Wed 20/02/19 Fri 08/03/19 24

28 SCAFFOLDING/FORMWORKS: Roof Beams 12 days Sat 09/03/19 Fri 22/03/19 27

29 REBARWORKS: Roof Beams 7 days Sat 09/03/19 Sat 16/03/19 27

30 CONCRETEWORKS: Roof Beams 8 days Mon 18/03/19 Tue 26/03/19 29

31 REBARWORKS: Retaining Walls / Stairs 15 days Mon 18/03/19 Wed 03/04/19 29

32 FORMWORKS/SCAFOLDING: Retaining Walls / Stair 15 days Sat 23/03/19 Tue 09/04/19 28

33 CONCRETEWORKS: Retaining Wall / Stair 8 days Fri 12/04/19 Sat 20/04/19 30

34 MASONRY WORKS (Walls) 30 days Tue 19/03/19 Mon 22/04/19 9,48

35 CONCRETEWORKS: Ground Floor Slab 12 days Thu 28/03/19 Wed 10/04/19 11

36 STRUCTURAL STEEL WORKS: 26 days Wed 27/03/19 Thu 25/04/19

37 Roofing 9 days Wed 10/04/19 Fri 19/04/19 40

38 Insulation 9 days Wed 10/04/19 Fri 19/04/19 40

39 Flashing/Gutter 5 days Sat 20/04/19 Thu 25/04/19 37,38

40 Roof Framing works 12 days Wed 27/03/19 Tue 09/04/19 30

41 ARCHITECTURAL WORKS: 14 days Tue 23/04/19 Wed 08/05/19

42 Ceiling works with metal furring 14 days Tue 23/04/19 Wed 08/05/19 34

43 Doors 6 days Tue 23/04/19 Mon 29/04/19 34

44 Windows 10 days Tue 23/04/19 Fri 03/05/19 34

45 Tile works 12 days Tue 23/04/19 Mon 06/05/19 34

46 Pre-cast Accesnt Columns and Mouldings 6 days Tue 23/04/19 Mon 29/04/19 34

47 ELECTRICAL WORKS/ELECTRONICS WORKS: 6 days Wed 16/01/19 Tue 22/01/19

48 ELECTRICAL WORKS/ELECTRONICS WORKS 6 days Wed 16/01/19 Tue 22/01/19 21

49 PLUMBING WORKS: 75 days Wed 26/12/18 Mon 25/03/19

50 Sanitary line and water lines 6 days Wed 26/12/18 Thu 03/01/19

51 Water closets and lavatory 2 days Tue 19/03/19 Wed 20/03/19 9,50

52 Urinals 2 days Tue 19/03/19 Wed 20/03/19 9,50

53 Storm drainage Pipe, fittings and downspouts 6 days Wed 26/12/18 Thu 03/01/19

54 Catch Basin 6 days Tue 19/03/19 Mon 25/03/19 9

55 Septic Vault 12 days Fri 08/02/19 Thu 21/02/19 53FS+30 days

56 PAINTING/ Waterproofing: 18 days Thu 09/05/19 Wed 29/05/19

57 PAINTING/ Waterproofing 18 days Thu 09/05/19 Wed 29/05/19 35,42,43,44,46

58 DEMOBILIZATION: 6 days Thu 30/05/19 Wed 05/06/19

59 CLEARING 5 days Thu 30/05/19 Tue 04/06/19 57,55,54,39,45

60 DEMOBILIZATION (Manpower/equipment/clearing) 1 day Wed 05/06/19 Wed 05/06/19 59

61 FINISH 0 days Wed 05/06/19 Wed 05/06/19 60 05/06

Project: WORK SCHEDULE Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Critical Split Manual Progress
Date: Fri 09/11/18 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Critical Progress