The length of an event connotes the length of an activity - T
2. Work packages in a WBS should not exceed 10 days - T 3. The manager alone can develop a WBS - F 4. All elements in a WBS should be at the same level - F 5. Critical path denotes activities with zero slack - T 6. Gantt chart displays an interrelationship among activities - F 7. WBS is synonymous to schedule - F 8. Network diagram is drawn from left to right - T 9. Changes in WBS does not affect the scope of a project - F 10. Gantt chart considers cost and resources – F
11. Consist of manufacturers' manual and instructions -
operations and instruction 12. Also termed as Top - down planning - WBS 13. The smallest unit of WBS - work packages 14. ES plus the duration of an activity is - LF 15. A simple block diagram that can be read by a layman - Gantt Chart 16. Unidentified branch in the WBS is termed as - scope creep 17. An accident that occurred in a construction site could lead to the following except: - none of the above 18. As stated in the contract agreement the withholding of final payment is termed as - retainage 19. A time consuming effort requires to perform a part of a work - activity 20. Deliverables divided into multi level system that can be in graphical or outline form - WBS 21. A quantifiable goods or services that will be provided upon the completion of a construction project - deliverables 22. Process of requirement audit and measurements to ensure quality appropriate standards - quality assurance 23. A series of activities that requires crucial monitoring - critical path 24. WBS helps to control and manage the following except: - people,materials and process 25. WBS and OBS can distinguish the following except: communication plan 26. The provision of too much detail in the development of WBS can lead to except: overlapping of works 27. Responsible to receive, log, monitor and control changes in a construction project - PM 28. Compensation for the breach of contract - penalty 29. A record that reflects all the alterations done in a construction project - Project log 30. The following are example of deliverables except: - none of the above 31. Deliverables indicated in the WBS can be altered through: - risk identification 32. A must in project management to achieve success - project monitoring 33. A parallel task means - can be accomplished simultaneously 34. Address how project be executed, planned, organized and control - Master plan 35. Project planning technique includes the following except - intellectual capital 36. Planning in construction project provides the following except: encourages creativity and innovation 37. Purpose of Bar chart except: - relationship of activities 38. Plan with the inclusion of time scale - Scheduling 39. Primary difference of bar chart and CPM - interrelationship of activities 40. Activities in arrow diagram is manifested by: - letters 41. Duration alloted for activities can be derived through except: - WILD GUESS 42. An activity that manifest precedence relationship - event 43. A technique in scheduling ideal for construction - CPM 44. Certifies punchlist has been complied - architect 45. A proof that the building complied with all pertinent codes and laws - building permit 46. Testing should be in the presence of the following except - none of the above 47. Project monitoring is part of - project management 48. Done during the close out process to facilitate startup of all systems - testing and inspection 49. does not require time - nodes 50. Project monitoring is base on the following except - management 51. The client decided to extend portion of the lanai from 15sm to 25 sm, in these case the contractor can - all of the above 52. Process of systematic alterations as anticipated in construction project - addendum 53. List of items that needs to be refine as specified - punchlist 54. a completion that is not the final but with significant amount - substantial completion 55. requires time and represented by arrow or node - activity 56. manifest a consecutive relationship among activities using nodes and arrows - precedence 57. A network diagram that represents nodes as activity - AON 58. Calculation done to establish ES and EF – forward pass 59. between 2 EF which would you select as ES of the succeeding activity - large value