1. INTRODUCTION
The purpose of this method of statement is to describe the procedure step by step to
implement the standard and correct practices for the installation of Cable Tray/Conduit for Feeder
System and to ensure that the job execution complies with the requirements, specification and
applicable cable tray installation code or other standards.
Specification and standards to be used will be as per the latest Philippine Electrical Code,
PEC-1, 2012, Utility Company (Enerzone) and Park Regulation.
2. GENERAL SCHEME
The sequence of installation of cable tray/conduit for Feeder System will be as follows:
3. LIST OF EQUIPMENT
c) Installing and fixing of cable tray/conduit for Feeder system, including cable bonding ground
connections
1. Upon confirmation of the work area, the engineer and supervisor will confirm the actual layout and
elevation (mounting height) of Cable Tray/conduit and supports as per approved construction
details/shop drawing.
2. Provide/install safety barrier and signboard to secure the work area of installation.
3. Make sure to coordinate with different system/trade of work before start of work.
4. Check for any damage or defects, details dimensions of all cable tray/conduit and accessories to be
Page 2
installed as per the specification and shop drawing approved prior to installation.
5. All cable tray/conduit to be properly identified per main and branch feeder homerun before
termination/connection in panels.
6. Installation of other cable tray/ c o n d u i t to be as shown in the approved shop drawings.
d) Perform inspections
1. Check all installed cable tray/conduit, accessories and support, including cable bonding ground as
per approved specification and construction drawing.
2. Conduct visual inspection prior to acceptance.
3. Inspection shall be based on completed and approved drawing and system documentation as per
standard requirements for the installation of cable tray/conduit for feeder system layout.
4. Field inspections shall be witnessed by engineer/client representative.
5. Record all gathered data and take photo during inspections.
e) System Hand-Over
1. After inspections, authorized service engineer representative shall prepare and provide training
demonstration to building facility maintenance team and client representative.
2. Submit record of completion and supporting documentations for the installation of cable tray/conduit
for Feeder System.
5. SAFETY CONTROL
a) Daily Toolbox Meeting (Engineer/Forman/Workers)
A daily toolbox meeting shall be conducted prior to start of every works highlighting and
discuss the dangers and hazards associated with and the precautions to take in the actual
works to be carried out.
6. QUALITY CONTROL
a) To ensure that the steps of the procedures are fully complied with, certain inspection on the materials
and works will be carried out. A general inspection sheets representing verification of cable tray,
accessories and support installation and quality test will be submitted for approval.