OPTIONAL QUOTATION COST BREAKDOWN

PROJECT : TANGGUH EXPANSION PROJECT REVISION : 01


REQ No. : TEP-900-REQ-ST-BP4-0003 DATE : 03/01/2019
REQ TITLE.: FIRE PROOFING BSB's SCOPE BIDDER NAME : PT. DUTACIPTA PAKARPERKASA
REQ Rev. : - (Additonal Quotation) CURRENCY UIT : IDR
BOQ

UNIT PRICE (IDR/UNIT)

FWC DESCRIPTION D/M PROVISIONAL UNIT MATERIAL (B1) LABOR EQUIPMENT PACKING TRANS EXPENSE SHOP TOTAL REMARKS
WORK PAINTING FIRE PORT DRAWING
PROOFING ATION
CODE (*2) VOLUME FOREIGN LOCAL

(A) (B2) (B3) (B5) (B6) (B7) (B8) (B)

(1) Unloading - 1 ton 400,000 400,000


(2) Painting Fire Proofing (thickness 10.5 mm) - 1 m2 - - - 3,552,000 - - - - 3,552,000 Aplication of fireproofing will be done at
workshop PT. DCP in Surabaya
(3) Painting Fire Proofing (Jet Fire, thickness 16 mm) - 1 m2 - - - 5,808,000 - - - - 5,808,000 Aplication of fireproofing will be done at
workshop PT. DCP in Surabaya
(4) Packing - 1 ton 1,909,260 1,909,260
(5) Transport - 1 ton 589,130 589,130

T O T A L
Notes :
1. The prices above are unit price only, the total value will reffer to actual volume/qty.
2. Exclude repair works if any.
3. Condition: FOT Marshalling yard CSTS in Gresik (Unloading by CSTS).
4. Works delay caused by Client, a minimum daily standby charge per team per workers and
equipment is USD. 400/Team/Day delay if the area to be fireproofed is less than the daily 50
m2 surface area per day to be protected. The delays will be calculated before the end of the
contract.

5. PFP repair damage chargeable that will include removal of damage PFP, exclude surface
preparation to bare metal, prime coating and tie coat application if damage occurred after
handover of the installed PFP, the repair shall be done at works site IDR. 1,867,000.00/spot

6. Exclude VAT. 10%.


SPECIFICATION FOR OPTIONAL QUOTATION FOR FIREPROOFING OF STRUCTURAL STEEL BY STEEL FA

No ITEM
1 Fireproofing Material Proposal to be
submitted
2 Material to be fireproofed

4 Fire Rating

5 Fireproofing shape
6 Thickness of Fireproofing

7 Accessories requirement

8 Fireproofing surface finish

9 Fireproofing top coat

10.A Portions to be installed at fabrication


shop

11 Others

Recommendable PFP vendor

Reference Documents
1 TEP-900-PHI-HS-BP4-0005 rev.B04
2 TEP-900-SPE-EM-BP4-0001 rev.B01
3 TEP-900-SPE-PP-BP4-1009 rev.B04
UOTATION FOR FIREPROOFING OF STRUCTURAL STEEL BY STEEL FABRICATOR

REQUIREMENT
Lightweight Concrete Intumescent Epoxy

Structural steel member

Fireproofed equivalent to 2,5 hours in UL 1709 temperature condition

Contour: following steel member shape


As required by fireproofing material to fulfill the Fire Rating

As required by fireproofing material

Trowel finish
Type of top coat & required thickness shall be as Not Required
per fireproofing material requirement

24,820 m2 of steel member surface

All material certificate, manuals, standard drawings and other applicable documents for
fireproofing shall be supplied

Vendor: International Paint Vendor: International Paint


Contact: Sylvia Ekasinta / 08161998411 Contact: Sylvia Ekasinta / 08161998411
Brand: International Interkote 1560 Brand: International Chartek 2218

Vendor: Tirta Citra Bara persada Vendor: Tirta Citra Bara persada
Contact: Harjoto Hadimurdjono / 081938275999, Contact: Harjoto Hadimurdjono / 081938275999,
Steyowati Kristiaji / 021-65307671 - 73 Steyowati Kristiaji / 021-65307671 - 73
Brand: Isolatek MII-P Brand: Carboline Thermolag 3000 SP

PASSIVE FIRE PROTECTION CRITERIA


PROJECT SPECIFICATION FOR INSTALLATION OF PASSIVE FIRE PROTECTION (PFP)
PROJECT SPECIFICATION FOR PROTECTIVE COATING
REMARKS
Steel fabricator to quote for both material

Refer to TEP-900-PHI-HS-BP4-0005 rev.B04, Passive Fire


Protection Criteria

Steel fabricator to supply and install all required


accessories for fire proofing installation such as stud,
pin, wire mesh/equivalent, touch up paint and others as
required by fireproofing material

Completely applied at shop


Analisa Transport KA - Tanjung Perak Port

SS MW
Sewa Trailer 4,500,000.00 4,500,000.00
Kubikasi 75.00 75.00
Rate 60,000.00 60,000.00
Ratio 7.00 M3/Ton 13.00 M3/Ton
Total 420,000.00 780,000.00
Total berat 1,000.00 kg 1,000.00 kg
Rate 420.00 IDR/Kg 780.00 IDR/Kg
Insurance 21.84 IDR 21.84 IDR
Total Price 441.84 IDR/Kg 801.84 IDR/Kg

Total Harga 45,615,033,440.00


Insurance 68,422,550.16
Total Weight 3,132,498
Rate 21.84
SUMMARY HPP FABRICATION COST ( FOR REFERENCE ) 2016
REV.0 14-Jan-16
Fabrication Cost ( Rp/ kg ) Total Remarks
No Describtion Weight Type Profile Overhead
Weld Jig & (Listrik, Air,
Man Hours Machine Hours Electrode GAS ELPIJI Gas O2 Gerinda NDT * Fixture Eng. FAT L/P * Fabrication Cost
Telpon)

1 Light Structure < 30 kg/mtr WF : WF 100 - WF 250 11,378.77 - 1,220.00 43.51 108.00 62.50 - - 50.00 - - 13,059.27 Light
H : H 100 - Extra Light
L : L 40 - L 130 3,413.63 1,220.00 43.51 108.00 62.50 50.00 5,094.12 Railing * Ladder

Base plate, end plate, gusset plate,

Optional
stiffener, baking plate dan semua plate
accessories
2 Medium Sructure 31 kg/mtr - 60 kg/mtrWF : WF 300 - WF 588 5,689.39 - 1,210.00 36.26 90.00 62.50 - - 50.00 - - 7,334.63
H : H 150 - H 200
L : L150 - L 200
3 Heavy Structure > 60 kg/mtr ≥ WF 600 5,234.24 - 1,140.00 29.01 72.00 62.50 - - 50.00 - - 6,784.22
H : H 250 , > H 400
including welded Beam
4 Tower Structure
TELECOMUNICATION

Mass Product, Fabrikasi Accessories


Angular Type 682.73 200.00 88.50 24.17 60.00 29.17 - 100.00 50.00 150.00 100.00 1,484.57 diperhitungkan tersendiri (ladder,
Base Plate, Cable Ladder)

Mass Product, Fabrikasi Accessories


Tubular Type 1,137.88 200.00 88.50 24.17 60.00 29.17 - - 100.00 50.00 150.00 100.00 1,939.72 diperhitungkan tersendiri (ladder,
Base Plate, Cable Ladder)
GANTRIES / TRANSMISSION LINE 682.73 200.00 88.50 24.17 60.00 29.17 - 100.00 50.00 150.00 100.00 1,484.57

Mass Product, Fabrikasi Accessories


Anchor Bolt 6,365.45 200.00 - - - - 100.00 50.00 150.00 100.00 6,965.45 diperhitungkan tersendiri (ladder,
Base Plate, Cable Ladder)
5 Plate Work DUCTING:
Round/ Circular Ducting (tebal 6 mm, CS) 4,923.93 - 354.00 36.26 90.00 87.50 50.00 200.00 350.00 50.00 200.00 125.00 6,466.69 harga fabrikasi man Hours sdh
termasuk biaya rolling
Rectangular Ducting (tebal 6 mm, CS) 4,323.93 - 354.00 36.26 90.00 87.50 50.00 200.00 350.00 50.00 200.00 125.00 5,866.69
HOPPER/BIN / SILO

Exclude linning for hopper, harga


Round/ Circular (tebal 12 mm, CS) 5,779.09 - 354.00 36.26 90.00 87.50 50.00 200.00 350.00 50.00 200.00 125.00 7,321.85 fabrikasi man Hours sdh termasuk
biaya rolling
Rectangular (tebal 12 mm, CS) 4,779.09 - 354.00 36.26 90.00 87.50 50.00 200.00 350.00 50.00 200.00 125.00 6,321.85
FAN HOUSING 5,163.63 - 354.00 36.26 90.00 87.50 50.00 200.00 350.00 50.00 200.00 125.00 6,706.39 Exclude Biaya Machinning
SHOP FABRICATED TANK
Exclude : Fullwater test, perijinan ,
Non Pressure Tank (tebal 12 mm, CS) 4,730.91 - 590.00 36.26 90.00 87.50 150.00 200.00 350.00 50.00 200.00 125.00 6,609.67 NDT UT & MT , harga fabrikasi man
Hours sdh termasuk biaya rolling

Note * item NDT harga diatas adalah adalah pekerjaan PT yang dilakukan sebesar 10% , nilai akan disesuaikan dengan spesifikasi teknis yang diminta
Khusus untuk Non Pressure Tank , NDT yang dilakukan adalah PT sebesar 100% , nilai akan disesuaikan dengan spesifikasi teknis yang diminta
* Loading / packing ( L/ P ) asumsi menggunakan packing standard , bila memerlukan kondisi khusus yang diminta di spesifikasi teknis , harga akan disesuikan