Академический Документы
Профессиональный Документы
Культура Документы
FOR THE
CARE AND OPERATION
OF
CIRCULATING FLUIDIZEDBED BOILER
(CFB)
FOREWORD
1.1.3.Fuel
The boiler combusts with Coal 1 (Jorong Coal),Coal 2 (Banpu Coal) or
Coal 3 (Sub-bituminous coal), and boiler performance with coal 2 shall be
1.1.4. Optimum Size distribution for coal (shown in fig 1-1) Ash
Analysis
Without limestone
1.1.5.Limestone
a. Limestone analysis (before calcined)
CaCO3 % 90
MgCO3 % 3.0
Moisture % 0.2
Inert % 1.0
1.1.6.Sand
Natural sand (feldspar) is used for start-up and make-up bed material.
The typical analysis is as follows:
1.1.8.Igniting Oil
1.1.9.Feedwater Quality
pH(250C) / 9.0-10.5
In the upper furnace, there are uniformly two (2) superheater wing
wall across the furnace width.
The back pass cage is made up of two parts, the upper part is a
steam-cooled convective heat recovery area (HRA) enclosure, the
lower part is a steel plate casing structure. the HRA contains high
temp. and low temp. superheaters, the casing structure contains
economizer and air preheater.
Between the low temp. superheater, superheater wing wall and high
temp. superheater there are two (2) stages water spray
attemperators to control final superheater steam temperature.
Heat to generate steam comes from the fluidized bed system. Initially
combusted bed materials are forced by flue gas upward through the
furnace and exit at the top to the two (2) steam-cooled cyclone
separators. Coarse hot bed material is separated from the flue gas in
the cyclones and sent back to the furnace via J-valves connected to
the bottom of the cyclones. The hot bed material re-enters the
furnace just above the grid plate to complete the circulation cycle
combustion. Flue gas exits via the outlet at the top of the cyclones
and enters the HRA through a gas screen near the top of the HRA
front wall. After flowing down the HRA, heating the HRA walls and
components, the hot gas leaves the steam generator through air-
preheater via the flue near the bottom of the HRA enclosure.
Steam leaves at elevation 29930 the HRA rear wall lower header
which also serves as the low temp. superheater inlet header, steam
flow through the horizontal low temp. superheater tubes which is in
an upward direction counter to the flow of hot flue gas in the HRA
then to the low temp. superheater outlet header at elevation of
31440. From only left ends of low temp. superheater outlet heater,
steam flow via one (1) 273×20 transfer pipes which involve the
primary spray attemperators is directed to furnace front wall
superheater wing wall inlet header at elevation 17960. From the inlet
distributing header, the steam flows into two (2) upper furnace
superheater wing walls. Then through the superheater wing wall
outlet distributing headers at elevation 36200 the steam flows into
superheater wing wall outlet header. Between this header and high
temp. superheater inlet header located at HRA rear wall at elevation
32710, there is one (1) 325×25 transfer pipes which involve the
secondary spray attemperator. Steam flow through the horizontal
high temp. superheater tubes is also in an upward direction to the
high temp. superheater outlet header at elevation 35710, finally the
satisfied main steam through six(6) Φ133×13 tranfer pipes is
gathered into the main steam contain header, and main steam leaves
the unit on the left side of boiler.
The flue gas and entrained solids exit the furnace, through two (2)
cyclone inlet circuits, to the two (2) cyclones where coarse solids are
separated from the gas stream which exits the top of each cyclone.
From the cyclones, the flue gas flows down through the HRA and
passes over the horizontal convection surfaces. Having given up its
heat to the steam circuits in the HRA, the gas passes through the
tubular air - preheater and enters the ESP for removal of fine
particulate. The cooled dust-free gas is then exhausted through the ID
fan to the stack for release to atmosphere.
The air and gas flow paths through the steam generator are shown in
Fig. 1-4.
For J-valve, there are two (2) blowers each is for 100% capacity. one
(1) of the blowers are in operation and one stands-by. Excess air is
directed through by-pass line to the first path of primary air since each
J-valve blower is constant volume device.
Dampers are provided throughout the air and gas flow system to
obtain proper control, shut-off and isolation during operation and
shutdown.
1.3.3.Combustion Process
After the bed is initially charged, the under-bed burners are fired,
during a cold start-up, to preheat combustion air to the ignition point
of solid fuel. After entering the plenum, the air enters the fluidized
bed through an air distribution grid plate. This grid plate consists of
bell-shaped air nozzles inserted on the fins of a water-cooled grid
floor. The nozzles provide a uniform distribution of air throughout the
bed. The layer of refractory casting between the top of the grid plate
and the ends of the nozzles provides an anti-corrosion and insulation
layer which results in a lower grid plate operation temperature.
Within the fluidized bed, air mixes with the fuel and limestone
products to facilitate combustion and sulfur capture. Solids, swept up
in the furnace by air and flue gas, exit through furnace rear wall
openings and enter the cyclones. The coarser particles are
separated in each cyclone for reinjection to the furnace.
1.3.4.Economizer
The steam drum is located at the top and across the width of the
furnace. the steam drum serves as a water reservoir for the steam
generation circuits. The drum contains steam separating equipment
and internal piping for distribution of chemicals to the water, for
distribution of feedwater and for blowdown of the water. Fig. 1 -
5shows the arrangement of the steam internal components.
Dosing pipe ---- lacunaris, confluxed to one outlet pipes in the middle
of drum.
The arc plate are mounted along whole straight section of drum,
forming a casing space at two sides of drum. Steam mixture introduced
from furnace rises enters the casing, and then goes into cyclone
separator for primary separation: separated water goes along wall
through discharge outlet into water space; while steam flows up
through cyclone separator top corrugated sheet separator into steam
space, and then through cleaning orifice, finally it is educed via steam
connecting pipe at the top of drum through wire mesh separator and
corrugated sheet separator. Water from economizer flows to cleaning
orifice plate through feedwater pipe and then into water space for next
primary circulating.
1.3.6.Furnace
The tube spacing for front wall (and roof), rear wall and side walls is
80 ( 60×5 tubes). Front wall and rear wall are each comprised of
89 tubes, side walls are each comprised of 56 tubes. The grid floor is
made of 44 riffled tubes (Φ63.5X7.5) with tube spacing of 160. The
plenum floor is comprised of 44 finned tubes (Φ60×5) with tube
spacing of160. The furnace waterwall inlet and outlet headers are all
219×30, 20G.
Cross section ratios of inlet pipe, outlet pipe and riser of each circuit are
indicated in the following table. Cross section ratios of downcomer and
furnace water wall riser is 0.295.
1200 above the grid floor. Two (2) limestone feed points are located respectively
within the front and rear wall 8420 above the grid floor. Secondary air ports are
arranged in two layers on the furnace front wall and rear wall as follows:
Two (2) flue gas outlets center line is at the 32200 elevation near the
top of the rear wall.
There are two (2) cyclone inlet circuits. Each cyclone inlet circuit
connects the rear wall flue gas outlet of the furnace to a
corresponding cyclone and is shaped to form a wide gas-tight tunnel
through which the flue gas can travel.
1.3.8.Cyclone
The top half of the cyclone is volute shaped and the lower half is
conical (funnel shaped). The flue gas outlet are made of many
pieces, which shaped altogether to form an open ended cylinder
extending nearly half way down into the center of the cyclone. The
fines and flue gas enter the bottom of the cylinder and flow up to exit
the cyclone. The coarse particles drop down into the funnel which is
directly connected to the J-valve.
The heat recovery area (HRA) means back pass cage, which is an
approximately 6295 wide×3025deep convection heat enclosure of
membrane wall and ends at the approximately 29930 elevation,
below which the remainder of the HRA is constructed of steel plate. A
flue gas outlet is at the elevation of 6700, the bottom of the HRA is
formed into an ash hopper which allows a portion of the particles to
drop down before entering ESP and decreases the gas solids
concentration. The HRA houses the horizontal banks of convection
economizer, low temp. superheater and high temp. super-heater tube
surfaces.
All four walls are connected by inlet and outlet header. The HRA front
wall tube spacing increases from 95 to 285 near the top to form an
inlet screen for flue gas. The HRA rear wall tubing bends toward the
front wall near the top of the wall to form the HRA roof tubes. The
front and rear walls are each comprised of 65 tubes (Φ42×5, and the
14 support tubes in the front wall screen areΦ60×11) and each side
wall is comprised of 32 tubes (Φ42×5). The HRA front wall upper
header is Φ273X36,20G, low temp. superheater outlet header l is
Φ273X20,12Cr1MoVG, high temp. superheater inlet header l
isΦ325X25,12Cr1MoVG, high temp. superheater outlet header l
isΦ273X36,12Cr1MoVG, while other HRA superheater headers are
Φ219X30,20G.
The low temp. superheater is located in the HRA and the inlet header
is at 29930 elevation, and consists of 16 loops of 2 loop-in-loop
horizontal tubes (Φ42X5 ) arranged in 65 sections across the width
of the unit, in counter to the gas flow. Along the steam flow, the first 8
loops are of 20G tubes, the other 8 loops are of 15CrMoG tubes. The
low temp. superheater outlet header ( 12Cr1MoVG, Φ273×20) is
located near the HRA rear wall at the 31440 elevation.
1.3.11. Primary Attemperator
There are two (2) pieces of wing wall arranged at upper furnace near
the front wall. The wing wall is membrane wall construction with tube
spacing of 63.5. Each piece consists of 25 tubes( 12Cr1MoV,
Three (3) coal feed systems located at furnace front wall, Two (2)
limestone feed points located respectively at furnace front and rear
wall, two biomass gas gun located in lower secondary air ports,
one(1) inert material accession port located at the left of furnace. A
spent bed (ash) removal system is connected to the bottom ash
cooler outlet, the air preheater ash drain and the ESP ash drain.
1.5. CIRCULATING SOLIDS REINJECTION SYSTEM
This system is used to reinject heavy circulation solids particles from
the cyclone back into the furnace. It consists of two (2) J-valves(trap)
connected between the solids outlets of the cyclones and the solids
inlets on the furnace rear wall.
Each J-valve utilizes the bed material exiting the J-valve stand pipe
to “seal” the trap. This trap maintains proper flow direction of the
circulation bed towards the furnace with the motive force of the
difference pressure between upward and downward stream of the
trap. The air is supplied by high pressure blower.
two oil burners for start up is provided on both side of air plenum
below the grid floor. Combusted hot gas heats the primary air to
870℃ which in turn heats bed material through air distribution air
nozzles to ignition temperature. The burner utilizes mechanic oil
atomizing gun to get good combustion to prevent nozzle damage
resulted from oil re-burn in the air distribution device. Oil
consumption of each oil gun is 480kg/h; oil pressure is 1.96Mpa at
burner inlet. When oil is already fired air flow for each gun burning is
at least 9000Nm3/h. High energy ignitor and flame scanner is
provided for the burner.
The major pressure parts of the boiler except steam drum are hung
by hangers from the top steel. Steam drum and other components of
the boiler, such as economizer, air preheater, under-bed burner,
loopseal, etc. are all stand on horizontal beams by supporting or
reinforcements.Platforms and stairs are provided where maintenance
or inspection is needed during boiler operation.
This unit utilizes fuel and limestone as the predominant bed material.
At normal operating bed temperatures, limestone is easily calcined
( CO2 is liberated ) resulting in a material that partially reacts with
SO2 in the burning fuel to form calcium sulfate (gypsum).
(m3) (m3)
OPERATION
The following instructions are some of the general precautions which apply
when placing a steam generator into operation. They are intended to
supplement the experience and judgement of those in charge of operation
and cannot cover all precautions which should be observed.
The manufacturer has complied with the national boiler code (GB china
standard) pertaining to the design and fabrication of the unit. A newly erected
unit, prior to being placed into operation, must be carefully inspected by
authority to assure that all component parts are properly assembled.
NOTE
c. Ensure that the ash removal system connection has been made to the
cooler and that the cooler is ready for operation.
g. The under-bed burners, shall be ready for operation with all safety
equipment verified operable, e.g., flame scanner, interlocks, etc.
i. All flues, ducts, pipes, chutes or conduits through which air, gas, water,
steam or solids flow shall be connected securely; check to ensure that
proper flow paths have been maintained.
When preparing a new steam generator for service, see that the following is
done as required:
All vent, drain and blowdown lines must be readily accessible and properly
piped to a blowdown tank or other safe location so as not to endanger the
operator at any time.
Valves that are located between the steam drum and water column of water
gage must be in the full open position and locked.
All safety valve gags and hydrostatic test plugs must be removed and the
valves must be in proper operating condition. Discharge pipes and drains
should be arranged and supported in accordance with the safety valve
manufacturer’s recommendations.
A leak test shall have been conducted on the steam generator’s air and flue
gas systems; all leaks shall be corrected in accordance with paragraph 2.8.
Expected hot areas of the steam generator shall be insulated or roped off to
provide suitable protection for personnel.
d. Air and gas passages must be free from obstruction and the unit
capable of being thoroughly purged by the circulation of air through the
unit.
When it is assured that the above precautions are fully understood and have
been complied with, then, and only then, should subsequent operations such
as“Drying Out”,“Boiling Out”,“Initial Starting”and“Normal Starting” be initiated.
CAUTION
b. Close stop and check valves, all drain and blowdown valves and valves
to any gages or other integral equipment not designed to withstand the
hydrostatic test pressure.
c. Open vents on the highest points of each component part of the unit.
d. Be sure that the water will not freeze during test and the unit will not be
subjected to freezing conditions following the hydrostatic test. If
hydrostatic testing of a drum will be at temperatures above 49 ℃,
exercise care during close examination to avoid possible burns from
water leakage.
e. Check that only authorized personnel are in the vicinity of the unit to be
tested.
f. Start filling the unit with water, which should be relatively close in
temperature to that of the pressure parts, so that the temperature of
drum metal and water is in accordance with the following before
applying a hydrostatic test pressure. All other pressure parts must be at
a temperature of not less than 20℃.
CAUTION
NOT
FUNCTIONING ( AS MAY BE THE CASE FOR INITIAL
OPERATION ), ANY ONE OF THE FOLLOWING METHODS
(1), (2), OR (3) IS RECOMMENDED. Heat from an external
source, to obtain the recommended minimum temperature as
indicated by the drum surface thermocouples.
(2) Use small oil and/or gas burners aimed through doors or
resting on the grid nozzles to raise the temperature to that
recommended. The burner flame should be kept away from
the boiler tubes.
(1) After filling the unit to normal water level, fire the under-bed
burners to raise the drum temperature to 2 ~ 5℃ above that
recommended. Extinguish fires and continue to fill unit.
Inspect drains and manhole for leaks as the unit fills. Close
the high point vents when water issues from them.
(5) Remove blanks or gags from safety valves and pins from
spring hangers after test has been completed.
2.4.1.General
Boiling out is the process of internally cleaning for the removal of oil
and grease, and the solvent usually consists of a strong alkaline
solution.
During the boiling out process, the gage glass may become badly
discolored and permanently etched. We have supplied replacement
of mica and mica repair kit, Our suggestion is that Restore the
inoperable gage glass to its original condition after boiling out and
chemical cleaning, and before the next filling of the unit with treated
condensate. The gage glass manufacturer’s instructions should be
consulted for the identification and the replacement procedure.
Alkaline chemicals such as soda ash and caustic soda are commonly
used for boiling-out a unit since these agents possess the ability to
saponify the oils and greases and form a soap compound that is
easily removed by high pressure blowdown during the boiling out
process, and after completion of boiling out, by flushing with a high
pressure hose using cold water.
For the most effective removal of oil from boiler metal surfaces, it is
recommended that a“wetting agent”be incorporated in the boiling out
mixture. These agents increase the“wetting power”of the water by
reducing the surface tension and therefore reduce the adherent
characteristics of oils and greases to a minimum. The combination of
a “wetting agent”along with the regular boiling out chemicals will
therefore break down the oil-sludge bond and remove the oil and
grease from the metal surfaces.
Refer to Item 1.10 for the amount of water required for normal filling
of this unit.
NOTE
NOTE
(2) All fuel and limestone feed equipment and fans should be
secured and tagged“Out of Service - Men Working in
Furnace”.
b. Open the vent valves indicated in the list within Paragraph 3.3. so that
air can be expelled as the boiler is being filled. Isolate gage glasses,
remote level indicators, pressure connections, sensitive
instrumentation and anything that could be damaged during boiling
out. Filling the unit should be accomplished using the feedwater
pumping and piping system normally used during boiler operation.
This will have a tendency to flush out the piping and auxiliaries ahead
of the boiler.
c. Inject chemicals into the boiler feed line downstream of the main feed
pump but upstream of the economizer. A main feed line piping drain or
economizer drain connection may be used for this purpose.
NOTE
d. Raise the water level so that it is just visible in the bottom of the lower
gage glass.
e. When the desired steam drum level is reached, close boiler feedwater
flow control by-pass valve.
NOTE
a. Start the induced draft and combustion air fans in accordance with the
fan manufacturer’s instructions and in the sequence outlined in
Section 3, Start-up Procedures.
c. Set the combustion air damper to maintain sufficient air flow to the
under-bed burner.
e. Close the steam drum vent valves when boiler pressure reaches
0.1MPa.
f. Continue to fire the under-bed burner or feed coal into the furnace
until the steam drum boiling out pressure reaches the value
corresponding to the design pressure for this unit. (See Figure 2-1).
g. The boiler feed pump must be kept available for operation should
make-up feedwater be required.
h. Fire the under-bed burner or feed coal into the furnace intermittently
as required to maintain steam drum boiling out pressure for at least
eight (8) hours.
i. Raise the water level to approximately 50mm from the top of the gage
glass.
j. When the high water level and steam drum boiling out pressure have
been reached, shut down the under-bed burner or interrupt coal
feeding.
k. Start blowing down each blow-off line by opening the drum mass
blow-off valve, furnace lower waterwall header drain valves. It is
recommended that, when blowing down these lines, the root valve
(closest valve to boiler) be opened first and closed last. The second
valve in the line should be used to control flow. A sufficient blow can
be accomplished by spinning the valve open and then spinning it
closed again (approximately 10 seconds.)
l. A cooled sample from the drum should be checked for phosphate, pH,
silica and total alkalinity and a record kept of the chemical
concentrations.
m. If the water in the steam drum falls to within 50mm from the bottom of
the gage glass, refill the steam drum and fire the under-bed burner or
feed coal into the furnace to maintain steam drum boiling out
pressure.
n. Repeat steps k and l once every four (4) hours for at least 24 hours
until all signs of oil have disappeared from the cooled boiler water
sample. Repeat step m. as required.
After boiling out, When the boiler has been cooled and drained, the
drum(s) should be inspected and any sediment removed. If the
quantity warrants, inspect headers. Where inspection nipples are not
provided on headers, inspection may be accomplished by cutting a
feeder or riser tube at the stub and bending the tube out of the way. If
any foreign material is found in a header, It can be removed manually
or flushed with a high pressure water hose. In addition to checking
for sediment, inspection should assure that the metal internal
surfaces are free from oil adherence.
After the drum and headers have all been cleaned and inspected,
the unit can be closed. New manhole gaskets should be installed on
the drum and inspection nipple caps or tubes cut for cleaning and
inspection should be replaced.
GENERATING CIRCUITS
2.6.1.General
The cleaning of modern high duty steam generators with chemical
solutions is an effective tool. A cleaning performed prior to initial operation
or a very short time thereafter, for the purpose of removing mill scale,
provides a thin, uniform protective coating of iron oxide and removes, from
the unheated portions of the system, much material that may be
redistributed to the heat transfer areas. There is merit to postponing this
type of cleaning until after some short period of operation as considerable
iron oxide and silica-bearing materials may be carried into the steam
generator from the feedwater and condensate system during initial
operation, unless the feedwater and condensate system are also
chemically cleaned.
2.6.3.Solvent Systems
To bring the unit to cleaning temperature, the unit may be filled with
condensate or demineralized water and heated by one of the
methods specified in paragraph 2.2. Using drum thermocouples, and
temporary thermocouples if necessary, monitor unit temperature to
assure that there are no areas above the limits for the solvent system
and inhibitor used. The limits must be specified by the solvent
system supplier. When the proper temperatures are attained, the
water may be drained to storage.
The unit is then filled with solvent by pumping the stored heated
water back into the unit and metering in the concentrated solvent to
give the desired concentration. Before the solvent pumping is
started, it should be checked for proper inhibition. If the water
temperature must be adjusted while refilling the unit, steam should
be injected ahead of the solvent to avoid corrosion of the mixing
equipment.
While the solvent is in the unit, the acid strength, iron concentration,
temperatures and any condition or constituent necessary for control
of the particular solvent system should be monitored on a regular
basis. When the cleaning is complete, as indicated by the leveling of
the iron concentration, the solvent is drained from the unit under a
nitrogen blanket.
The unit may be filled and drained one or more times to flush the
solvent from the cleaned area. The rinse may contain an iron
complex agent to prevent precipitation of iron on the cleaned
surfaces.
2.7.1.General
2.8.1.General
a. Having continuous supply of feed water to make-up water lost in the period
of the steam purging.Check of electric drawings
b. Check of the duct pilot layout drawings
c. Finish the check of the meters
d. Test of the safety chains
e. Set and check the safety valves
f. Have finished the test of the boiler and all auxiliaries
g. Install the temporary purging piping, purging valve and silencer, also the
check and pressure test
h. Strike all the temporary scaffolds, devices and some other unnecessary
equipments in the area of steam purging
2.8.2.Initial condition
a. Continuous communication has been established between device
operators, field persons and the master-control room
b. When the boiler runs in the condition which has lower steam pressure and
lower temperature for 5%-10% than required, the boiler and the
assistant system is steady. The required steam purging power is
determined by the following formula: R=(W/ Wr )2V/Vr( R: steam
purging power W: steam flow during the period of steam purging Wr:
the designed steam flow V: the specific volume in the inlet of the
superheater during the period of steam purging, is expressed by
cubic feet/pound). If we apply continuous purging method, R should
be 1.5—1.6 and for impulse or intermittent purging R should be 1.0—
1.2. Because the thermal impact and dynamic force generated by the
fast variation of the steam condition ( pressure and temperature )
accelerates the purging progress, intermittent method is better than
continuous method.
c. All valves on the steam piping, until all the temporary steam purging valves
is opened, all piping have been blowd and been preheated
d. Warning limit should be set in the adjacent area of steam purging and
temporary piping, and suspend the standards to prevent people enter
this area
e. All adjacent people have been informed
a. According to the requirement of liability, please make sure that the boiler
can generate steam
b. Isolation is for the temporary joints of the steam piping
c. Make sure that all temporary joints be drained, cooled and striked
d. Recover the piping and valves of the permanent devices to their raw
condition.
h. De-pressurize system.
j. If leaks were found, repeat the air test following leak repair.
3.1. GENERAL
The Critical precautions that the operator must observe and exercise
during all phase of operation of this unit are listed below.
a. All doors at lower furnace must not be opened during normal unit
operation to protect personnel from any danger as this steam
generating unit will have internal pressure greater than atmospheric
pressure.
(e) All air flow controls transfer to manual mode and hold last
position.
NOTE
The normal drum water level is 180mm below the centerline of the
drum. The alarms are set at 75mm below and 75mm above normal
water level and the trips are set at 120mm below and 120mm above
normal water level.
NOTE
All safety valves are set by the valve manufacturer but should be
rechecked under actual operating conditions as the boiler is being
brought up to pressure during initial operation. If a safety valve does
not lift at the pressure stamped on its nameplate or reseat properly,
the valve should be readjusted. It is not allowed to change the
settings of any safety valve without authorization.
Care should be exercised to ensure that the proper fuel-air ratio for
good combustion is maintained. The excess air requirement at 100%
MCR load is measured at the HRA outlet and corresponds to an
oxygen measurement of approximately 3.1% by volume on a wet
basis. (See Figure 3-1.) It is just for reference and should be set by
combustion adjustment. Operation with less than the specified
excess air can be detrimental from the standpoint of good
combustion and safe operation of the unit.
h. Readiness Inspection
There are also four (4) thermocouples in transfer pipes between the
right cyclone outlet and the HRA inlet.
NOTE
A similar procedure should be used for all other pressure taps on the
air and gas side of the steam generator.
b. Make sure the test gags and/or plugs are removed from all safety
valves.
c. Check availability of utility services, power, ignition and main fuel, and
suitably treated feedwater.
g. Close all access doors and observation ports after it is proven that no
one is inside the unit. Release all safety tags on equipment to be
placed in service.
h. Place the boiler vent, drain and instrument valves in the following
position. This list assumes the unit is empty.
(PER BOILER)
i. Fill the boiler by admitting water, via By-pass Feed Control Valve, to
the economizer using water from the regular feedwater source.
k. Check that the drum remote level indicators are operating in the
control room and that they compare accurately with local gage glass
readings.
l. Check that all pressure and draft gages are calibrated and functioning
properly.
o. Check that all lubricating and cooling systems for all driving facilities
meet the manufacturers’ technical requirements and all cooling
mediums are available for equipment that requires cooling.
p. Position dampers in the air ducts and gas flues as indicated below.
Damper positions are displayed in the control room. All fuel,
limestone and other manual isolation and / or slide gate dampers
should be closed at this time.
DAMPER DESCRIPTION POSITION
3.3.2.Purging
Note
c. Ensure that the fuel supply valve to the under-bed burner is closed.
d. Check that all limestone fuel feeders are off and spent bed removal
system is off.
e. Start the induced draft (ID), forced draft (FD) and one J-Valve blower
as follows:
CAUTION
NOTE
1. Ensure that all flue and duct dampers are in the positions specified in
2. Start one J-valve blowers. Set the J-valve aeration rates to correspond
to those values listed in attached table 6 and fig.3-8 for each J-valve.
(a) Refer to Table 1, Fig.3-5 Fig3-6 and Fig.3-7 for proper operating
parameters.
(b) Place J-valve upflow and downflow plenum air flow controls on
auto.
(c) Place J-valve blower pressure control valve on auto and check
that it is properly functioning.
(e) Place upflow leg and downflow leg aeration flow control on
auto.
(g) Record aeration air flow rates, and J-valve temperature and
compare to Table 6.
(h) Air flow rates that vary widely from values given in Table 6
should be adjusted to agree. Switch to a manual aeration
mode. Adjust air flow towards the tabulated value in 14Nm 3/h
increments while recording pressure differentials. Set air flow at
lowest stable pressure differential.
3. Start the ID fan. The ID fan inlet control vanes will close, the ID fan
breaker will close and the motor will start running. Once the motor is
proved running and up to speed, the inlet control vanes are released
to furnace pressure control.
4. Start the Secondary and Primary fan. The fan inlet control vanes will
close, the fan breaker will close and the motor will start running. Once
the motor is proved running, the inlet control vanes are released to
combustion control. However, the Secondary FD fan should be started
and adjust the air flow to minimum prior to start-up of the Primary FD
fan.
5. The control system will automatically adjust the unit to a“ready for
purge”condition.
g. Purge the unit with at least 25% (but not greater than 40%) total air
flow for at least 5 minutes.
h. After the steam generator has been completely purged, reset the
master fuel trip (MFT) and perform the following:
position.
(a) Position the under-bed burner and furnace fluidizing air (to
plenum) control damper for proper combustion air.
CAUTION
NOTE
the superficial fluidizing velocity should not be allowed
to drop below 1.2m/sec, the minimum superficial
fluidizing velocity required to maintain fluidization.
CAUTION
Close fully and then open 1/2 turn the following drain valves:
NOTE
f. Heat the bed material and raise the drum pressure. Mixture gas flue
temperature should be regulated to increase drum pressure and
temperature at a rate not exceeding 50℃/hr.
g. While the unit is heating up and building drum pressure, check drum
metal temperature and drum level.
NOTE
j. When the drum pressure reaches 0.69 ~ 1.03bar, close the following
vent valves:
l. At this time, the drain valve(s) downstream of the main steam outlet
header should remain open to ensure that all water is drained from
the steam circuit.
m. After achieving approximately 1.7 bar in the drum, recheck the drum
water gage glass operation by a short blowdown. Maintain visible
water level in the gage glass. Water level in the drum will rise due to
swelling of water in the system. Blow down the drum as required by
opening the steam drum continuous blowdown and / or emergency
release valves.
n. Place the drum level control loop in automatic control in the single
element (drum level control) mode.
The following procedure must be integrated with the boiler and main
steam piping, such that a flow path is maintained for the steam being
produced by the circulating fluidized bed boiler.
b. Check that the spray control isolation block valves are open.
c. Start three coal feeders and adjust to feed fuel into the furnace at 15%
capacity. Operate at this capacity for 5 minutes and then shut down
the feeder. Monitor O2 and average bed temperature (ABT) to
establish a trend over time. During the first several minutes, average
bed temperature should decrease initially and then start increasing.
O2 should remain steady initially and then begin to decrease
preceding average bed temperature rise. Establish a time interval
required to completely and safely combust the quantity of fuel just
fed. This time interval should be measured from the time of feed
commencement to the highest average bed temperature and lowest
O2. The time interval may be set by the field after having experienced,
but the duration may be changed with varying fuels. With some low
reactivity fuels coupled with varying unit designs, it may be necessary
to change the duration of batch feeding.
NOTE
d. Start the same feeder again at 15% capacity and batch feed fuel for
another 5 minute period. Shut down the feeder. Monitoring average
bed temperature and O2, restart the feeder at 15% capacity just prior
to reaching peak bed temperature. Add fuel for another 5 minute
period.
k. When conditions permit, put drum level, steam temperature and air
flow on automatic control.
m. Adjust combustion air flow and fuel flow to establish bed temperature
of 900℃ while removing the under-bed burner; maintain O 2 at 3.1%.
q. Unit load can now be raised to 100% (MCR) by using the boiler
master control. Observe the following guide lines:
The boiler may be shut down for a period of time and held in the hot
condition (slumped but ready to operate again). When the boiler is to
be hot slumped, the fuel feed should be stopped and the O 2 indicator
at the boiler exit monitored. As soon as the %O 2 starts to increase,
stop the fluidizing air flows to the furnace to minimize bed heat loss.
This O2 increase indicates that most of the fuel has been burned and
the beds can be slumped by decreasing fluidizing air flows to zero.
the FD and ID blowers and the limestone feed system are stopped.
The J-valve blower should remain in operation after the fans and
other blowers are shut down.
NOTE
All valves and air control dampers are closed so that a minimum
amount of heat is lost. No fire is maintained or introduced into the
furnace; therefore the pressure in the steam drum will decrease, but
proper drum level must be maintained.
NOTE
c. Start one (1) J-valve blowers and set air flow for proper
fluidizing velocity. Place on Auto.
d. Start ID fan and FD fan per the procedures described for a cold
start-up, Paragraph 3.3.2.
CAUTION
e. Adjust combustion air for 25% MCR conditions. When all fans
are running, proper air flows must again be established along
with restart of the fuel feeds. Since the bed temperature can
drop rapidly, it is important to acquire proper air flows and fuel
feed rates. Otherwise, bed temperatures and O 2 values will not
respond accordingly. If the unit does not respond to the proper
feed rates of air and fuel, discontinue the hot start-up procedure
and begin the cold start-up methods. Make certain to purge the
unit of combustibles prior to lighting the under-bed burner.
f. If during the hot restart solid fuel has been overfed into the bed
and has not fully combusted as a higher bed temperature is
again established, the bed temperatures may rise rapidly and
O2 decrease rapidly. If this should happen, no further fuel feed
should be added until the bed has stabilized. If the temperature
rise appears to be rapid enough to climb above 930 ℃, the
following should be implemented in advance of achieving
930℃.
NOTE
NOTE
3.5.1.Firing
a. The primary technique for changing the boiler load involves varying fuel
feed rate and air flow. Bed temperature may be varied between
790℃ and 920℃ to permit large increments of change within a short
period of time. However, after obtaining the desired steam rate, bed
temperature should be re-established at 900℃ and boiler load held
steady by adjusting bed inventory and firing rate. Normally when
changing load, the best method is to maintain the bed temperature at
a constant value if possible. In all cases, make sure that air flow
tracks fuel flow either manually or automatically, to maintain a set
excess O2 value.
b. The SO2 emissions from the boiler should be monitored at all times. The
limestone feed rate must be adjusted, either manually or
automatically, to maintain an SO2 emissions level at the stack that is
in compliance with concerned regulations.
NOx emissions are inherently low within the furnace at the normal
temperature operating range. NOx emissions are increased as
furnace temperature is increased. The NO x emission level at the
Continuous Emission Monitoring System (CEMS) (stack) should be
checked periodically. Adjustments, if necessary, should be made to
operating furnace temperature and secondary air distribution through
various airport levels.
e. Periodically inspect the fuel and limestone feed systems for plugging,
improper sounds, vibration, belt tracking, lubrication and
temperatures.
f. Continuously monitor the fluidized bed level and maintain it at its normal
level by adding limestone or increasing bed extraction rate. Bed
material extraction will be required to maintain proper bed material
inventory and SO2 control.
NOTE
a. Assure that the desired boiler water salt concentration and chemistry are
maintained. Improper boiler water can lead to fouling or corrosion of
internal surfaces, reducing the efficiency of the unit and possibly
resulting in overheating of tubes leading to tube failure
b. Assure that moisture carryover from the drum is within permissible limits.
For operation within design condition, the steam separation
equipment will keep salt carryover within acceptable limits. Moisture
carried over can include salt and other impurities which may deposit
on surfaces downstream of the boiler.
3.5.3.SootBlowing
b. After the unit is placed in service, operate the sootblowers to remove any
deposits which may be present. Sootblowing should always be done
on the pre-established schedule basis regardless of the operating
load; however, below 50% load the FD and ID fans should be in
manual control during the sootblowing operation.
3.5.4.Spray Attemperation
Do not desuperheat the steam entering the SH wing wall and H/T
superheater inlet header to less than 11 ℃ above saturation
temperature at the inlet pressure of the transfer pipes.
f. Reduce unit load to minimum stable. Maintain minimum unit load for
approximately 30 minutes to help cool cyclone refractory, otherwise
cyclone tube temperatures will rise to greater than 420 ℃. In such
case, opening the cyclone upper header vent system.
h.close all fuel silo hopper outlet shut-off valves and run all fuel off the
feeders ( if an extended shutdown is expected). Also, empty the fuel
storage silos to their lowest safe levels.
i. Stop limestone feeder systems.
j. Monitor boiler oxygen levels and bed temperatures; when oxygen starts
to increase and bed temperatures start to decrease, closing off the
air (to plenum) control damper.
l. After all fires have been extinguished, leave the FD and ID fans in
operation for at least five minutes to purge the setting of
combustibles.
o.If the boiler is to be out of service for an extended period or entered for
maintenance, continue to cool down the unit using the fans, while
removing bed material via the bottom ash cooler. The H/T
superheater outlet header downstream drain valves may be
regulated along with other superheater drains to decrease drum
pressure at the desired rate. Cool the unit as uniformly as possible.
The residual heat in the setting and the boiler components will
continue to generate steam for considerable time. During this
period, the boiler water level should be maintained near the upper
limit of gage glass visibility. Once all bed material is removed from
the unit, purge the boiler setting for five (5) minutes. The bottom ash
cooler should then be removed from service. When the unit is cool
enough for entry, the fans can be taken out of service.
q.The J-valve blower should remain in operation after the FD and ID f air
fans are shut down. To prevent damage to J-valve components, the
J-valve blower should remain on until valve cools to below 260 ℃.
s.If the unit is to be drained, open all vents and drains when the drum
pressure has decreased to 1bar. Temperature of the boiler water
should not exceed 120℃ when the unit is drained. Draining the unit
when there is still a small amount of pressure on the unit is
preferred as the residual heat will assist in drying the internal
surfaces.
t. Superheater header drain and vent valves should remain open during
short outages.
u.Idle boilers should not be allowed to remain partially filled with water for
any appreciable length of time. Fill them completely with deaerated
alkaline water into which hydrazine has been added as a protection
against corrosion. If the outage will amount to several weeks or
months, or should weather prohibit filling the unit, drain and dry the
unit, placing shallow pans of a predetermined quantity of silica gel in
the drums to absorb moisture and maintain the internal surfaces in
a dry condition. When the unit is to be out of service for several
days or longer, all ash and soot deposits should be removed since
moisture absorbed by sulfur bearing ash or soot causes corrosion. It
is advisable to sootblow the unit just before taking it out of service, if
possible.
3.7. EMERGENCIES
e.All air flow controls transfer to manual mode and hold last position.
f. Fan controls transfer to manual mode and hold last position unless the
cause is a fan trip, in which case, fan controls follow fan logic.
6. Steam drum level high high, +120mm above normal ( with time
delay ) (2 out of 3 logic ).
7. Steam drum level low low, -120mm below normal ( with time
delay ) ( 2 out of 3 logic ).
8. ID fan tripped.
10. Total air flow low, less than 25% (with time delay) (from
Combustion control System).
12. Total air/fuel ratio less than minimum (from Combustion Control
System).
Continue to operate fans and maintain air flow to the furnace to keep
material moving into the bottom ash cooler. Some air flow to the
secondary air ports should be established to keep moisture out of
ducts. Reduce drum pressure as slowly as possible and maintain
drum level, if possible. Continue to cool the unit and extract bed
material until the unit is empty of bed material and cool enough to
enter. During cool-down, do not exceed a 40 ℃ differential
temperature between top and bottom of the steam drum. The drum
level should be maintained until the boiler water temperature is
reduced below 120℃; then the boiler should be drained. If the tube
leak is in the furnace, it may be necessary to use the under-bed
burner while removing the bed material from the furnace to assist
with evaporation of the lost boiler water. If the bed is damp and drops
below 180℃, it may plug the ash handling system or stay within the
furnace. If the under-bed burner is utilized, it is important that the
burner temperature be kept below 315℃.
Before entering the unit for any reason, check that safe temperature
has been reached, conduct gas sniff test for safety levels and wear
proper protective clothing.
When access to the bed is possible and all bed material that is
possible to remove is extracted, enter the unit to assess the extent of
the tube leak and amount of bed material remaining. Any material,
wet or dry, left in the beds should be removed as soon as possible
before it has a chance to solidify. Solidified bed material below the
level of the grid nozzles need not be removed. However, the grid
nozzles must be inspected and any plugged nozzles cleaned out by
rodding with high pressure air from below the nozzles. Make certain
no one is working on the opposite side of the nozzle.
Excessive high bed temperature can lead to clinkers (fused ash) and
damage to in-bed thermowell, thermocouples, grid nozzles, etc.
The actual cool-down time is dependent upon the boiler load and
bed temperature at the time of shutdown. Also, When the drum water
temperature drops to 120℃, the unit can be drained to aid cooling.
During cool down, a maximum of 40℃ differential temperature
between the top and bottom of the drum should not be exceeded.
Maintain minimum air flow, equivalent to 1.2m/sec superficial
velocity, to the bed for cooling and to ensure transfer of loose bed
material to the bed drain. When the unit is cool and no more bed
material can be removed through the bed drain system, shut down
the fans and make the necessary safety preparations to enter the
furnace. Enter the unit and evaluate the extent of the clinkers. Small
accumulations can be broken up and removed. Inspect for any
damage to the bed thermocouples and grid nozzles. Repair or
replace as necessary. All grid nozzles should be inspected for
plugging and cleaned out as required.
3.7.3.Overpressure Protection
(Bar)
Safety Valve Main steam header 1 105
Safety Valve Steam Drum 1 118.9
3.8. MAINTENANCE
CAUTION
If an idle boiler is not drained, the areas above the water level in the
drum should be filled with nitrogen through the above mentioned
access on the drum. The nitrogen cap should be established when
the pressure of the boiler being removed from service decreases to
about 0.35Bar. Maintain the nitrogen cap during the shut down
period. During idle periods, the boiler must be protected against
freezing conditions. This may be done by firing the under-bed burner
with low heat input to maintain temperatures throughout the boiler
above freezing.
b. When the unit is shut down for repairs, it should never be entered until it
has been determined that all fuel shut off valves and dampers are
locked in the closed position. Should there be some questions about
their tightness, it is recommended that the fuel lines be blanked off.
CAUTION
CAUTION
c. Only approved safety types of lights and flashlights should be used when
inspecting and working in the boiler.
e. Inspect each air distribution grid plate nozzle for plugging and clean out
as necessary.
f. When inspection door are opened for access, the used gaskets should
be replaced with new ones.
h. Repair all tube leaks as soon as possible. Leaks which are allowed to
persist can cause further damage due to water or steam cutting of
adjacent tubes.
j. Check all fuel and limestone feed piping and bed material extraction
piping for plugging, erosion, overheating, etc. Repair or replace as
necessary.
k. All valve and packing leaks should be repaired during the outage period.
This will help prevent forced outages.
m. Check plenum floor for accumulation of spent bed material due to back
sifting through grid plate air nozzles. Remove material if excessive.
4. Figure
Boiler Specification
Name & sign Unit Result Name & sign Unit Result
Boiler rating vapour Rating steam outlet
t/h 130 ℃ 510
volume D temperature tgr
Steam outlet Drum working
Bar (g) 100 Bar (g) 111
pressure Pgr pressure Pgt
Feedwater Economizer inlet
℃ 170 Bar (g) 116
temperature tgs feedwater pressure Pgs
Continious Cooling air
% 2 ℃ 30
blowdown rate Ppw temperature tlk
Fuel Calculation
Name & sign Unit Result Name & sign Unit Result
As-received basis As-received basis
% 62.61 % 4.08
Cy Hy
As-received basis As-received basis
% 6.09 % 1.01
Oy Ny
As-received basis As-received basis
% 0.72 % 13.89
Sy Wy
As-received basis Combustionable
% 13.89 % 40
Ay group volatile
Low heating value Fuel check value
kcal/kg 5831 kcal/kg 5820
Qdwy Qv
Theoretic air value
Nm3/kg 6.43
VAirA
Furnace outlet
Boiler outlet excessive
excessive air / 1.2 1.25
air coefficient
coefficient
Temperature of
bottom ash Material circulation
℃ 200 21.2
discharged from ratio
furnace bottom
Carbon contents in Carbon contents in
% 5 % 1
fly ash bottom bottom ash
Limestone Features
Calcium carbonate Magnesium
% 90 % 3.0
CaCO3 carbonate MgCO3
Moisture % 0.2 Inertia index % 1.0
Desulfurazing
Ca/S Moore ratio / 2.5 % 83
efficiency
Heat Balance Calculation
Name & sign Unit Result Name & sign Unit Result
Loss due to chemical
Heat loss due to
% 5.29 incomplete combustion % 0.1
flue gas exhaust q2
q3
Loss due to
Loss due to heat
mechanical incomplete % 1.07 % 0.4
radiation q5
combustion q4
Decalescence in SO2 sulfation
% 0.39 % -0.37
calcining limestone radiation
Heat loss due to
Manufacturer
bottom ash % 0.04 % 0.25
margin
radiation q6
Calculated boiler heat Guaranteed boiler
% 93.09 % 92.8
efficiencyηgl heat efficiency
Calculated fuel
kg/h 15224 Fuel consumption B Kg/h 15389
consumption Bj
Limestone
kg/h 952 Total burnt air Mn3/h 118800
consumption
Inertia material kg/h 0
Flue gas at boiler
mn3/h 132400 Total bottom ash Kg/h 3071
outlet
Fly ash kg/h 2303 Bottom bottom ash Kg/h 768
Primary input air in
mn3/h 53500 Coaling input air Mn3/h 10000
furnace bottom
input air for
Secondary input air mn3/h 55300 Mn3/h 1150
returning material
Furnace
Name & sign Unit Result Name & sign Unit Result
Outlet flue gas
Bed temperatureθ" ℃ 899 ℃ 917
temperatureθ"
Boiler outlet discharge
Fly ash
Primary discharge
concentration at g/mn3 17.5 mg/mn3 1671
of SO2
boiler outlet
Discharge of SO2
mg/mn3 284
after desulfurization
Discharge Discharge
concentration of mg/mn3 <300 concentration of mg/mn3 <250
NOx CO
Desuperheater calculation
Name & sign Unit Result Name & sign Unit Result
Desuperhe
Desuperheater ating by Spraying water
℃ 170
type water temperature T
spray
Total water sprayed
by desuperheater T/h 7.4
△D
Water sprayed by
T/h 3.5
desuperheater I △D
Steam temperature at
Steam temperature at
℃ 409 desuperheater I outlet ℃ 388
desuperheater I inlet t1
t2
Water sprayed by
T/h 3.9
desuperheater II △D
Steam temperature at Steam temperature at
desuperheater II inlet ℃ 453 desuperheater II outlet ℃ 426
t1 t2
Heat transfer component calculating results collection
Wall
Screen High Low
enclosur
type Cyclone temp. Temp.
Name & sign Unit e
superhe separator superheat superhe
superhe
ater er ater
ater
Tube size mm φ42×7 φ42×6 φ42×5 φ42×6 φ42×5
Flue gas inlet
℃ / 917 867 822 668
temperature
Flue gas outlet
℃ / 867 / 668 576
temperature
Working medium
inlet ℃ 388 319 344 426 370
temperature
Working medium
outlet ℃ 453 344 370 510 409
temperature
Flue gas average
m/s / / / 11.7 10.3
velocity
Primary
Secondary
Economize Economizer Economize Economizer ducting
Name & sign Unit ducting air
r IV III r II I air
preheater
preheater
Tube size mm φ32×4 φ32×4 φ32×4 φ32×4 φ40×1.5 φ40×1.5
Flue gas inlet ℃ 576 466 389 313 260 /
temperature
Flue gas outlet ℃ 466 389 313 260 / 135
temperature
Working medium ℃ 240 214 188 170 30 30
inlet temperature
Working medium ℃ 275 240 214 188 185 185
outlet temperature
Flue gas average m/s 8.4 8.1 8.0 6.9 7.6 7.2
velocity
Table 2. Boiler check coal rank COAL1 thermodynamic
Desuperheater calculation
Name & sign Unit Result Name & sign Unit Result
Desuperhe
Desuperheater ating by Spraying water
℃ 170
type water temperature T
spray
Total water sprayed by
T/h 7.2
desuperheater △D
Water sprayed by
T/h 3.5
desuperheater I △D
Steam temperature at
Steam temperature at
℃ 408 desuperheater I outlet ℃ 387
desuperheater I inlet t1
t2
Water sprayed by
T/h 3.7
desuperheater II △D
Steam temperature at Steam temperature at
℃ 452 ℃ 427
desuperheater II inlet t1 desuperheater II outlet t2
Heat transfer parts calculation result collection
Wall High Low
Cyclone
Name & sign Unit Wing wall enclosure temperature temperature
separator
superheater superheater superheater
Tube size mm φ42×7 φ42×6 φ42×5 φ42×6 φ42×5
Flue gas inlet
℃ / 883 866 820 668
temperature
Flue gas outlet
℃ / 866 / 667 575
temperature
Working medium
inlet ℃ 387 319 344 427 369
temperature
Working medium
outlet ℃ 452 344 369 510 408
temperature
Flue gas average
m/s / / / 11.7 10.2
velocity
Primary Secondary
Economize Economizer Economize Economizer
Name & sign Unit ducting air ducting air
r IV III r II I
preheater preheater
Tube size mm φ32×4 φ32×4 φ32×4 φ32×4 φ40×1.5 φ40×1.5
Flue gas inlet ℃ 575 465 388 312 259 /
temperature
Flue gas outlet ℃ 465 388 312 259 / 135
temperature
Working medium ℃ 239 214 188 170 30 30
inlet
temperature
Working medium ℃ 274 239 214 188 185 185
outlet
temperature
Flue gas average m/s 8.3 8.0 7.8 6.8 7.5 7.1
velocity
Table 4. Flue Gas and Air Resistance Collection Table
Loop-seal
device
Secondary
Primary air Flue gas high
Coal rank Unit air
resistance resistance pressure
resistance
air
resistance
Coal 1 Pa 14000 9500 4000
Coal 2 Pa 13500 9000 3700 48000
Coal 3 Pa 13500 9000 3700
Table 5. Steam water Resistance Collection Table
12050A9~A12Charge aperture2010Subtotal:14060Total:435190