Вы находитесь на странице: 1из 7

Managed Pressure Drilling

Aerated fluids drilling used in Philippines field


to minimize well interference while infill drilling
By Manuel S Ogena, Romerico C Gonzales, Given the fact that LGPF has been pro- to initiate steam discharge. It is believed
PNOC - EDC; Felbert Palao, Julmar Shaun ducing since 1983, most of the replace- that the production zones may have been
Toralde, Elias Bayking Jr, Weatherford ment wells are drilled infill, which means blocked during the cementing opera-
International they are located within the same res- tions while drilling an adjacent well,
ervoir and near existing wells. Drilling 313D. Drilling of well 313D was done
Three wells in the Leyte problems encountered related to inter- from 3 November 2003 to 22 April 2004.
Geothermal Production Field (LGPF) ference with actively producing wells A permeable fault intersecting well 307D
were drilled by the Philippine National prompted PNOC-EDC to experiment with was encountered while drilling the new
Oil Company – Energy Development the utilization of aerated fluids. Using well from 1,060 m until a total loss of
Corporation (PNOC-EDC) and Weatherford underbalanced systems, circulation was encountered at 1,100 m.
Weatherford International using aer- three new wells were drilled in LGPF. A series of cement plugs were conducted
ated drilling fluids. The aim was to to seal off the loss zones from 14-17
determine the technology’s feasibility in Well interference during infill drilling January 2004. This correlated with the
terms of minimizing, if not eliminating, was observed when two wells being sudden loss of steam flow (11 kg/s) from
well interference while conducting infill drilled in LGPF adversely affected the a steam separator in the area connected
drilling within shallow to intermediate performance of two actively producing to well 307D during the said dates.
depths in an actively producing two- wells in their immediate vicinity. The
phase zone of a geothermal reservoir. drilling of well 313D affected 307D, while The drilling of another well, 419D, in
The results of a well interference moni- drilling operations for well 419D inter- the same field but in the Upper Mahiao
toring program reveal that aerated fluids fered with the performance of well 409D. sector, began on 31 January 2004. The
drilling technology is capable of minimiz- Wells 313D and 307D are located in the well was programmed to a total depth
ing well interference during infill drilling Malitbog-South Sambaloran sector, while of 2,900 m MD/2,663 m VD, but the well
in a geothermal reservoir. wells 409D and 419D are in the Upper encountered drilling interference with
Mahiao sector of LGPF. a nearby well, 409D, which resulted in
its cessation of discharge, while blind
Introduction Well 307D was a production well that drilling in the 12 ¼-in. section of the hole
The LGPF is the largest wet steam field was producing 6 MWe as of 28 July starting from 823 m. The drilling of well
in the world and home to the world’s 2003. However, in May 2004, the well 419D was then prematurely terminated
single largest power station — the 232.5 was found not producing anymore and at a depth of 1,269 m.
MW Malitbog geothermal power plant. could no longer develop steam pressure

Table
Table1:1.Typical
Typicalwell
Wellprofile
Profile of wells ininLGPF
of Wells the Leyte Geothermal
(Source: Production Field (LGPF) in the Pilippines.
PNOC-EDC)

Hole Size
26” 17-1/2” 12-1/4” 8-1/2”
Measured depth 0-110 m 110-450 m 450-1500 m 1200-300 m
Casing O.D. 20” 13-3/8” 9-5/8” 7-5/8”
Casing I.D. 19.124” 12.415” 8.681” 6.875”
Casing type Surface Anchor Production Slotted liner
Approximate temperature 50-150 °C 80-200 °C 110-220 °C 220-350 °C
Static formation 60-100 °C 60-110 °C 60-150 °C 80-220 °C
bottomhole circulation
temperature
Average drift angle 0-2.5° 0-2.5° 30-45° 30-45°
Likely contaminants Cement, acid minerals, Cement, oxygen, acid Cement, oxygen, acid Cement, oxygen, acid
reactive clays such as minerals, reactive clays minerals, reactive clays minerals, reactive clays
smectite, illite, etc. such as smectite, illite, such as smectite, illite, such as smectite, illite,
etc. Recycled sump water etc. Recycled sump etc. Recycled sump
water, geothermal fluids water, geothermal fluids
with chlorides of 5000 to with chlorides of 5000 to
8000 ppm. 8000 ppm.
Remarks Losses, soft with Losses, above water table Losses, above water table Losses, above water table
boulders, above water at about 500 m. Induced at about 500 m. Induced at about 500 m. Induced
table. Steam infrequent draft cooling tower on for draft cooling tower on for draft cooling tower on for
drilling. Steam infrequent drilling. Steam kicks likely drilling, with returns.
Drilling blind with water
and occasional mud slugs
if recovery is impossible.
Steam kicks likely. No
cement except at 9-5/8”
casing shoe.

76 March/April 2007 D r i l l i n g contractor


Underbalanced Operations

Table2:2.Location
Table Locationand
anddrilling
Drilling data
Data for
for the
the LGPF
LGPFWells
wellsDrilled
drilledwith
withAerated
aeratedFluids
fluids. 1. Throttle/choke valve. The use of a
throttle valve to control the flow of liq-
Well 422D Well 315D Well 421D uids from the hole effectively exercised
Location Upper Mahiao South Sambaloran Upper Mahiao a measure of control on the bottomhole
Pad 406 300B 406 pressure. Previous air drilling projects
Elevation 571.58 m AMSL 824.69m AMSL 571.58 m AMSL did not use a choke or throttle valve.
Wellhead Coordinates 1,236,048.88 m N 1,234,412.00 m N 1,236,055.56 m N
460,588.42 m E 461,925.00 m E 460,549.70 m E 2. Greater compression capacity. Three
12-1/4” section compressors (1,500 cfm / 200 psig) were
Aug 07 to Sep 05, Oct 15 to Nov 04, Nov 29 to Dec 31, used in this project, as opposed to previ-
Date Drilled
2005 2005 2005 ous projects that used two (1,600 cfm /
Drilling time (h) 145 130 183.5 125 psi); the number and capacity of the
Depth Drilled (m) 997 752 1025 boosters used were the same as before.
Depth Range 654-1651 m 906-1705m 682-1707 m
Average Penetration 3. Computerization. The use of downhole
6.90 5.79 5.59 well-profiling software and computers to
Rate (m/h)
Bits Used 9 9 7 model the system and isolate the operat-
Mud/Water Pumping ing envelope at which the hole can be
300-810 200-550 300-850 drilled underbalanced.
Range (gpm)
Air Flow Range (scfm) 1000-3200 400-3200 550-3600
4. String float subs. There is no mention
Temperature Range
10-154 18-66 11-204 of the use of string float subs in previ-
(°C)
8-1/2” section ous drilling operations involving aerated
Sep 13 to Oct 03, Nov 13 to Nov 21, fluids. The use of this device allows for
Date Drilled - faster connections as pressure within
2005 2005
Drilling time (h) 189 17 - the string no longer needs to be bled off.
Depth Drilled (m) 940 46 -
Depth Range 1650-2590 m 1814-1860m Aerated Fluids Drilling
Average Penetration
5 2.70 - Operation
Rate (m/h)
Bits Used 13 4 - Underbalanced drilling, as defined by
Mud/Water Pumping the International Association of Drilling
200-486 180-550 - Contractors, is “drilling with the hydro-
Range
Air Flow Range 1400-3500 2000-3200 - static head of the drilling fluid intention-
Temperature Range 10-120 20-41 - ally designed to be lower than the pres-
sure of the formations being drilled.”
In geothermal drilling in the Philippines, mechanical rig, was used to drill well This can be induced by adding natural
when zones of total lost circulation 315D. The drilling depth range of the two gas, nitrogen or air to the liquid phase of
are encountered, the use of mud is rigs is 8,000–12,000 ft. The rigs used a 13 the drilling fluid.
stopped, and blind drilling with water 5
/8-in. x 3000 psi double ram and a 13 /8
5
Underbalanced drilling techniques are
is conducted in order to save on mud -in. x 3000 psi annular BOP to meet the
commonly divided into three categories:
and chemical additives. Now that blind anticipated pressure requirement.
drilling with water, which was previ- 1. Performance drilling: the application
ously deemed more economical than The equipment for aerated fluids geo-
of air, mist or foam drilling fluid systems
drilling with aerated fluids, was caus- thermal drilling consisted of three 1,500
to drill subhydrostatically. It aims to
ing adverse economic consequences cfm / 200 psig Quincy QSS primary air
reduce drilling costs by increasing the
through well interference, drilling with compressors; two 1,500 psig Joy WB-
rate of penetration.
aerated fluids was again viewed as a 12 two-stage air pressure boosters;
substitute. one 1,500 psig meter run; one 2,000 psi 2. Managed pressure drilling: drilling
Barton dry-flow recorder; one 50-500°F with a closed, pressurizable fluid system
The wells that were drilled during the Barton temperature recorder; one 1,500 to more precisely control the wellbore
tenure of the PNOC-EDC–Weatherford psig Gardner-Denver single-acting tri- pressure profile. It intends to ascertain
Aerated Fluids Drilling Project were plex mist pump; two 1,500 psig Texsteam the downhole pressure environment lim-
422D, 315D and 421D, in this order. Model 5007 chemical injection pumps; its and to manage the annular hydraulic
Wells 422D and 421D were drilled in one set of 2,000 psig main air supply line pressure profile accordingly.
Pad 406 of the Upper Mahiao sector, piping; one 2,000 psig floor manifold; one
near the affected well 409D, while 315D 500 psig Williams Model 9200 geothermal 3. Underbalanced reservoir drilling: drill-
is located in Pad 300B of the Malitbog- rotating head; one banjo box or flow tee; ing with the borehole pressure designed
South Sambaloran sector, in the same one 10-in. emergency shut-down (ESD) and maintained below reservoir pressure
pad where 313D drilling caused massive valve; one 10-in. throttle valve; and one to intentionally invite fluid influx. It is
interference with other wells. air/fluid/steam separator. intended to increase reservoir productiv-
ity by reducing formation damage and
Rigs 8 and 12 of PNOC-EDC were used Compared with previous aerated drilling enhancing reservoir characterization.
for the project. Rig 8, a Continental operations conducted in the country, the
Emsco D-3 electric rig, was used to drill equipment used in the project differs in Since the main objective of the project was
wells 422D and 421D. Rig 12, which is the following points: to determine if the use of aerated drill-
a Romanian Model TF-25 single-drum ing fluids can minimize interference with

D r i l l i n g contractor March/April 2007 77


Managed Pressure Drilling

adjacent wells during drilling, the tech- drilling reached the deeper sections of amount of TSS found will be indicative
niques employed by Weatherford for the the wells. A similar technique was previ- of the level of interference being experi-
project were focused on underbalanced ously used for drilling well Palinpinon- enced in adjacent wells to the hole being
reservoir drilling and managed pressure 18D. In this well, aerated mud was used drilled.
drilling. Also, unlike the previous aerated while drilling from 5,050 ft to 9,175 ft,
fluids drilling projects, it was not focused and aerated water was utilized from Results
on performance drilling. Operational pro- 9,175 ft to 10,730 ft.
cedures and decisions were concentrated Well 422D, with an elevation of 571.78
on intentionally inviting fluid influx into A corrosion control program was imple- m above mean sea level (AMSL) and
the well being drilled and keeping drilling mented to minimize the degradation of located in pad 406 in Upper Mahiao, was
fluids away from the other wells adjacent drilling materials and equipment as a the first of three wells drilled using aer-
to it. In fact, drilling was restricted to peri- consequence of the use of aerated fluids. ated drilling fluids technology in LGPF.
ods when circulation was present. Also, It involved the treatment of the drilling Drilling using aerated fluids for this well
when circulation losses were encountered, fluid used and the injection of corrosion started at the 12 ¼-in. section until the
operational parameters were immediately inhibition chemicals into the system. The target depth of the 8 ½-in. section. The
adjusted to regain circulation as soon target corrosion rate of the program, operation was completed within 65 days.
as possible prior to drilling ahead. The as indicated by corrosion ring coupons Total actual aerated drilling time was 32
improvement in the rate of penetration placed in the cross-over heavyweight days.
was, therefore, not prioritized. Managed drillpipe and in the kelly saver sub, was
< 2 lb/sq ft/year. Most of the 12 ¼-in. section was drilled
pressure drilling techniques were also with full returns, except for an incident
used, as information pertinent to drilling involving a TLC and where pipe got
parameters was consistently gathered and Well Interference stuck, left a fish-in-the-hole and required
processed using well-profiling software to Monitoring a sidetrack. Drilling for this section
periodically model the downhole pressure covered a depth range of 654 m to 1,651
environment. PNOC-EDC instituted a well interfer-
ence monitoring program for each of the m, or 997 m, and required nine bits.
It is interesting to note that the previ- three wells drilled using aerated fluids Average penetration rate was 6.90 m/hr.
ous use of aerated fluids limited it to in order to determine whether the use It should be noted that this figure, along
drilling the 8 ½-in. section of a well. In of aerated drilling has minimized, if not with other data in this section involving
LGPF, particularly for wells 422D and eliminated, interference within the shal- penetration rate, is inclusive of periods
315D, aerated fluids were used to drill low to intermediate depths of the res- of drilling conducted not using aerated
the 12 ¼-in. and 8 ½-in. sections of the ervoir. The objective was to monitor for drilling. The rate of mud/water pumping
hole, while with well 421D, drilling with breakthroughs of drilling fluids/materials was from 300 to 810 gpm, and air flow
air was limited to the 12 ¼-in. section of that may be detrimental to production from 1000-3200 scfm, with the tempera-
the hole. This marks the first time that wells surrounding the well being drilled. ture ranging from 10-154 °C.
aerated fluids drilling technology was The 8 ½-in. section was drilled with
utilized to drill the 12 ¼-in. section of full returns to target depth. All of the
a geothermal well in the country. This The parameters that were monitored on planned target geological structures of
was done in consideration of the fact the surrounding production wells were: this well were encountered. However,
that interference with other wells was (1) total suspended solids (TSS) and the planned depth of 2,700 m was not
previously encountered while drilling in color of samples, (2) wellhead pressure reached because PNOC-EDC decided to
these depths. The upper sections of the (WHP) and (3) steamflow of the separa- TD the well when tight hole and a sus-
well, the 26-in. and 17 ½-in. sections, tor vessels where the wells were hooked pected collapsing formation was encoun-
were drilled using conventional drilling up. The collection of samples was start- tered at 2,590 m. Drilling for this section
methods. ed at twice a week during re-entry of the covered a depth range of 1,650-2,590 m,
As to the type of fluids used during drill- hole being drilled. Once a partial loss of or 940 m. Thirteen bits were used on
ing, aerated mud was first used to drill circulation (PLC) or total loss of circula- this section, two of which were worn out
the upper sections of the wells. A shift tion (TLC) was experienced, sample col- immediately as the drill string casing
was later made to aerated water when lection was increased to once a day. The protectors were falling off, thus wearing

78 March/April 2007 D r i l l i n g contractor


Underbalanced Operations

the bit severely. The average penetration m to 1,577 m. However, cuttings were lift the cuttings to the surface.
rate was 5 m/hr. The rate of mud/water observed in a nearby production well, so
pumping was from 200 to 486 gpm, blind drilling was immediately stopped. Well 421D
and air flow from 1400 to 3,500 scfm. A depth range of 906-1,705m, or 752 m,
Temperature had a minimum of 10°C and was covered for this section, requiring Well 421D, which is located near well
a maximum of 120°C. nine bits. Average penetration rate is 422D, was the last of the three wells.
5.79 m/hr. Mud/water pumping ranged For this well, aerated fluids drilling was
One of the lessons learned after drilling from 200 to 550 gpm, and air flow from confined to the 12 ¼-in. section. Aerated
well 422D involved the fact that circula- 400 to 3200 scfm. Compared with the fluid drilling operation was completed
tion must be maintained during drilling other two wells drilled using aerated after 39 days. The entire 12 ¼-in. section
to minimize the chances of having the fluids in the area, 315D was cold, with a was drilled with full returns.
pipe getting stuck. If circulation losses temperature range of only 18-66°C.
are encountered, full circulation should All of the planned target geological
be regained before drilling ahead. This Aerated fluid drilling was used to assist structures in the 12 ¼-in. section of the
can be accomplished by promptly adjust- in drilling through a portion of the 8 ½- hole, including a number of unexpected
ing the air and water injection param- in. section from 1,814 m until a massive drilling breaks, were encountered. These
eters with respect to the behavior of the loss zone was encountered at 1,860 m. geological structures brought about
well. While drilling the 8 ½-in. section, While drilling this section of the hole, a momentary partial, and sometimes total,
circulation was regained by starting jet sub was installed at 650 m from the loss of circulation, but circulation was
with a low mud/water pumping rate (300 surface to improve the lifting of cuttings. immediately restored after adjustments
gpm) and a high air flow rate (3,300 Weatherford was released when a major were made to aerated drilling param-
scfm) and subsequently increasing the loss zone was encountered at 1,860 m. eters. Drilling this section covered the
water-pumping rate once circulation was The drilling of this section registered depth range of 682-1,707 m or a depth
established to keep the bit cool. a penetration rate of 2.70 m/hr and drilled of 1,025 m at a rate of 5.59 m/hr
required four bits. Mud/water pumping and requiring seven bits. Mud or water
It was also realized that, based on the ranged from 180 to 550 gpm, and air flow pumping rate ranged from 300-850 gpm,
formation pressure profile and the soft- from 2,000-3,200 scfm. The temperature while air flow fluctuated in between
ware-calculated circulating pressure, range at this section was lower, pegged the broad range of 550-3,600 scfm. The
422D was drilled mostly at a slightly at 20-41°C. temperature of this well was high, the
overbalanced state. When drilling under- highest of the three wells drilled with air,
balanced in well 422D, problems with Drilling well 315D revealed that drilling with its range pegged at 11-204 °C.
high-temperature returns and well kicks wells with low formation pressure at
were encountered. Drilling slightly over- high elevation would require additional With the elevated temperature levels of
balanced minimized this problem. Lastly, compression capacity. At an elevation well 421D, the following lessons were
the BOP stack must be aligned with the of 824 m AMSL, the maximum output learned on how to drill using aerated flu-
crown block before aerated fluid drilling of the air compression package was ids in geothermal wells like it.
starts in order to maximize the life of the only 3,200 scfm. However, software First, that the use of controlled over-
stripper rubbers. A total of 12 stripper computations revealed that more than balanced drilling during appropriate
rubbers were worn out during the course 3,200 scfm of air was needed to drill the conditions, aside from underbalanced
of drilling this well because of this mis- deeper portion of the 12 ¼-in. section of drilling, can be utilized to keep rapid
alignment. well 315D using the minimum required temperature spikes and well kicks at
vertical velocity to transport cuttings bay, especially in multi-feed zones,
Well 315D (150 ft/min). Increasing the water rate thereby allowing drilling operations to
to increase velocity would result in proceed continuously. Restricting drilling
Well 315D, with an elevation of 824.69 loss of circulation due to low forma-
m AMSL and located in Pad 300B of to periods when circulation was pres-
tion pressure. Using 3,200 scfm and the ent also helped to ensure that drilling
South Sambaloran, was the second well. maximum water rate (before circulation
Aerated fluids drilling was utilized for problems were minimized. However,
loss occurs) was not enough to lift the problems were brought about by the con-
drilling the entire 12 ¼-in. section, but cuttings.
plans to drill the entire 8 ½-in. section of stant fluctuation in the performance of
315D with aerated fluid were canceled, This deficiency was compensated by the rig mud pumps, causing the constant
and drilling continued using blind drill- using high-viscosity mud sweeps every- re-adjustment of other aerated drill-
ing. However, aerated fluids were briefly time half of the length of the kelly has ing parameters and making it difficult
utilized to drill the 8 ½-in. section when been drilled. However this method to accurately tune them to bring about
the drill string got stuck while blind drill- involved additional drilling time since underbalanced, balanced or overbal-
ing. Weatherford was released when a circulation is momentarily lost when cir- anced conditions.
major loss zone was encountered. The culating out the sweep, and drilling must When drilling wells in areas with
aerated fluid drilling operation was com- stop until the sweep arrives at the sur- proven high steam output, it is neces-
pleted within 51 days. Total actual aer- face. The addition of a fourth compres- sary to have accurate and dependable
ated drilling time was 28 days. sor should be considered when aerated parameter values, especially on mud/
fluids drilling is again utilized in a well water pumping rates, as it exercises a
The entire 12 ¼-in. section was drilled with similar wellhead elevation and for-
with full returns, and the planned target vital role in the balancing act between
mation pressure. The same can be said maintaining circulation and controlling
depth of the 12 ¼-in. section of this well for the 8 ½-in. section, where more than
was attained. PNOC-EDC experimented temperature. Also, the use of cold fresh
3,200 scfm of air was required, together water, instead of fluids coming from
with drilling ahead blind in this sec- with a sufficient water pumping rate, to
tion and was able to drill from 1,530 the active tanks, for a calibrated period

D r i l l i n g contractor March/April 2007 79


Managed Pressure Drilling Figure 4. Well 422D Well Interference Monitoring Results (Source: PNOC-EDC)

of time, is useful in staving off sharp


increases in temperature. 500 1 ACS Sidetrack
Finally, it is more time-efficient, espe- 2 645m 1202m
→TLC
DB
cially in areas where temperature is at 1000 4
3 56
an elevated level, to address tempera- LN
7
1500 TOF 8 9
ture concerns by lowering the air flow Depth Stuck 1270m PCS
rate after making a connection, in order (mRKB) BC Pipe 1651m
2000
to accelerate the process of regaining
circulation, and by immediately increas-
2500
ing mud/water pumping values during DB - Dakung Bukid Fault
circulation for returns after kelly down, LN - Litid North Fault, BC - Balabag C Fault
3000
and, at times, quenching the well before
connection.
80
A number of other benefits for geother-

← BASELINE
mal drilling were also realized by the use
60
of aerated fluids to conduct underbal-
anced drilling. They include: (1) absence
of differential pressure pipe sticking, (2) 40
the availability of geological informa- TSS 413D
(mg/L)
tion from the steady supply of cuttings 20
brought about by constant circulation,
and (3) good hole cleaning.
0
406 412D 416D
Well Interference
-20
Monitoring
The results of the well interference -40
monitoring program of each of the three
7/31 8/10 8/20 8/30 9/09 9/19 9/29 10/09
wells drilled using aerated fluids, as
provided by PNOC-EDC, are presented Date
in this section. The graphs reflecting the
level of TSS detected in wells adjacent Figure 1: During the drilling of the 12 ¼-in. section of well 422D, spikes in the TSS
to wells 422D, 315D and 421D are pre- values were monitored in wells 406, 412D, 413D and 416D. The spikes generally
sented in Figures 1, 2 and 3. occurred in total losses of circulation or during cementing activities.
Wells 406, 412D, 413D and 416D were the
wells that were monitored for TSS val- the increase in the TSS values were tem- went back to normal after cementing and
ues when well 422D was drilled (Figure porary since cementing activities were after circulation was restored.
1). During the drilling of the 12 ¼-in. sec- immediately concluded and, more impor-
tantly, circulation losses were addressed It should also be noted that the control
tion of well 422D, which spans the depth and minimization of well interference
of 654-1,651 m, spikes in the TSS values through the use of aerated fluids. This is
because with aerated fluids drilling, good is very important in the 12 ¼-in. sec-
generally occurred when TLCs were tion of the hole, since this is the area
encountered (more particularly TLCs circulation is still possible even at the
loss zones, as opposed to drilling with- where massive well interference was
No. 3 to 8) or when cementing activities previously encountered when drilling
were conducted. It should be noted that out returns or blind drilling. TSS values
well 419D. As a precautionary measure,

80 March/April 2007 D r i l l i n g contractor


Figure 5. Well 315D Well Interference Monitoring Results (Source: PNOC-EDC) Underbalanced Operations

½-in. section of the hole, Weatherford


was only able to drill with air in this
SCS = 105.5m
500 section on 13-14 November 2005, after
ACS = 902m PLC which blind drilling was again employed.
1000 C TLC During the period that air drilling was
LG used, only well 305D was affected, and
Blind drlg w/
this was because there was total loss of
Depth 1500 sweeping at every
(mRKB) LS half kelly & kelly down circulation during drilling.
PCS = 1705m
2000 After 14 November, the effect of blind
drilling on TSS levels was immediately
K
2500 C - Caticlan LG - Litid Gamay felt, as values reached their highest lev-
1600
LS - Lower Sambaloran K - Kadluman els and all of the wells were immediately
Filtered Solids = white, flaky / globular and constantly affected by interference
515D
(Polymer?)
503 from the well being drilled. The results
302 of the well interference monitoring
1200
program therefore provide tangible
evidence of the importance of utilizing
305D aerated fluids drilling, as compared with
800 and instead of blind drilling, in order to
TSS 309D minimize well interference when drilling
(mg/L) wells infill.
400 304D
The results of the monitoring done for
well 421D are shown in Figure 3. Six
Baseline < 80 mg/L
wells were monitored when drilling was
0
513D 310D undertaken for well 421D. These are
slight to mid-murky wells 406 and 416D in Pad 406, wells 409
(like mud); blind drlg w/
slugging along Cat. & Litid Gamay
and 411D in Pad 409, and wells 412D
-400 and 414D in Pad 401. The results show
that during the course of aerated drilling
10
10 7
10 2

10 2
11 7
11 1

11
11 6
11

12 1
9/2
9/2
10

10

11 6

12 6
12
12 6

in the shallow to intermediate section


/02
/0
/1
/17
/2
/2
/0
/0
/11
/1
/21
/2
/01
/0
/1
/16
2
7

of the reservoir, interference with the


Date other wells has been minimal, restricted
only to periods when there was either
Figure 2: Since both the 12 ¼-in. and 8 ½-in. sections of well 315D utilized both
cement plugging (CP) or partial/total
aerated fluids drilling and blind drilling, this graph is most reflective of the effects loss of circulation (P/TLC). At times
that these two different drilling techniques have on the levels of TSS in the wells when there were TLCs or PLCs, however,
adjacent to the well being drilled. It shows that while drilling with air, TSS levels the interference that took place was
in wells 513D, 503, 515D, 302, 304D, 305D, 309D and 310D rose rapidly when at best temporary and momentary, as
there was total loss of circulation but soon returned to their baseline values. the subsequent results of the monitor-
When the well was drilled blind, and in the absence of circulation losses, the TSS ing show that the amount of TSS in the
values of adjacent wells spiked and continued to increase. affected wells immediately went down
and returned to baseline levels.
PNOC-EDC has increased the space or alternately utilized both aerated fluids
Besides, of the six wells being moni-
radius between wells to more than the drilling and blind drilling, this graph is
tored, only three wells were affected,
previous value of 200 m. Also, when most reflective of the effects that these
particularly wells 409, 411D, 416D, and
cementing is performed during drilling two different drilling techniques have on
only for very short periods of time. It
operations, certain production wells are the levels of TSS in the wells adjacent to
should be pointed out that four of the six
shut momentarily to avoid damage. The the well being drilled. It shows that while
spikes seen in the graph, those before
spikes observed during the drilling of drilling well 315D with air, TSS levels
15 December, occurred during cement
the 8 ½-in. hole using aerated foam that rose rapidly when there was total loss
plugging.
do not coincide with either cementing of circulation, more particularly during
or loss of circulation are said to have 26-28 October 2005, but soon returned to Furthermore, the fact that a major part
been caused by fine cuttings that were their baseline values. of the 12 ¼-in. section of 421D was
transported during circulation losses. No drilled at a state of “controlled overbal-
permanent damage was found in any of However, when the well was drilled blind
ance” at times does not reflect or appear
the wells that were monitored after the from 29-31 October 2005, and in the
in the graph, providing evidence that the
drilling of well 422D. absence of circulation losses, the TSS
practice of this technique does not inter-
values of adjacent wells spiked and con-
fere with adjacent wells. It also supports
When well 315D was drilled, the produc- tinued to increase, particularly for wells
the contention that the well does not
tion wells monitored for interference 503 and 515D. In fact, interference with
have to be underbalanced at all times
were 513D, 503, 515D, 302, 304D, 305D, well 304D was evident when PNOC-EDC
to accomplish the minimization of well
309D and 310D, the results of which are decided to drill blind with water from
interference during infill drilling.
shown in Figure 2. Since both the 12 1,530 m to 1,577 m. Blind drilling was
¼-in. and 8 ½-in. sections of well 315D stopped when this occurred. For the 8 The use of “controlled overbalanced

D r i l l i n g contractor March/April 2007 81


M aFigure
nage P r421D
6.dWell e s sWell
ure D r i l l iMonitoring
Interference ng Results (Source: PNOC-EDC)
2. PNOC-EDC. www.energy.com.ph.

800
3. PNOC-EDC. Drilling Program for Well 422D.

TLC → 4. PNOC-EDC. Drilling Program for Well 315D.


700
56 789 10
11
12
13
14
15 5. PNOC-EDC. Drilling Program for Well 421D.
CP →
600 6. Rizo, T.M., Jr. and Cuenca, A.P.: “Aerated
Fluid Drilling Observations in Geothermal
Operation in Luzon, Philippines,” SPE 12455,
500
5th Offshore Southeast Asia Conference and
411D
TSS 409 Exhibition, World Trade Center, Singapore,
400 21-24 February 1984. Pages 14-81 to 14-96.
(mg/L)
7. PNOC-EDC. “PN-18D Drilling Report.”
300
8. PNOC-EDC. “Well 307D Workover 2 Final
200 Drilling Report.”
412D
9. PNOC-EDC. “Well 313D BH Final Drilling
Baseline 414D Report.”
100
406 416D
10. PNOC-EDC. “Well 419D Final Drilling
0 Report.”
11
11 1

11 5
11

12

12 3
12 5

12 3
12 5
11 3

12
12
12
12
12

12 1

12 7
12 9
12 1
11. PNOC-EDC. “Aerated Fluids Drilling
/2
/2
/2
/2 7
/2 9
/1
/3
/5
/7
/9
/1
/1
/1
/1
/1
/2
/2
/2
/2 7
Services Requirement for PNOC-EDC
Geothermal Projects (Contract No. 03-133)
Date Technical Specifications.”
Figure 3: Monitoring for well 421D shows that during the course of aerated drilling 12. PNOC-EDC. “Well Summary of Puhagan
in the shallow to intermediate section of the reservoir, interference with the other 18-D.”
wells was minimal, restricted only to periods when there was either cement plug- 13. PNOC-EDC. “In-house Addendum to
ging or partial/total loss of circulation. Puhagan 18-D Well Report.”

14. Weatherford Foundation Training


drilling,” aside from underbalanced Using aerated fluids drilling technology, Program. “Introduction to Underbalanced
drilling, in appropriate conditions can three new wells were drilled infill at Drilling.”
contribute greatly in gaining control over LGPF to assess whether the technology
15. PNOC-EDC. “Well Monitoring Program for
the temperature fluctuation of the well can be employed as a solution to the
Well 421D.”
during the course of drilling, especially problem of well interference during infill
in multi-feed zones, and especially with drilling. An approach that combined This article is based on a presentation made
high-temperature or “hot” wells. underbalanced reservoir drilling and at the 2006 SPE/IADC Managed Pressure
Drilling and Underbalanced Operations
managed pressure drilling techniques
In relation to the results of the well inter- Conference & Exhibition, 28-29 March 2006,
was used for the project, with adjust- Galveston, Texas.
ference monitoring program, it should ments and corrections made to the
be emphasized that during and after the procedures employed as circumstances
drilling of three wells in LGPF using aer- required. The results achieved with the
ated drilling fluids, no production well in drilling of wells 422D, 315D and 421D in
the Leyte Geothermal Production Field LGPF, especially that from the well inter-
has “ceased to discharge” or “died” as ference monitoring program conducted
a consequence of aerated fluids drilling by PNOC-EDC, reveal that aerated fluids
activities performed in areas adjacent to drilling technology, by establishing good
these wells. circulation during drilling even at loss
zones, is capable of minimizing well
Conclusion interference during infill drilling.
Aerated fluids drilling, though not new in Compared with the previous practice of
the Philippines, was recently employed using blind drilling and cement plugging of
to determine if well interference can be loss zones, and even discounting the other
minimized, if not eliminated, while drill- benefits that can be derived from drilling
ing within shallow to intermediate depth underbalanced, aerated fluids drilling has
of an actively producing two-phase zone the undeniable advantage of successfully
of a reservoir, more particularly a reser- allowing the drilling of new infill wells in
voir in the Leyte Geothermal Production the geothermal field without adversely
Field, Philippines. Infill drilling activities affecting actively producing ones.
of PNOC-EDC, the company managing
the geothermal field, which utilized blind
drilling and cement plugging of loss References
zones, have lately been adversely affect- 1. “Full Steam Ahead: Empowering The
ing production wells in the neighborhood Future.” Vincent S. Perez, Secretary, PNOC-EDC
Department of Energy, Philippines. Keynote
of the well being drilled. Speech delivered at the World Geothermal This map shows the location of the Leyte
Congress, Antalya, Turkey, 24 April 2005. Geothermal Production Field.

82 March/April 2007 D r i l l i n g contractor

Вам также может понравиться