Part - A
01. Project Title : Construction of Bangladesh-Myanmar Direct Link Road
(BMDRL - 1st Phase, Appendix-P)
03. Objectives of the Project : The main objective is to construct 2 km long Balukhali-
Gundum road within Bangladesh and 23 km long
Taungbro-Bawlibazar road within Myanmar for
establishing direct road link between Bangladesh and
Myanmar to promote trade, tourism and to facilitate
regional transport linkage. With this end in view the
Governments of the People’s Republic of Bangladesh and
the Union of Myanmar signed a Memorandum of
Understanding (MOU) for the Establishment of Road
Link between Myanmar & Bangladesh, on 4 April 2004.
Following the MOU, an agreement has been signed on
27th July 2007 to construct the road. This proposed road
would establish a direct road link between them.
04. Location of the Project : Location map attached a) Bangladesh – Cox’s Bazaar District
(Attach map, where necessary)
b) Myanmar – Rakhain Province
05. Estimated Cost of the Project : i. Total 19584.59
(Taka in Lacs) ii. GoB (F.E) 19584.59 (140)
iii. PA (RPA) -
06. Location wise cost break-down :
(Attached in Annexure-I)
07. Mode of Financing with source :
Project Aid
Other (GOB-F.E)
Economic Code
CONTASA, SAFE,
% of the
Imprest
DOSA,
Sl Code Description GOB Total Total
DPA
RPA
Cost
** Cost excalation and other items are supposed to be shown under 7980 economic group.
** The Cost estimate may vary after detailed survey and design.
2
10. Institutional arrangements for -
implementation/Execution
c) Attach proposed project : The project will be managed through a new management setup
management setup (As per deputed from RHD. Formation of new project management Set-up is
Annexure-II) Attached in Annexure-II and salary structure & requirement is stated
in Appendix-B.
a) If Yes, briefly narrate the : After completion the Bangladesh portion will be transferred to RHD
institutional arrangement and revenue budget for maintenance and the Myanmar portion will be
financial requirement for operation transferred to Myanmar Government for maintenance.
and maintenance.
3
Signature of Officer(s) responsible for the Preparation of the DPP with seal and date.
4
Part - B
[Project Details]
14. Background, Objectives, Rationale : Politically Bangladesh & Myanmar are two different countries. But
including linkages, Targets and the geographical pattern of Land at Gundum & Thaungbro is of
Outputs of the Project same nature. The construction of the proposed road will connect
Bangladesh & Myanmar while promoting trade & commerce as
well as developing Political friendship between the two countries in
particular & the region in general.
(Taka In Lac)
A. Bangladesh Portion
Economic
Item of Works Unit Qty Rate Amount
Code
Revenue Component 1167.49
4500 4501 Salary & Allowances for 460.49
project personnel
4800 4899 Other expenditure 707.00
6900 Acquisition of Land and 12.72
others properties
6901 Acquisition of Land Hector 2.12 6.00 12.72
7000 Construction of Works 809.15
7016 General & site facilities km 2.00 1.00 2.04
7021 Road embankment construction km 2.00 186.00 372.02
/ Earth cutting
7021 Construction of new flexible km 2.00 104.00 208.31
pavement
7026 Construction of RCC Box m 47.54 (7nos) 4.00 190.20
Culvert - 7 nos.
7041 Drainage structure / Retaining m 33.34 0.20 6.59
wall
7021 Road Appurtenance
Installation of Sign, Signal km 2.00 5.00 10.00
Installation of KM post & km 2.00 10.00 20.00
boundary pillar
Sub-Total (A) = 1989.36
B. Myanmar Portion
4800 Supply & Services 2150.85
4874 Cost for Consultancy services 2038.05
4801 Cost for traveling and 108.00
inspection of Task force
4883 Cost for remuneration of 4.80
member of PEC and TEC
6800 Acquisition of Assets/Purchase 320.00
6807 Project Vehicles, 4 Jeep, No 4.00 50.00 200.00
6807 5 Pick Up No 5.00 20.00 100.00
6807 Speed Boat No 1.00 20.00 20.00
6
7000 Civil Works 13216.69
7021 General & site facilities km 23.00 1.02 23.47
7021 Road embankment construction km 23.00 186.01 4278.21
/ Earth cutting
7021 Construction of new flexible km 23.00 104.15 2395.52
pavement
7026 Construction of RCC Bridge - m 222.46 5.00 1112.30
18 nos.
7026 Construction of PC Bridge - 3 m 318.90 8.93 2849.28
nos.
7026 Construction of RCC Box m 364.33 4.00 1457.62
Culvert - 121 nos.
7026 Drainage structure / Retaining m 2000.00 0.2 395.29
wall
7081 Protective work
Hill side protection m 1000.00 0.2 200.00
Toe side retaining wall m 800.00 0.2 160.00
7021 Road Appurtenance
Installation of Sign, Signal km 23.00 5.00 115.00
Installation of KM post & km 23.00 10.00 230.00
boundary pillar
7980 Capital Block Allocation & 1907.69
Miscellaneous Expenditure
7981 Survey, Investigation etc for km 110.00 LS 140.00
next 110 km
7981 Price contingency (5%) 883.84
7981 Physical contingency (5%) 883.84
Sub-Total (B = 17595.23
Total (A+B) = 19584.59
(ii) Women and children : Vulnerable group of people that includes women and children
will get better healthcare facilities and education. The women
will participate in the economic development of the country
due to increased economic opportunities.
(iv) Institutional productivity In both the countries institutional development in the sector
of trade, commerce & transport will be accelerated after the
completion of the proposed project.
26. Any other important details, : Best Technical and Economical Alternate has been selected.
technical or otherwise (e.g.
sustainability, governance)