Академический Документы
Профессиональный Документы
Культура Документы
I am often asked what the building owner’s options are when faced with a material breach of a ERNEST C. BROWN
construction contract and the Project is brought to a standstill. Smith Currie & Hancock, LLP
ecbrown@smithcurrie.com
I have been asked the same question by our general contractor clients where there is a subcon-
tractor in material default and the project schedule and budget is in jeopardy.
Often, this is accompanied by a contractor (or subcontractor) who is asking for more money to
complete the construction project. Of course, at times there are legitimate reasons for a contrac-
tor to stop work, ask for payment of claims or otherwise halt the work. For the purposes of this
paper, we will assume there are no legitimate reasons for the work stoppage.
The owner may be stuck with the possibility of paying a good deal more than the original con-
tract, or risking that the contractor will simply walk away. If he walks away, you will need to find
another contractor who may well charge you a remaining amount that will exceed your original
budget. And with many private contracts, and most subcontracts, there may not be a perfor-
mance or payment bond, leaving the owner (or general contractor) holding the bag for increased
project completion costs and a lawsuit to try to recover those costs from the owner.
A termination for fault almost always guarantees a protracted lawsuit. The owner wants their
money, and the contract will fight for their reputation and costs incurred to date.
As such, this is an outline of the typical problems and solutions that we consider in these situa-
tions – often called the most traumatic type of event on a project.
Let’s face it, contract terminations are significant legal events. If you wish to go down that path,
you need expert legal counsel. Anyone reading this should consider it to be background material
regarding contract disputes and termination issues and not specific legal guidance for your case.
www.navigant.com/construction
If you are considering termination of a constructor or subcontractor, I projects to small jobs, such as the license number of the contractor
think hiring a lawyer would be a good first step. These are a few of the (see item 2., above). But if it is a smaller residential remodel project
major issues to consider before going forward: (which in San Francisco could be a multi-million dollar effort), there
1. Please, carefully review your contract. Most standard construction are numerous provisions required in a home remodel project (for
contracts are quite specific about grounds for termination. If your some of these provisions, applicable in California, see
if it does not have any of the traditional boilerplate language that 6. In some cases, a contractor might give you a proposal, which
defines the typical relationship between an owner and contractor, both parties signed, but did not follow through with a formal
then the termination will likely be governed by prevailing case law contract. This is extremely bad practice… which the contractor’s
and specialized statutes. license board would almost certainly respond with a disciplinary
2. Consider which type of termination you might wish to follow. A investigation and fines, or worse.
typical termination for default provision allows you to take over the 7. In most instances, we then look to the construction contract for
materials and equipment, restart the project, then sue the original your remedies in the event of material default. Often, the contract
contractor for the increased costs to complete. has a formal termination clause, or 24 or 48 hour cure clause. In
some cases, the owner’s legal rights are a bit more vague than a
However, a termination for convenience clause would generally
traditional contract.
provide the contractor all their costs to date, as well as reasonable
profit and overhead on accomplished work. Some termination for 8. Whether you terminate or not at this point in the job, you need to
convenience clauses also provide for payment of future profits on first determine and then fully document that the contractor is in
work that is being taken from the contractor. So, know what type of material breach (or whatever the standard for triggering the default
clause you have and how to trigger the correct one! provisions of the contract).
As such, I also strongly suggested that you photograph, video and
In the Federal arena, and in many private contracts, the failure to
otherwise document the status of the physical condition of the
prove the termination was for default renders the termination one
property, the status of payments and materials on site, and the
for convenience, opening the gates to a substantial contractor cost-
overall condition of the property.
reimbursement claim.
It would be ideal that such photography be accomplished on the
3. See if the contractor is currently licensed. In one large airport
day that you actually send out the notice of default, as it would
project that I advised, the contractor for a major element of the
document the status upon termination.
project was not currently licensed due to a loss of their qualifying
person that they did not replace within the statutory period. The 9. Also, you should provide your insurance agent notice of the
lack of a license is an automatic ground for termination for default situation, so they can be sure you have appropriate insurance in
in most states. In fact, it can be a criminal offense for an owner place to protect your property (covering builder’s risk, rain damage,
(or general contractor) to continue employing an unlicensed vandalism, etc.).
subcontractor on the project. 10. You may also are exposed at the moment to large mechanics liens
4. Next, see if there is a performance or payment (labor and being filed by material suppliers and subcontractors, as well as
materials) bond on their work. If so, those provisions need to be builder themselves (for a general background on mechanics liens
strictly followed or you will exonerate the surety. and stop notice problems, see ConstructionLawyers.com and click
5. Does the contract comply with the contractor’s license board on Construction Law 101.
requirements. There are general requirements for large infrastructure
regulatory agency to seek fines or punishment. architect or engineer involved in the process. Their concurrence
is often required in many AIA and similar contracts preferred by
© 2012 Navigant Consulting, Inc. All rights reserved. Navigant Consulting is not a certified public accounting firm and does not provide audit, attest, or public accounting services. Navigant is a consulting firm
that does not practice architecture or engineering on design or construction projects in the United States.
See www.navigant.com/licensing for a complete listing of private investigator licenses.