CONCRETING PLAN
Date: 26-09-2018
Location: Car Dumper – Tunnel D – Top Slab
Concrete qty: 187.00m3
Estimated duration of pour: 7Hrs – (15:00 – 22:00)
Work will be carried out with no breaks. (During break, standby team will be present for masons
& helpers, and teams will work in shifts with no stoppage of work.)
Names and contact numbers for the following:
o Primary contact at the jobsite for person in charge of on-site workers
Name: Mr. Lokesh. Naik Phone#:624939928
Name: Mr. Someshwar. Dhumal Phone#:624935746
Name: Mr. Ajay Phone#:626264861
Name: Mr. Pachatan Phone#:626267148
o Quality Representative
Name: Mr. Lakshmaiah Chowdari V Phone#:624935749
Name: Mr. Prashant Phone#:626267146
Equipments:
1. Boom Placer – 2No’s (One on Standby)
2. Transit mixers – 5No’s (Capacity – 6m3 each)
3. Needle vibrators – 6No’s (40mm –3No’s & 60mm – 3No’s)
4. Concrete Pump – 1No (Standby)
Manpower:
i. Engineer In charge – 1no’s
ii. Supervisors – 1no’s
BAUXITE EXPORT PROJECT, GUINEA - CC - 006
CONCRETING PLAN
Materials Required
i. Cement – 82MT (Available in stock)
ii. Aggregate – 10mm – 64.30m3(Available in stock)
20mm – 67.10m3(Available in stock)
iii. Crushed Sand – 77m3(Available in stock)
Stages of Concreting
Estimated
CONCRETE No of Millers
SL.NO STAGES LENGTH Duration of
QTY(m3) Required
Pour
1 I 5 24.65 1 4
2 II 5 24.65 1 4
3 III 5 24.65 1 4
4 IV 5 24.65 1 4
5 V 5 24.65 1 4
6 VI 5 24.65 1 4
7 VII 5 24.65 1 4
8 VIII 3.079 14.45 1 3
.
Planned location of Boom placer & Concrete Pump, if used:
On the East side of the CDV - Tunnel
Plan of movement and sequence of concrete trucks into and out of the lot:
Plan of movement of trucks marked in the drawing attached
Direction of pour – From South to North
BAUXITE EXPORT PROJECT, GUINEA - CC - 006
CONCRETING PLAN
.
Plan of action for notice to workers and trucks that entrance and exit of the Arbors:
At the entrance and exit Flagmen will be allotted and all working crew will be informed
regarding the direction of movement of trucks before the start of work.
Plan for the concrete truck washout location, and how each truck and the pump truck will
access the selected location:
Concrete trucks will be washed at Batching plant.
Truck movement & Access location of Pump truck is marked in the drawing attached.
Note: In case of rain, Concreting area will be covered with tarpaulin covers and concreting will
be continued.