Вы находитесь на странице: 1из 5

PLANILLA DE METRADOS

OBRA: I.E. ILO

PROPI: MUNICIPALIDAD DISTRITAL DE ILO


FECHA Feb-17

SUB PROYECTO SISTEMA MODULAR AULAS

ITEM PARTIDA/DESCRIPCION CANTIDAD TOTAL


UND Nº ELEM
IGUALES LARGO ANCHO ALTO PARCIAL

1.01 OBRAS DE CONCRETO SIMPLE

1.01.01 FALSO PISO DE 4" DE CONCRETO 9.81 Mpa (100 KG/CM2) CEM TIPO V

Eje 1 - 5 (A - B) M2 1 17.05 8.00 136.40

1.01.02 ENCOFRADO Y DESENCOFRADO NORMAL EN CIMIENTO CORRIDO

CC - 01 M2 2 2.78 0.70 3.89

CC - 02 M2 2 4.00 0.70 5.60

1.01.03 ENCOFRADO Y DESENCOFRADO SOBRECIMIENTO HASTA 0.30 MT

CC - 01 M2 2 2.78 0.40 2.22

CC - 02 M2 2 4.00 0.80 6.40

1.02 OBRAS DE CONCRETO ARMADO

1.02.01 ACERO PARA ZAP, VC, COL , VIG, ETC

1.02.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA VIGA DE CIMENTACION, SOBRECIMIENTO ARMADO

EJE A M2 2 10.18 0.80 16.28

EJE B M2 2 10.25 0.80 16.40

VC - 01 M2 2 20.85 0.60 25.02

VC - 02 M2 2 5.80 0.60 6.96

VC - 02 /M-1 M2 2 1.95 0.80 3.12

VC - 03 / M-2 M2 2 2.90 0.80 4.64

ZAP - 01 M2 1 26.80 0.50 13.40

ZAP - 02 M2 2 24.10 0.50 24.10

ZAP - 03 M2 1 26.30 0.50 13.15

1.02.03 ENCOFRADO Y DESENCOFRADO NORMAL PARA COLUMNAS, PLACAS,

CA - 1 M2 4 0.80 8.10 25.92

CA - 2 M2 7 1.00 8.10 56.70

CA - 3 M2 1 0.80 8.10 6.48

CA - 4 M2 8 0.80 8.10 51.84

CA - 5 M2 1 0.80 8.10 6.48

CA - 6 M2 1 0.80 8.10 6.48

CA - 7 M2 6 0.80 8.10 38.88

P - 01 M2 2 19.00 7.60 288.80

P - 02 M2 2 3.50 7.60 53.20

P - 03 M2 1 5.20 7.60 39.52

P - 04 M2 2 3.50 7.60 53.20

P - 05 M2 1 3.50 7.60 26.60

1.02.04 ENCOFRADO Y DESENCOFRADO NORMAL PARA VIGAS AEREAS, LOSAS ALIGERADA LOSA MACIZA

V - 101 M2 2 27.75 1.20 66.60

V - 102 M2 2 9.75 0.65 12.68

V - 103 M2 2 10.85 0.65 14.11

V - 104 M2 2 11.80 0.55 12.98

V - 105 M2 2 12.73 0.55 14.00

V -106 M2 2 7.50 0.65 9.75

LOSA ALIGERADA M2 2 17.05 7.50 255.75

LOSA MACIZA M2 2 12.73 2.25 57.29

1.02.05 ENCOFRADO Y DESENCOFRADO NORMAL ESCALERAS

1.03 ALBALIÑERIA

1.03.01 MUROS SOGA DE LADRILLO KK 9x14x24 C:M 1:4 X 1.5CM.

EJE A M2 1 1.45 2.05 2.97

EJE B M2 1 2.40 2.05 4.92

1.03.02 MUROS CABEZA LADRILLO KK 9x14x24 C:M 1:4 X 1.5CM.

EJE A M2 6 2.40 1.05 15.12

EJE B M2 2 2.40 1.05 5.04

1.04 TARRAJEO REVOQUES Y ENLUCIDOS

1.04.01 TARRAJEO PRIMARIO CON ACABADO CON CEMENTO-ARENA

1.04.02 TARRAJEO EN INTERIORES ACABADO CON CEMENTO-ARENA

P - 01 M2 2 8.00 7.60 121.60

P - 02 M2 2 1.25 7.60 19.00

P - 03 M2 1 2.20 7.60 16.72

P - 04 M2 2 1.25 7.60 19.00

P - 05 M2 1 1.25 7.60 9.50

1.04.03 TARRAJEO EN EXTERIORES ACABADO CON CEMENTO-ARENA

P - 01 M2 2 8.00 7.60 121.60

P - 02 M2 2 1.25 7.60 19.00

P - 03 M2 1 2.20 7.60 16.72

P - 04 M2 2 1.25 7.60 19.00

P - 05 M2 1 1.25 7.60 9.50

1.04.04 TARRAJEO DE COLUMNAS

CA - 1 M2 4 0.80 8.10 25.92

CA - 2 M2 7 1.00 8.10 56.70

CA - 3 M2 1 0.80 8.10 6.48

CA - 4 M2 8 0.80 8.10 51.84

CA - 5 M2 1 0.80 8.10 6.48

CA - 6 M2 1 0.80 8.10 6.48


PLANILLA DE METRADOS

OBRA: I.E. ILO

PROPI: MUNICIPALIDAD DISTRITAL DE ILO


FECHA Feb-17

SUB PROYECTO SISTEMA MODULAR AULAS

ITEM PARTIDA/DESCRIPCION CANTIDAD TOTAL


UND Nº ELEM
IGUALES LARGO ANCHO ALTO PARCIAL

CA - 7 M2 6 0.80 8.10 38.88

1.04.05 TARRAJEO DE VIGAS

V - 101 M2 2 27.75 1.20 66.60

V - 102 M2 2 9.75 0.65 12.68

V - 103 M2 2 10.85 0.65 14.11


V - 104 M2 2 11.80 0.55 12.98
V - 105 M2 2 12.73 0.55 14.00
V -106 M2 2 7.50 0.65 9.75

1.04.06 VESTIDURA DE DERRAMES ACABADO CON CEMENTO-ARENA

1.05 CIELORRASOS

1.05.01 CIELORRASOS CON MEZCLA DE CEMENTO-ARENA

LOSA ALIGERADA M2 2 17.05 7.50 255.75

LOSA MACIZA M2 2 12.73 2.25 57.29

1.06 PISOS Y PAVIMENTOS

1.06.01 CONTRAPISO E=50MM

Eje 1 - 5 (A - B) M2 2 17.05 8.00 272.80

1.06.02 PISO DE DE CEMENTO PULIDO E=0.10M

M2 3 17.05 8.00 409.20

1.06.03 PISO DE PORCELANATO DE COLOR

1.06.04 PISO DE LOSETA CERAMICA ANTIDESLIZANTE 30X30 CM.

1.05 OBRAS DE CONCRETO ARMADO

1.05.01 ZAPATAS

1.05.01.01 CONCRETO EN ZAPATAS Fc= 210 kg/cm2 M3 11.52

16 1.20 1.20 0.50 11.52

1.05.01.02 ACERO GRADO 60 EN ZAPATAS KG 446.38

1.05.02 VIGAS DE CIMENTACION

1.05.02.01 CONCRETO EN VIGAS DE CIMENTACIÓN Fc= 210 kg/cm2 M3 2.70

16 2.25 0.25 0.30 2.70

1.05.02.02 ENCOFRADO Y DESENCOFRADO DE VIGAS DE CIMENTACIÓN M2 21.60

16 2.25 2.00 0.30 21.60

1.05.02.03 ACERO GRADO 60 EN VIGAS DE CIMENTACIÓN KG 405.85

1.05.03 COLUMNAS

1.05.03.01 CONCRETO EN COLUMNAS Fc= 210 kg/cm2 M3 8.46

16 0.38 0.25 2.75 4.13


16 0.38 0.25 2.75 4.13
2 0.25 0.15 2.75 0.21

1.05.03.02 ENCOFRADO Y DESENCOFRADO DE COLUMNA M2 92.40

16 1.00 2.00 2.75 88.00


2 1.00 0.80 2.75 4.40

1.05.03.03 ACERO GRADO 60 EN COLUMNAS KG 1,404.85

1.05.04 VIGAS

1.05.04.01 CONCRETO EN VIGAS F'c= 210 kg/cm2 M3 19.97

16 3.05 0.25 0.90 10.98


16 3.05 0.13 0.63 4.00
16 0.25 0.35 2.30 3.22
2 0.15 0.65 5.80 1.13
2 0.25 0.40 2.55 0.51
1 0.25 0.20 2.55 0.13

1.05.04.02 ENCOFRADO Y DESENCOFRADO DE VIGA M2 195.42

16 3.05 2.05 1.00 100.04


16 3.05 1.39 1.00 67.83
16 0.25 4.95 1.00 19.80
2 0.15 12.25 1.00 3.68
2 0.25 5.50 1.00 2.75
1 0.25 5.30 1.00 1.33

1.05.04.03 ACERO GRADO 60 EN VIGAS KG 2,313.89

1.05.05 COLUMNETAS

1.05.05.01 CONCRETO EN COLUMNAS Fc= 175 kg/cm2 M3 3.94

42 0.25 0.15 2.50 3.94

1.05.05.02 ENCOFRADO Y DESENCOFRADO DE COLUMNETA M2 26.25

42 0.25 1.00 2.50 26.25

1.05.05.03 ACERO GRADO 60 EN COLUMNETAS KG 464.35

1.05.06 VIGUETAS

1.05.06.01 CONCRETO EN VIGUETAS Fc= 175 kg/cm2 M3 0.88

16 0.25 0.10 2.20 0.88


PLANILLA DE METRADOS

OBRA: I.E. ILO

PROPI: MUNICIPALIDAD DISTRITAL DE ILO


FECHA Feb-17

SUB PROYECTO SISTEMA MODULAR AULAS

ITEM PARTIDA/DESCRIPCION CANTIDAD TOTAL


UND Nº ELEM
IGUALES LARGO ANCHO ALTO PARCIAL

1.05.06.02 ENCOFRADO Y DESENCOFRADO DE VIGUETA M2 7.04

16 2.00 0.10 2.20 7.04

1.05.06.03 ACERO GRADO 60 EN VIGUETAS KG 81.21

1.05.07 LOSAS MACIZAS

1.05.07.01 CONCRETO EN LOSA ALIGERADAS Fc=210 Kg/cm2 M3 5.83

16 2.35 1.55 0.10 5.83

1.05.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS MACIZAS M2 58.28

16 2.35 1.55 1.00 58.28

1.05.07.03 ACERO ESTRUCTURAL TRABAJADO PARA LOSAS MACIZAS KG 1,580.45

1.05.08 LOSAS ALIGERADAS

1.05.08.01 CONCRETO EN LOSA ALIGERADAS Fc=210 Kg/cm2 M3 0.51

2 1.15 2.55 0.09 0.51

1.05.08.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS ALIGERADAS M2 5.87

2 1.15 2.55 1.00 5.87

1.05.08.03 LADRILLO PARA TECHO 0.30X0.30X0.15M UND 48.86

SH 2 1.15 2.55 8.33 48.86

1.05.08.04 ACERO ESTRUCTURAL TRABAJADO PARA LOSAS ALIGERADAS KG 16.97

1.06 ALBAÑILERIA

1.06.01 MURO DE SOGA LADRILLO KK(9X14X24) MEZCLA 1:4 X 1.5 CM M2 2 1.95 0.85 3.32 56.24

1 2.65 2.24 5.94

2 1.95 1.95 7.61

1 1.15 0.85 0.98

1 0.95 1.95 1.85

2 19.69

S.H. 1 1.95 1.20 2.34

2.55 2.45 6.25

2.75 2.45 6.74

15.33

PARAPETO S.H. 2 2.55 0.30 1.53

1.06.02 MURO DE CABEZA LADRILLO KK(9X14X24) M2 2 1.55 2.65 8.22 8.22

1.07 REVOQUES ENLUCIDOS Y MOLDURAS

1.07.01 TARRAJEO EN INTERIORES ACABADO CON CEMENTO ARENA M2 84.82 94.18

AULAS MURO VENTANAS ALTAS 2 6.30

2 5.43

2 6.30

AULAS MURO VENTANAS BAJAS 2 3.83

2 3.83

2 3.37

MURO CERRADO Y DE INGRESO A S.H. 2 7.53

2 5.82

42.41

SH INTERIOR AULAS 2 7.20 0.65 9.36

1.07.02 VESTIDURA DE DERRAMES EN PUERTAS , VENTANAS Y VANOS M2 18.30

V-1 2X3 5.58 0.15 5.02

V-2 2X2 31.12 0.15 4.67

V-3 2 3.88 0.15 1.17

V-4 2 5.78 0.15 1.74

V-5 2 3.10 0.15 0.93

P-1 2 5.20 0.15 1.56

P-2 2 5.60 0.15 1.68

P-3 2 5.10 0.15 1.53

18.30

1.07.03 TARRAJEO EN EXTERIORES CON CEMENTO ARENA M2 2 69.47 138.94

24.40 3.35 81.75

2.56 2.95 7.55

VANOS - 19.23

VANOS - 6.95

1.07.04 DERRAMES EXTERIORES M2 24 2.75 0.10 6.60 9.29

12 2.24 0.10 2.69

1.08 CIELORASOS

1.08.01 CIELO RASOS CON MEZCLA DE CEMENTO ARENA M2 AREA 39.00 39.00 61.20

VIGAS 2.52 8.00 18.15

CLARABOYA - 2.55 - 2.55

1.09 PISOS Y PAVIMENTOS

1.09.01 FALSO PISO DE 4" DE CONCRETO 1:10 M2 86.60

AULA 2 40.00 80.00

S.H. 2 2.75 1.20 6.60

1.09.02 PISO DE CERÁMICO DE COLOR 30X30 (aula y ss.hh.) M2 2 40.00 80.00 86.60

2 2.75 1.20 6.60

1.1 ZOCALOS

1.10.01 ZOCALO DE CERÁMICO 20X30 (S.H.) M2 2 7.40 1.30 19.24 20.00

1.11 CONTRAZÓCALO

1.11.01 CONTRAZÓCALO CERÁMICO H=10 cm M2 2 23.70 0.10 4.74 4.50

1.12 COBERTURAS

1.12.01 COBERTURA TEJA ANDINA M2 131.40

RADIO 3.43 74.00


PLANILLA DE METRADOS

OBRA: I.E. ILO

PROPI: MUNICIPALIDAD DISTRITAL DE ILO


FECHA Feb-17

SUB PROYECTO SISTEMA MODULAR AULAS

ITEM PARTIDA/DESCRIPCION CANTIDAD TOTAL


UND Nº ELEM
IGUALES LARGO ANCHO ALTO PARCIAL

- 0.90 8.30

2 65.70

1.12.02 COBERTURA LADRILLO PASTELERO ASENTADO CON MEZCLA M2 2.55 2.75 7.01 7.00

1.13 CARPINTERÍA DE MADERA

1.13.01 PUERTA DE TABLERO REBAJADO INC/CHAPA TRAVEX 444 Y PINTADO CON BARNIZ DOS UND 2.00

1.13.02 PUERTA CONTRAPLACADA H= 2.45 M INC/ CERRADURA POMO YALE BRONCE PINTADO UND 4.00

1.14 CARPINTERÍA METÁLICA

1.14.01 VENTANAS METÁLICA INC/ ACCESORIOS GLB 1.00

1.15 CERRAJERÍA

1.15.01 CERRADURA PARA PUERTA PRINCIPAL CON JALADOR TRAVEX 444 PZA 2 2.00

1.15.02 CERRADURA PUERTA BAÑO TIPO PERILLA POMO YALE BRONCE PZA 2 2.00 4.00

1.16 VIDRIOS, CRISTALES Y SIMILARES

1.16.01 VIDRIOS SEMIDOBLES INCOLORO CRUDO P2 314.26

VENTANAS P2 AULAS

3 13.44 2 3 80.64

2 39.72 2 2 158.88

1 6.52 2 13.04

1 22.12 2 44.24

1 6 2 12

VIDRIO PUERTA CONTRAPLACADA 2 2.73 5.46

1.17 PINTURA

1.17.01 PINTURA LATEX EN CIELO RASO 2 MANOS M2 AREA 39.00 39.00 61.20

VIGAS 2.52 8.00 18.15

CLARABOYA - 2.55 - 2.55

1.17.02 PINTURA EN MUROS EXTERIORES 2 MANOS M2 138.94

1.17.03 PINTURA EN MUROS INTERIORES 2 MANOS M2 112.48

1.18 VARIOS

1.18.01 JUNTAS CON TEKNOPORT Y JEBE MICROPOROSO M 126.00

1.18.02 PIZARRA PANEL DE FORMICA SOBRE MDF DE 1.2 X 2.80 INC/TICERO UND 2.00

1.19 INSTALACIONES SANITARIAS

1.19.01 DESAGUE Y VENTILACIÓN

1.19.01.01 SALIDA DE DESAGUE C/TUBERÍA PVC SAL 2" PTO 8.00

1.19.01.02 SALIDA DE DESAGUE C/TUBERÍA PVC SAL 4" PTO 4.00

1.19.01.03 TUBERIA PVC SAL 2" M 7.00

1.19.01.04 TUBERIA PVC SAL 4" M 10.00

1.19.01.05 SALIDAS DE PVC SAL PARA VENTILACION DE 2" PTO 1.00

1.19.01.06 REGISTRO ROSCADO DE BRONCE D=4" UND 2.00

1.19.01.07 SUMIDERO DE BRONCE D=2" PZA 2.00

1.19.01.08 CAJA DE REGISTRO DE DESAGUE DE 12"X24" UND 1.00

1.19.01.09 CONEXIÓN A LA RED INTERIOR DESAGUE UND 1.00

1.19.01.10 INSTALACIÓN RED AULAS A RED EXTRIOR DESAGUE GLB 1.00

1.19.02 SISTEMA DE AGUA FRÍA


1.19.02.01 SALIDA DE AGUA FRÍA CON TUB. PVC SAP 3/4 PTO 4.00

1.19.02.02 TUBERÍA PVC SAP 3/4" CL-10 M 5.00

1.19.02.03 TUBERÍA PVC SAP 1" CL-10 M 5.00

1.19.02.04 VALVULA DE COMPUERTA DE BRONCE 3/4" UND 2.00

1.19.02.05 NICHO PARA VALVULA UND 2.00

1.19.02.06 CAJA DE CONCRETO Y TAPA DE Fº Gº UND 2.00

1.19.02.07 CONEXIÓN A LA RED INTERIOR-AGUA UND 1.00

1.19.02.08 INSTALACIÓN RED AULAS A RED EXTRIOR DESAGUE GLB 1.00

1.19.02.09 PRUEBA DE AGUA GLB 1.00

1.19.03 APARATOS Y ACCESORIOS SANITARIOS

1.19.03.01 LAVATORIO TREBOL BLANCO PZA 2.00

1.19.03.02 INODORO TREBOL MODELO BABY C/ACCESORIOS DE TANQUE PZA 2.00

1.19.03.03 URINARIO TREBOL MODELO BAMBY PZA 2.00

1.19.03.04 PAPELERA DE LOSA BLANCA PZA 2.00

1.19.03.05 INSTALACIÓN DE APARATOS Y ACCESORIOS PZA 8.00

1.19.04 INSTALACIONES PLUVIALES

1.19.04.01 EVACUACIÓN DE AGUAS PLUVIALES

1.19.04.01.01 MONTANTES DE PVC-SAP 3" H=3.25M UND 7.00

1.21 INSTALACIONES ELECTRICAS

1.21.01 SALIDA DE INSTALACIONES

1.21.01.01 SALIDA PARA CENTRO DE LUZ TECHO PTO 10.00

1.21.01.02 SALIDA PARA CENTRO DE LUZ PARED PTO 7.00

1.21.01.03 SALIDA DE TOMACORRIENTE DOBLE CON PUESTA A TIERRA PTO 15.00

1.21.01.04 INTERRUPTOR UNIPOLAR SIMPLE PTO 9.00

1.21.01.05 INTERRUPTOR DE CONMUTACIÓN PTO 2.00

1.21.02 CANALES Y TUBERÍAS

1.21.02.01 TUBERÍA EMPOTRADA SALIDA DE LUZ Y TOMACORRIENTES PVC-SEL 3/4" M 153.00

1.21.02.02 CURVA PVC-SEL 3/4" UND 36.00

1.21.02.03 UNIÓN PVC SEL 3/4" UND 35.00

1.21.03 CONDUCTORES Y/O CABLES

1.21.03.01 CABLE TW-2,5 MM2 M 431.74

1.21.04 ARTEFACTOS

1.21.04.01 ARTEFACTO PARA ADOSAR,02 LAMPARAS FLUORECENTES 2X40 CON PANTALLA OPAL PZA 8.00

1.21.04.02 ARTEFACTO LAMPARA INCANDESCENTE (FOCO) PZA 2.00


PLANILLA DE METRADOS

OBRA: I.E. ILO

PROPI: MUNICIPALIDAD DISTRITAL DE ILO


FECHA Feb-17

SUB PROYECTO SISTEMA MODULAR AULAS

ITEM PARTIDA/DESCRIPCION CANTIDAD TOTAL


UND Nº ELEM
IGUALES LARGO ANCHO ALTO PARCIAL

1.21.04.03 LAMPARA PARA BRAQUET PZA 7.00

1.22 VARIOS

1.22.01 CLARABOYA CON POLICARBONATO DE 6MM TRASLUCIDO UND 2.00