Вы находитесь на странице: 1из 45

Section 11 - Piping Systems, Valves and Pumps 11-1

S e c t i o n 11

Piping Systems, Valves and Pumps

A. General S fresh water cooling systems


S lubricating oil systems
1. Scope
S starting air, control air and working air
These requirements apply to pipes and piping systems, systems
including valves, fittings and pumps, which are
necessary for the operation of the main propulsion S exhaust gas systems
plant together with its auxiliaries and equipment. They S bilge systems
also apply to piping systems used in the operation of
the ship whose failure could directly or indirectly S ballast systems
impair the safety of ship or cargo, and to piping
S cross flooding arrangements
systems which are dealt with in other sections.
S air, overflow and sounding pipes including
Cargo and process piping on ships for the carriage of
details of filling pipe cross sections
liquefied gases in bulk are additionally subject to the
provisions of the Rules for Ships Carrying Liquefied S overflow systems
Gases in Bulk, Volume IX.
S sanitary water piping (fresh water, seawater)
Cargo piping for the carriage of chemicals in bulk are
additionally subject to the provisions of the Rules for S sewage discharge piping
Ships Carrying Dangerous Chemical in Bulk, Volume S sewage discharge piping
X.
S drinking water systems
Gas welding equipment is subject to the “Guidelines
for the Design, Equipment and Testing of Gas Welding S equipment for the treatment and storage of
Equipment on Seagoing Ships”. bilge water and fuel oil residues.
Ventilation systems are subject to rules to the
provisions of Regulations for Ventilation Systems on 2.1.2 For remotely controlled valves:
Board Seagoing Ships S diagrammatic piping plans and diagrammatic
2 Documents for Approval plans of the arrangement of piping and
control stands in the ship
2.1. The following drawings/documents are to be
submitted for approval in triplicate1 S diagrammatic plans and electrical circuit
diagrams of the control stations and power
2.1.1 Diagrammatic plans of the following piping units, as well as drawings of the remotely
systems including all the details necessary for approval controlled valves, control stands and the
(e.g. lists of valves, fittings and pipes) : corresponding pressure accumulators.
S steam systems 2.1.3 For steam lines with working
temperatures > 400 !C, the corresponding stress
S boiler feed water systems
calculations together with isometric data are to be
S condensate systems submitted.
S thermal oil systems 3. Pipe classes
S fuel systems (bunkering, transfer and supply For the testing of pipes, selection of joints, welding
systems) and heat treatment, pipes are subdivided into three
classes as indicated in Table 11.1.
S seawater cooling systems

1
) For ships flying Indonesian flag in quadruplicate, one of
which intended for Indonesian Government.
11-2 Section 11 - Piping Systems, Valves and Pumps

Table 11.1 Classification of pipes into pipe classes

Medium/type of pipeline Design pressure PR [bar]


Design temperature t [oC]
Pipe Class I II III
Toxic media all - -
Corrosive media
Inflammable media with service temperature above the flash point
1
Inflammable media with a flash point below 60 !C or less all ) -
Liquefied gases (LG)
PR > 16 PR " 16 PR " 7
Steam or and and
t > 300 t " 300 t " 170
Thermal oil PR > 16 PR " 16 PR " 7
or and and
t > 300 t " 300 t " 150
Air, gas
Non-flammable hydraulic fluid PR > 40 PR " 40 PR " 16
Boiler feed water, condensate or and and
Seawater and freshwater for cooling t > 300 t " 300 t " 200
Brine in refrigerating plant
PR > 16 PR " 16 PR " 7
Liquid fuels, lubricating oil, flammable hydraulic fluid or and and
t > 150 t " 150 t " 60
Cargo pipelines for oil tankers - - all
Cargo and venting lines for gas and chemical tankers all - -
Refrigerants - all -
Open-ended pipelines (without shutoff), e.g. drains, venting pipes,
- - all
overflow lines and boiler blow down lines
1
) Classification in Pipe Class II is possible if special safety arrangements are available and structural safety precautions are
arranged

B. Materials, Testing 2.2 Pipes, valves and fittings of steel


1. General Pipes belonging to Classes I and II must be either
seamless drawn or fabricated by a welding procedure
Materials must be suitable for the proposed application approved by BKI. In general, carbon and car-
and comply with the BKI's Rules for Materials, bon-manganese steel pipes, valves and fittings are not
Volume V. to be used for temperatures above 400 !C. However,
In case of especially corrosive media, BKI may they may be used for higher temperatures provided that
impose special requirements on the materials used. For their metallurgical behavior and their strength property
welds, see the Rules for Welding, Volume VI. For the according to C.2.3 after 100 000 h of operation are in
materials used for pipes and valves for steam boilers, accordance with national or international regulations
see Section 7. or standards and if such values are guaranteed by the
steel manufacturer. Otherwise, alloy steels in accor-
2. Materials dance with BKI Rules for Materials, Volume V are to
be used.
2.1 Material Manufacturers
Pipes, elbows, fitting, valve casings, flanges and semi- 2.3 Pipes, valves and fittings of copper and
finished products intended to be used in pipe class I copper alloys
and II are to be manufactured by BKI approved Pipes of copper and copper alloys must be of seamless
manufacturers. drawn material or fabricated by a method approved by
For the use in pipe class III piping systems an BKI. Copper pipes for Classes I and II must be
approval according to other recognized standards may seamless.
be accepted. In general, copper and copper alloy pipe lines shall not
be used for media having temperatures above the
Section 11 - Piping Systems, Valves and Pumps 11-3

following limits: 2.6.1 Plastic piping system are to be type approved


by BKI. 2)
- copper and aluminum brass 200 !C
Each applicable pipe connection, i.e. flange-,
- copper nickel alloys 300 !C adhesive bond joint or bell and spigot connections, is
- high-temperature bronze 260 !C to be included in the type approval programme.
Regarding the use of flex type couplings, D.2.6 is to
be observed.
2.4 Pipes, valves and fittings of nodular
ferritic cast iron 2.6.2 Plastic piping systems including valves are
to be designed and manufactured according to
Pipes, valves and fittings of nodular ferritic cast iron recognized standards.
according to the Rules for Materials, Volume V may
be accepted for bilge, ballast and cargo pipes within 2.6.3 Pipe penetrations through watertight
double-bottom tanks and cargo tanks and for other bulkheads and decks as well as through fire divisions
purposes approved by BKI. In special cases are to be approved by BKI.
(applications corresponding in principle to classes II
and III) and subject to BKI special approval, valves 2.6.4 The use of plastic piping system is approved
and fittings made of ferritic nodular cast iron may be for piping systems included in pipe class III only.
accepted for temperatures up to 350 !C. Nodular Dependent on the application and installation location
ferritic cast iron for pipes, valves and fittings fitted on specific means respectively additional flame test may
the ship's side must comply with BKI Rules for be required. 2)
Materials, Volume V (see also Regulation of the 1966
Convention on Load Lines).
2.7 Aluminum and aluminum alloys

2.5 Pipes, valves and fittings of lamellar Aluminum and aluminum alloys must comply with
graphite cast iron (grey cast iron) BKI Rules for Materials, Volume V and may in
individual cases, with the agreement of BKI, be used
Pipes, valves and fittings of grey cast iron may be for temperatures up to 200 !C. They are not accept-
accepted by BKI for Class III. Pipes of grey cast iron able for use in fire extinguishing lines.
may be used for cargo pipelines within cargo tanks of
tankers. 2.8 Application of materials

Pipes, valves and fittings of grey cast iron may be For the pipe classes mentioned in A.3 materials must
used for cargo lines on the weather deck of oil tankers be applied according to Table 11.2
up to a working pressure of 16 bar.
3. Testing of materials
Ductile materials must be used for cargo hose con-
3.1 For piping systems belonging to class I and
nections and distributor headers.
II, tests in accordance with BKI Rules for Materials,
This applies also to the hose connections of fuel and Volume V and under BKI supervision are to be
lubricating oil filling lines. carried out in accordance with table 11.3 for :
The use of grey cast iron is not allowed: - pipes, bends and fittings
- in cargo lines on chemical tankers (see the - valve bodies and flanges
Rules for Ships Carrying Dangerous
- valve bodies and flanges > DN 100 in cargo
Chemical in Bulk, Volume X),
and process pipelines on gas tankers with
- for pipes, valves and fittings for media design temperature < -55 !C
having temperatures above 220 !C and for
3.2 Welded joints in pipelines of classes I and II
pipelines subject to water hammer, severe
are to be tested in accordance with the Rules for
stresses or vibrations,
Materials, Volume V, and the Rules for Ships
- for sea valves and pipes fitted on the ship Carrying Liquefied Gas in Bulk, Volume IX.
sides and for valves fitted on the collision
bulkhead,
- for valves on fuel and oil tanks subject to
static head.
The use of grey cast iron in cases other than those
stated is subject to BKI approval.

2
) See IMO Resolution A.753(18), “Guidelines for the
2.6 Plastic pipes systems Application of Plastic Pipes on Ships”
11-4 Section 11 - Piping Systems, Valves and Pumps

Table 11.2 Approved materials

Material Pipe Class


or
Application I II III

Pipes Steel pipes for high-temperature Pipes for Steel not subject to any special
above 300 !C, pipes made of steel general quality specification, weldability in
with high/low temperature applications accordance with Rules for Welding
toughness at temperatures below
- 10 !C, stainless steel pipes for
chemicals

Forgings, Steels suitable for the corresponding loading and processing conditions, high
plates, temperature steel for temperature above 300!C,
Steels

flanges, steel steels with high/low temperature toughness for temperatures below -10!C
sections and
bars

Bolts for general machinery


Bolts, nuts construction, high temperature steel
for temperatures above 300 !C, Bolts for general machine construction
steels with high/low temperature
toughness for temperatures below
-10 !C

High-temperature cast steel for


temperatures above 300 !C, cast
Cast steel steel with high/low temperature Cast steel for general applications
Castings (valves, fittings, pipes)

toughness at temperatures below


-10 !C, stainless castings for
agressive media

Nodular cast Only ferritic grades, elongation A5 at least 15 %


iron

Cast iron with Up to 220 !C, grey cast iron not


lamellar permitted for valves and fittings
graphite - - on ship’s side, on the collision
bulkhead and on fuel and oil
tanks and for relief valves.

In cargo lines on chemical tankers


(valves, fittings, pipes)

Copper, only with special approval, low- For seawater and alkaline water only corrosion
Non-metallic material Non-ferrous metals

copper alloys temperature copper-nickel alloys by resistant copper and copper alloys
special agreement

Aluminum, In cargo and processing lines on gas Only with the agreement of BKI up to 200 !C,
aluminum. tanker not permitted in fire extinguishing systems
alloys

Plastics - - On special approval


(see 2.5)
Section 11 - Piping Systems, Valves and Pumps 11-5

Table 11.3 Approved materials and types of certificates

Type of Approved Design Pipe Nominal diameter Type of material


component material temperature class DN certificate according
to EN 10204 : 2004

3.2 3.1 2.2

Pipes 1), Steel, I > 50 X - -


Pipe elbows, Copper, - " 50 - X -
Fittings Copper alloys
Aluminium II > 50 - X -
Aluminium alloys " 50 - - X
Plastics
III All - - X

Valves 1), Steel,


Flanges, Cast steel, > 300 !C
Nodular cast iron DN > 100 X - -
I,II
DN " 100 - X -
Copper,
Copper alloys > 225 !C

Steel, PB x DN > 2500 X - -


Cast steel, " 300 !C or DN > 250
Nodular cast iron
PB x DN " 2500 - X -
and DN " 250

Steel,
Cast steel, - III All - - X
Nodular cast iron,
Grey cast iron

Copper, PB x DN > 1500 X - -


Copper alloys "225 !C
I,II
Aluminium, PB x DN " 1500 - X -
Aluminium alloys "200 !C

According to
Type
Plastics III All - - X
Approval
Certificate

Semi-finished
products, I,II - - X -
Screws and
other According to - III - - - X
components Table 11.2

1
) Casings of valves and pipes fitted on ship’s side and bottom and bodies of valves fitted on collision bulkhead are to be included
in pipe

4. Hydraulic tests on pipes 4.1.2 Nominal pressure, PN [bar]


4.1 Definitions This is the term applied to a selected pressure
temperature relation used for the standardization of
4.1.1. Maximum allowable working pressure, PB structural components. In general, the numerical value
[bar], Formula symbol: pe,perm of the nominal pressure for a standardized component
This is the maximum allowable internal or external made of the material specified in the standard will
working pressure for a component or piping system correspond to the maximum allowable working
with regard to the materials used, piping design pressure PB at 20! C.
requirements, the working temperature and undis-
turbed operation.
11-6 Section 11 - Piping Systems, Valves and Pumps

4.1.3 Test pressure, PP [bar] $ perm (100# )


Formula symbol: pp p c ! 1,5 "
This is the pressure to which components or piping
$ perm ( t ) " p c
systems are subjected for testing purposes. where
4.1.4 Design pressure, PR [bar] !perm (100!) permissible stress at 100 !C
Formula symbol: pc
!perm (t) permissible stress at the design
This is the maximum allowable working pressure PB temperature (!C)
for which a component or piping system is designed
with regard to its mechanical characteristics. In However, the test pressure need not exceed:
general, the design pressure is the maximum
pp = 2 # pc [bar]
allowable working pressure at which the safety
equipment will interfere (e.g. activation of safety With the approval of BKI, this pressure may be
valves, opening of return lines of pumps, operating of reduced to 1,5 $ pc where it is necessary to avoid
over pressure safety arrangements, opening of relief excessive stress in way of bends, T-pieces and other
valves) or at which the pumps will operate against shaped components.
closed valves.
In no case may the membrane stress exceed 90 % of
The design pressure for fuel pipes shall be chosen the yield strength or 0,2 % of the maximum
according to Table 11.4. elongation.
Table 11.4 Design pressure for fuel pipes 4.2.2 Where for technical reasons it is not possible
to carry out complete hydraulic pressure tests on all
Max.working sections of piping before assembly on board, pro-
temperature posals are to be submitted to BKI for approval for
T " 60 oC T > 60 oC testing pipe connections on board, particularly in
Max. respect of welding seams.
working pressure
4.2.3 Where the hydraulic pressure test of piping
PB " 7 bar 3 bar or 3 bar or is carried out on board, these tests may be conducted
max. max. in conjunction with the tests required under 4.3.
working working 4.2.4 Pressure testing of pipes with a nominal
pressure, pressure, diameter less than DN 15 mm may be omitted at
whichever whichever is BKI's discretion depending on the application.
is greater greater
4.3 Test after installation on board
PB > 7 bar max. 14 bar or
working max. 4.3.1 After assembly on board, all pipelines
pressure working covered by these Rules are to be subjected to a
pressure, tightness test in the presence of a BKI Surveyor.
whichever is In general, all pipe systems are to be tested for leak-
greater age under operational conditions. If necessary, special
techniques other than hydraulic pressure tests are to
4.2 Pressure test prior to installation on be applied.
board
4.3.2 Heating coils in tanks and pipe lines for fuels
4.2.1 All Class I and II pipes as well as steam are to be tested to not less than 1,5 PR but in no case
lines, feed water pressure pipes, compressed air and less than 4 bar.
fuel lines having a design pressure PR greater than
3,5 bar together with their integral fittings, connecting 4.4 Pressure testing of valves
pieces, branches and bends, after completion of The following valves are to be subjected in the in the
manufacture but before insulation and coating, if this manufacturer's works to a hydraulic pressure test in
is provided, shall be subjected to a hydraulic pressure the presence of a BKI Surveyor.
test in the presence of the Surveyor at the following
value of pressure: - valves of pipe classes I and II to 1,5 PR,
pp = 1,5 # pc [bar] - valves on the ship's side to not less than 5 bar.
where pc is the design pressure.For steel pipes and Shutt-off devices of above type are to be additionally
their integral fittings intended to be used in systems tested for tightness with the nominal pressure.
with working temperature above 300 !C the test
Shut off devices for boilers, see Section 7I, E.13.
pressure PP is to be as follows:
Section 11 - Piping Systems, Valves and Pumps 11-7

5. Structural tests, heat treatment and so [mm] calculated thickness


non-destructive testing
da [mm] outer diameter of pipe
Attention should be given to the workmanship in
pc [bar] design pressure 3), see B.4.1.4
construction and installation of the piping systems
according to the approved data in order to obtain the !perm [N/mm2] maximum permissible design
maximum efficiency in service. For details concern- stress, see 2.3
ing structural tests and tests following heat treat-
ments, see Rules for Materials, Volume V. b [mm] allowance for bends, see 2.2
v [-] weld efficiency factor, see2.5
c [mm] corrosion allowance, see 2.6
C. Calculation of Wall Thickness and
2.2 For straight cylindrical pipes which are to be
Elasticity
bent, an allowance (b) shall be applied for the
1. Minimum wall thickness bending of the pipes. The value of (b) shall be such
that the stress due to the bending of the pipes does not
1.1 The pipe thicknesses stated in Tables 11.5 to exceed the maximum permissible design stress (!perm).
11.8 are the assigned minimum thicknesses, unless The allowance (b) can be determined as follows :
due to stress analysis, see 2., greater thicknesses are
necessary. (2)
Provided that the pipes are effectively protected
against corrosion, the wall thicknesses of group M R [mm] bending radius
and D stated in Table 11.6 may with BKI agreement
be reduced by up to 1 mm, the amount of the 2.3 Permissible stress: !perm
reduction is to be in relation to the wall thickness. 2.3.1 Steel pipes
Protective coatings, e.g. hot-dip galvanizing, can be The permissible stress !perm to be considered in
recognized as an effective corrosion protection formula (la) is to be chosen as the lowest of the
provided that the preservation of the protective following values :
coating during installation is guaranteed.
a) Design temperature " 350 !C
For steel pipes the wall thickness group correspond-
ing to the laying position is to be as stated in
Table11.5.
1.2 The minimum wall thicknesses for austenitic
stainless steel pipes are given in Table 11.7. Rm,20o = specified minimum tensile strength at room
1.3 For the minimum wall thickness of air, temperature
sounding and overflow pipes through weather decks, ReH,t = specified minimum yield stress at design
see R. Table 11.20a temperature; or
For CO2 fire extinguishing pipelines, see Section Rp0.2,t = minimum value of the 0,2 % proof stress at
12, Table 12.6. design temperature
1.4 Where the application of mechanical joints b) Design temperature > 350 !C, whereby it is to
results in reduction in pipe wall thickness (bite type be checked whether the calculated values
rings or other structural elements) this is to be taken according to a) give the decisive smaller value
into account in determining the minimum wall
thickness.
2. Calculation of pipe wall thicknesses
Rml00000 = minimum stress to produce rupture
2.1 The following formula is to be used for
in 100000 hours at the design
calculating the wall thicknesses of cylindrical pipes
temperature t
and bends subject to internal pressure :
[mm] (1) Rp,100000.t = average stress to produce 1% creep
in 100000 hours at the design
temperature t
[mm] (1a)

3
) For pipes containing fuel heated above 60 !C the
s [mm] minimum thickness, see 2.7 design pressure is to be taken not less than 14 bar.
11-8 Section 11 - Piping Systems, Valves and Pumps

Table 11.5 Minimum wall thickness groups N, M and D of steel pipes and approved locations

Location

Condensate and feedwater tanks


Fuel and changeover tanks

Fresh cooling water tanks

Cargo tanks, tanks ships

Cofferdams, tanks ships


Cofferdams/void spaces

Drinking water tanks


Lubricating oil tanks
Piping system

Cargo pump rooms


Hydraulic oil tanks
Ballast water tanks
Machinery spaces

Thermal oil tanks

Accomodation

Weather deck
Cargo holds

Bilge lines M D M x M -
1 M
Ballast lines M D x )
M x x
Seawater lines D x x M M
2
)
x
Fuel lines D N x

x - -
Lubricating lines - x x N x
N
Thermal oil lines N

Steam lines M M M M M - M N
N
Condensate lines N
N
Feedwater lines x
M x x x x x x
Drinking water lines x x N N
x
Fresh cooling water lines D N D x - -
x
Compressed air lines M M x N N
M M N N N
Hydraulic lines x x x x N
1) See Section 15, B.4.3.
2) Seawater discharge lines, see T.
x Pipelines are not to be installed.
(-) Pipelines may be installed after special agreement with BKI.
Section 11 - Piping Systems, Valves and Pumps 11-9

Table 11.6 Minimum wall thickness for steel pipes

Group N Group M Group D

da s da s da s da s

[mm] [mm] [mm] [mm] [mm] [mm] [mm] [mm]

10,2 1,6 from 406,4 6,3 from 21,3 3,2 from 38,0 6,3
from 13,5 1,8 from 660,0 7,1 from 38,0 3,6 from 88,9 7,1
from 20,0 2,0 from 762,0 8,0 from 51,0 4,0 from 114,3 8,0
from 48,3 2,3 from 864,0 8,8 from 76,1 4,5 from 152,4 8,8
from 70,0 2,6 from 914,0 10,0 from 177,8 5,0 from 457,2 8,8
from 88,9 2,9 from 193,7 5,4
from 114,3 3,2 from 219,1 5,9
from 133,0 3,6 from 244,5 6,3
from 152,4 4,0 from 660,4 7,1
from 177,8 4,5 from 762,0 8,0
from 244,5 5,0 from 863,6 8,8
from 323,9 5,6 from 914,4 10,0

Table 11.7 Minimum wall thicknesses for Table 11.8 Minimum wall thicknesses for
austenitic stainless steel pipes copper and copper alloy pipes

Pipe outside Minimum wall Pipe outside Minimum wall thickness


diameter thickness s
diameter [mm]
da s da
[mm] [mm] [mm] Copper Copper alloys

up to 17,2 1,0
up to 48,3 8 - 10 1,0 0,8
up to 88,9 1,6 12 - 20 1,2 1,0
up to 168,3 2,0 25 - 44,5 1,5 1,2
up to 219,1 2,3 50 - 76,1 2,0 1,5
up to 273,0 2,6 88,9 - 108 2,5 2,0
up to 406,0 2,9 133 - 159 3,0 2,5
over 406,0 3,6 193,7 - 267 3,5 3,0
4,0 273 - 457,2 4,0 3,5
(470) 4,0 3,5
508 4,5 4,0

Rm 100000 (t + 15) = average stress to produce rupture in 100000 hours at the design
11-10 Section 11 - Piping Systems, Valves and Pumps

temperature t plus 15 !C, a) For seamless pipes v = 1,0


see 2.4.
b) In the case of welded pipes, the value of v is to
be equal to that assigned at the works
In the case of pipes which : acceptance test.
- are covered by a detailed stress analysis 2.6 Corrosion allowance, c
acceptable to BKI and
The corrosion allowance c depends on the application
- are made of material tested by BKI, BKI may, of the pipe, in accordance with Tables 11.11a and
on special application, agree to a safety factor B 11.11b. With the agreement of BKI, the corrosion
of 1,6 (for A and B see Table 11.10). allowance of steel pipes effectively protected against
2.3.2 Pipes made of metallic materials without corrosion may be reduced by not more than 50 %.
a definite yield point With the agreement of BKI, no corrosion allowance
Materials without a definite yield point are covered need be applied to pipes made of corrosion-resistant
by Table 11.9. For other materials, the maximum materials (e.g. austenitic steels and copper alloys)
permissible stress is to be stated with BKI agreement, (see Table 11.7 and Table 11.8).
but must be at least : 2.7 Tolerance allowance t
R m,t The negative manufacturing tolerances on the
$ perm ! thickness according to the standards of the technical
5 terms of delivery are to be added to the calculated
where Rmt is the minimum tensile strength at the wall thickness (so) and specified as the tolerance
design temperature. allowance (t). The value of t may be calculated as
follows :
2.3.3 The mechanical characteristics of materials
which are not included in the Rules of Materials,
Volume V, are to be agreed with BKI, reference to [mm] (3)
Table 11.10.
Steel pipes without guaranteed properties may be where
used only up to a working temperature of 120 !C a [%] = negative tolerance on the
where the maximum allowable stress !perm " 80 thickness
N/mm2 will be approved.
so [mm] = calculated wall thickness
2.4 Design temperature according to 2.1.
2.4.1 The design temperature is the maximum 3. Analysis of elasticity
temperature of the medium inside the pipe. In case of
steam pipes, filling pipes from air compressors and 3.1 The forces, moments and stresses caused by
starting air lines to internal combustion engines, the impeded thermal expansion and contraction are to be
design temperature is to be at least 200 !C. calculated and submitted to BKI for approval for the
following piping systems:
2.4.2 Design temperatures for superheated steam
lines are as follows : - Steam pipes with working temperatures above
400 !C
a) Pipes behind desuperheaters:
- Pipes with working temperatures below -110 !C
- with automatic temperature control :
3.2 Only approved methods of calculation may be
the working temperature 4 ) (design tempera- applied. The change in elasticity of bends and fittings
ture) due to deformation is to be taken into consideration.
- with manual control : Procedure and principles of methods as well as the
the working temperature + 15 !C 4) technical data are to be submitted for approval. BKI
reserves the right to perform confirmatory
b) Pipes before desuperheaters: calculations.
the working temperature + 15 !C 4)

2.5 Weld efficiency factor v

4
) Transient excess in the working temperature need not
be taken into account when determining the design
temperature.
Section 11 - Piping Systems, Valves and Pumps 11-11

Table 11.9 Allowable stress, !perm for copper and copper alloys (annealed)

Minimum Allowable stress !perm [N/mm2]


Pipe material tensile
strength 50 75 100 125 150 175 200 225 250 275 300
[N/mm2] !C o
C o
C o
C o
C o
C o
C o
C o
C o
C o
C

Copper 215 41 41 40 40 34 27,5 18,5 - - - -

Aluminium brass 325 78 78 78 78 78 51 24,5 - - - -


Cu Zn 20 Al

Cu Ni 5 Fe
nickel alloys

275 68 68 67 65,5 64 62 59 56 52 48 44
Cu Ni 10 Fe
Copper

Cu Ni 30 Fe 365 81 79 77 75 73 71 69 67 65,5 64 62

Table 11.10 Coefficient A,B for determining the Table 11.11a Corrosion allowance c for carbon
permitted stress !perm steel pipes

Pipe class I II, III Type of piping system Corrosion


Material A B A B allowance
c
Unalloyed and 2,7 1,6 2,7 1,8 [mm]
alloyed carbon steel
Superheated steam lines 0,3
Rolled and forged 2,4 1,6 2,4 1,8
stainless steel Saturated steam lines 0,8

Steel with yield 3,0 1,7 3,0 1,8 Steam heating coils inside cargo 2,0
strength1 tanks
> 400 N/mm2
Feedwater lines :
Grey cast iron - - 11 -
in closed circuit systems 0,5
Nodular cast iron - - 5,3 3,0
in open circuit systems 1,5
Cast steel 3,2 - 4,0 -
Boiler blowdown lines 1,5
1
) Minimum yield strength or minimum 0,2 % proof
stress at 20 !C Compressed air lines 1,0

Hydraulic oil lines, lubricating oil


lines 0,3

Fuel lines 1,0

Cargo oil lines 2,0

Refrigerants lines for Group 1 0,3


refrigerants
Refrigerant lines for Group 2 0,5
refrigerants
Seawater lines 3,0
Freshwater lines 0.8
11-12 Section 11 - Piping Systems, Valves and Pumps

Table 11.11b Corrosion allowance c for non- proposed material at design


ferrous metals temperature t
!perm standard = permissible stress according to 2.3 for
Pipe material Corrosion the material at the temperature
allowance c corresponding to the strength data
[mm] specified in the standard
Copper, brass and similar pstandard = nominal PN pressure specified in the
alloys standard
0,8
Copper-tin alloys except
those containing lead

Copper nickel alloys 0,5 D. Principles for the Construction of Pipes,


(with Ni % 10%) Valves, Fittings and Pumps

For determining the stresses, the hypothesis of the 1. General principles


maximum shear stress is to be considered. The 1.1 Piping systems are to be constructed and
resulting comparison of stress of primary loads due to manufactured on the basis of standards generally used
internal pressure and the dead weight of the piping in shipbuilding.
system itself (inertia forces) may not exceed the
maximum allowable stress according to 2.3. The 1.2 Welded connections rather than detachable
stress obtained by adding together the above couplings should be used for pipelines carrying toxic
mentioned primary forces and the secondary forces media and inflammable liquefied gases as well as for
due to impeded expansion or contraction may not superheated steam pipes with temperatures exceeding
exceed the mean value of the fatigue stress or the 400 !C.
average stress to produce rupture in 100 000 hours,
1.3 Expansion in piping systems due to heating and
where for fittings such as bends, T-connections,
shifting of their suspensions caused by deformation of
headers etc. approved factors for increased stress are
the ship are to be compensated by bends,
to be considered.
compensators and flexible pipe connections. The
4. Fittings arrangement of suitable fixed points is to be taken
into consideration.
Pipe branches may be dimensioned according to the
equivalent surface areas method where an appropriate 1.4 Where pipes are protected against corrosion by
reduction of the maximum allowable stress as special protective coatings, e.g. hot-dip galvanishing,
specified in 2.3 is to be proposed. Generally, the rubber lining etc., it is to be ensured that the
maximum allowable stress is equal to 70 % of the protective coating will not be damaged during
value according to 2.3 for diameters over 300 mm. installation.
Below this figure, a reduction to 80 % is sufficient.
2. Pipe connections
Where detailed stress measuring, calculations or type
approvals are available, higher stresses can be 2.1 The following pipe connections may be used:
permitted.
- full penetration butt welds with/without
5. Calculation of flanges provision to improve the quality of the root
Flange calculations by a recognized method and using - socket welds with suitable fillet weld thickness
the permitted stress specified in 2.3 are to be and possibly in accordance with recognized
submitted if flanges do not correspond to a standards
recognized standard, if the standards do not provide
for conversion to working conditions or where there - mechanical joints (e.g. pipe unions, pipe
is a deviation from the standards. couplings, press fittings) of an approved type.

Flanges in accordance with standards in which the For the use of welded pipe connections, see Table
values of the relevant stresses or the material are 11.12
specified may be used at higher temperatures up to 2.2 Flange connections
the following pressure :
2.2.1 Dimensions of flanges and bolting shall
comply with recognized standards.
2.2.2 Gaskets are to be suitable for the intended
media under design pressure and temperature
conditions and their dimensions and construction
shall be in accordance with recognized standards.
!perm(t,material) = permissible stress according to 2.3 for
Section 11 - Piping Systems, Valves and Pumps 11-13

2.2.3 Steel flanges may be used as shown in table and tapered threads shall comply with requirements of
11.16 and 11.17 in accordance with the permitted recognized national or international standards.
pressures and temperatures specified in the relevant
standards. 2.4.2 Screwed socket connections with parallel
threads are permitted for pipes in class III with an
2.2.4 Flanges made of non-ferrous metals may be outside diameter "%60,3 mm as well as for subordinate
used in accordance with the relevant standards and systems (e.g. sanitary and hot water heating systems).
within the limits laid down in the approvals. Flanges They are not permitted for systems for flammable
and brazed or welded collars of copper and copper media.
alloys are subject to the following requirements :
2.4.3 Screwed socket connections with tapered
a) welding neck flanges according to standard up threads are permitted for the following:
to 200 !C or 300 !C according to the maximum
temperatures indicated in Table 11.9; applicable – class I, outside diameter not more than 33,7 mm
to all classes of pipe. – class II and class III, outside diameter not more
b) loose flanges with welding collar; as for a). than 60,3 mm

c) plain brazed flanges: only for pipe class III up Screwed socket connections with tapered threads are
to a nominal pressure of 16 bar and a not permitted for piping systems conveying toxic or
temperature of 120 !C. flammable media or services where fatigue, severe
erosion or crevice corrosion is expected to occur.
2.2.5 Flange connections for pipe classes I and II
with temperatures over 300 oC are to be provided with 2.5 Brazed connections may be used after special
necked-down bolts approval by BKI.

2.3 Welded socket connections 2.6 Mechanical joints

Welded socket connections may be accepted 2.6.1 Type approved mechanical joints may be
according to Table 11.12. Following conditions are to used as shown in Tables 11.13 to 11.15.
be observed. 2.6.2 Mechanical joints in bilge and seawater
– The thickness of the sockets is to be in systems within machinery spaces or spaces of high
accordance with C.1.1 at least equal to the fire risk, e.g. cargo pump rooms and car decks, must
thickness of the pipe. be flame resistant.

– The clearance between the pipes and the socket 2.6.3 Mechanical joints are not to be used in
is to be as small as possible. piping sections directly connected to sea openings or
tanks containing flammable liquids.
– The use of welded socket connections in
systems of pipe class II may be accepted only 2.6.4 The use of pipe couplings is not permitted
under the condition that in the systems no in:
excessive stress, erosion and corrosion are - bilge lines inside ballast and fuel tanks
expected.
- seawater and ballast lines inside cargo holds
Table 11.12 Pipe connections and fuel tanks
- fuel and oil lines inside machinery spaces,
Outside cargo holds and ballast tanks
Type of connections Pipe class
diameter
- non water filled pressure water spraying
Welded butt-joints systems (dry pipe systems)
with special
I,II,III Slip-on joints inside tanks may be permitted only if
provisions for root
side the pipes contain the same medium as the tanks.
Welded butt-joints all Unrestrained slip on joints may be used only where
without special required for compensation of lateral pipe movement.
II,III
provisions for root
3. Layout, marking and installation
side
Socket weld III 3.1 Piping systems must be adequately identified
according to their purpose. Valves are to be
II " 60,3 mm permanently and clearly marked.
3.2 Pipes penetration leading through
2.4 Screwed socket connections bulkheads/decks and tank walls must be water and oil
tight. Bolts through bulkheads are not permitted.
2.4.1 Screwed socket connections with parallel Holes for set screws may not be drilled in the tank
11-14 Section 11 - Piping Systems, Valves and Pumps

walls. accessible. Seawater inlet and outlet valves must be


capable of being operated from above the floor plates.
3.3 Sealing systems for pipe penetrating through Cocks on the ship's side must be so arranged that the
watertight bulkheads and decks as well as through fire handle can only be removed when the cock is closed.
divisions which are not welded are to be approved by
BKI (see Rules for Hull, Volume II, Section 26, C.8) 5.3 Valves with only one flange may be used on
5
) the shell plating and on the sea chests only after
special approval.
3.4 Piping close to electrical switchboards must
be so installed or protected that leakage cannot 5.4 On ships with > 500 GT, in periodically
damage the electrical installation. unattended machinery spaces, the controls of sea inlet
and discharge valves shall be sited so as to allow to
3.5 Piping systems are to be so arranged that reach and operate sea inlet and discharge valves in
they can be completely emptied, drained and vented. case of influx of water within 10 minutes after
Piping systems in which the accumulation of liquids triggering of the bilge alarm.
during operation could cause damage must be
equipped with special drain arrangements. Non return discharge valves need not to be
considered.
3.6 Pipes lines laid through ballast tank, which
are coated in accordance with Rules for Hull, 6. Remote control of valves
Volume II, Section 1, N.3. are to be either effectively
protected against corrosion or they are to be of low 6.1 Scope
susceptibility to corrosion. These requirements apply to hydraulically,
The method of corrosion protection of tanks and pipes pneumatically or electrically operated valves in
shall be compatible. piping systems and sanitary discharge pipes.

3.7 The wall thickness of pipes between ship’s 6.2 Construction


side and first shut-off device is to be in accordance 6.2.1 Remote controlled bilge valves and valves
with Tables 11.20b column B. Pipes are to be important to the safety of the ship are to be equipped
connected by welding or flanges. with an emergency operating arrangement.
4. Shut-off devices 6.2.2 For the emergency operation of remote
4.1 Shut-off devices must comply with a recog- controlled valves in cargo piping systems, see
nized standard. Valves with screwed-on covers are to Section 15, B.2.3.3.
be secured to prevent unintentional loosening of the 6.3 Arrangement of valves
cover.
6.3.1 The accessibility of the valves for maintenance
4.2 Hand-operated shut-off devices are to be and repair is to be taken into consideration.
closed by turning in the clockwise direction.
4.3 Valves must be clearly marked to show Valves in bilge lines and sanitary pipes must always
whether they are in the open or closed position. be accessible.

4.4 Change-over devices in piping systems in 6.3.2 Bilge lines


which a possible intermediate position of the device
could be dangerous in service must not be used. Valves and control lines are to be located as far as
possible from the bottom and sides of the ship.
4.5 Valves are to be permanently marked. The
marking must comprise at least the following details: 6.3.3 Ballast pipes

- material of valve body The requirements stated in 6.3.2 also apply here to the
location of valves and control lines.
- nominal diameter
Where remote controlled valves are arranged inside
- nominal pressure. the ballast tanks, the valves should always be located
in the tank adjoining that to which they relate.
5. Valves on the shell plating
5.1 For the mounting of valves on the ship's
side, see Rules for Hull, Volume II, Section 6.G.
5.2 Valves on the shell plating shall be easily

5
) Regulations for the Performance of Type Tests, Part 3 -
Test Requirements for Sealing Systems of bulkhead and
Deck Penetrations.
Section 11 - Piping Systems, Valves and Pumps 11-15

Table 11.13 Examples of mechanical joints

Pipe Unions

Welded and
brazed type

Compression Couplings

Swage type

Press type

Bite type

Flared type

Slip-on Joints

Grip type

Table 11.13 Examples of mechanical joints (continued)


11-16 Section 11 - Piping Systems, Valves and Pumps

Slip-on Joints

Machine grooved type

Slip type

Table 11.14 Application of mechanical joints

Kind of connections

System Pipe Unions Compression couplings6) Slip-on joints

Flammable fluids (flash point < 60 oC)

Cargo oil + + + 5)

Crude oil washing + + + 5)

Vent + + + 3)

Inert gas

Water seal effluent + + +

Scrubber effluent + + +

Main + + + 2,5)

Distributions + + + 5)

Flammable fluids (flash point > 60 oC)

Cargo oil + + + 5)

Fuel oil + + + 2,3)

Table 11.14 Application of mechanical joints (continued)


Section 11 - Piping Systems, Valves and Pumps 11-17

Lubricating oil + + + 2,3)

Hydraulic oil + + + 2,3)

Thermal oil + + + 2,3)

Sea Water

Bilge + + + 1)

Fire main & water spray + + + 3)

Foam + + + 3)

Sprinkler + + + 3)

Ballast + + + 1)

Cooling water + + + 1)

Tank cleaning + + +

Non-essential system + + +

Fresh Water

Cooling water system + + + 1)

Condensate return + + + 1)

Non-essential system + + +

Sanitary / Drains / Scuppers

Deck drain (internal) + + + 4)

Sanitary drains + + +

Scupper and discharge + + -


(overboard)

Sounding / Vent

Water tanks/dry spaces + + +


o
Oil tank (fp > 60 C) + + + 2,3)

Miscellaneous

Starting/control air 1) + + -

Service air (non-essential) + + +

Brine + + +

CO2 system1) + + -

Steam + + -

Abbreviations : Footnotes :
+ Application is allowed 1) Inside machinery spaces of category A - only approved fire resistant types
2) Not inside machinery spaces of category A or accommodation spaces. May be accepted in other
- Application is not allowed
machinery spaces provided the joints are located in easily visible and accessible positions
3) Approved fire resistant types
4) Above freeboard deck only
5) In pump rooms and open decks - only approved fire resistant type
6) If compression couplings include any components which readily deteriorate in case of fire, they
are to be of approved fire resistant type as required for Slip-on joints.
11-18 Section 11 - Piping Systems, Valves and Pumps

Table 11.15 Application of mechanical joints depending upon the class of piping

Type of joints Classes of piping systems

I II III

Pipe Unions

Welded and brazed type + + +


(da " 60,3 mm) (da " 60,3 mm)

Compression Couplings

Swage type + + +

Press type - - +

Bite type + + +
Flared type (da " 60,3 mm) (da " 60,3 mm)

Slip-on Joints

Machine grooved type + + +

Grip type - + +

Slip type - + +

Abbreviations :
+ Application is allowed
S Application is not allowed

Table 11.16 Use of flange types

Toxic, corrosive and Steam, Lubricating


Pipe combustible media, thermal oils oil, fuel oil Other media
class liquefied gases (LG)

PR Type of Temperatur Type of Type of flange Temperature Type of flange


[bar] flange e flange [!C]
[!C]

I > 10 A > 400 A A,B > 400 A


" 10 A,B1) " 400 A, B1) " 400 A, B

II - A, B, C > 250 A, B, C A,B,C,E2) > 250 A, B, C


" 250 A,B,C,D,E " 250 A,B,C,D,E,

III - - - A,B,C,D,E A,B,C,E - A, B, C


A,B,C,D,E,F3)
1
) Type B only for da < 150 mm
2
) Type E only for t < 150 !C and PR < 16 bar
3
) Type F only for water pipes and open-ended lines
Section 11 - Piping Systems, Valves and Pumps 11-19

Table 11.17 Types of flange connections


Type A

Welding neck flange Loose flange with welding


neck
Type B

Slip-on welding flange-fully welded


Type C

Slip-on welding flange


Type D Type E Type F

Socket screwed flange Plain flange Lap joint flange


- conical threads - - welded on both sides - - on flanged pipe -

6.3.4 Fuel pipes Remote controlled valves mounted on fuel tanks lo-
11-20 Section 11 - Piping Systems, Valves and Pumps

cated above the double bottom must be capable of plied with air from the general compressed air system.
being closed from outside the compartment in which
they are installed. (see also G.2.1 and H.2.2) Where the quick-closing valves of fuel tanks are
closed pneumatically, a separate pressure accumulator
If remote controlled valve are installed inside fuel or is to be provided. This is to be of adequate capacity
oil tanks, 6.3.3 has to be applied accordingly. and is to be located outside the engine room. Filling of
this accumulator by a direct connection to the general
6.3.5 Bunker lines compressed air system is allowed. A non-return valve
Remote controlled shut-off devices mounted on fuel is to be arranged in the filling connection of the
tanks shall not be automatically closed in case the pressure accumulator.
power supply fails, unless suitable arrangements are The accumulator is to be provided either with a pres-
provided, which prevent excessive pressure raise in the sure control device with a visual and acoustic alarm or
bunker line during bunkering. with a hand-compressor as a second filling appliance.
6.3.6 Cargo pipes The hand-compressor is to be located outside the en-
For remote controlled valves inside cargo tanks, see gine room.
Section 15.B.2.3.3. 6.6 After installation on board, the entire system is to
6.4 Control stands be subjected to an operational test.

6.4.1 The control devices of remote controlled 7. Pumps


valves of a system are to be arranged together in one 7.1 For materials and construction requirements the
control stand. "Regulations for Construction and Testing of Pumps"
6.4.2 The control devices are to be clearly and of BKI are to be applied.
permanently identified and marked. 7.2 For the pumps listed below, a performance test is
6.4.3 The status (open or close) of each remote to be carried out in the manufacturer's works under
controlled valve is to be indicated at the control stand. BKI supervision.

6.4.4 The status of bilge valves “open”/”close” is to - bilge pumps/bilge ejectors


be indicated by BKI approved position indicators. - ballast pumps
In case of position indicators directly mounted on the - cooling sea water pumps
valve a drawing approval by BKI is to be carried out.
- cooling fresh water pumps
Position indicators based on direct measuring
principles, i.e. volumetric position indicators, need to - fire pumps
be type approved.
- emergency fire pumps including drive units
6.4.5 In case of volumetric position indicators the
- condensate pumps
system pressure of the control line is to be monitored
by a BKI type approved pressure switch (series - boiler feedwater pumps
connection of pressure switch and flow switch).
- boiler water circulating pumps
6.4.6 The control devices of valves for changeable
tanks are to be interlocked to ensure that only the valve - lubricating oil pumps
relating to the tank concerned can be operated. The - fuel oil booster and transfer pumps
same also applies to the valves of cargo holds and
tanks, in which dry cargo and ballast water are carried - circulating pumps for thermal oil installations
alternately.
- brine pumps
6.4.7 On passenger ships, the control stand for
- refrigerant circulating pumps
remote controlled bilge valves is to be located outside
the machinery spaces and above the bulkhead deck. - cargo pumps
6.5 Power units - cooling pumps for fuel injection valves
6.5.1 Power units are to be equipped with at least - hydraulic pumps for controllable pitch propellers
two independent sets for supplying power for remote
controlled valves. Other hydraulic pumps/motors, see Section 14.

6.5.2 The energy required for the closing of valves 8. Protection of piping systems against over
which are not closed by spring power is to be supplied pressure
by a pressure accumulator.
The following piping systems are to be fitted with
6.5.3 Pneumatically operated valves can be sup- safety valves to avoid excessive over pressures:
Section 11 - Piping Systems, Valves and Pumps 11-21

- piping systems and valves in which liquids can must be capable of being operated from a control panel
be enclosed and heated; located on the navigation bridge, where it must be
indicated when the valve is in the "closed" position.
- piping systems which may be exposed in service This requirement does not apply to valve which are
to pressures in excess of the design pressure. opened at sea only shortly for supervised operations.
Safety valves must be capable of discharging the 9.7.4 Overflow pipes of tanks in different water-
medium at a maximum pressure increase of 10 % of tight compartments which are connected to one
the allowable working pressure. Safety valves are to be common overflow system are either
fitted on the low pressure side of reducing valves.
S to be led, prior to being connected to the system,
9. Piping on ships with added classification mark within the relevant compartment, on passenger
! or ! ships high enough above the bulkhead deck and
9.1 The following requirements apply additionally to on other ships above the most unfavorably
ships for which proof of buoyancy in the damaged damage water line, or
condition is provided : S a shut off valve is to be fitted to each overflow
9.1.1 Passenger ships according to Rules for hull, pipe. This shut-off valve is to be located at the
Volume II, Section 26, K. as well as N.5 of this watertight bulkhead of the relevant compartment
Section and is to be secured in open position to prevent
unintended operation. The shut-off valves must
9.1.2 Gas tankers according to Rules for Ships be capable of being operated from a control
Carrying Liquefied Gases in Bulk, Volume IX. panel located on the navigation bridge, where it
must be indicated when the valve is in the
9.1.3 Chemical tankers according to Rules for Ships
“closed” position.
Carrying Dangerous Chemical in Bulk, Volume X.
9.7.5 If on ships other than passenger ships, the
9.1.4 Other cargo ships according to Rules for Hull,
bulkhead penetrations for these pipes are arranged high
Volume II, Section 28, E.
enough and so near to midship that in no damage
9.2 Rules for Hull, Volume II, Section 21, D is to be condition, including at temporary maximum heeling of
additionally applied for scuppers and discharge lines, the ship, will be below the waterline, then the shut off
Volume II, Section 21, E is to be additionally applied valves may be dispensed with.
for vent, overflow and sounding pipes.
For closed cargo holds on passenger ships, see N.4.4.
E. Steam Lines
9.3 For pipe penetrations through watertight
1. Operation
bulkheads, see Rules for Hull, Volume II Section 11,
A.3.4. 1.1 Steam lines are to be so laid out and arranged
that important consumers can be supplied with steam
9.4 Pipelines with open ends in compartments or
from every main boiler as well as from a stand-by
tanks are to be so laid out that no additional
boiler or boiler for emergency operation.
compartments or tanks can be flooded in any damaged
condition to be considered. 1.2 Important consumers are:
9.5 Where shut-off devices are arranged in cross - all consuming units important for the propulsion,
flooding lines of ballast tanks, the position of the manoeuverability and safe operation of the ship
valves is to be indicated on the bridge. as well as the important auxiliary machines
according to Section 1, H.
9.6 For sewage discharge pipe, see T.2.
- all consuming units necessary to the safety of the
9.7 Where it is not possible to lay the pipelines
ship.
outside the damage zone, tightness of the bulkheads is
to be ensured by applying the provision in 9.7.1 to 1.3 Every steam consuming unit must be capable of
9.7.4. being shut off from the system.
9.7.1 In bilge pipelines, a non-return valve is to be 2. Calculation of pipelines
fitted either on the watertight bulkhead through which
the pipe passes to the bilge suction or at the bilge 2.1 Steam lines and valves are to be constructed for
suction itself. the design pressure (PR) according to B.4.1.4.

9.7.2 In ballast water and fuel pipelines for the 2.2 Calculations of pipe thickness and elasticity
filling and emptying of tanks, a shut off valve is to be analysis in accordance with C. are to be carried out.
fitted on the watertight bulkhead through which the Sufficient compensation for thermal expansion is to be
pipe leads to the open end in the tank. proven.

9.7.3 The shut-off valves required in para 9.7.2 3. Laying out of steam lines
11-22 Section 11 - Piping Systems, Valves and Pumps

3.1 Steam lines are to be so installed and supported 1. Feed water pumps
that expected stresses due to thermal expansion,
external loads and shifting of the supporting structure 1.1 At least two feed water pumps are to be provided
under both normal and interrupted service conditions for each boiler installation.
will be safely compensated. 1.2 Feed water pumps are to be so arranged or
3.2 Steam lines are to be so installed that water equipped that no back flow of water can occur when
pockets will be avoided. the pumps are not in operation.

3.3 Means are to be provided for the reliable 1.3 Feed water pumps are to be used only for feeding
drainage of the piping system. boilers.

3.4 Steam lines are to be effectively insulated to 2. Capacity of feed water pumps
prevent heat losses. 2.1 Where two feed water pumps are provided, the
3.4.1 At points where there is a possibility of contact, capacity of each is to be equivalent to at least 1,25
the surface temperature of the insulated steam lines times the maximum permitted output of all the
may not exceed 80 !C. connected steam generators.

3.4.2 Wherever necessary, additional protection 2.2 Where more than two feed water pumps are
arrangements against unintended contact are to be installed, the capacity of all other feed water pumps in
provided. the event of the failure of the pump with the largest
capacity is to comply with the requirements of 2.1.
3.4.3 The surface temperature of steam lines in the
pump rooms of tankers may not exceed 220 oC, see 2.3 For continuous flow boilers the capacity of the
also Section 15. feed water pumps is to be at least 1,0 times the
maximum steam output.
3.5 Steam heating lines, except for heating purposes,
are not to be led through accommodation. 2.4 Special requirements may be approved for the
capacity of the feed water pumps for plants incor-
3.6 Sufficiently rigid positions are to be arranged as porating a combination of oil fired and exhaust gas
fixed points for the steam piping systems. boilers.
3.7 It is to be ensured that the steam lines are fitted 3. Delivery pressure of feed water pumps
with sufficient expansion arrangements.
Feed water pumps are to be so laid out that the deliv-
3.8 Where a system can be supplied from a system ery pressure can satisfy the following requirements:
with higher pressure, the former is to be provided with
reducing valves and relief valves on the low pressure - The required capacity according to 2. is to be
side. achieved against the maximum allowable
working pressure of the steam producer.
3.9 Welded connections in steam lines are subject to
- In case the safety valve is blowing off the
the requirements specified in Rules for Welding,
delivery capacity is to be 1,0 times the approved
Volume VI.
steam output at 1,1 times the allowable working
4. Steam strainers pressure.
Wherever necessary, machines and apparatus in steam The resistance to flow in the piping between the feed
systems are to be protected against foreign matter by water pump and the boiler are to be taken into
steam strainers. consideration. In the case of continuous flow boilers
the total resistance of the boiler must be taken into
5. Steam connections to equipment and pipes account.
carrying oil, e.g. steam atomizers or steamout ar-
rangements, are to be so secured that fuel and oil 4. Power supply to feed water pumps for main
cannot penetrate into the steam lines. boilers
6. Inspection of steam lines for expanding 4.1 For steam-driven feed water pumps, the supply of
all the pumps from only one steam system is allowed
Steam lines for superheated steam at above 500 !C are provided that all the steam producers are connected to
to be provided with means of inspecting the pipe for this steam system. Where feed water pumps are driven
expanding. This can be in the form of measuring solely by steam, a suitable filling and starting up pump
sections on straight lengths of pipe at the superheater which is to be independent of steam is to be provided.
outlet if it is possible. The length of these measuring
sections is to be at least 2 # da. 4.2 For electric drives, a separate lead from the
common bus-bar to each pump motor is sufficient.
5. Feed water lines
F. Boiler Feed Water and Circulating Arrange-
ment, Condensate Recirculation Feed water lines may not pass through tanks which do
Section 11 - Piping Systems, Valves and Pumps 11-23

not contain feed water. 7.2 One storage tank may be considered sufficient
for auxiliary boiler units.
5.1 Feed water lines for main boilers
7.3 Two evaporators are to be provided for main
5.1.1 Each main boiler is to be provided with a steam producer units.
main and an auxiliary feed water line.
8. Condensate recirculation
5.1.2 Each feed water line is to be fitted with a shut
off valve and a check valve at the boiler inlet. Where 8.1 The main condenser is to be equipped with two
the shut off valve and the check valve are not directly condensate pumps, each of which must be able to
connected in series, the intermediate pipe is to be fitted transfer the maximum volume of condensate produced.
with a drain.
8.2 The condensate of all heating systems used to
5.1.3 Each feed water pump is to be fitted with a heat oil (fuel, lubricating, cargo oil etc.) is to be led to
shut off valve on the suction side and a screw-down condensate observation tanks. These tanks are to be
non-return valve on the delivery side. The pipes are to fitted with air vents.
be so arranged that each pump can supply each feed
water line. 8.3. Heating coils of tank containing fuel or oil
residues, e.g. sludge tanks, leak oil tanks, bilge water
5.2 Feed water lines for auxiliary steam tanks etc. are to be provided at the tank outlet with
producers (auxiliary and exhaust gas shut-off devices and devices for testing the condensate
boilers) for the presence of oil. See Section 10, B.5.4.
5.2.1 The provision of only one feed water line for
auxiliary and exhaust gas boilers is sufficient if the
preheaters and automatic regulating devices are fitted G. Oil Fuel Systems
with by-pass lines.
1. Bunker lines
5.2.2 The requirements in 5.1.2 are to apply as
appropriate to the valves required to be fitted to the The bunkering of oil fuels is to be effected by means
boiler inlet. of permanently installed lines either from the open
deck or from bunkering stations located below deck
5.2.3 Continuous flow boilers need not be fitted which are to be isolated from other spaces.
with the valves required according to 5.1.2 provided
that the heating of the boiler is automatically switched Bunker stations are to be so arranged that the
off should the feed water supply fail and that the feed bunkering can be performed from both sides of the
water pump supplies only one boiler. ship without danger. This requirement is considered to
be fulfilled where the bunkering line is extended to
6. Boiler water circulating systems both sides of the ship. The bunkering lines are to be
6.1 Each forced-circulation boiler is to be fitted with blind flanges on deck.
equipped with two circulating pumps powered inde- 2. Tank filling lines and suction lines
pendently of each other. Failure of the circulating
pump in operation is to be signaled by an alarm. The 2.1 Filling and suction lines from storage, settling
alarm may only be switched off if a circulating pump and daily service tanks situated above the double
is started or when the boiler firing is shut down. bottom and in case of their damage fuel oil may leak,
are to be fitted directly on the tanks with shut off
6.2 The provision of only one circulating pump devices capable of being closed from a safe position
for each boiler is sufficient if: outside the space concerned.
- the boilers are heated only by gases whose In the case of deep tanks situated in shaft or pipe
temperature does not exceed 400 !C or tunnel or similar spaces, shut off devices are to be
- a common stand-by circulating pump is provided fitted on the tanks. The control in the event of fire may
which can be connected to any boiler or be effected by means of an additional shut off device
in the pipe outside the tunnel or similar space. If such
- the burners of oil or gas fired auxiliary boilers additional shut off device is fitted in the machinery
are so arranged that they are automatically shut space it shall be operated from a position outside this
off should the circulating pump fail and the heat space.
stored in the boiler does not cause any
unacceptable evaporation of the available water 2.2 Shut-off devices on fuel oil tanks having a
in the boiler. capacity of less than 500 liters need not be provided
with remote control.
7. Feed water supply, evaporators
2.3 Filling lines are to extend to the bottom of the
7.1 The feed water supply is to be stored in several tank. Short filling lines directed to the side of the tank
tanks. may be admissible.
11-24 Section 11 - Piping Systems, Valves and Pumps

Storage tank suction lines may also be used as filling 3.6 Glass and plastic components are not permitted
lines. in fuel systems.
2.4 Where filling lines are led through the tank top Sight glasses made of glass located in vertical
and end below maximum oil level in the tank, a overflow pipes may be permitted.
non-return valve at the tank top is to be arranged.
3.7 Fuel pumps must be capable of being isolated
2.5 The inlet connections of suction lines are to be from the piping system by shut-off valves.
arranged far enough from the drains in the tank so that
water and impurities which have settled out will not 4. Fuel transfer, feed and booster pumps
enter the suctions. 4.1 Fuel transfer, feed and booster pumps shall be
2.6 For the release of remotely operated shut-off designed for the proposed operating temperature of the
devices, see Section 12, B.10 medium pumped.

3. Pipe layout 4.2 A fuel transfer pump is to be provided. Other


service pumps may be used as a stand-by pump
3.1 Fuel lines may not pass through tanks containing provided they are suitable for this purpose.
feed water, drinking water, lubricating oil or thermal
oil. 4.3 At least two means of oil fuel transfer are to be
provided for filling the service tanks.
3.2 Fuel lines which pass through ballast tanks are to
have an increased wall thickness according to 4.4 Where a feed or booster pump is required to
Table 11.5. supply fuel to main or auxiliary engines, a stand-by
pump shall be provided. Where pumps are attached to
3.3 Fuel lines may not be laid in the vicinity of the engines, a stand-by pump may be dispensed with.
boilers, turbines or equipment with high surface for auxiliary engines.
temperatures (over 220 !C) or in way of other sources
of ignition. 4.5 For emergency shut-down devices, see
Section 12, B.9.
3.4 Flanged and screwed socket connections in fuel
oil lines shall be screened or otherwise suitable 5. Plants with more than one main engine
protected to avoid, as far as practicable, oil spray or oil
leakage onto hot surfaces, into machinery air intakes, For plants with more than one engine, complete spare
or other surfaces of ignition. feed or booster pumps stored on board may be
accepted instead of stand-by pumps provided that the
The number of detachable pipe connections is to be feed or booster pumps are so arranged that they can be
limited. In general, flanged connections according to replaced with the means available on board.
recognized standards shall be used.
For plants with more than one main engine, see also
3.4.1 Flanged and screwed socket connections in Section 2, G.
fuel oil lines which lay directly above hot surfaces or
other sources of ignition are to be screened and 6. Shut-off devices
provided with drainage arrangements.
6.1 On cargo ships of 500 gross tonnage or above
3.4.2 Flanged and screwed socket connections in and on all passenger ships for plants with more than
fuel oil lines with a maximum allowable working one engine shut-off devices for isolating the fuel
pressure of more than 0,18 N/mm2 and with about 3 m supply and overproduction/recirculation lines to any
from hot surfaces or other sources of ignition and engine from a common supply system shall be
direct sight of line must be screened. Drainage provided. These valves shall be operable from a
arrangements need not to be provided position not rendered inaccessible by a fire on any of
the engines.
3.4.3 Flanged and screwed socket connections in
fuel oil lines with a maximum allowable working 6.2 Instead of shut-off devices in the
pressure of more than 0,18 N/mm2 and with about 3 m overproduction/recirculation lines check valves may be
from hot surfaces or other sources of ignition shall be fitted. Where shut-off devices are fitted, they are to be
assessed individual taking into account working locked in the operating position.
pressure, type of coupling and possibility of failure. 7. Filters

3.4.4 Flanged and screwed socket connections in 7.1 Fuel oil filters are to be fitted in the delivery line
fuel oil lines with a maximum allowable working of the fuel pumps.
pressure of more than 1,6 N/mm2 need normally to be 7.2 For ships with Class Notation OT the filter
screened equipment shall satisfy the requirement of Rules for
3.5 Shut off valves in fuel lines in the machinery Automation, Volume VII, Section 2.
spaces are to be operable from above the floor plates. 7.3 Mesh size and filter capacity are to be in
accordance with the requirements of the manufacturer
Section 11 - Piping Systems, Valves and Pumps 11-25

of the engine. 10 Service tanks


7.4 Uninterrupted supply of filtered fuel has to be 10.1 On cargo ships of 500 gross tons or above and all
ensured under cleaning and maintenance conditions of passenger ships two fuel oil service tanks for each type
filter equipment. In case of automatic back-flushing of fuel used on board necessary for propulsion and
filters it is to be ensured that a failure of the automatic vital systems are to be provided. Equivalent
back-flushing will not lead to a total loss of filtration. arrangements may be permitted.
7.5 Back-flushing intervals of automatic back- 10.2 Each service tank shall have a capacity of at least
flushing filters provided for intermittent back-flushing 8 hours at maximum continuous rating of the
are to be monitored. propulsion plant and normal operation load of the
generator plant.
7.6 Fuel oil filters are to be fitted with differential
pressure monitoring. On engines provided for 11. Operation using heavy fuel oils
operation with gas oil only, differential pressure
monitoring may be dispensed with. 11.1 Heating of heavy fuel oil

7.7 Engine for the exclusive operation of emergency 11.1.1 Heavy fuel oil tanks are to be fitted with a
generators and emergency fire pumps may be fitted heating system.
with simplex filters. The capacity of the tank heating system is to be in
7.8 Fuel transfer units are to be fitted with a simplex accordance with the operating requirements and the
filter on the suction side. quality of fuel oil intended to be used.

7.9 For filter arrangement, see Section 2, G.3. With BKI’s consent, storage tanks need not be fitted
with a heating system provided it can be guaranteed
8. Purifiers that the proposed quality of fuel oil can be pumped
under all ambient and environmental conditions.
8.1 Manufacturer of purifiers for cleaning fuel and
lubricating oil must be approved by BKI. For the tank heating system, see Section 10, B.5.
8.2 Where a fuel purifier may exceptionally be used 11.1.2 Heat tracing is to be arranged for pumps,
to purify lubricating oil the purifier supply and filters and oil fuel lines as required.
discharge lines are to be fitted with a change-over ar-
rangement which prevents the possibility of fuel and 11.1.3 Where it is necessary to preheat injection
lubricating oils being mixed. valves of engines running with heavy fuel oil, the in-
jection valve cooling system is to be provided with
Suitable equipment is also to be provided to prevent additional means of heating.
such mixing occurring over control and compression
lines. 11.2 Treatment of heavy fuel oil

8.3 The sludge tanks of purifiers are to be fitted with 11.2.1 Settling tanks
a level alarm which ensures that the level in the sludge Heavy fuel settling tanks or equivalent arrangements
tank cannot interfere with the operation of the purifier. with sufficiently dimensioned heating systems are to
9 Oil firing equipment be provided

Oil firing equipment shall be installed in accordance Settling tanks are to be provided with drains, emptying
with Section 9. Pumps, pipelines and fittings are arrangements and with temperature measuring
subject to the following requirements. instruments.

9.1 Oil fired main boilers shall be equipped with at 11.2.2 Heavy fuel oil cleaning for diesel engines
least two service pumps and two pre-heaters. For filter For cleaning of heavy fuels, purifiers or purifiers
see 7. Pumps and heaters are to rated and arranged that combined with automatic filters are to be provided.
the oil firing equipment remains operational even if
one unit should fail.
This also applies to oil fired auxiliary boilers and 11.2.3 Fuel oil blending and emulsifying
thermal oil heaters unless other means are provided for equipments
maintaining continuous operation at sea even if a Heavy fuel oil/diesel oil blending and emulsifying
single unit fails. equipments require approval by BKI.
9.2 Hose assemblies for the connection of the burner 11.3 Service tanks
may be used. Hose assemblies shall not be longer than
required for retracting of the burners for purpose of 11.3.1 For the arrangement and equipment of
routine maintenance. Only approved hose assemblies service tanks, see Section 10, B.
may be used.
11.3.2 The capacity of the service tanks shall be
11-26 Section 11 - Piping Systems, Valves and Pumps

such that, should the treatment plant fail, the supply to 11.6 End preheaters
all the connected consumers can be maintained for at
least 8 hours. Two mutually independent end preheaters are to be
provided.
11.3.3 Where the overflow pipe of the service tank
is terminated in the settling tanks, suitable means shall The arrangement of only one preheater may be ap-
be provided to ensure that no untreated heavy fuel oil proved where it is ensured that the operation with fuel
can penetrate into the service tank in case of over- oil which do not need preheating can be temporary
filling of a settling tank. maintained. The necessary tanks for such fuel oil are
to be arranged.
11.3.4 Daily service tanks are to be provided with
drains and with discharge arrangements. 11.7 Viscosity control

11.4 Change-over arrangement diesel oil/ 11.7.1 Where main and auxiliary engines are oper-
heavy oil ated on heavy fuel oil, automatic viscosity control is to
be provided.
11.4.1 The change-over arrangement of the fuel
supply and return lines is to be so arranged that faulty 11.7.2 Viscosity regulators are to be fitted with a
switching is excluded and to ensure reliable separation local temperature indicator.
of the fuels. 11.7.3 Local control devices
Change-over valves which allow interpositions are not The following local control devices are to be fitted
permitted. directly before the engine
11.4.2 The change-over devices are to be accessible - a pressure gauge,
and permanently marked. Their respective working
position must be clearly indicated. - a temperature indicator.

11.4.3 Remote controlled change-over devices are to 11.8 The heavy fuel system is to be effectively
be provided with limit position indicators at the control insulated as necessary.
platforms.
11.5 Fuel supply through stand pipes H. Lubricating Oil Systems
11.5.1 Where the capacity of stand pipes exceeds 1. General requirements
500 litres, the outlet pipe is to be fitted with a remote
controlled quick-closing valve operated from outside 1.1 Lubricating oil systems are to be constructed to
the engine room. Stand pipes are to be equipped with ensure reliable lubrication over the whole range of
air/gas vents and with self-closing connections for speed and during run-down of the engines and to
emptying and draining. Stand pipes are to be fitted ensure adequate heat transfer.
with a local temperature indicator.
1.2 Priming pumps
11.5.2 Atmospheric stand-pipes (pressureless)
Where necessary, priming pumps are to be provided
Having regard to the arrangement and the maximum for supplying lubricating oil to the engines.
fuel level in the service tanks, the stand-pipes are to be
so located and arranged that a sufficient free space for 1.3 Emergency lubrication
degasification is available inside the stand pipes. A suitable emergency lubricating oil supply (e.g.
11.5.3 Closed stand-pipes (pressurized systems) gravity tank) is to be arranged for machinery which
may be damaged in case of interruption of lubricating
Closed stand-pipes are to be designed as pressure oil supply.
vessels and are to be fitted with the following
equipment: 1.4 Lubricating oil treatment

- a non-return valve in the recirculating lines from 1.4.1 Equipment necessary for adequate treatment
the engines, of lubricating oil such as purifiers, automatic
back-flushing filters, filters and free-jet centrifuges are
- an automatic degases or a gas blanket monitor to be provided.
with manual degases,
1.4.2 In the case of auxiliary engines running on
- a local pressure gauge, heavy fuel which are supplied from a common
lubricating oil tank, suitable equipment is to be fitted
- a local temperature indicator,
to ensure that in case of failure of the common
- a drain/emptying device, which is to be locked in lubricating oil treatment system of ingress of fuel or
the closed position. cooling water into the lubricating oil circuit, the
auxiliary engines required to safeguard the power
supply in accordance with the Rules for Electrical
Section 11 - Piping Systems, Valves and Pumps 11-27

Installation, Volume IV, Section 3.C remain fully of filtration.


operational.
2.3.4 Back-flushing intervals of automatic back-
2. Lubricating oil systems flushing filter provided for intermittent back-flushing
are to be monitored
2.1 Lubricating oil circulating tanks and
gravity tanks 2.3.5 Main lubricating oil filters are to be fitted
with differential pressure monitoring. On engines
2.1.1 For the capacity and location of these tanks provided for operation with gas oil only, differential
see Section 10, C. pressure monitoring may be dispensed with.
2.1.2 Where an engine lubricating oil circulation 2.3.6 Engines for the exclusive operation of
tank extends to the bottom shell plating on ships for emergency generators and emergency fire pumps may
which a double bottom is required in the engine room, be fitted with simplex filters.
shut-off valve are to be fitted in the drain pipes
between engine casing and circulating tank. These 2.3.7 For the protection of the lubricating oil
valves are to be capable of being closed from a level pumps, simplex filter may be installed on the suction
above the lower platform. side of the pumps if they have a minimum mesh size of
100 µ.
2.1.3 The suction connections of lubricating oil
pumps are to be located as far as possible from drain 2.3.8 For the arrangement of filters, see Section 2,
pipes. G.3.
2.1.4 Gravity tank is to be fitted with an overflow 2.4 Lubricating oil coolers
pipe which leads to the circulating tank. Arrangements
are to be made for observing the flow of excess oil in It is recommended that turbine and large engine plants
the overflow pipe. be provided with more than one oil cooler.

2.2 Filling and suction lines 2.5 Oil level indicators


Machines with their own oil charge are to be provided
2.2.1 Filling and suction lines of lubricating oil
with a means of determining the oil level from outside
tanks with capacity of 500 litres and more and located
during operation. This requirement also applies to
above the double bottom and which in case of their
reduction gears, thrust bearings and shaft bearings.
damaged lubricating oil may leak, are to be fitted with
directly on the tanks with shut-off devices according to 2.6 Purifiers
G.2.1. The remote operation of shut off devices
according to G.2.1, which are kept closed during The requirements in G.7 apply as appropriate.
normal operation, can be dispensed with. 3. Lubricating oil pumps
S for valves which are kept closed during normal 3.1 Main engines
operation.
3.1.1 Main and independent stand-by pumps are to
S where an unintended operation of a quick closing
be arranged.
valve would endanger the safe operation of the
main propulsion plant or essential auxiliary Main pumps driven by the main engines are to be so
machinery designed that the lubricating oil supply is ensured over
the whole range of operation.
2.2.2 Where lubricating oil lines must be led in the
vicinity of hot machinery, e.g. superheated steam 3.1.2 For plants with more than one main engine,
turbines, steel pipes which should be in one length and see Section 2, G.4.2.3.
which are protected where necessary are to be used.
2.2.3 For screening arrangements of lubricating oil
pipes G.3.4 applies as appropriate. 3.2 Main turbine plant
2.3 Filters 3.2.1 Main and independent stand-by lubricating oil
2.3.1 Lubricating oil filters are to be fitted in the pumps are to be provided.
delivery lines of the lubricating oil pumps. 3.2.2 Emergency lubrication
2.3.2 Mesh size and filter capacity are to be in The lubricating oil supply to the main turbine plant for
accordance with the requirements of the engine cooling the bearings during the run-down period is to
manufacturer.. be assured in the event of failure of the power supply.
2.3.3 Uninterrupted supply of filtered lubricating By means of suitable arrangements such as gravity
oil has to be ensured under cleaning and maintenance tanks the supply of oil is also to be assured during
conditions of filter equipment. In case of automatic starting of the emergency lubrication system.
back-flushing filters it is to be ensured that a failure of 3.3 Main reduction gearing (motor vessels)
the automatic back-flushing will not lead to a total loss
11-28 Section 11 - Piping Systems, Valves and Pumps

3.3.1 Lubricating oil is to be supplied by a main valves fitted directly to the sea chests. Compressed air
pump and an independent stand-by pump. for blowing through sea chest gratings may exceed 2
bar only if the sea chests are constructed for higher
3.3.2 Where a reduction gear has been approved by pressures.
the BKI to have adequate self-lubrication at 75 % of
the torque of the propelling engine, a stand-by 1.6 Where a sea chest is exclusively arranged as
lubricating oil pump for the reduction gear may be chest cooler the steam or compressed airlines for
dispensed with up to a power ratio of clearing, may with BKI’s agreement, be dispensed
with according to 1.5.
P/nl [kW/Rpm] " 3,0
2. Special rules for ships with ice class
nl [Rpm] gear input revolution
2.1 For one of the sea chests specified in 1.1 the sea
3.3.3 The requirements under 3.1.2 are to be ap- inlet is to be located as near as possible to midship and
plied for multi-propeller plants and plants with more as far as possible to aft. The seawater discharge line of
than one engine. the entire engine plant is to be connected to the top of
3.4 Auxiliary machinery the sea chest.

3.4.1 Diesel generators 2.1.1 For ships with ice class ES 1 to ES 4 the sea
chest is to be arranged as follows:
Where more than one diesel generator is available,
stand-by pumps are not required. - In calculating the volume of the chest the
following value shall be applied as a guide
Where only one diesel generator is available (e.g. on
turbine-driven vessels where the diesel generator is about 1 m3 for every 750 kW of the ship's engine
needed for start-up etc.) a complete spare pump is to output including the output of auxiliary engines.
be carried on board. - The sea chest shall be of sufficient height to
3.4.2 Auxiliary turbines allow ice to accumulate above the inlet pipe.

Turbogenerators and turbines used for driving


- The free area of the strum holes shall be not less
important auxiliaries such as boiler feed water pumps
than four times the sectional area of the inlet
etc. are to be equipped with a main pump and an
pipe.
independent auxiliary pump. The auxiliary pump is to
be designed to ensure a sufficient supply of lubricating 2.1.2 As an alternative two smaller sea chests of a
oil during the start-up and run-down operation. design as specified in 2.1.1 may be arranged.
2.1.3 All discharge valves shall be so arranged that
I. Seawater Cooling Systems the discharge of water at any draught will not be
obstructed by ice.
1. Sea suctions, sea chests
2.2 Where necessary, a steam connection or a
1.1 At least two sea chests are to be provided. heating coil is to be arranged for de-icing and thawing
Wherever possible, the sea chests are to be arranged as the sea chests.
low as possible on either side of the ship.
2.3 Additionally, cooling water supply to the engine
1.2 For service in shallow waters, it is recommended plant may be arranged from ballast tanks with
that an additional high seawater intake should be circulation cooling.
provided.
This system does not replace the requirement stated in
1.3 It is to be ensured that the total seawater supply 2.1.1.
for the engines can be taken from only one sea chest.
2.4 For the fire pumps, see Section 12, E.1.3.6.
1.4 Each sea chest is to be provided with an effective
3. Sea valves
vent. The following venting arrangements will be
approved: 3.1 Sea valves are to be so arranged that they can be
- an air pipe of at least 32 mm ID which can be operated from above the floor plates.
shut off and which extends above the bulkhead 3.2 Discharge pipes for seawater cooling systems are
deck to be fitted with a shut-off valve at the shell.
- adequately dimensioned ventilation slots in the 4. Strainer
shell plating.
The suction lines of the seawater pumps are to be fitted
1.5 Steam or compressed air connections are to be with strainers.
provided for clearing the sea chest gratings. The steam
or compressed air lines are to be fitted with shutoff The strainers are to be so arranged that they can be
cleaned during services.
Section 11 - Piping Systems, Valves and Pumps 11-29

Where cooling water is supplied by means of a scoop, 5.3 Plants with more than one main engine
strainers in the main seawater cooling line can be
dispensed with. For plants with more than one engine and with
separate cooling water systems, complete spare pumps
5. Seawater cooling pumps on board may be accepted instead of stand-by pumps
provided that the main seawater cooling pumps are so
5.1 Diesel engine plants arranged that they can be replaced with the means
5.1.1 Main propulsion plants are to be provided available on board.
with main and stand-by cooling water pumps. 5.4 Cooling water supply for auxiliary engines
5.1.2 The main cooling water pump may be Where a common cooling water pump is provided to
attached to the propulsion plant. It is to be ensured that serve more than one auxiliary engine, an independent
the attached pump is of sufficient capacity for the stand-by cooling water pump with the same capacity
cooling water required by main engine and auxiliary is to be fitted. Independently operated cooling water
equipments over the whole speed range of the pumps of the main engine plant may be used to supply
propulsion plant. cooling water to auxiliary engines while at sea,
The drive of the stand-by cooling water pump is to be provided that the capacity of such pumps is sufficient
independent of the main engine. to meet the additional cooling water requirement.

5.1.3 Main and stand-by cooling water pumps are If each auxiliary engine is fitted with an attached
each to be of sufficient capacity to meet the maximum cooling water pump, no stand-by cooling water pumps
cooling water requirements of the plant. need be provided.

Alternatively, three cooling water pumps of the same 6. Cooling water supply in dock
capacity and delivery head may be arranged, provided It is recommended that a supply of cooling water, e.g.
that two of the pumps are sufficient to supply the from a water ballast tank, should be available so that at
required cooling water for full load operation of the least one diesel generator and, if necessary, the
plant. domestic refrigerating plant may be run when the ship
With this arrangement it is permissible for the second is in dock.
pump to be automatically put into operation only in the Cargo and container cooling systems shall conform to
higher temperature range by means of a thermostat. the requirements stated in Rules for Refrigerating
5.1.4 Ballast pumps or other suitable seawater Installations, Volume VIII, Section l, I.4.
pumps may be used as stand-by cooling water pumps.
5.1.5 Where cooling water is supplied by means of
a scoop, the main and stand-by cooling water pumps K. Fresh Water Cooling Systems
are to be of a capacity which will ensure reliable
operation of the plant under partial load conditions and 1. General
astern operation as required in Section 2, E.5.1.1.e). 1.1 Fresh water cooling systems are to be so
The main cooling water pump is to be automatically arranged that the engines can be sufficiently cooled
started as soon as the speed falls below that required under all operating conditions.
for the operation of the scoop.
1.2 Depending on the requirements of the engine
5.2 Steam turbine plants plant, the following fresh water cooling systems are
5.2.1 Steam turbine plants are to be provided with allowed:
a main and a stand-by cooling water pump. - a single cooling circuit for the entire plant
The main cooling water pump is to be of sufficient - separate cooling circuits for the main and
capacity to supply the maximum cooling water auxiliary plant
requirements of the turbine plant. The capacity of the
stand-by cooling water pump is to be such as to ensure - several independent cooling circuits for the main
reliable operation of the plant also during astern engine components which need cooling (e.g.
operation. cylinders, pistons and fuel valves) and for the
auxiliary engines
5.2.2 Where cooling water is supplied by means of
a scoop, the main cooling water pump is to be of - separate cooling circuits for various temperature
sufficient capacity for the cooling water requirements ranges.
of the turbine plant under conditions of maximum
1.3 The cooling circuits are to be divided that, should
astern output.
one of the circuits fail, operation of the auxiliary
The main cooling water pump is to start automatically systems can be maintained.
as soon as the speed falls below that required for the
Change-over arrangements are to be provided for this
operation of the scoop.
11-30 Section 11 - Piping Systems, Valves and Pumps

purpose if necessary. damage to or faults in one system cannot affect the


other system.
1.4 As far as possible, the temperature controls of
main and auxiliary engines as well as of different 3.2 Expansion tanks are to be fitted with filling
circuits are to be independent of each other. connections, aeration/de-aeration devices, water level
indicators and drains.
1.5 Where, in automated engine plants, heat
exchanger for fuel or lubricating oil are incorporated in 4. Fresh water cooling pumps
the cylinder cooling water circuit of main engines, the
entire cooling water system is to be monitored for fuel 4.1 Main and stand-by cooling water pumps are to be
and oil leakage. provided for each fresh water cooling system.

1.6 Common cooling water systems for main and 4.2 Main cooling water pumps may be driven
auxiliary plants are to be fitted with shut off valves to directly by the main or auxiliary engines which they
enable repairs to be performed without taking the are intended to cool provided that a sufficient supply
entire plant out of service. of cooling water is assured under all operating
conditions.
2. Heat exchanger, coolers
4.3 The drives of stand-by cooling water pumps are
2.1 The construction and equipment of heat to be independent of the main engines.
exchanger and coolers are subject to requirement of
Section 8. 4.4 Stand-by cooling water pumps are to have he
same capacity as main cooling water pumps.
2.2 The coolers of cooling water systems, engines
and equipment are to be constructed to ensure that the 4.5 Main engines are to be fitted with at least one
specified cooling water temperatures can be main and one stand-by cooling water pump. Where
maintained under all operating conditions. Cooling according to the construction of the engines more than
water temperatures are to be adjusted to meet the one water cooling circuit is necessary, a stand-by
requirements of engines and equipment. pump is to be fitted for each main cooling water pump.

2.3 Heat exchangers for auxiliary equipment in the 4.6 For fresh cooling water pumps of essential
main cooling water circuit are to be provided with auxiliary engines the requirements for sea water
by-passes if by this means it is possible, in the event of cooling pumps in I.5.4 may be applied.
a failure of the heat exchanger, to keep the system in 4.7 A stand-by cooling water pump of a cooling
operation. water system may be used as a stand-by pump for
2.4 It is to be ensured that auxiliary machinery can another system provided that the necessary pipe
be maintained in operation while repairing the main connections are arranged. The shut-off valves in these
coolers. If necessary, means are to be provided for connections are to be secured against unintended
changing over to other heat exchangers, machinery or operation.
equipment through which a temporary heat transfer 4.8 Equipment providing for emergency cooling
can be achieved. from another system can be approved if the plant and
2.5 Shut-off valves are to be provided at the inlet and system are suitable for this purpose.
outlet of all heat exchanger. 4.9 For plants with more than one main engine the
2.6 Every heat exchanger and cooler is to be requirements for sea water cooling pumps in I.5.3 may
provided with a vent and a drain. be applied.

2.7 Keel coolers, box coolers 5. Temperature control

2.7.1 Arrangement and construction drawings of Cooling water circuits are to be provided with
keel and box coolers are to be submitted for approval. temperature controls in accordance with the
requirements. Control devices whose failure may
2.7.2 Permanent vents for fresh water are to be impair the functional reliability of the engine are to be
provided at the top of keel coolers and box coolers. equipped or manual operation.
2.7.3 Keel coolers are to be fitted with pressure 6. Preheating for cooling water
gauge connections at the fresh water inlet and outlet.
Means are to be provided for preheating fresh cooling
3. Expansion tanks water. Exception are to be approved by BKI.
3.1 Expansion tanks are to be arranged at sufficient 7. Emergency generating units
height for every cooling water circuit.
Internal combustion engines driving emergency
Different cooling circuits may only be connected to a generating units are to be fitted with independent
common expansion tank if they do not interfere with cooling systems. Such cooling systems are to be made
each other. Care must be taken here to ensure that proof against freezing.
Section 11 - Piping Systems, Valves and Pumps 11-31

when laying out and suspending the lines.


1.3 Where exhaust gas lines discharge near water
L. Compressed Air Lines level, provisions are to be taken to prevent water from
1. General entering the engines.

1.1 Pressure lines connected to air compressors are 2. Silencers


to be fitted with non-return valves at the compressor Engine exhaust pipes are to be fitted with effective
outlet. silencers or other suitable means are to be provided.
1.2 For oil and water separators, see Section 2, 3. Water drains
M.4.3.
Exhaust lines and silencers are to be provided with
1.3 Starting air lines may not be used as filling lines suitable drains of adequate size.
for air receivers.
4. Insulation
1.4 Only type-tested hose assemblies made of
metallic materials may be used in starting air lines of Insulation of exhaust gas lines inside machinery
diesel engines which are permanently kept under spaces, see Section 12, B.4.1.
pressure. 5. For special requirements for tankers refer to Sec-
1.5 The starting air line to each engine is to be fitted tion 15, B.9.3.
with a non-return valve and a drain. Engine exhaust gas lines are additionally subject to
1.6 Tyfons are to be connected to at least two Section 2, G.7.
compressed air receivers.
1.7 A safety valve is to be fitted behind each
pressure-reducing valve. N. Bilge Systems
1.8 Pressure water tanks and other tanks connected 1. Bilge lines
to the compressed air system are to be considered as
pressure vessels and must comply with the 1.1 Layout of bilge lines
requirements in Section 8 relating to the working 1.1.1 Bilge lines and bilge suction are to be so
pressure of the compressed air system. arranged that the bilges can be completely drained
1.9 For compressed air connections for blowing even under unfavorable trim conditions.
through sea chests refer to I.1.5. 1.1.2 Bilge suction are normally to be located on
1.10 For compressed air supply to pneumatically both sides of the ship. For compartments located fore
operated valves and quick-closing valve refer to D.6. and aft in the ship, one bilge suction may be consid-
ered sufficient provided that it is capable of completely
1.11 Requirements for starting engines with com- draining the relevant compartment.
pressed air, see Section 2.H.2.
1.1.3 Spaces located forward of the collision
2. Control air systems bulkhead and aft of the stern tube bulkhead and not
connected to the general bilge system are to be drained
2.1 Control air systems for essential consumers are
by other suitable means of adequate capacity.
to be provided with the necessary means of air
treatment. 1.1.4 The required pipe thicknesses of bilge lines
are to be in accordance with Table 11.5.
2.2 Pressure reducing valves in the control air system
of main engines are to be redundant. 1.2 Pipes laid through tanks
1.2.1 Bilge pipes may not be led through tanks for
lubricating oil, thermal oil, drinking water or feed
water.
M. Exhaust Gas Lines
1.2.2 Bilge pipes from space not be accessible
1. Pipe layout during the voyage if running through fuel tanks located
above double bottom are to be fitted with a non-return
1.1 Engine exhaust gas pipes are to be installed valve directly at the point of entry into the tank.
separately from each other, taking into account the
structural fire protection. Other designs are to be 1.3 Bilge suction and strums
submitted for approval. The same applies to boiler
1.3.1 Bilge suction are to be so arranged as not to
exhaust gas pipes.
impede the cleaning of bilges and bilge wells. They are
1.2 Account is to be taken of thermal expansion to be fitted with easily detachable, corrosion resistant
strums.
11-32 Section 11 - Piping Systems, Valves and Pumps

1.3.2 Emergency bilge suction are to be arranged in


such a manner that they are accessible, with free flow (4)
and at a suitable distance from the tank top or the
ship's bottom. b) Branch bilge pipes

1.3.3 For the size and design of bilge wells see


(5)
Rules for Hull Construction, Volume II, Section 8.
B.6.2.
where
1.3.4 Bilge alarms of main and auxiliary machinery
spaces, see Section 1, E.5 and Rules for Automation, dH [mm] calculated inside diameter of main
Volume VII, Section 6, H bilge pipe

1.4 Bilge valves dz [mm] calculated inside diameter of branch


bilge pipe
1.4.1 Valves in connecting pipes between the bilge
and the seawater and ballast water system, as well as L [m] length of ship between
between the bilge connections of different perpendiculars
compartments, are to be so arranged that even in the B [m] moulded breadth of ship
event of faulty operation or intermediate positions of
the valves, penetration of seawater through the bilge H [m] depth of ship to the bulkhead deck
system will be safely prevented.
[m] length of the watertight
1.4.2 Bilge discharge pipes are to be fitted with compartment
shut off valves at the ship's shell.
1.4.3 Bilge valves are to be arranged so as to be 2.3 Tankers
always accessible irrespective of the ballast and
loading condition of the ship. The diameter of the main bilge pipe in the engine
rooms of tankers and bulk cargo/oil carriers is cal-
1.5 Reverse-flow protection culated using the formula:
A screw-down non-return valve or a combination of a
non-return valve without positive means of closing and (6)
a shut-off valve are recognized as reverse-flow
protection.
where:
1.6 Pipe layout
1 [m] total length of spaces between
1.6.1 To prevent the ingres of ballast and seawater
into the ship through the bilge system, two means of cofferdam or pump-room bulkhead
reverse-flow protection are to be fitted in the bilge and stern tube bulkhead
connections. Other terms as in formulae (4) and (5).
One of such means of protection is to be fitted in each Branch bilge pipes are to be dimensioned in
suction line. accordance with 2.2 b). For bilge installations for
1.6.2 The direct bilge suction and the emergency spaces in the cargo area of tankers and bulk cargo/oil
injection need only have one means of reverse-flow carriers see Section 15.
protection as specified in 1.5.1. 2.4 Minimum diameter
1.6.3 Where a direct seawater connection is The inside diameter of main and branch bilge pipes is
arranged for attached bilge pumps to protect them not to be less than 50 mm. For ships under 25 m
against running dry, the bilge suction are also to be length, the diameter may be reduced to 40 mm.
fitted with two reverse flow protecting devices.
3. Bilge pumps
1.6.4 The discharge lines of oily water separators
are to be fitted with a reverse flow protecting valve at 3.1 Capacity of bilge pumps
the ship's side.
Each bilge pump must be capable of delivering:
2. Calculation of pipe diameters
(7)
2.1 The calculated values according to formulae (4)
to (6) are to be rounded up to the next higher nominal
diameter. where:

2.2 Dry cargo and passenger ships Q [m3/h] minimum capacity

a) Main bilge pipes dH [mm] calculated inside diameter of main


Section 11 - Piping Systems, Valves and Pumps 11-33

bilge pipe b) through one direct suction connected to the


largest independent bilge pump
3.2 Where centrifugal pumps are used for bilge
pumping, they must be self-priming or connected to an c) through an emergency bilge suction
air extracting device. connected to the cooling water pump of the
main propulsion plant or through another
3.3 One bilge pump with a smaller capacity than suitable emergency bilge system.
that required according to formula (7) is acceptable
provided that the other pump is designed for a 4.1.2 If the ship's propulsion plant is located in
correspondingly larger capacity. However, the capacity several spaces, a direct suction in accordance with
of the smaller bilge pump shall not be less than 85 % 4.1.1 b) is to be provided in each watertight
of the calculated capacity. compartment in addition to branch bilge suction, in
accordance with 4.1.1 a).
3.4 Use of other pumps for bilge pumping
When the direct suctions are in use, it must be possible
3.4.1 Ballast pumps, stand-by seawater cooling to pump simultaneously from the main bilge line by
pumps and general service pumps may also be used as means of all the other bilge pumps.
independent bilge pumps provided they are self-
priming and of the required capacity according to The diameter of the direct suction may not be less than
formula (7). that of the main bilge pipe.
3.4.2 In the event of failure of one of the required 4.1.3 On steam ships the diameter of the emergency
bilge pumps, one pump each must be available for fire bilge suction in accordance with 4.1.1 c) is to be at
fighting and bilge pumping. least 2/3 of the diameter and on motor ships equal to
the diameter of the cooling water pump suction line.
3.4.3 Fuel and oil pumps may not be connected to Exceptions to this requirements the approval of BKI.
the bilge system. The emergency bilge suction must be connected to the
3.4.4 Bilge ejectors are acceptable as bilge cooling water pump suction line by a reverse-flow
pumping arrangements provided that there is an protection according to I.5.
independent supply of driving water. This valve is to be provided with a plate with the
3.5 Number of bilge pumps for cargo ships notice :

Cargo ships are to be provided with two independent, Emergency bilge valve!
To be opened in an emergency only!
power bilge pumps. On ships up to 2000 tons gross,
one of these pumps may be attached to the main Emergency bilge valves and cooling water inlet valves
engine. must be capable of being operated from above the
floor plates.
On ships of less than 100 tons gross, one engine driven
bilge pump is sufficient. The second independent bilge 4.1.4 Rooms and deck in engine rooms are to be
pump may be a permanently installed manual bilge provided with drains to the engine room bilge. A drain
pump. The engine-driven bilge pump may be coupled pipe which passes through a watertight bulkhead is to
to the main propulsion plant. be fitted with a self-closing valve.
4.2 Shaft tunnel
3.6 Number of bilge pumps for passenger A bilge suction is to be arranged at the aft end of the
ships shaft tunnel. Where the shape of the bottom or the
length of the tunnel requires, an additional bilge
At least three bilge pumps are to be provided. One
suction is to be provided at the forward end. Bilge
pump may be coupled to the main propulsion plant.
valves for the shaft tunnel are to be arranged outside
Where the criterion numeral is 306) or more, an
the tunnel in the engine room.
additional bilge pump is to be provided.
4.3 Cargo holds
4. Bilge pumping for various spaces
4.3.1 Cargo holds are to be normally fitted with
4.1 Machinery spaces
bilge suctions fore and aft.
4.1.1 On ships of more than 100 tons gross, the
For water ingress protection systems, see Rules for
bilges of every main machinery space must be capable
Electrical Installations, Volume IV, Section 18,
of being pumped as follows:
B.4.1.9
a) through the bilge suctions connected to the
4.3.2 Cargo holds having a length under 30 m may
main bilge system,
be provided with only one bilge suction on each side.
4.3.3 On ships with only one cargo hold, bilge
6
wells are to be provided fore and aft.
) See SOLAS 1974, Chapter II-1, Part B, Regulation 6.
11-34 Section 11 - Piping Systems, Valves and Pumps

4.3.4 For cargo holds for the transport of - water contaminated with petrol or other
dangerous goods, see Section 12, P.7. dangerous sunstances is not drained to
machinery spaces where sources of ignition
4.3.5 In all Ro/Ro cargo spaces below the bulkhead may be present,
deck where a pressure water spraying system
according to Section 12, L.2.3 is provided, the - where the enclosed cargo space is protected
following is to be complied with : by a carbon dioxide fire extinguishing system
the deck scuppers are fitted with means to
S the drainage system shall have a capacity of prevent the escape of the smothering gas.
not less than 1,25 times of the capacity of
both the water spraying system pumps and 4.5 Spaces which may be used for ballast
required number of fire hose nozzles water, oil or dry cargo
S the valve of drainage arrangement shall be Where dry-cargo holds are also intended for carrying
operable from outside the protected space at ballast water or oils, the branch bilge pipes from these
a position in the vicinity of the drencher spaces are to be connected to the ballast or cargo pipe
system controls system only by change-over valves/connections.
S bilge wells shall be of sufficient holding The change-over valves must be so designed that an
capacity and shall be arranged on either side intermediate positioning does not connect the different
directly at the longitudinal bulkhead, not piping systems. Change-over connections are to be
more than 40 m longitudinally apart from such that the pipe not connected to the cargo hold is to
each other. be blanked off.
If in cargo ships above arrangements are not possible, For spaces which are used for dry cargo and ballast
the additional weight of water and the influence of the water the change over connection shall be so that the
free surfaces is to be taken into account in the ship’s system (bilge or ballast system) not connected to the
stability information. cargo hold can be blanked off.
4.6 Refrigerated cargo spaces
4.4 Closed cargo holds above bulkhead decks Refrigerated cargo spaces and thawing trays are to be
and above freeboard decks provided with drains which cannot be shut off. Each
drain pipe is to be fitted at its discharge end with a trap
4.4.1 Cargo holds above bulkhead decks of to prevent the transfer of heat and odours.
passenger ships or freeboard decks of cargo ships are
to be fitted with drainage arrangements. 4.7 Spaces for transporting livestock
4.4.2 The drainage arrangements shall have a Spaces intended for the transport of livestock are to be
capacity that under consideration of a 5o list of the additionally fitted with pumps or ejectors for dis-
ship, at least 1,25 times both the capacity of the water charging the waste overboard.
spraying systems and required number of fire hose
nozzles can be drained 4.8 Spaces above fore and aft peaks
These spaces shall either be connected to the bilge
4.4.3 Closed cargo holds may be drained directly to
system or are to be drained by means of hand pumps.
overboard, only when at a heel of the ship of 5o, the
edge of the bulkhead deck or freeboard deck will not Spaces located above the aft peak may be drained to
be immersed. the shaft tunnel or to the engine room bilge, provided
the drain line is fitted with a self-closing valve which
Drains from scuppers to overboard are to be fitted with
is to be located at a highly visible and accessible
reverse flow protecting devices according to, Rules for
position. The drain lines shall have a diameter of at
Hull Construction, Volume II, Section 21.
least 40 mm.
4.4.4 Where the edge of the deck, when the ship
4.9 Cofferdams, pipe tunnels and void spaces
heel 5o is located at or below the summer load line
(SLL) the drainage shall be led to bilge wells or drain Cofferdams, pipe tunnels and void spaces adjoining
tanks with adequate capacity. the ship's shell are to be connected to the bilge system.
4.4.5 The drainage tanks are to be fitted with a high Where the after peak is adjoining the engine room, it
level alarm and are to be provided with draining may be drained over a self-closing valve to the engine
arrangements with a capacity according to 4.4.2. room bilge.

4.4.6 It is to be ensured that For cofferdams, pipe tunnels and void spaces located
above the deepest load water line equivalent means
- bilge arrangements prevent excessive may be accepted by BKI after special agreement.
accumulation of free water,
4.10 Drainage systems of spaces between bow
Section 11 - Piping Systems, Valves and Pumps 11-35

doors and inner doors on Ro-Ro valves shall not move from the demanded position.
ships.
4.13.6 Bilge wells shall comply with 1.3.1.
A drainage system is to be arranged in the area
between bow door and ramp, as well as in the area 4.13.7 Dewatering and pumping arrangements shall
between the ramp and inner door where fitted. The be such that when they are in operation the following
system is to be equipped with an audible alarm shall be available:
function to the navigation bridge for water level in – The bilge system shall remain ready for use
these areas exceeding 0,5 m above the car deck level. for any compartment.
For bow doors and inner door, see Rules for Hull, – The immediate start of the fire fighting
Volume II, Section 6, H.7. pumps and supply of fire fighting water shall
4.11 Chain lockers remain available.

Chain lockers are to be drained by means of – The system for normal operation of electric
appropriate arrangements. power supply, propulsion and steering shall
not be affected by operating the drainage and
4.12 Condensate drain tanks of charge air pumping system.
coolers
For water ingress detection systems see Rules for
4.12.1 If condensate from a drain tank of a charge air Electrical Installations, Volume IV, Section 18.
cooler shall be pumped overboard directly or
indirectly, the discharge line is to be provided with an 4.13.8 The capacity of the dewatering system
approved 15 ppm alarm. If the oil content exceeds 15 according 4.12.1 is to be calculated according
ppm an alarm is to be released and the pump shall stop following formula :
automatically. Q = 320 . A [m3/h]
The 15 ppm alarm is to be arranged so that the bilge A is the free cross section area in m2 of the largest air
pump will not be stopped during bilge pumping from pipe or ventilation opening connecting the exposed
engine room to overboard. deck with the space for which dewatering is required.
4.12.2 Additionally the tank is to be provided with 5 Additional requirements for passenger
a connection to the oily water separator. vessels
4.13 Dewatering of forward spaces of bulk 5.1 Bilge pipe arrangement and bilge valves
carriers
5.1.1 The arrangement of bilge pipes
4.13.1 On bulk carriers means for dewatering and
pumping of ballast tanks forward of the collision - within 0,2 B of the ship's side measured at
bulkhead and bilges of dry spaces forward of the the level of the subdivision load line,
foremost cargo hold are to be provided. - in the double bottom lower than 460 mm
4.13.2 The means are to be controlled from the above the base line or
navigation bridge, the propulsion machinery control - below the horizontal level specified in Rules
position or an enclosed space which is readily for Hull Construction, Volume II, Section 29.
accessible from the navigation bridge or the propulsion F.
machinery control position without traveling exposed
freeboard or superstructure decks. is permitted only if a non-return valve is fitted in the
compartment in which the corresponding bilge suction
A position which is accessible via an under deck
is located.
passage, a pipe trunk or other similar means of access
is not to be taken as readily accessible. 5.1.2 Valve boxes and valves of the bilge system
are to be installed in such a way that each
4.13.3 Where piping arrangements for dewatering of
compartment can be emptied by at least one pump in
forward spaces are connected to the ballast system 2
the event of ingress of water.
non-return valves are to be fitted to prevent water
entering dry spaces from the ballast system. One of Where parts of the bilge arrangement (pump with
these non-return valves shall have positive means of suction connections) are situated less than 0,2 B from
closure. The valve shall be operated from a position as the shell, damage to one part of the arrangement must
stated in 4.12.2. not result in the rest of the bilge arrangement being
rendered inoperable.
4.13.4 The valve required in P.1.3.3 shall be
operated from a position as stated in 4.12.2. 5.1.3 Where only one common piping system is
provided for all pumps, all the shut-off and change-
4.13.5 It must be recognizable by positive indication
over valves necessary for bilge pumping must be
at the control stand whether valves are fully open or
arranged for operating from above the bulkhead deck.
closed. In case of failure of the valve control system
11-36 Section 11 - Piping Systems, Valves and Pumps

Where an emergency bilge pumping system is supervision.


provided in addition to the main bilge system, this is to
be independent of the latter and must be so arranged as
to permit pumping of any flooded compartment. In this
case, only the shut-off and change-over valves of the O. Equipment for the Treatment and Storage
emergency system need be capable of being operated of Bilge Water, Fuel/Oil Residues 7)
from above the bulkhead deck.
1. Oily water separating equipment
5.1.4 Shut off and change-over valves which must
be capable of being operated from above the bulkhead 1.1 Ships of 400 tons gross and above shall be
deck should be clearly marked, accessible and fitted fitted with an oily water separator or filtering
with a position indicator at the control stand of the equipment for the separation of oil/water mixtures.
bilge system. 1.2 Ships of 10000 tons gross and above shall be
5.2 Bilge suctions fitted, in addition to the equipment required in 1.1,
with a 15 ppm alarm system.
Bilge pumps in the machinery spaces must be pro-
vided with direct bilge suctions in these spaces, but not 1.3 A sampling device is to be arranged in a
more than two direct suctions need be provided in any vertical section of the discharge line of oily water
one space. separating equipment/filtering systems.

Bilge pumps located in other spaces are to have direct 1.4 By-pass lines are not permitted for oily-water
suctions to the space in which they are installed. separating equipment/filtering systems.

5.3 Arrangement of bilge pumps 1.5 Recirculating facilities have to be provided to


enable the oil filtering equipment to be tested with the
5.3.1 Bilge pumps must be installed in separate overboard discharge closed.
watertight compartments which are to be so arranged
that they will not be flooded by the same damage. 2. Discharge of fuel/oil residues

Ships with a length of 91,5 m or over or having a 2.1 A sludge tank is to be provided. For the
criterion of service numeral according SOLAS 74 of fittings and mountings of sludge tanks, see Section 10,
30 6) or more are to have at least one bilge pump E.
available in all flooding conditions for which the ship 2.2 A self-priming pump is to be provided for
is designed to withstand. This requirement is satisfied sludge discharge to reception facilities. The capacity of
if the pump shall be such that the sludge tank can be
- one of the required pumps is a submersible emptied in a reasonable time.
emergency bilge pump connected to its own 2.3 A separate discharge line is to be provided for
bilge system and powered from a source discharge of fuel and oil residues to reception
located above the bulkhead deck or facilities.
- the pumps and their sources of power are 2.4 Where incinerating plants are used for fuel
distributed over the entire length of the ship and oil residues, compliance is required with
the buoyancy of which in damaged condition Section 9 and with the Resolution MEPC.76(40)
is ascertained by calculation for each “Standard Specification for Shipboard Incinerators”.
individual compartment or group of
compartments, at least one pump being
available in an undamaged compartment.
5.3.2 The bilge pumps specified in 3.6 and their P. Ballast Systems
energy sources may not be located forward of the 1. Ballast lines
collision bulkhead.
1.1 Arrangement of piping - general
5.4 Passenger vessels for limited range of
service 1.1.1 Suction in ballast water tanks are to be so
arranged that the tanks can be emptied despite
The scope of bilge pumping for passenger vessels with unfavorable conditions of trim and list.
limited range of service, e.g. navigation in sheltered
water service, can be agreed with BKI.
6. Additional Rules for tankers 7
) With regard to the installation on ships of oily water
separators, filter plants, oil collecting tanks, oil discharge
See Section 15, B.4. lines and a monitoring and control system or a 15 ppm
alarm device in the water outlet of oily water separators,
7. Bilge testing compliance is required with the provisions of the
International Convention for the Prevention of Pollution
All bilge arrangements are to be tested under BKI’s from Ships, 1973, (MARPOL) and the Protocol of 1978.
Section 11 - Piping Systems, Valves and Pumps 11-37

1.1.2 Ships having very wide double bottom tanks follows :


are also to be provided with suction at the outer sides
of the tanks. Where the length of the ballast water – A shut-off device is to be provided in the
tanks exceeds 30 m, BKI may require suction to be cross channel between the tanks destined for
provided in the forward part of the tanks. this purpose before and after the anti-heeling
pump.
1.2 Pipes passing through tanks
– These shut-off devices and the pump are to
Ballast water pipes may not pass through drinking be remotely operated. The control devices are
water, feed water, thermal oil or lubricating oil tanks. to be arranged in one control stand.
1.3 Piping systems – At least one of the arranged remote
controlled shut-off devices shall
1.3.1 Where a tank is used alternately for ballast automatically shut down in the case of power
water and fuel (change-over tank), the suction in this supply failure.
tank is to be connected to the respective system by
three-way cocks with L-type plugs, cocks with open – The position “closed“ of the shut-off devices
bottom or change-over piston valves. These must be shall be indicated on the control standby type
arranged so that there is no connection between the approved end position indicators.
ballast water and the fuel systems when the valve or
– Additionally, Rules for Electrical
cock is in an intermediate position. Change-over pipe
Installations, Volume IV, Section 7, G is to
connections may be used instead of the above
be observed.
mentioned valves. Each change-over tank is to be
individually connected to its respective system. For 2. Ballast pumps
remotely controlled valves see D.6.
The number and capacity of the pumps must satisfy the
1.3.2 Where ballast water tanks may be used ship operational requirements.
exceptionally as dry cargo holds, such tanks are also to
be connected to the bilge system. The requirements 3. Cross-flooding arrangements
specified in N.4.5 are applicable. 3.1 Passenger ships
1.3.3 Where, on cargo ships, pipelines are led As far as possible, cross-flooding arrangements for
through the collision bulkhead below the freeboard equalizing of asymmetrical flooding in case of damage
deck, a shut-off valve is to be fitted directly at the should operate automatically. Where the arrangement
collision bulkhead inside the fore peak. does not operate automatically, any shut-off valves and
The valve has be capable of being remotely operated other devices must be capable of being operated from
from above the freeboard deck. above the bulkhead deck. The position of each closing
devices has to be indicated on the bridge and at the
Where the fore peak is directly adjacent to a central operating location (see also Rules for Hulls,
permanently accessible room (e.g; bow thruster room) Volume II, Section 26, J and Rules for Electrical
which is separated from the cargo space, this shut-off Installations, Volume IV Section 7, H). The
valve may be fitted directly at the collision bulkhead cross-flooding arrangements must ensure that in case
inside this room without provision for remote control. of flooding, equalization is achieved within 15
minutes.
1.3.4 On passenger ships, only one pipeline may be
led through the collision bulkhead below the freeboard 3.2 Cargo ships
deck. The pipeline is to be fitted with a remote
controlled shutoff inside the forepeak directly at the As far as possible, cross-flooding arrangements for
collision bulkhead. The remote control must be oper- equalizing of asymmetrical flooding in case of damage
ated from above the freeboard deck. Where the should operate automatically. Where the arrangement
forepeak is divided into two compartments, two does not operate automatically, any shut-off valves and
pipelines may in exceptional cases be passed through other devices must be capable of being operated from
the collision bulkhead below freeboard deck. above the bulkhead deck. The position of each closing
devices has to be indicated on the bridge and at the
1.3.5 Ballast water tanks on ships with ice class central operating location (see also Rules for Hulls,
ES1 to ES4 which arranged above the ballast load line Volume II, Section 26, J and Rules for Electrical
shall be equipped with means to prevent the water Installations, Volume IV, Section 7, H). The
from freezing, see Rules for Hulls, Volume II, Section cross-flooding arrangements must ensure that in case
15, A.2.3. of flooding, equalization is achieved within 10
minutes.
1.4 Anti-heeling arrangements
3.3 Cross-flooding arrangements for equalizing
Anti-heeling arrangements, which may counteract
asymmetrical flooding in case of damage are to be
heeling angles of more than 10° according to Rules for
submitted to BKI for approval.
Hull, Volume II, Section 1.E.3, are to be designed as
11-38 Section 11 - Piping Systems, Valves and Pumps

4. Additional rules for Tankers 3.5 The laying of pipes through accommodation,
public or service spaces is not permitted.
See Section 15, B.4.
3.6 Pipelines passing through cargo holds are to
5. Operational testing be installed in such a way that they cannot be
The ballast arrangement is to be subjected to damaged.
operational testing under BKI’s supervision. 3.7 Pipe penetrations through bulkheads and
decks are to be insulated against conduction of heat
into the bulkhead. See also Section 12, B.7.
3.8 Means of bleeding (of any air) are to be so
Q. Thermal Oil Systems arranged that oil/air mixtures will be drained safely.
Thermal oil systems shall be installed in accordance Bleeder screws are not permitted.
with Section 7 II. 3.9 For screening arrangements of thermal oil
The pipelines, pumps and valves belonging to these pipes G.3.4 applies as appropriate.
systems are also subject to the following requirements. 4. Drainage and storage tanks
1. Pumps 4.1 Drainage and storage tanks shall be equipped
1.1 Two circulating pumps which are to be with air vents and drains. For storage tanks see also
independent of each other are to be provided. Section 10, D.

1.2 A transfer pump is to be installed for filling 4.2 The air vents for the drainage tanks shall
the expansion tank and for draining the system. terminate above open deck. Air pipe closing devices
see R.1.3.
1.3 The pumps are to be so mounted that any oil
leakage can be safely disposed of. 4.3 Drains shall be of self-closing type if the
tanks are located above double bottom.
1.4 For emergency shut-down see Section 12,
B.9. 5. Pressure testing

2. Valves See B.4.

2.1 Only valves made of ductile materials may be 6. Tightness and operational testing
used. After installation, the entire arrangement is to be
2.2 Valves shall be designed for a nominal subjected to tightness and operational testing under the
pressure of PN 16. supervision of BKI.

2.3 Valves are to be mounted in accessible po-


sitions.
R. Air, Overflow and Sounding Pipes
2.4 Non-return valves are to be fitted in the
pressure lines of the pumps. General
2.5 Valves in return pipes are to be secured in the The laying of air, overflow and sounding pipes is
open position. permitted only in places where the laying of the
corresponding piping system is also permitted, see
2.6 Bellow sealed valves are to be preferably Table 11.5.
used.
For special strength requirements regarding for deck
3. Piping fittings, see Rules for Hulls, Volume II, Section 21,
3.1 Pipes in accordance with Table 11.1 or B.2.1 E.5.
are to be used. 1. Air and overflow pipes
3.2 The material of the sealing joints is to be 1.1 Arrangement
suitable for permanent operation at the design tem-
perature and resistant to the thermal oil. 1.1.1 All tanks, void spaces etc. are to be fitted at
their highest position with air pipes or overflow pipes.
3.3 Provision is to be made for thermal expansion Air pipes must normally terminate at the open deck.
by an appropriate pipe layout and the use of suitable
compensators. 1.1.2 Air and overflow pipes are to be laid
vertically.
3.4 The pipelines are to be preferably connected
by means of welding. The number of detachable pipe 1.1.3 Air and overflow pipes passing through cargo
connections is to be minimized. holds are to be protected against damage.
Section 11 - Piping Systems, Valves and Pumps 11-39

1.1.4 For the height above deck of air and overflow 1.1.15 For the connection to a common line of air
pipes and the necessity of fitting brackets on air pipes, and overflow pipes on ships with the character of
see Rules for Hull Construction, Volume II, Section classification mark ! or ! see D.9.
21.E.
1.1.16 For the cross-sectional area of air pipes and
The wall thickness of air pipes on the exposed deck air/overflow pipes, see Table 11.18.
shall be in accordance with Tables 11.20a and 20b.
1.2 Number of air and overflow pipes
1.1.5 Air pipes from unheated leakage oil tanks and
lubricating oil tanks may terminate at clearly visible 1.2.1 The number and arrangement of the air pipes
positions in the engine room. Where these tanks from is to be so performed that the tanks can be aerated and
part of the ship’s hull, the air pipes are to terminate deaerated without exceeding the tank design pressure
above the free board deck, on passenger ships above by over- or under pressure.
the bulkhead decks. It must be ensured that no leaking 1.2.2 Tanks which extend from side to side of the
oil can spread onto heated surfaces where it may ship must be fitted with an air/overflow pipe at each
ignite. side. At the narrow ends of double bottom tanks in the
1.1.6 Air pipes from lubricating oil tanks and forward and after parts of the ship, only one
leakage oil tanks which terminate in the engine room air/overflow pipe is sufficient.
are to be provided with funnels and pipes for safe 1.3 Air pipe closing devices
drainage in the event of possible overflow.
Air/overflow pipes terminating above the open deck
1.1.7 On cargo ships of 500 gross tons or above and are to be fitted with approved pipe heads.
on all passenger ships air pipes of lubricating oil tanks
which terminate on open deck are to be arranged such To prevent blocking of the air pipe head openings by
that in the event of a broken air pipe this shall not their floats during tank discharge the maximum
directly lead to the risk of ingress of sea or rain water. allowable air velocity determinated by the
manufacturer is to be observed.
1.1.8 Wherever possible, the air pipes of feedwater
and distillate tanks should not extend into the open 1.4 Overflow systems
deck. Where these tanks form part of the ship’s shell
l.4.1 Ballast water tanks
the air pipes are to terminate within the engine room
casing above the freeboard deck, in passenger ships Proof by calculation is to be provided for the system
above the bulkhead deck. concerned that under the specified operating
conditions the design pressures of all the tanks
1.1.9 Air pipes for cofferdams and void spaces with
connected to the overflow system cannot be exceeded.
bilge connections are to be extended above the open
deck respectively on passenger vessels above the
bulkhead deck.
1.4.2 Fuel oil tanks
1.1.10 On cargo ships of 500 gross tons or above and
on all passenger ships air pipes of fuel service and The requirements to be met by overflow systems of
settling tanks which terminate an open deck are to be heavy oil tanks are specified in BKI "Regulation for
arranged such that in the event of a broken air pipe this the Construction, Equipment and Testing of Closed
shall not directly lead to the risk of ingress of se aor Fuel Overflow Systems".
rain water, see also Section 10, B.5.2. Table 11.18 Cross-sectional areas of air and
1.1.11 Where fuel service tanks are fitted with overflow pipes
change-over overflow pipes, the change-over devices
Cross-sectional areas of air
are to be so arranged that the overflow is led to one of Tank filling and overflow pipes
the storage tanks. systems
AP AOP
1.1.12 The overflow pipes of changeable tanks must
be capable of being separated from the fuel overflow by 1/3 f per tank -
system. filling gravity
1.1.13 Where the air and overflow pipes of several mode by - 1,25 f per
tanks situated at the ship's shell lead to a common line, pumping tank 1)
the connections to this line are to be above the
freeboard deck if possible but at least so high above
the deepest load waterline that should a leakage occur
in one tank due to damage to the hull or listing of the
ship, fuel or water cannot flow into another tank.
1.1.14 The air and overflow pipes of lubricating oil
and fuel tanks shall not be led to a common line.
11-40 Section 11 - Piping Systems, Valves and Pumps

Explanatory note : 2.1.3 As far as possible, sounding pipes are to be


AP = air pipe
laid straight and are to extend as near as possible to the
bottom.
AOP = air/overflow pipe
f = cross-sectional area of tank filling pipe 2.1.4 Sounding pipes which terminate below the
1
deepest load waterline are to be fitted with self-closing
) 1,25 f as the total cross-sectional area is sufficient if it
shut-off devices. Such sounding pipes are only
can be proved that the resistance to flow of the air and
overflow pipes including the air pipe closing devices permissible in spaces which are accessible at all times.
at the proposed flow rate cannot cause unacceptably
high pressure in the tanks in the event of overflow All other sounding pipes are to be extended to the open
deck. The sounding pipe openings must always be
1.4.3 The overflow collecting manifolds of fuel accessible and fitted with watertight closures.
tanks are to be led at a sufficient gradient to an over- 2.1.5 Sounding pipes of tanks are to be provided
flow tank of sufficient capacity. close to the top of the tank with holes for equalizing
The overflow tank is to be fitted with a level alarm the pressure.
which operates when the tank is about 1/3 full. 2.1.6 In cargo holds, a sounding pipe is to be fitted
1.4.4 For the side of the air and overflow pipes, see to each bilge well.
Table 11.19. 2.1.7 Where level alarms are arranged in each bilge
1.4.5 The use of a fuel storage tank as overflow well of cargo holds, the sounding pipes may be
tank is permissible but requires the installation of a dispensed with. The level alarms are to be
high level alarm and an air pipe with 1,25 times the independent from each other and are to be type
cross-sectional area of the main bunkering line. approved by BKI. 8)

1.5 Determination of the pipe cross-sectional 2.1.8 In cargo holds, fitted with non weather tight
areas. hatch covers, 2 level alarms are to be provided in each
cargo hold, irrespective if sounding pipes are fitted.
1.5.1 For the cross-sectional areas of air and The level alarms are to be independent from each other
overflow pipes, see Tables 11.18 and 11.19. and are to be type approved by BKI.
Air and overflow pipes shall have an outside diameter 2.1.9 Sounding pipes passing through cargo holds
of at least 60,3 mm. are to be laid in protected spaces or they are to be
protected against damage.
On ships > 80 m in length in the forward quarter only
air/overflow pipes with and outer diameter % 76,1 mm 2.2 Sounding pipes for fuel, lubricating oil and
may be used, see also Rules for Hull, Section 21. thermal oil tanks
1.5.2 The clear cross-sectional area of air pipes on 2.2.1 Sounding pipes which terminate below the
passenger ships with cross-flooding arrangement must open deck are to be provided with self-closing devices
be so large that the water can pass from one side of the as well as with self-closing test valves, see also
ship to the other within 15 minutes, see also P.3. Section 10, B.3.3.7.
1.6 The minimum wall thicknesses of air and 2.2.2 Sounding pipes shall not to be located in the
overflow pipes are to be in accordance with Table vicinity of firing plants, machine components with
11.20a and 11.20b, whereby A, B and C are the groups high surface temperatures or electrical equipment.
for the minimum wall thicknesses.
2.2.3 Sounding pipes must not terminate in
1.7 The pipe material are to be selected according accommodation or service spaces.
to B.
2.2.4 Sounding pipes are not to be used as filling
2. Sounding pipes pipes.
2.1 General 2.3 Cross-sections of pipes
2.1.1 Sounding pipes are to be provided for tanks, 2.3.1 Sounding pipes shall have an inside diameter
cofferdams and void spaces with bilge connections and of at least 32 mm.
for bilges and bilge wells in spaces which are not
accessible at all times. 2.3.2 The diameters of sounding pipes which pass
through refrigerated holds at temperatures below 0 !C
On application, the provision of sounding pipes for are to be increased to an inside diameter of 50 mm.
bilge wells in permanently accessible spaces may be
dispensed with. 2.3.3 The minimum wall thicknesses of sounding

2.1.2 Where tanks are fitted with remote level


indicators which are type-approved by BKI the 8
) National Regulations, where existing, are to be
arrangement of sounding pipes can be dispensed with. considered
Section 11 - Piping Systems, Valves and Pumps 11-41

pipes are to be in accordance with Tables 11.20a and an open funnel or with means of preventing back-flow.
11.20b.
4. Pressure water tanks/calorifiers
2.4 For pipe materials see B.
For design, equipment, installation and testing of
pressure water tanks and calorifiers, Section 8, A. and
E. are to be observed.
5. Drinking water pumps
S. Drinking Water Systems 8)
5.1 Separate drinking water pumps are to be
1. Drinking water tanks provided for drinking water systems.
1.1 For the design and arrangement of drinking 5.2 The pressure lines of the pumps of drinking
water tanks see Rules for Hull, Volume II, Section 12. water pressure tanks are to be fitted with screw-down
1.2 On ships with ice class ES1 and higher non-return valves.
drinking water tanks located at the ship's side above
6. Drinking water generator
the ballast waterline are to be provided with means for
tank heating to prevent freezing. Where the distillate produced by the ship's own
evaporator unit is used for the drinking water supply,
2. Drinking water tank connections the treatment of the distillate has to comply with
2.1 Filling connections are to be located current regulations of national health authorities.
sufficiently high above deck and are to be fitted with
a closing device.
2.1.1 Filling connections are not to be fitted to air
pipes.
2.2 Air/overflow pipes are to be extended above
the open deck and are to be protected against the entry
of insects by a fine mesh screen.
Air pipe closing devices, see Section 11, R.1.3.
2.3 Sounding pipes must terminate sufficiently
high above deck.
3. Drinking water pipe lines
3.1 Drinking water pipe lines are not to be
connected to pipe lines carrying other media.
3.2 Drinking water pipe lines are not to be laid
through tanks which do not contain drinking water.
3.3 Drinking water supply to tanks which do not
contain drinking water (e.g. expansion tanks of the
fresh water cooling system) is to be made by means of

Table 11.19 Cross-sectional areas of air and overflow pipes (closed overflow systems)

Tank filling and overflow Cross-sectional areas of air and overflow pipes Remarks
systems AP OP 2)
DP
1/3 f - - cross-sectional area of
Stand-pipe
stand-pipe % 1,25 F
Filling
1/3 f 1) min. 1,25 F - cross-sectional of relief
Relief valve
valve % 1,25 F
11-42 Section 11 - Piping Systems, Valves and Pumps

Overflow chest 1/3 F at chest min. 1,25 F 1,25 F -


Overflow
Manifold 1/3 F min. 1,25 F - -
system
Overflow tank 1/3 F - - -
Explanatory notes :
AP = air pipe
OP = overflow pipe
DP = drainage pipe
f = cross-sectional area of tank filling pipe
F = cross-sectional area of main filling pipe
1) 1/3 f only for tanks in which an overflow is prevented by structural arrangements
2) Determined in accordance with 1.4.

Table 11.20a Classification of minimum wall thicknesses groups

Location
Air, sounding and
Drain lines and scupper pipes
overflow pipes
Piping
system or below freeboard
Tank
position of Tank with deck or bulkhead
with above Cargo Machinery
open pipe disparate- deck above below
same free- holds spaces
outlets media weather weather
media without with board
shutt-off shut-off deck deck
deck
on ship's on ship's
side side
Air,
Overflow
and C - - C A A
sounding
pipe
Scupper
pipes from A
open deck
Discharge
and scupper A A
pipes
B -
leading - -
B A
directly
overboard B

Discharge
pipes of
pumps for A
sanitary
systems

Table 11.20b Minimum wall thicknesses of air,


overflow, sounding and sanitary 38 - 82,5 4,5 7,1 6,3
pipes 88,9 4,5 8 6,3
101,6 - 114,3 4,5 8 7,1
Outside pipe Minimum wall thickness
[mm] 127 - 139,7 4,5 8,8 8
diameter da 152,4 4,5 10 8,8
[mm] A1) B1) C1)
159 - 177,8 5 10 8,8
193,7 5,4 12,5 8,8
Section 11 - Piping Systems, Valves and Pumps 11-43

1 wall thickness groups, see Table 11.20a see R.1.3.


2.7.2 Sewage tanks are to be fitted with a filling
connection, a rinsing connection and a level alarm.
2.7.3 The discharge lines or sewage tanks and
sewage treatment tanks are to be fitted at the ship's side
T. Sewage Systems with screw-down non-return valves.
1. General When the valve is not arranged directly at the ship’s
1.1 Ships of 400 gross tonnage and above and ships side, the thickness of the pipe is to be according to
of less than 400 gross tonnage which are certified to Table 11.20b, column B.
carry more than 15 persons and with keel laying on or 2.7.4 A second means of reverse-flow protection is
after 27 September 2003 are to be fitted with the to be fitted in the suction or delivery line of the sewage
following equipment: pump from sewage tanks or sewage treatment plants if,
– a sewage treatment plant approved according to in the event of a 5! heel to port or starboard, the lowest
Resolution MEPC.2(VI), or internal opening of the discharge system is less than
200 mm above the summer load line. 9)
– a sewage comminuting and disinfecting system
(facilities for the temporary storage of sewage The second means of reverse-flow protection may be
when the ship is less than 3 nautical miles from a pipe loop having an overflow height above the
the nearest land, to be provided), or summer load line of at least 200 mm at a 5! heel. The
pipe loop is to be fitted with an automatic ventilation
– a holding tank device located at 45! below the crest of the loop.
1.2 A pipeline for the discharge of sewage to a 2.7.5 Where at a heeling of the ship of 5o at port or
reception facility is to be arranged. The pipeline is to starboard, the lowest inside opening of the sewage
be provided with a standard discharge connection. system lies on the summer load line or below, the
2. Arrangement discharge line of the sewage collecting tank is to be
fitted in addition to the required reverse-flow
2.1 For scuppers and overboard discharges see Rules protection device according to 2.7.4 with a gate valve
for Hull, Volume II, Section 21. directly on the ship’s plating. In this case the reverse
flow protection device need not to be of screw-down
2.2 The minimum wall thicknesses of sanitary pipes type.
below free board and bulkhead decks are specified in
Tables 11.20a and 11.20b. 2.7.6 Ballast and bilge pumps may not be used for
emptying sewage tanks.
2.3 For discharge lines above freeboard
deck/bulkhead deck the following pipes may be used:
- steel pipes according to Table 11.6, Group N 3. Additional rules for ships with character of
classification ! or !
- pipes having smaller thicknesses which are
specially protected against corrosion, on special 3.1 The sanitary arrangement and their discharge
approval lines are to be so located that in the event of damage of
one compartment no other compartments can be
- special types of pipes according to recognized flooded.
standards, e.g. socket pipes, on special approval.
3.2 If this condition cannot be fulfilled, e.g. when:
2.4 For sanitary discharge lines below freeboard
deck/bulkhead deck within a watertight compartment, - water tight compartments are connected with
which terminate in a sewage tank or in a sanitary each other through internal openings of the
treatment plant, pipes according to 2.3 may be used. sanitary discharge lines, or
2.5 Penetrations of pipes of smaller thickness, pipes - sanitary discharge lines from several water tight
of special types and plastic pipes through bulkheads of compartments are led to a common drain tank, or
type A are to be approved by BKI.
- parts of the sanitary discharge system are located
2.6 If sanitary discharge pipes are led through cargo within the damage zone (see D.9.) and these are
holds, they are to be protected against damage by connected to other compartments over internal
cargo. openings
2.7 Sewage tanks and sewage treatment
systems 9
) Where sanitary treatment arrangements are fitted with
2.7.1 Sewage tanks are to be fitted with air pipes emergency drains to the bilge or with openings for
leading to the open deck. For air pipe closing devices chemicals, these will be considered as internal openings
in the sense of these requirements.
11-44 Section 11 - Piping Systems, Valves and Pumps

the water tightness is to be ensured by means of remote 2.1 High-pressure hose assemblies made of
controlled shut-off devices at the watertight bulkheads. non-metallic materials
The operation of the shut-off devices must be possible Hose assemblies which are suitable for use in systems
from an always accessible position above the bulkhead with distinct dynamic load characteristics.
deck on passenger ships and above the unsuitable leak
water line on other ships. The position of the shut-off 2.2 Low-pressure hose assemblies and
devices must be monitored at the remote control compensators made of non-metallic
position. materials

3.3 Where the lowest inside opening of the sanitary Hose assemblies or compensators which are suitable
discharge system is below the bulkhead deck, a screw- for use in systems with predominant static load
down non-return valve and a second reverse-flow characteristic.
protection device are to be fitted in the discharge line 2.3 Maximum allowable working pressure
of the sanitary water treatment arrangement. In this respectively nominal pressure of hose
case, discharge line of sanitary collecting tanks are to assemblies and compensators made of non-
be fitted with a gate valve and two reverse-flow metallic materials
protection devices. Concerning the shut-off devices
and reverse-flow protection devices, 2.7.3, 2.7.4 and 2.3.1 The maximum allowable working pressure for
2.7.5 are to be applied. high-pressure hose assemblies is the maximum
dynamic internal pressure which may be imposed on
the components.
2.3.2 The maximum allowable working pressure
U. Hose Assemblies and Compensators
respectively nominal pressure for low-pressure hose
1. Scope assemblies and compensators is the maximum static
internal pressure which may be imposed on the
1.1 The following requirements are applicable for components.
hose assemblies and compensators made of non-
metallic and metallic materials. 2.4 Test pressure
1.1.1 Hose assemblies and compensators made of 2.4.1 For non-metallic high-pressure hose
non-metallic and metallic materials may be used assemblies the test pressure is 2 times the maximum
according to their suitability in fuel-, lubricating oil-, allowable working pressure.
hydraulic oil, bilge, ballast, fresh water cooling,
2.4.2 For non-metallic low-pressure hose
seawater cooling, compressed air, auxiliary steam 10),
assemblies and compensators the test pressure is 1,5
exhaust gas and thermal oil systems as well as in
times the maximum allowable working pressure or 1,5
secondary piping systems.
times the nominal pressure.
1.2 Hose assemblies and compensators made of
2.4.3. For metallic hose assemblies and
non-metallic materials are not permitted in
compensators the test pressure is 1,5 times the
permanently pressurized starting air lines. Furthermore
maximum allowable working pressure or 1,5 times the
it is not permitted to use hose assemblies and
nominal pressure.
compensators in fuel injection piping systems of
combustion engines.
1.3 Compensators made of non-metallic materials are 2.5 Burst pressure
not approved for the use in cargo lines of tankers.
For non-metallic as well as metallic hose assemblies
2. Definitions and compensators the burst pressure is to be at least 4
times the maximum allowable working pressure or 4
Hose assemblies consist of metallic or non-metallic
times the nominal pressure. Excepted hereof are non-
hoses completed with end fittings ready for
metallic hose assemblies and compensators with a
installation.
maximum allowable working pressure or nominal
Compensators consist of bellows with end fittings as pressure of not more than 20 bar. For such components
well as anchors for absorption of axial loads where the burst pressure has to be at least 3 times the
angular or lateral flexibility is to be ensured. End maximum allowable working pressure or 3 times the
fittings may be flanges, welding ands or approved pipe nominal pressure.
unions.
For hose assemblies and compensators in process and
Burst pressure is the internal static pressure at which a cargo piping for gas and chemical tankers the burst
hose assembly or compensator will be destroyed. pressure is required to be at least 5 times the maximum
allowable working pressure.
3. Requirements
10
) Metallic hose assemblies and compensators only
Section 11 - Piping Systems, Valves and Pumps 11-45

3.1 Hoses and compensators used in the systems 5.1 Hose assemblies and compensators are to be
mentioned in 1.1.1 are to be of approved type.11) subjected in the manufacturer's works to a pressure test
in accordance with 2.4 under the supervision of the
3.2 Manufacturers of hose assemblies and BKI.
compensators must be recognized by BKI.
5.2 For compensators intended to be used in exhaust
3.3 Hose assemblies and compensators including gas pipes the pressure test according 5.1 may be
their couplings must be suitable for the operating ommited.
media, pressures and temperatures they are designed
for. 6. Ship Cargo hoses
3.4 The selection of hose assemblies and 6.1 Ship cargo hoses for cargo-handling on chemical
compensators is to be based on the maximum tankers and gas tankers shall be type approved. 11)
allowable working pressure of the system concerned.
A pressure of 5 bar is to be considered as the minimum Mounting of end fitting is to be carried out only by
working pressure. approved manufacturers. 12)

3.5 Hose assemblies and compensators for the use in 6.2 Ship cargo hoses are to be subjected to final
fuel-, lubricating oil, hydraulic oil, bilge and seawater inspection at the manufacturer under supervision of a
systems are to be flame-resistant. BKI Surveyor as follows :

4. Installations - visual inspection


- hydrostatic pressure test with 1,5 times the
4.1 Hose assemblies and compensators shall only be
maximum allowable working pressure or 1,5
used at locations where they are required for
times the nominal pressure. The nominal pressure
compensation of relative movements. They shall be
shall at least 10 bar.
kept as short as possible under consideration of the
installation instructions of the hose manufacturers. The - measuring of the electrical resistance between the
number of hose assemblies and compensators is to be end fittings. The resistance shall not exceed 1 k".
kept to minimum.
6.3 Cargo hoses on gas tankers are additionally
4.2 The minimum bending radius of installed hose subject to the Rules for Ships Carrying Liquefied
assemblies shall not be less than those specified by the Gases in Bulk, Volume IX, Section 5.7.
manufacturers.
6.4 Cargo hoses on chemical tankers are additionally
4.3 Non-metallic hose assemblies and compensators subject to the Rules for Ships Carrying Dangerous
are to be located at visible and accessible positions. Chemical in Bulk, Volume X, Section 5.7.
4.4 In fresh water systems with a working pressure of 7. Marking
" 5 bar and in charging air and scavenging air lines,
hoses may be fastened to the pipe ends with double Hose assemblies and compensators must be perma-
clips. nently marked with the following particulars:

4.5 Where hose assemblies and compensators are - manufacturer's mark or symbol
installed in the vicinity hot components they must be - date of manufacture
provided with approved heat-resistant sleeves.
- type
4.6 Hose assemblies and compensators conveying
flammable liquids that are in close proximity of heated - nominal diameter
surface are to be provided with screens or other similar
- maximum allowable working pressure
protection to avoid the risk of ignition due to failure at
respectively nominal pressure.
the hose assembly or compensator.
- marking number of the responsible BKI
5. Tests
inspection office

11
) See “Regulations for the Performance of Type Tests, Part
12
5 - Test Requirement for Mechanical Components and ) See”Regulations for the Recognition of Manufacturers of
Equipments” Hose Assemblies and Compensators”

Вам также может понравиться