Академический Документы
Профессиональный Документы
Культура Документы
SOUTH COTABATO II
ELECTRIC COOPERATIVE,
INC. (SOCOTECO II),
.Applicant~
x-------------------------x
DECISION
DISCUSSION
PROJECT COST
PARTICULARS
(PhP)
NElWORK
Installation of the two 35/43.75 MVA Transformer Bank at
125,208,186.00
Lagao Substation
Installation of 2-69 kV Sectionalized Circuit Breaker 4,900,000.00
Total Network 130,108,186.00
NElWORK
Relocation of SOCOTECO II's Proposed New Headquarters 55,000,000.00
Total Non-Network 55,000,000.00
TOTALProiect Cost ner Annlication (PhP) 185,108,186.00
FORECASTING
PERFORMANCE ASSESSMENT
Capacity
Reliability
Non-Network Projects
PROJECT FORMULATION
COSTANALYSIS
PROJECT STATUS
2016CAPEXProjects: .
• Installation of 2 units of 69 kV Sectionalized Circuit Breaker;
and
• Relocation of SOCOTECOII's Proposed New Headquarters
2017 CAPEXProjects:
• Installation of the other 35/43.75 MYA Substation
FINANCING SCHEME
RFSC on hand
(beginning of
year) (PhP)
- 96,844,448.42 1:>09,948,153,38 275,255,684.8, 82,450,599.7- ~36,637,694.74 -
Kilowatt-hour
609.832.863.00 678.329.993.00 700.882.833.00 683.473.767.00 7'6.949,002.00 751.643.668.00 4.141,112,126.00
Sales
CASH
INFLOWS
RFSC collected 208.201,990.18 218,277,321.19 1,202,578,961.39
177.095.463.42 '96.987,029.97 203.536.374.70 198.480.781.94
funds @ 0.2904
- -- - -- -- ..... - --- --- - --
Total Cash
177,095,463.42 196,987,029.97 1203,536,374.70 198,480,781.94 1:<08,201,990.18 218,277,321.19 1,202,578,961.39
Inflo\-\'s
Available ,
cash for 654,915,015.92 1,202,578,961.39
177,095.463.42 293,831,478.38 1413,484,528.09 473,736,466.77 ~90,652,589.9"
disbursement
(PhP) - - -- ... -
CASH
OUTFLOWS
CAPEX 59,9°0,000.00 62,604,°93.00 178,955,455.25
56,451,362.25
Requirement
Network Projects
1. Installation ofthe second 62,604,093.00 62,604,093.00
"Sec. 20. Acts requiring the approval of the Commission. - Subject to established limitations and exceptions and
saving provisions to the contrary, it shall be unlawful for any public service or for the owner, lessee or operator
thereof, without the approval and authorization of the Commission previously had - Xxx
(e) Hereafter to issue any stock or stock certificates representing an increase of capital; or issue any share of stock
without par value; or issue any bonds or other evidence of indebtedness payable in more than one year fro~ the
issuance thereof, provided that it shall be the duty of the Co~mission, after hea~ing,to appro~e any SUChrss~e
maturing in more than one year from the date thereof, when satisfied that the same IS to be made 10 accordance~
law, and the purpose of such issue be approved by the Commission." / j('
ERCCase No. 2012-128 RC
DECISIONj24 May 2016
Page 11of 14
PhP178,955,455.25
----------------------------- x PhPO.75 = PhP1,342,165.92
PhP100.00
SO ORDERED.
(On Leave)
GLORIA VICTORIA C. YAP-TARDC
Commissioner
(On Leave)
JOSEFINA PATRICIA A. MAGPALE-ASIRIT ONIMO D. STA. ANA
Commissioner Commissioner
M
&(/AP~
.
C~E NO.2012-128RCSOCOTECO
II-DECISION
..
ERC Case No. 2012-128 RC
DECISION/24 May 2016
Page 13 of 14
Copy Furnished:
9. Municipal Mayor
Alabel, Sarangani Province
21. President
Philippine Chamber of Commerce and Industry (PCCI)
3rd Floor, ECC Building, Sen. Gil Puyat Avenue
Makati City
I. NETWORK PROJECTS
Pro'ect No. 1
Pro'ect Title Installation of 2-35/43.75 MVA Substations
Pro'ect Code SS001
Pro'ect T e Ca acit
Priorit Rank
Project Category Substation Pro'ect
Project Justification
• SOCOTECO II's proposed installation of 2-35/43.75 MVA Substation in
Lagao is due to the increasing demand of power in General Santos City
brought about by the development of business establishments. The
existing 20 MVA in Lagao will be replaced by 2-35/43.75 MVA and the
said 20 MVA will be transferred to Polomolok to address the location's
ower re uirement.
Technical Analysis
• There are four main substations that support the power requirement in
General Santos' business commercial district, namely: 15/18.75 MVA
New Society Substation, 20/25 MVA Lagao Substation, 20/25 MVA Leon
L1ido Substation and 20/25 MVA Calumpang Substation. The 4
substations have a total rated maximum capacity of 93.75 MVA.
• The table below shows that SOCOTECO II's system capacity can no
longer address its power requirement in the next years to come without
additional capacity.
I
DEMAND (MVA) 74.169 75.776 83.546 87.274 91.107 95.046 99.091 103.241
Section 1.2 of the 2011 Distribution Utility Planning Manual provides that:
The projected demand shown in the table was determined through load
forecasting; where scientific load forecasting models were formulated and
tested for validity to ensure that the forecast will be within the acceptable
accuracy. The measure of the overall error in the forecast for an entire set
of data was also computed and it passes the maximum 3% forecast error
measured in terms of maximum absolute percentage error (MAPE).
Albeit the delay from its proposed year of installation (2012), SOCOTECO
II implemented the installation of the first 35 MVA Substation located in
Lagao as a response to the projected rapid increase of power demand.
Thereafter, the second 35 MVA Substation is planned to be installed on
2017.
Economic and Cost Analysis
• SOCOTECO II, in its substation economic analysis presented three
alternatives to determine the most economical and least cost
transformer size to be installed in the system and to address the 15
years forecasted power requirement. The transformer sizes considered
are 20 MVA, 35 MVA and 40 MVA power transformers, which provides
the following Present Value (PV):
..'
. Alternative 3: 2-40 MVAPowerTransform'er: . , .
20 25 4 92,752,031.00
...
, • .. .... : -, "
. 60,820,830.00
..
35 ...
43.75 :.; '2 .
..
"
40 50 2 74,804,800.00
• Among the three (3) alternatives, the 2-35 MVA Substation is the most
technically feasible solution to be undertaken with the lowest net present
value.
Project Justification
• The proposed installation of 2 units - 69 kV circuit breakers will mitigate
the continuous line tripping resulting in the improvement of the reliability
of electric service in the municipality of Maasim, Kiamba, Maitum, Alabel
and Glan.
Technical Analysis
• The proposed project aims to mitigate the impact of line tripping and
advance the reliability performance by installing electronically controlled
circuit breakers to the identified low reliability 69 kV lines.
• Using the failure rates and repair time, reliability indices can be further
quantified, analyzed and compared to help determine if a project can
improve the reliability of the lines. The simulated result of the existing
system in comparison with the system adopting the proposed project is
provided as follows:
Expected Enerav Not ServedIYr. Total Potential
Without the With the Energy
Project Project SavedIYr.
Klinan to Kiamba Line 1,968,482KWhr 1,416,516KWhr 551,966 KWhr
Klinan to Glan Line 3,981,027 KWhr 1,452,824KWhr 2,528,203 KWhr
a) that the internal rate of return of the project satisfies the criteria;
b) net present value of the investment of the proposed project is
positive, which means that the discounted value of the income from
the ro'ect is hi her than the discounted value of the ex enditure;
c) The benefit cost ratio of the net present value of all savings to net
present value of all costs is greater than 1.
• Therefore, the financial evaluation confirms that the projects benefit will
contribute to the development of SO COTE CO II's system and to the
economic development of the area.
Project Justification
• The proposed project will improve the efficiency of the employees,
particularly the Maintenance Crew, in delivering prompt and quality
service to the customer.
Commission's Discussion
• SOCOTECO II's administrative office had been in place at the heart of
General Santos City since 1972. That time, the location was
strategically planned to efficiently address the demands and needs of
the member-consumer. However, with the development of the city, the
current administrative office location would not be ideal anymore for
engineering and other technical services, hence, the need to relocate.
• Time and distance are the two factors that will trigger the cause of
discomfort and stress, thereby having complaints. These complaints
made SOCOTECO II's Management to decide that it is only proper to
conduct a study on the performance of SOCOTECO II in providing
service considering traffic and location as main factor.
• For 2014 Consumer Complaint Response Data, it was noted that there
were 203 filed reports that needed major repairs.
• Out of the 203 filed reports, it has been tracked that the Maintenance
Crew spent 92.10 hours travelling before they reach the repair site. If
the New Headquarters will be relocated at the location of the warehouse
in New Society, Apopong, more than 50% of the travel time will be
saved by SO COTE CO II's crew.