Вы находитесь на странице: 1из 23

British Standard

A single copy of this


British Standard is licensed to
Giorgio Cavalieri
on March 16, 2001

This is an uncontrolled copy.


Ensure use of the most current
version of this standard by
searching British Standards Online
at bsonline.techindex.co.uk
BRITISH STANDARD BS 8204-4:
1993

In-situ floorings —
Part 4: Code of practice for terrazzo
wearing surfaces
Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI

UDC 693.73:692.53
BS 8204-4:1993

Committees responsible for this


British Standard

The preparation of this British Standard was entrusted by Technical


Committee B/544 Plastering, rendering, dry lining, screeds and in-situ
flooring, to Subcommittee B/544/6 Screeds and in-situ floorings, upon which
the following bodies were represented:

Association of Lightweight Aggregate Manufacturers


British Aggregate Construction Materials Industries
British Resin Manufacturers Association

Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI


Building Employers Confederation
Chartered Institute of Building
Concrete Society
Contract Flooring Association
Department of the Environment (Building Research Establishment)
Department of the Environment (Property Services Agency)
Federation of Associations of Specialists and Subcontractors
Federation of Plastering and Drywall Contractors
Federation of Resin Formulators and Applicators (FeRFA)
Mastic Asphalt Council and Employers Federation
Mortar Producers Association Limited
National Federation of Terrazzo-Marble and Mosaic Specialists
Scottish Master Plasterers Association
Society of Chemical Industry

This British Standard, having


been prepared under the
direction of Technical
Committee B/544, was
published under the authority
of the Standards Board and
comes into effect on Amendments issued since publication
15 October 1993

© BSI 02-1999 Amd. No. Date Comments

The following BSI references


relate to the work on this
standard:
Committee reference B/544/6
Draft for comment 92/16922 DC

ISBN 0 580 22452 X


BS 8204-4:1993

Contents

Page
Committees responsible Inside front cover
Foreword iii
1 Scope 1
2 Normative references 1
3 Definitions 1
4 Exchange of information and time schedule 1
4.1 General 1
4.2 Exchange of information 1
Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI

4.3 Time schedule 2


5 Materials 2
5.1 Cement 2
5.2 Aggregates 2
5.3 Pigments 2
5.4 Admixtures 2
5.5 Additional materials 2
5.6 Water 3
5.7 Reinforcement 3
5.8 Dividing strips 3
6 Design considerations 3
6.1 Concrete bases to receive flooring 3
6.2 Screeds 3
6.3 Preparation of concrete base and screed 3
6.4 Backing for terrazzo skirtings, risers, treads and strings 3
6.5 Methods to minimize cracks in the terrazzo flooring 3
6.6 Size of terrazzo aggregate 4
6.7 Terrazzo mix proportions 4
6.8 Terrazzo thicknesses 4
6.9 Tolerances on level and surface regularity 4
6.10 Slip resistance 4
6.11 Conductive flooring 4
6.12 Movement joints 5
7 Work on site 5
7.1 Workmanship 5
7.2 Protection against the weather 5
7.3 Preparation of the concrete base 5
7.4 Screed mix 6
7.5 Pumping the screed 6
7.6 Laying the screed 6
7.7 Dividing strips 6
7.8 Curing the screed 6
7.9 Terrazzo mix proportions 6
7.10 Batching and mixing terrazzo 7
7.11 Laying the terrazzo flooring 7
7.12 Surfaces other than floors 7
7.13 Curing the terrazzo flooring 7
7.14 Surface grinding 7
7.15 Curing after final machining 8
7.16 Protection 8

© BSI 02-1999 i
BS 8204-4:1993

Page
8 Inspection and testing of flooring 8
9 Cleaning and maintenance 9
Annex A (normative) Method for the assessment of levels and
surface regularity 10
Annex B (normative) Determination of slip resistance value (SRV) 10
Figure A.1 — Slip gauges for checking surface regularity 10

Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI


Figure B.1 — Friction tester 11
Table 1 — Mechanical properties of terrazzo aggregates 2
Table B.1 — Properties of the friction tester slider (soft rubber) 13
Table B.2 — Temperature corrections for SRV readings using
soft rubber slider 13
List of references Inside back cover

ii © BSI 02-1999
BS 8204-4:1993

Foreword

This Part of BS 8204 has been prepared under the direction of Technical
Committee B/544 Plastering, rendering, dry lining, screeds and in-situ flooring.
It gives recommendations for terrazzo floorings laid in-situ on a cement and sand
screed applied to a concrete slab and finished by grinding and polishing the
surface. Annex A and Annex B give relevant test methods.
If terrazzo flooring is laid well and ground to a fine grit finish, it provides a hard,
durable surface which is easy to clean and not inherently slippery. In addition, it
is mainly unaffected by water.
BS 8204-4 is one of a series dealing with in-situ floorings; the other Parts of
BS 8204 are as follows.
Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI

— Part 1:1987, Code of practice for concrete bases and screeds to receive in-situ
floorings.
— Part 2:1987, Code of practice for concrete wearing surfaces.
— Part 3:1993, Code of practice for polymer modified cementitious wearing
surfaces.
— Part 51): Code of practice for mastic asphalt underlays and wearing surfaces.
An additional Part of BS 8204 dealing with cold-setting resin wearing surfaces is
to be prepared.
BS 8204-4 supersedes section 3 of CP 204-2:1970, which will be withdrawn
when BS 8204-5 is published.
As a code of practice, this British Standard takes the form of guidance and
recommendations. It should not be quoted as if it were a specification and
particular care should be taken to ensure that claims of compliance are not
misleading.
A British Standard does not purport to include all the necessary provisions of a
contract. Users of British Standards are responsible for their correct application.
Compliance with a British Standard does not of itself confer immunity
from legal obligations.

Summary of pages
This document comprises a front cover, an inside front cover, pages i to iv,
pages 1 to 14, an inside back cover and a back cover.
This standard has been updated (see copyright date) and may have had
amendments incorporated. This will be indicated in the amendment table on
the inside front cover.

1)
In preparation.

© BSI 02-1999 iii


Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI

blank
iv
BS 8204-4:1993

1 Scope 4.1 General


This Part of BS 8204 gives recommendations for the Consultations and exchange of information between
materials, design and work on site for in-situ all parties concerned with the building operations
cementitious terrazzo flooring, and should be read should be arranged at an early date, so that each
in conjunction with BS 8204-1:1987. may have full knowledge of the particulars of the
work and be able to cooperate in producing the
2 Normative references conditions required by the others to complete a
satisfactory job.
This Part of BS 8204 incorporates, by reference,
provisions from specific editions of other 4.2 Exchange of information
Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI

publications. These normative references are cited The designer should provide in good time all
at the appropriate points in the text and the relevant information to those responsible for laying
publications are listed on the inside back cover. the flooring and to others whose work could be
Subsequent amendments to, or revisions of, any of affected, including whichever of the following are
these publications apply to this Part of BS 8204 only applicable:
when incorporated in it by updating or revision. a) description, situation and address of site and
means of access;
3 Definitions
b) those conditions of contract which could
For the purposes of this Part of BS 8204, the practically affect this particular work;
definitions given in BS 6100-6.1:1984, c) location and area of flooring to be laid;
BS 6100-6.2:1986, BS 6100-6.3:1984 and
BS 6100-6.4:1986 apply, together with the d) age and nature of the base, including
following. information about the previous use of the floor
which could impair adhesion, and any
3.1 preparatory treatment required;
floor base
e) specification including mix proportions of
material that supports a screed or flooring flooring to be laid;
3.2 f) thickness of floor and flooring;
flooring g) finished floor level, surface regularity falls and
uppermost fixed layer of a floor that is designed to maximum permissible departure from datum;
provide a wearing surface h) class of surface regularity of base
3.3 (see BS 8204-1:1987);
screed i) type of damp-proofing and insulation;
layer of well-compacted material, commonly a j) type (bonded or unbonded) and thickness of new
mixture of cement and sand, applied in-situ to a screed;
base at the appropriate thickness, suitably finished k) any work consequent upon services passing
to receive the flooring to be applied and to enable the through the floor;
flooring to be laid to a designated level
l) treatment of joints;
3.4
m) treatment of channels;
terrazzo
n) treatment of skirtings;
mixture of marble or other natural stone aggregates
with Portland cement, incorporating colouring o) treatment of junctions with adjacent floor and
pigments where required, which is ground after floorings;
setting to expose the aggregate and provide a p) type of finish of base;
smooth hard-wearing finish q) any special requirements related to underfloor
heating;
4 Exchange of information and time
r) minimum intervals between stages of work and
schedule the application of heat in the building;
NOTE This clause deals with the exchange of information and s) date for the completion of the base to receive
time schedule for the whole floor, including bases and screeds.
the terrazzo;
t) dates for the start and completion of various
sections of the floor;
u) details of any conformity testing required.

© BSI 02-1999 1
BS 8204-4:1993

4.3 Time schedule 5.2.4 Deleterious material


In considering the schedule, in addition to the usual Aggregates should not contain any deleterious
intervals between commencement and completion of material in sufficient quantity to affect adversely
work by the various trades involved, additional the surface finish. For example, coal, lignite and
allowances should be made for the following: iron pyrites in the aggregate can cause “pop-outs”.
a) curing and drying of the base concrete before 5.3 Pigments
the screed and flooring is laid, where applicable; Colouring agents should conform to BS 1014:1992;
b) period of protection of the completed floor from other pigments may be used by agreement between
damage by other trades, including restriction of

Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI


the parties concerned, however, those not covered by
access. BS 1014 could be subject to fading.
5.4 Admixtures
5 Materials
The following admixtures may be used.
5.1 Cement
a) Air-entraining. Air-entraining admixtures
The cement should be grey or white Portland should conform to BS 5075-2:1982. Admixtures
cement conforming to class 42.5N in BS 12:1991. which entrain a small amount of fine air bubbles
5.2 Aggregates could help to reduce “bleeding” of free water and
5.2.1 Aggregates for fine concrete screeds improve the finished surface of the concrete base
or screed. An excessive amount of entrained air
Aggregates for fine concrete screeds should be can reduce the strength of the concrete to an
composed of 10 mm single-sized coarse aggregate in unacceptable degree.
accordance with Table 3 of BS 882:1992 and of sand
in accordance with 5.2.2 of this standard. b) Water reducing. Water reducing admixtures
should conform to BS 5075-1:1982. These
5.2.2 Sand for cement: sand screeds admixtures may be used to improve workability
Sands for cement and sand screeds should conform and reduce the water content otherwise required
to grading limit C or M of Table 4 of BS 882:1992 in the mix. They may also entrain a small
but with not more than 10 % passing sieve quantity of air.
size 150 4m and with an additional requirement of c) Superplasticizing. Superplasticizing
not more than 3 % passing sieve size 75 4m. admixtures should conform to BS 5075-3:1985.
5.2.3 Aggregates for terrazzo flooring These admixtures greatly increase workability at
normal water contents for a short period to
Aggregates for terrazzo wearing surfaces should be
produce “flowing concrete” which needs little or
crushed marble and should be angular as distinct
no compaction. Alternatively they may be used as
from elongated and flaky and free from fines and
water reducing admixtures.
dust. Aggregates should be washed single-sized
between 3 mm and 25 mm and could be used d) Accelerating. Accelerating admixtures should
individually or mixed, depending on the decorative conform to BS 5075-1:1982. These admixtures
effect required. The mechanical properties of may be used to accelerate the rate of setting and
terrazzo aggregates should be within the ranges hardening of concrete in cold weather.
given in Table 1. Admixtures which contain calcium chloride
should not be used in, or in materials adjacent to,
Table 1 — Mechanical properties of terrazzo
reinforced concrete or concrete or screed
aggregates containing embedded metal.
Property Range Reference e) Retarding. Retarding admixtures should
%
conform to BS 5075-1:1982. These admixtures
Aggregate crushing 15 to 30 BS 812-110:1990 decrease the initial rate of reaction between
value (ACV) cement and water and thereby retard the setting
Aggregate impact 15 to 35 BS 812-112:1990 of the concrete.
value (AIV)
5.5 Additional materials
Aggregate abrasion 7 to 15 BS 812-113:1990
value (AAV) Additional materials may be used, both in the
screed and terrazzo flooring, by agreement between
the relevant parties, provided evidence of
satisfactory performances is available. These
include materials such as polymer dispersions,
microsilica fume, pulverized-fuel ash and ground
granulated blastfurnace slag.

2 © BSI 02-1999
BS 8204-4:1993

5.6 Water Where an unbonded screed is to be constructed


Water should be fresh, clean and drinkable. either on a new floor or an old one being renovated,
the base should be sufficiently clean and smooth to
5.7 Reinforcement receive any separating material specified. Before
Where light reinforcement is required in a screed it the screed is laid the reasons for any cracking or
should consist of steel fabric, reference D49 or D98 hollowness of the existing base should be diagnosed
in accordance with BS 4483:1985. and appropriate remedial treatment carried out.
5.8 Dividing strips Cracks and loose or hollow portions should be cut
out and made good.
Dividing strips should be made of brass, aluminium
An unbonded screed should be increased in
Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI

alloy or plastics and should incorporate a


thickness to not less than 60 mm and may consist of
mechanical key for fixing into the screed.
cement and sand as described for bonded screeds, or
preferably, should be a fine concrete using 10 mm
6 Design considerations
maximum size aggregate with the
6.1 Concrete bases to receive flooring proportions 1 : 4.5 ± 0.5 cement: dry aggregate by
Concrete bases should be designed and constructed weight (e.g. 1 : 2 : 3, cement : sand : coarse
following the recommendations contained in aggregate). The screed should contain a light steel
BS 8204-1:1987. Any damp-proof membrane and/or fabric reinforcement placed approximately mid
thermal insulation required should be placed below thickness.
the concrete base slab. 6.3 Preparation of concrete base and screed
The surface should be provided with a float finish The concrete base should be prepared as given
with a surface regularity of class SR3 as given in 7.3. The terrazzo flooring should be laid
in Table 2 of BS 8204-1:1987. Any falls required within 2 days of laying the screed.
should be formed in the base.
6.4 Backing for terrazzo skirtings, risers,
6.2 Screeds treads and strings
6.2.1 Bonded screed On vertical surfaces the thickness of the bonded
A cement and sand screed should be bonded to a cement : sand backing should be between 10 mm
concrete base to provide a levelling layer to receive and 20 min. The mix proportions should be as given
in-situ terrazzo flooring. in 7.4.1.
The mix proportions of cement to dry sand should be 6.5 Methods to minimize cracks in the terrazzo
within the range 1 : 4 + 0.5 by weight. flooring
– 1.0
The thickness of the screed at any point should not Unless precautions are taken, the flooring could
be less than 25 min. crack or craze due to differential shrinkage or
NOTE Because of the deviation in level of the base some movement between the terrazzo, screed and the
variation in screed thickness has to be accepted and to achieve base. The following precautions should be taken.
this minimum thickness a design thickness of up to 40 mm will
normally be required. a) Size of terrazzo panels. The floor finish should
In some circumstances, the thickness of the screed be divided into panels generally not
may have to be increased above 40 mm but it should exceeding 1 m2 in area and separated by dividing
be noted that above this thickness there will be an strips. The length of the panels generally should
increasing risk of loss of adhesion with the base. not be greater than twice the width. Increasing
the length of panels in relation to their width,
6.2.2 Unbonded screed increases the risk of cracking.
Although bonded screeds are generally preferred, it b) Size of aggregate. Aggregates smaller
may be necessary to use unbonded screeds, than 3 mm should not be used. Large aggregates
e.g. when terrazzo is to be laid on an old cracked reduce the risk of crazing.
floor, over precast concrete floor beams, where
c) Water content. The water content of the mix
movement is expected, or if there is likely to be
should be as low as possible, consistent with
vibration of the floor. The screed should be laid on
obtaining thorough compaction, in order to
an isolating membrane of 500 gauge or 1 000 gauge minimize drying shrinkage.
plastics sheeting or building paper conforming to
BS 1521:1972 and should be lapped at least 50 mm d) Conditions during laying. The laying of
at all joints. terrazzo in areas exposed to high temperature,
strong sunlight, strong draughts or winds should
be avoided, since under these conditions surface
crazing is likely to occur.

© BSI 02-1999 3
BS 8204-4:1993

Where terrazzo has to be laid in such 6.9 Tolerances on level and surface regularity
unfavourable conditions, care should be taken to 6.9.1 General
ensure that the surface of the screed does not
rapidly absorb water from the terrazzo. In Flatness or surface regularity is a measure of the
addition, immediately after the normal rolling deviations from a parallel plane over a large area of
and trowelling the terrazzo should be covered the floor, as well as over small local areas. Some
with waterproof sheeting in order to retain the variations in surface level can be allowed without
moisture and prevent rapid drying. The sheeting detriment to the satisfactory use of the floor.
should be left undisturbed for at least 24 h. 6.9.2 Departure from datum

Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI


6.6 Size of terrazzo aggregate The designer should specify the maximum
Aggregates smaller than 3 mm should not be used permissible departure of the level of the flooring
for terrazzo. from datum, taking into account the area of the floor
and its use. For normal purposes ± 15 mm from
The location of the flooring will govern the size of
datum will be found to be satisfactory. Greater
aggregate used, and areas such as treads, risers, accuracy to datum could be required in small rooms,
strings and skirtings should not be expected to along the line of partition walls, in the vicinity of
accommodate the larger sizes.
door openings and where specialized equipment is to
Where fine mixes are required, aggregate of be installed directly on the floor. Terrazzo flooring
size 3 mm to 5 mm should be mixed with an equal or should not be used to make major adjustments to
greater proportion of size 5 mm to 6 mm. the level of the floor.
For pavings, larger aggregates up to 25 mm may be 6.9.3 Surface regularity
used. The technique is to lay a base of finer material
and scatter the large aggregate evenly over the For in-situ terrazzo flooring, a high standard of
surface, afterward beating and rolling it into the surface regularity is normally required. The
matrix. maximum permissible departure from the
underside of a 3 m straightedge resting in contact
6.7 Terrazzo mix proportions with the floor under its own weight is 3 mm. Details
The mix proportions should be as given in 7.9. of the method of checking are given in Annex A.
6.8 Terrazzo thicknesses There should be no noticeable change in level across
any joints in the terrazzo flooring.
6.8.1 Flooring
6.10 Slip resistance
The thickness of terrazzo flooring should be not less
than 15 mm when the aggregate used is of 10 mm Terrazzo flooring is not inherently slippery and the
maximum size or less. With aggregate larger normal finish obtained by grinding with a fine
than 10 mm, the flooring thickness should be abrasive stone should be suitable for most locations.
increased proportionately. However, on staircase treads and ramped surfaces
the use of pre-fabricated anti-slip strips set in the
6.8.2 Skirtings
terrazzo should help to increase grip. To improve
A screed not less than 10 mm thick should be slip resistance a proportion of silicon carbide or
applied first to the wall to form a base. The aluminous grit may be incorporated in the terrazzo
thickness of skirtings should be 6 mm and the mix mix.
proportions should be similar to those for adjacent
6.11 Conductive flooring
flooring.
To ensure the safe discharge of static electricity in
6.8.3 Stairs and strings
some operating theatres, anaesthetizing rooms and
For stairs and strings the minimum thickness of rooms in maternity units for abnormal deliveries,
terrazzo for these items should be as follows. terrazzo flooring incorporating carbon black could
Treads: 15 mm be used. Specification details for this type of flooring
Risers: 10 mm should be as given in HTM 2:1977 [1].
Strings: 6 mm

4 © BSI 02-1999
BS 8204-4:1993

6.12 Movement joints 7.3 Preparation of the concrete base


Where joints in the concrete base are liable to move, 7.3.1 General
they should be carried through the screed and The bond between the screed and the concrete base
terrazzo flooring to the floor surface by means of depends to a great extent upon the condition of the
proprietary metal-edged movement joint profiles. surface of the base at the time of laying the screed.
These vary in depth and thickness, have a Where the screed is laid on a set and hardened base
mechanical key and may also be used to form joints complete bond cannot be ensured. (See 7.3.3.)
other than structural ones. They should also be used
7.3.2 High degree of bond
around columns, between in-situ terrazzo and other
Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI

types of flooring, and centrally over supporting 7.3.2.1 Roughening of the base
beams and walls of suspended structural floors. In the case of in-situ slabs or precast units, where a
high degree of bond is required, the laitance on the
7 Work on site base should be entirely removed, by suitable
7.1 Workmanship mechanized techniques, preferably by contained
shot blasting equipment to expose cleanly the coarse
Care should be taken to ensure good workmanship aggregate. All loose debris and dirt should be
and efficient supervision. Trained operatives should removed, preferably by vacuum equipment.
be employed.
Where the base is a concrete layer over precast
7.2 Protection against the weather concrete units it should be prepared as above except
7.2.1 Cold weather that, if the layer is thin (below 100 mm) and
If mixing and laying are to proceed in cold weather, roughening by heavy mechanical scabbling is likely
measures should be taken to ensure that stored to damage it or the precast layer below,
consideration should be given to the use of shot
aggregates and cement are maintained at
blasting equipment.
temperatures above freezing. Laying should only
take place when the temperature is above 5 °C, can These operations should be delayed until shortly
be maintained above 5 °C and is unlikely to drop before the screed is laid to prevent contamination or
below this figure for 48 h after laying. Freshly laid accumulation of dirt.
screeds and terrazzo flooring should be protected by 7.3.2.2 Bonding treatment
means of tarpaulins or sheeting lapped and
The base concrete should be kept wet for several
supported clear of the surface on a temporary
hours before the screed is to be laid, e.g. overnight,
framework in such a manner that the wind cannot
any excess water being brushed off before grouting.
blow underneath. Unless adequate precautions can
Within a period of 30 min before the screed is to be
be taken it would be preferable to delay operations
laid (less in hot weather), a thin layer of neat cement
until the arrival of warmer weather.
grout of creamy consistency should be brushed into
7.2.2 Hot or drying weather the surface of the base concrete. It is essential that
In hot or drying weather care should be taken that the screed is compacted on to the base while the
the screed or terrazzo mix does not stiffen or dry out grout is still wet.
to an extent that prevents thorough compaction. A proprietary bonding agent may be used or a
After compaction and finishing, the surface should proprietary bonding admixture may be added to the
not be allowed to dry out quickly, and this may be grout in accordance with the manufacturer’s
achieved by protection with plastics sheeting or instructions. In these cases the appropriate
other suitable means. In addition, where the screeds procedure of 7.3.2.1 should still be carried out.
and terrazzo flooring are laid in the open or 7.3.3 Unbonded screeds
otherwise exposed to direct sunlight, their surface
should be protected from the sun to reduce the risk Where an unbonded screed is to be constructed
of thermal cracking. Similarly, these precautions either on a new floor or on an old one being
should be observed where winds or draughts could renovated, the base should be sufficiently clean and
affect the surface of the screeds and terrazzo smooth to receive any separating material specified.
flooring by causing rapid drying and consequent Before the screed is laid the reasons for any cracking
cracking or crazing. or hollowness of the existing base should be
diagnosed and appropriate remedial treatment
7.2.3 Wet weather carried out. Cracks and loose or hollow portions
If no protection is provided by the structure, freshly should be cut out and made good.
laid screeds and terrazzo flooring should be covered
to prevent damage to the surface by rain.

© BSI 02-1999 5
BS 8204-4:1993

7.4 Screed mix NOTE Experience has shown that most efficient pumping will
be achieved when well-graded sand with not less than 15 %
7.4.1 Mix proportions passing a 300 4m sieve is used. It is often difficult to pump
satisfactorily mixes richer than 1 : 4 at water contents suitable
For both bonded and unbonded screeds the mix for screeds.
proportions, by mass, should be within the following
ranges: 7.6 Laying the screed
a) Cement: sand screeds Screeds should always be laid by the terrazzo layer.
Cement: sand, 1 : 45 + 0.5 Narrow strips of screed material, laid and
– 1.0 thoroughly compacted to finished level, should be
b) Fine concrete screeds used to establish the level of the screed. The screed

Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI


Cement: total aggregates, 1 : 45 ± 0.5. should be placed and compacted immediately after
Where possible, cement and aggregates should be laying the strips. Where the edge of a strip forms a
batched by mass. This may not be practicable on daywork joint it should be formed or cut to produce
many sites and in these circumstances the a vertical joint. Alternatively, screed battens,
aggregates could be volume batched. The cement carefully levelled and trued, should be fixed at the
should be batched by the whole bag and the sand correct height for the required thickness of screed.
and coarse aggregate by means of a suitable Battens should be removed before laying the
container of known volume. Due allowance should adjacent bay of screed. At daywork joints all bedding
be made for the bulking of damp sand. screed beneath the battens should be cut away to
Where the thickness of the screed is 50 mm or form a vertical joint.
greater it should be of fine concrete. The mix should be spread on the prepared base with
adequate surcharge, thoroughly compacted, either
7.4.2 Method of mixing
by heavy tamping or by mechanical means, levelled
The materials should be thoroughly and efficiently with a screed board and finished with a wood float.
mixed by means of forced action mechanical mixers,
In order to facilitate the compaction of thicker
e.g. trough and pan paddle mixers and paddle
screeds, i.e. over 50 mm thickness, the screed may
mixers attached to screed pumps. The amount of be laid in two layers. Both layers should be of the
water added should be the minimum necessary to same mix and water content and be approximately
give sufficient workability for laying and thorough
equal in thickness. To ensure satisfactory adhesion
compaction.
the surface of the compacted lower layer should be
NOTE 1 Free-fall drum mixers have been found to produce lightly roughened, e.g. by raking, before adding the
inconsistent mixing of low moisture content material and their
use is not recommended for such mixes. second layer. It is essential that the upper layer be
NOTE 2 A common problem is the use of too dry, badly mixed placed and compacted immediately after
cement and sand mixes which cannot be properly compacted, compaction of the lower layer.
with the result that the screed has a dense upper crust with an
underlying screed very weak and friable. The result of this has 7.7 Dividing strips
been that point loads have caused localized failures in the screed.
Dividing strips for the terrazzo panels should be
When mixing by machine is not possible, materials inserted and fixed at the positions specified and at
may be mixed on a clean non-absorbent surface the correct level while the screed is still workable.
using clean hand tools. Whatever method of mixing
is used, the materials should be thoroughly blended 7.8 Curing the screed
in the dry state before water is added. Mixing should The screed surface should be protected from drying
be continued until the batch has a uniform by covering with a suitable sheet material,
consistency. e.g. polyethylene, until the terrazzo flooring is laid
No water should be added once mixing is complete. which should be within 2 days.
Any screed mix unused within 2 h of adding the 7.9 Terrazzo mix proportions
mixing water should be discarded.
The proportions of cement and aggregate will
7.4.3 Ready mixed screeds depend upon the maximum size and grading of the
Ready-to-use screed mixes should conform to aggregate but mixes richer than 1 part cement
section 4 of BS 4721:1981. to 2 parts aggregate by volume should be avoided
7.5 Pumping the screed except for thin sections. Cement should be either
Portland cement or white or coloured Portland
The pumping system should deliver the material to cement; alternatively a coloured matrix may be
the working area in a condition suitable for laying. produced by incorporating pigments in the mix.

6 © BSI 02-1999
BS 8204-4:1993

The quantity of water used should be kept to the 7.12 Surfaces other than floors
minimum necessary to ensure thorough compaction. A cement/water slurry should be well brushed into
The lowest effective water content will minimize the surface of the backing mix. The terrazzo mix
drying shrinkage. Increasing the water content of a should then be immediately applied by trowel to the
mix will increase the drying shrinkage of terrazzo required thickness and line, and subsequently
flooring, increasing the risk of cracking. compacted and trowelled to the required finish.
The mix proportions for stairs and strings should be
7.13 Curing the terrazzo flooring
similar to those for the adjacent flooring. The
proportion of cement to aggregate may be increased Curing involves keeping the terrazzo damp for as
to 2 : 3 by volume for thin sections. long as necessary and is usually carried out by
Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI

means of waterproof sheeting kept in close contact


7.10 Batching and mixing terrazzo
with the surface, ensuring that it is properly lapped
The two alternative methods of mixing and laying and securely held in position.
terrazzo flooring are as follows: Curing should commence as soon as the terrazzo
a) incorporating all the aggregates in the mix flooring can be covered without damage to its
before it is laid; surface, and should continue until the flooring is
b) incorporating only the fine aggregates in the ready for grinding. The curing period which should
mix, laying it, then scattering the large aggregate be at least 24 h will vary depending on
on the surface and beating and rolling it in. temperatures and site conditions and should be
determined by the terrazzo installer.
All ingredients for the mix should be accurately
gauged using gauge boxes and thoroughly mixed to 7.14 Surface grinding
produce a mix with uniform colour and distribution Grinding should commence 3 or 4 days after
of aggregates. Where pigments are used they should completion of laying, or sooner if the rate of
be thoroughly mixed with the cement by hand or hardening permits. Grinding is normally carried out
mechanically before the aggregate is added. When by machine but small areas may be done by hand.
the dry materials have been thoroughly mixed
For the first grinding, coarse grit stones
water should be added until a workable consistency
(usually 20 grit) should be used with plenty of
has been obtained.
water. Grinding should continue until the aggregate
7.11 Laying the terrazzo flooring is exposed and the surface is completely smooth
The thickness of the terrazzo flooring should be not when the floor should be washed and rinsed
less than 15 mm when the aggregate used is thoroughly. Any voids revealed by grinding should
of 10 mm maximum size or less. With aggregates be cleaned out and the entire surface grouted with
larger than 10 mm, the thickness should be neat cement. If required, this should be tinted to
increased proportionately. match the colour used in the terrazzo mix. It is
A cement/water slurry of the same colour as that essential to work the paste well into the floor
surface to ensure adhesion and to fill all voids.
used in the terrazzo mix should be well brushed into
the surface of the screed and, while this is still wet, After grouting, the floor should be kept damp and
the terrazzo should be placed into the panels formed free from excessive changes of temperature for
by the dividing strips, ensuring that it is firmly about 3 days or until it is considered ready for final
pressed into the corners at junctions of strips. machining. This should be carried out using a finer
Trowelling should be carried out to the necessary grade of stone (usually 80 grit) with an ample
level and where required aggregate should be supply of water, to produce a hard, smooth and
scattered uniformly over the surface and tamped in. non-dusting surface.
The terrazzo should then be compacted by rolling Where a finer finish to the floor is required a
and trowelling at intervals depending on the rate of specialist’s advice should be sought.
setting of the mix, to remove excess cement and The use of dry sanding machines for grinding should
water and produce a surface with regular be restricted to small areas where it is not practical
distribution of aggregate in the minimum amount of to use a wet-process machine, e.g. in toilets, on
matrix. Final trowelling should reveal the lines of staircases or skirtings.
the dividing strips.

© BSI 02-1999 7
BS 8204-4:1993

7.15 Curing after final machining 8.2 Testing


After final machining, floors should be covered with At the appropriate time after laying the flooring,
plastics sheeting and protected against damage tests may be carried out for the following:
from following trades or traffic. a) levels and surface regularity (see 8.3);
In order to reduce the risk of shrinkage cracking, the b) density (see 8.4);
terrazzo floor should be allowed to dry out slowly
c) slip resistance (see 8.5);
and naturally. The building should not be
artificially heated for 6 to 8 weeks, then the d) adhesion of the flooring to the base (see 8.6).
temperature should be increased gradually. 8.3 Levels and surface regularity

Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI


7.16 Protection When the flooring is tested by the methods
Finished and partly finished flooring should be described in Annex A the departure from datum and
protected from damage or contamination from the surface regularity should be within the limits
following trades. During the laying and grinding specified (see 6.9).
operations the area being treated should be The number of measurements required to check
accessible only to the flooring operatives. Completed levels and surface regularity should be agreed
terrazzo work should not be subjected to traffic until between the parties concerned bearing in mind the
protection has been provided. standard required and the likely time and costs
The terrazzo should be kept clean and free from involved.
cement and plaster droppings and all materials 8.4 Density
likely to cause stains. Particular care should be
The density of the terrazzo flooring should be
taken with substances that could cause permanent
above 2 000 kg/m3 after drying to a constant weight
staining, e.g. oils, grease and paint.
at (105 ± 5) °C when sampled and tested by the
Sheeting and/or boards should be laid over the method given clause 10 of BS 1881-114:1983.
finished work to protect it. Sawdust should not be
used for this purpose. 8.5 Slip resistance
Stair finishings, especially nosings, are vulnerable The floor should be tested in accordance with the
to damage from following trades and should be method described in Annex B.
protected by temporary casings. The slip resistance value (SRV) should be greater
than 39 in both the wet and dry state except for
8 Inspection and testing of flooring situations where ease of cleaning is more critical
than slip resistance and/or where all who use or are
8.1 Inspection
likely to use the floor will wear specially provided
The work should be inspected during progress and slip resistant boots or shoes, a slip resistance value
after completion, special attention being paid to the in the wet of 33 may be deemed acceptable.
following:
8.6 Adhesion of the flooring to the base
a) that materials are as specified;
8.6.1 General
b) preparation of the base (see 7.3.2.1 or 7.3.3);
The adhesion between the flooring to the base may
c) mix proportions and mixing of the screed be estimated by tapping the surface, e.g. with a rod
(see 7.4 or 7.5); or a hammer, a hollow sound indicating lack of
d) priming of the base (see 7.3.2.2); adhesion.
e) compaction of the screed (see 7.6); NOTE 1 Hollowness, if any, is usually found at the edges and
corners of bays and at each side of any cracks, if any, that have
f) positioning of dividing strips (see 6.5 a) developed in the flooring.
and 7.7); NOTE 2 Terrazzo flooring on an unbonded screed is likely to
g) curing of the screed (see 7.8); sound hollow when tested as above.

h) mix proportions and mixing of the terrazzo Tests to check the adhesion of a flooring to its base
(see 7.9 and 7.10); should be made as late as possible in a construction
programme when the maximum effect of drying
i) compaction of the terrazzo flooring (see 7.11); shrinkage has taken place. Account should be taken
j) surface texture and finish (see 7.14); of the time required for replacement of a section of
k) levels and surface regularity (see 6.9). flooring, if any, to be laid within the construction
programme.
NOTE 3 However good the preparation of the base, there is no
guarantee that adhesion will always be complete. The best
workmanship will reduce loss of adhesion to a minimum.

8 © BSI 02-1999
BS 8204-4:1993

Loss of adhesion does not necessarily mean that the 9 Cleaning and maintenance
flooring is unsatisfactory. Loss of adhesion is
Terrazzo can usually be cleaned effectively by
unsatisfactory when it is accompanied by visible or
washing or scrubbing with warm water and a
measurable lifting of the edges of bays or at cracks,
neutral sulphate-free detergent suitable for
to the extent that the flooring could deflect and
break under the loads imposed in use. cleaning terrazzo. Greasy deposits can be removed
Those areas of flooring that are considered by detergent incorporating an organic solvent or an
alkaline detergent (pH > 9), but these should be
unsatisfactory should be treated by one of the
used only occasionally and never for regular
following methods:
cleaning. The occasional use of mild abrasive
a) made good by injecting the hollow areas with a
Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI

cleaners can be beneficial in removing stubborn


low-viscosity resin, e.g. epoxide or polyester to marks, but household soaps are not recommended
stabilize and improve the bond between the as they tend to leave a slippery scum, particularly in
flooring and the base; hard-water areas.
b) isolating the area by sawing, removing and Regular use of scrub and rinse cleaning machines
relaying the affected flooring. When removing an fitted with abrasive pads other than the finest
area of flooring care should be taken to minimize grades, or the use of machines with hard plastics
any loss of adhesion in the adjacent part of the bristles, could result in damage to the surface of
flooring. terrazzo. Damage could also be caused by frequent
8.6.2 Alternative test method use of unsuitable cleaning agents, including highly
An alternative method of testing the adhesion of the acidic or alkaline detergents and chemicals.
flooring to the base is given in B.2 of Resistance to staining can be increased by the use of
BS 8204-3:1993. When tested by this method a bond certain proprietary chemical hardeners, and sealing
strength in excess of 0.8 N/mm2 is usually can enhance the appearance of the terrazzo, but
satisfactory. care should be taken to ensure that sealers have
been manufactured for use on terrazzo. The wrong
type of treatment can cause floors to become
slippery; wax polishes and linseed oil should never
be used.

© BSI 02-1999 9
BS 8204-4:1993

Annex A (normative) Annex B (normative)


Method for the assessment of levels Determination of slip resistance
and surface regularity value (SRV)
Check levels to datum using standard surveying B.1 Principle
methods. The floor surface is swept over a given area by a
Check surface regularity by using a slider at the end of a pendulum. The retardation
straightedge 3 m long laid in contact with the floor which is caused by the friction so generated is
surface and resting under its own weight. Measure measured by the extent to which the pendulum fails

Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI


the deviations of the surface from the underside of to reach its original release height. This
the straightedge by means of a slip gauge or other measurement, referred to as the slip resistance
suitable accurate measuring device. An example of value (SRV) is recorded on a scale and approximates
a suitable form of slip gauge is shown in Figure A.1. to 100 times È, the dynamic coefficient of friction.
B.2 Apparatus
B.2.1 TRL pendulum slip resistance tester
B.2.1.1 The friction test shall be made with a tester
(see Figure B.1) manufactured to the design of the
Transport Research Laboratory (TRL). All bearings
and working parts of the instrument shall be
enclosed as far as possible, and all materials used
shall be treated to prevent corrosion under wet
conditions.

Figure A.1 — Slip gauges for checking surface regularity

10 © BSI 02-1999
BS 8204-4:1993

B.2.1.2 The tester shall have the following features. e) A pointer balanced about the axis of
a) A spring-loaded rubber slider of the mass, size suspension, indicating the position of the
and shape specified in B.2.1.3 to B.2.1.6. It shall pendulum arm throughout its forward swing and
be mounted on the end of a pendulum arm so that moving over the circular scale. The mass of the
the sliding edge is approximately 510 mm from pointer shall be not more than 85 g. The friction
the axis of suspension. in the pointer mechanism shall be adjustable so
that, with the pendulum arm swinging freely
b) Means for setting the column of the instrument
from a horizontal position, the outward tip of a
vertical.
nominal 300 mm long pointer can be brought to
c) Means for raising and lowering the axis of rest on the forward swing of the arm at a
Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI

suspension of the pendulum so that the slider point 10 mm below the horizontal.
can:
f) A main scale as detailed in TRL drawings for a
1) swing clear of the surface of the floor; and sliding length of 126 mm.
2) be set to slide over a fixed length of flat B.2.1.3 The mass of the swinging arm, including the
surface of (126.0 ± 1.0) mm, as near as is slider, shall be (1.50 ± 0.03) kg. The centre of
visually possible. gravity shall lie on the axis of the arm at a distance
d) Means of holding and releasing the pendulum of (410 ± 5) mm from the centre of suspension.
arm so that it falls freely from a horizontal
position.

Figure B.1 — Friction tester

© BSI 02-1999 11
BS 8204-4:1993

B.2.1.4 For wet floors the slider shall consist of a B.4.2 Level the base, using the spirit level and the
rubber pad the properties of which shall be as given three levelling screws on the base-frame. Raise the
in Table B.1. The pad shall be (76 ± 1.0) mm wide head so that the pendulum arm swings clear of the
and (25.4 ± 1.0) mm long (in the direction of swing) surface.
and (6.35 ± 0.50) mm thick. This shall be held on a NOTE Movement of the head of the friction tester, carrying the
rigid base with a central pivoting axis and combined swinging arm, graduated scale, pointer and release mechanism,
mass of slider and base shall be (20 ± 5) g. The slider is controlled by a rack and pinion on the rear of the vertical
column. After unclamping the locking knob at the rear of the
assembly shall be mounted on the end of the column, raise or lower the head as required by turning either of
swinging arm in such a way that, when the arm is at the vertical movement control knobs. When the required height

Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI


the lowest point of its swing with the trailing edge of is obtained, it is essential to lock the head unit in position again
by clamping the locking knob at the rear of the column.
the slider in contact with the test surface, the plane
of the slider is angled at (26 ± 3)° to the horizontal. B.4.3 Check the zero setting as follows.
In this configuration the slider can turn about its a) Raise the swinging arm to the horizontal
axis without obstruction to follow unevenness of the release position on the right-hand side of the
surface as the pendulum swings. apparatus, so that it is locked automatically in
For dry floors a more appropriate result will be the release catch.
obtained using a (76 ± 1.0) mm wide leather slider b) Bring the pointer round to its stop in line with
and/or a (25 ± 1.0) mm wide hard rubber slider. This the pendulum arm.
latter should have a hardness of (85 ± 5) IRHD. c) Release the pendulum arm by pressing the
B.2.1.5 The slider shall be spring-loaded against the release button.
test surface. The nominal static force on the slider NOTE The pointer is carried with the pendulum arm on the
as set by the procedure defined in the equipment’s forward swing only.
calibration instructions shall be (22.2 ± 0.5) N in its d) Catch the pendulum arm on its return swing,
median position; the change in the static force on and note the pointer reading.
the slider shall be not greater than 0.2 N per e) Return the arm to the release position.
millimetre deflection of the slider. The resilience
and hardness of the sliders shall conform f) Correct the zero setting as necessary by
to Table B.1. adjustment of the friction rings. If the pointer has
swung past the zero position, screw the rings up
B.2.1.6 The working edges of the slider shall be a little more tightly. If it has not reached zero,
prepared by several swings over fine grade unscrew the rings a little.
sandpaper when the pendulum is set up as given
in B.4. Before testing, the bevel formed by wear on g) With the pendulum arm free and hanging
the working edge shall be measured and if greater vertically, place the spacer, which is attached to a
than 2.0 mm the slider shall be replaced. The chain on the base of the vertical column, under
rubber shall be free from contamination, by, for the lifting-handle setting screw in order to raise
example, abrasive or oil and in sheet or slider form the slider. Lower the head of the tester so that the
shall be stored in the dark at a temperature slider just touches the test surface and clamp in
of (20 ± 5) °C. position. Remove the spacer.
B.2.2 Thermometer, capable of measuring surface h) Check the sliding length of the rubber slider
temperatures. (the distance between two points where the slider
edge of the rubber touches the test surface) by
B.2.3 Potable water at 20 °C and brush for wetting gently lowering the pendulum arm until the
floor surface. slider just touches the surface, first on one side
B.2.4 150 mm scale for setting the swept length. and then on the other side of the vertical. To
B.3 Selection of test area prevent undue wear of the slider when moving
Test areas can be selected in either a strict grid the pendulum arm through the arc of the contact,
pattern or on a random basis. Normally a minimum raise the slider off the test surface by means of
of four tests would be required but in large areas one the lifting handle.
test per 250 m2 would be appropriate. On very large Adjust the sliding length to between 125 mm
areas the sampling rate may be decreased if it is and 127 mm by raising or lowering the head as
found that there is a consistency between results, necessary.
conversely, in smaller areas this sampling rate may NOTE On the scale provided, the outer marks are 127 mm
be increased if there are wide variations in results. apart and the inner ones each indicate the tolerance allowed.

B.4 Setting up procedure i) Place pendulum arm in its release position.


B.4.1 Record the temperature of the floor surface.

12 © BSI 02-1999
BS 8204-4:1993

Table B.1 — Properties of the friction tester slider (soft rubber)


Property Temperature (°C)

0 10 20 30 40

Resilience (%) a 43 to 49 58 to 65 66 to 73 71 to 77 74 to 79
Hardness (IRHD)b 55 ± 5 55 ± 5 55 ± 5 55 ± 5 55 ± 5
a
Lüpke rebound test in accordance with BS 903-A8:1990.
b
International Rubber Hardness Degrees in accordance with BS 903-A26:1969.

B.5 Test procedure B.5.6 Calculate the slip resistance value as the
Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI

B.5.1 For wet tests, wet the slider and the surface to mean of the five recorded readings. Temperature
be tested over the whole area which will be in corrections for SRV readings using a soft rubber
contact with the slider with potable water slider are given in Table B.2.
at (20 ± 4) °C. Table B.2 — Temperature corrections for
For dry tests, unless conducting “as found” tests, SRV readings using soft rubber slider
thoroughly clean and dry the surface. Surface temperature Correction to SRV
NOTE If this test is carried out after the wet test, the action of °C
testing in the wet is normally sufficient to clean the surface and
it is only then necessary to thoroughly dry the surface before 8 to 11 –3
conducting the dry test. 12 to 15 –2
B.5.2 Bring the pointer round to its stop. Release 16 to 18 –1
the pendulum arm by pressing the release button 19 to 22 0
and catch it on the return swing before the slider 23 to 28 +1
strikes the test surface. Return the arm and pointer 29 to 35 +2
to the release position, keeping the slider clear of the
surface by means of the lifting handle. B.6 Test report
B.5.3 Repeat B.5.2, spreading water over the The test report shall include the following:
contact area with a brush between each swing. a) the number, date and reference of this British
B.5.4 Record five successive readings, provided they Standard, i.e. BS 8204-4:1993: Annex B;
do not differ by more than 3 units. If the range is b) location of the site and a drawing showing the
greater than this, repeat the test until a set of five position of the tests;
successive readings are within 3 units. c) a description of the flooring and its age;
When readings are above 75 this requirement can d) dry or wet test conditions;
be relaxed to within 6 units.
e) the slip resistance value at each position tested
B.5.5 Raise the head of the tester so that it swings and the mean of all results.
clear of the surface and check the free swing for zero
error.

© BSI 02-1999 13
Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI

blank
14
BS 8204-4:1993

List of references (see clause 2)

Normative references

BSI standards publications


BRITISH STANDARDS INSTITUTION, London

BS 12:1991, Specification for Portland cement.


BS 812, Testing aggregates.
BS 812-110:1990, Methods for determination of aggregate crushing value (ACV).
Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI

BS 812-112:1990, Method for determination of aggregate impact value (AIV).


BS 812-113:1990, Method for determination of aggregate abrasion value (AAV).
BS 882:1992, Specification for aggregates from natural sources for concrete.
BS 903, Physical testing of rubber.
BS 903-A8:1990, Method for determination of rebound resilience.
BS 903-A26:1969, Determination of hardness.
BS 1014:1975, Specification for pigments for Portland cement and Portland cement products.
BS 1521:1972, Specification for waterproof building papers.
BS 1881, Testing concrete.
BS 1881-114:1983, Methods for determination of density of hardened concrete.
BS 4483:1985, Specification for steel fabric for the reinforcement of concrete.
BS 4721:1981, Specification for ready-mixed building mortars.
BS 5075, Concrete admixtures.
BS 5075-1:1982, Specification for accelerating admixtures, retarding admixtures and water reducing
admixtures.
BS 5075-2:1982, Specification for air-entraining admixtures.
BS 5075-3:1985, Specification for superplasticizing admixtures.
BS 6100, Glossary of building and civil engineering terms.
BS 6100-6, Concrete and plaster.
BS 6100-6.1:1984, Binders.
BS 6100-6.2:1986, Concrete.
BS 6100-6.3:1984, Aggregates.
BS 6100-6.4:1986, Admixtures.
BS 8204, In-situ floorings.
BS 8204-1:1987, Code of practice for concrete bases and screeds to receive in-situ floorings.
BS 8204-2:1987, Code of practice for concrete wearing surfaces.
BS 8204-3:1993, Code of practice for polymer modified cementitious wearing surfaces.

Other reference

[1] Hospital Technical Memorandum No. 2 Anti-static precautions: Flooring in Anaesthetizing Areas, 1977,
London: HMSO

© BSI 02-1999
|
|
|
|
|
|
|
|
|
BSI Ð British Standards Institution
|
|
|
|
|
|
| BSI is the independent national body responsible for preparing British Standards. It
|
| presents the UK view on standards in Europe and at the international level. It is
| incorporated by Royal Charter.
|
|
| Revisions
|
|
| British Standards are updated by amendment or revision. Users of British Standards
|
| should make sure that they possess the latest amendments or editions.
|
|
| It is the constant aim of BSI to improve the quality of our products and services. We
|
| would be grateful if anyone finding an inaccuracy or ambiguity while using this

Licensed Copy: Giorgio Cavalieri, ALSTOM, 16-Mar-01, Uncontrolled Copy. © BSI


| British Standard would inform the Secretary of the technical committee responsible,
|
| the identity of which can be found on the inside front cover. Tel: 020 8996 9000.
|
| Fax: 020 8996 7400.
|
|
| BSI offers members an individual updating service called PLUS which ensures that
|
| subscribers automatically receive the latest editions of standards.
|
|
| Buying standards
|
| Orders for all BSI, international and foreign standards publications should be
|
| addressed to Customer Services. Tel: 020 8996 9001. Fax: 020 8996 7001.
|
|
| In response to orders for international standards, it is BSI policy to supply the BSI
|
| implementation of those that have been published as British Standards, unless
|
| otherwise requested.
|
|
| Information on standards
|
| BSI provides a wide range of information on national, European and international
|
| standards through its Library and its Technical Help to Exporters Service. Various
|
| BSI electronic information services are also available which give details on all its
|
| products and services. Contact the Information Centre. Tel: 020 8996 7111.
|
| Fax: 020 8996 7048.
|
|
| Subscribing members of BSI are kept up to date with standards developments and
| receive substantial discounts on the purchase price of standards. For details of
|
| these and other benefits contact Membership Administration. Tel: 020 8996 7002.
|
| Fax: 020 8996 7001.
|
|
| Copyright
|
|
| Copyright subsists in all BSI publications. BSI also holds the copyright, in the UK, of
|
| the publications of the international standardization bodies. Except as permitted
| under the Copyright, Designs and Patents Act 1988 no extract may be reproduced,
|
| stored in a retrieval system or transmitted in any form or by any means ± electronic,
|
| photocopying, recording or otherwise ± without prior written permission from BSI.
|
|
| This does not preclude the free use, in the course of implementing the standard, of
|
| necessary details such as symbols, and size, type or grade designations. If these
|
| details are to be used for any other purpose than implementation then the prior
| written permission of BSI must be obtained.
|
|
| If permission is granted, the terms may include royalty payments or a licensing
|
| agreement. Details and advice can be obtained from the Copyright Manager.
|
| Tel: 020 8996 7070.
|
|
|
|
|
|
|
|
|
BSI |
|
389 Chiswick High Road |
|
London |
|
W4 4AL |
|
|
|
|
|
|

Вам также может понравиться