Вы находитесь на странице: 1из 25

TAP AG Project Title / Facility Name:

Trans Adriatic Pipeline Project

Document Title:

Method Statement
Lifting Plan for Pipe of 28 Ton Weight

A 30.06.2018 Issued For Review IFR K.Liko F.Bacja A.Fuga

Revision Date Prepared Checked Approved


Rev. Reason for issue and Abbreviation for it
(dd-mm-yyyy) by by by

Contractor Name: JV Renco SpA – Terna SA

Contractor Project No.: 7920

Contractor Doc. No.: 7920-MO-007054

Vendor Doc. No.:

Tag No's.:

TAP AG Contract No.: C1448 Project No.:

PO No.: RD Code: Page: 1 of 27

TAP AG Document No.:

ACS03-C1448-1070-537-V-TPB-0002
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
2 of 22

1. INTRODUCTION

The Trans Adriatic Pipeline will transport gas from the Turkish-Greek border via Greece and Albania across the Adriatic Sea
to Italy.
The project is aimed at enhancing security of supply as well as diversification of gas supplies for the European markets. TAP
will open a new so-called Southern Gas Corridor to Europe and market outlet for natural gas from the Caspian Sea and
Middle East regions and is designed to expand transportation capacity from 10 to 20 BCM per year depending on stage of the
Project.
To achieve this aim the gas transported through the pipeline has to be pressurised at several locations. For this first 10
BCMY- case two compressor stations are required, one in Kipoi (GCS00 - Greece) and one at Fier, close to the Albanian
landfall (ACS03 - Albania). Additionally at the Greece/Albanian border a metering station has to be installed (ACS02).
For the 20 BCMY-case two additional compressor stations have to be installed, on in the area of Serres (GCS01) and one at
the Greece/Albanian border (ACS02).
The pipeline ends at a pipeline receiving terminal (PRT - IPR01) in Puglia (Italy) where the gas is tied in into the Snam Rete
Gas (SRG) Network.

The TAP system will be remote-controlled from the supervisory control centre located at the PRT in Italy. The SCADA
system will be designed to ensure safe operation, control and monitoring of the pipeline system. For data transmission, a ring
of fibre-optic cables to be laid along the whole pipeline route will be used.
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
3 of 22

The construction of the Compressor Station ACS03 will be executed by Joint Venture called JV Renco S.P.A. and Terna
S.A. (the Contractor) with international experience in such projects.
The building and construction industry as a whole has an unacceptably high accident rate and workers involved
in handling and erecting steelwork are in the group which suffers one of the highest serious injury rates in the
industry. The majority of the accidents are as a result of falls from heights. In addition, many serious accidents
occur due to the workers being struck by falling materials.

This procedure establishes the safety measures for erecting steel structures and ensuring compliance with the
requirements of HSE management plan.

Also it is to assist in the assessment of risks and the identification of various control measures so that risks
can be eliminated, avoided or reduced by practical measures, and not by placing sole reliance on the skill of
workers

2. PURPOSE

This procedure is to be used by the members of ETI/APM Project Management Team, Supervisors and
Subcontractors who supervise and control steel structures activities in the whole of the Project.

3. SCOPE

This procedure is to be used by the members of ETI/APM Project Management Team, Supervisors and
Subcontractors who supervise and control steel structures activities in the whole of the Project.

4 RESPONSABILITIES

4.1 SITE MANAGER

He is responsible to: Ensure that the related work packages are being prepared according with the safe system of
work .Coordinate the overall activities of the contractors to be complied with the Project HSE rules.

4.2 HSE MANAGER

To oversee steel structure erection activities to ensure they are performed in accordance with the
requirements of this procedure.
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
4 of 22
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
5 of 22
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
6 of 22

DRAWINGS

Crane Details
Lifting KRUPP KMK 4070
Machine
Max. Load 100 ton
Capacity
Counter 28 Ton
Weight
Lifting 2 X 20 Ton x 10 m
Chain:(2 Legs
Chain Slings)
Shackles 4 X 17 ton (D type)
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
7 of 22

Positioning of the Cranes & Trailer (Draw. 1)


Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
8 of 22

3 m3
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
9 of 22
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
10 of 22
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
11 of 22

TASK DESCRIPTION
(all tasks from beginning to the end)

"Preparing the work on the concrete basis for the installation of the emergency generator:
In the area to be erected the erection and erection will be clean

1 Wet Condition Good weather Condition Hard-Hats, Safety


Inproper driller for Proper driller to be used for Shoes, Safety
Main the scope the scope Goggles, High
Isolations PPE:
Risks: Inproper hand tools Industrial hand tools to be visibility vest,
Bad weather used Handgloves
condition
Mobile crane to enter at site and placed in the Diesel Generator Area with the help of Rigger
Traffic Accident Traffic signs and speed limits Hard-Hats, Safety
Unconsolidated to be followed. Driver to follow Shoes, Safety
2 Main
ground Isolations directions of Riggers, PPE: Goggles, High
Risks:
well leveled and consolidated visibility vest,
ground. Handgloves
a) Mobile Crane to be positioned and full outrigging in well leveled and consolidated ground, as per
drawing, ready for the Lifting of Diesel Generator.
b) Crane operators will arrange that the crane boom is placed ready for lifting procedure and with the
help of slingers, chain sling (2 Sets (4 Legs), WLL= 20 ton per each Leg, Length = 8 m) will be secured by
ring on the crane's hook.

Collision of Operator to follow Rigger's Hard-Hats, Safety


3
vehicles/equipment directions. Exclusion zones & Shoes, Safety
and/or interface signs, ground inspection, Full Goggles, High
Main with personnel.
Isolations outriggers. Slingers to adjust PPE: visibility vest,
Risks: Crane failure, all gears and accessories Handgloves
ground failure, safely. Inspection-color coding
hands injury. of all gears, accessories, well
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
12 of 22

Unconsolidated leveled and consolidated


ground ground

a) Slingers with help of a platform put 2 shackles ( WLL 20 ton) and 4 shackles (WLL 20 ton) on the lifting
lugs that are on top of Diesel Generator,
b) Slingers will attach two taglines on Diesel Generator to control the movement of Generator.

Hands injury, slip, Slingers to adjust all gears and Hard-Hats, Safety
trip and fall accessories safely. Remove all Shoes, Safety
Main
Isolations waste unwanted material from PPE: Goggles, High
Risks:
the lifting area/zone visibility vest,
Handgloves
a) Rigger to have clear visibility all the time with Crane operator to direct him to lift the Diesel Generator
slowly,

5 Unit hitting Gears-accessories pre Hard-Hats, Safety


personnel or inspection/color coding to be Shoes, Safety
damaging confirmed. Slingers to control Goggles, High
Main
equipments. Unit Isolations through taglines the PPE: visibility vest,
Risks:
damage. Personnel movement. Handgloves
under suspended
loads
a) Ensure that the tube is repeatedly positioned to catch
b) The bearer operator will lower the boom for lifting the chain hobs.
6 c) The winch will be parked in the designated area with the help of Rigger.
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
13 of 22

Hands injury - line of Mandatory to use PPE, Hard-Hats, Safety


fire, unsecured Vent The fitters to take care during Shoes, Safety
Main Stack erection of the vent stack to Goggles, High
Isolations PPE:
Risks: Fall from height not trap hands or fingers. visibility vest,
Handgloves, Safety
harnes
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
14 of 22
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
15 of 22
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
16 of 22
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
17 of 22
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
18 of 22
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
19 of 22
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
20 of 22
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
21 of 22

Personnel Involved in Lifting And Installation Of The Emergency Generator

Number Name Surname Position


1 Klodjan Zotaj Lifting Supervisor
2 Jonida Gega Supervisor
3 Albano Zyka 80 t Mobail crane
4 Juljan Bali 100 t mobile crane
5 Arjan Hoxhaj Slingers
6 Andi Bracja Slingers
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
22 of 22

Certificates
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
23 of 22
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
24 of 22
Error!
TAP AG Reference
Rev. No.: source
Doc. no.:
not
found.

Method Statement
Doc. Title: Lifting Plan for Pipe of 28 Ton Weight Page:
25 of 22

Вам также может понравиться