Академический Документы
Профессиональный Документы
Культура Документы
Chapter 4
1
KEY TERMS
2
Project Integration Management
• Includes the processes and activities needed to identify, define,
combine, unify, & coordinate the various processes & project
management activities within the project management process groups.
3
Project Integration Management
Monitoring &
Controlling Processes
Planning
Processes
Executing
Processes
Knowledge Process
Area Initiating Planning Executing Monitoring & Control Closing
• Develop • Develop • Direct and • Monitor and Control • Close
Project Project Manage Project Work Project
Processes
Charter Management Project • Perform Integrated
Plan Execution Change Control
4
4.1- Develop Project
Charter
6
4.1- Develop Project Charter
The process of developing a document that formally authorizes a project
or a phase and documenting initial requirements that satisfy the
stakeholder’s needs and expectations ( PROJECT BIRTH CERTIFICATE )
Project are authorized by someone external to the project such as
sponsor, PMO, portfolio steering committee.
Project charter can be created by them or delegated to Project Manager.
7
7
Develop Project Charter INPUTS :
1- Project Statement of Work.
2- Business Case
Provide the necessary information from business standpoint to
determine whether or not the project is worth the required investment.
It is a result for:
Two categories:
Linear programming
Integer programming
Dynamic programming
Multi-objective programming
9
Project Selection – Economic Models
FV FV = future value
PV 1 r n r = interest rate
n = number of time period
Question
What is the present value PV of $300,000 received three years from now if we
expect the interest rate to be 10 percent?
$300,000 / (1 + 0.1)3
PV = $300,000/1.331 = $225,394.
An organization has two projects to choose from. Project A will take three years
to complete and has an NPV of $45,000. Project B will take six years to
complete and has an NPV of $85,000. Which one is a better investment?
Answer Project B.
0 0 0 200 200
1 50 45 100 91
2 100 83 0 0
3 300 225 0 0
TOTAL 353 291
NPV = 353-291 = 62
11
Internal rate of return (IRR): Project with greater IRR value is better.
It is the rate between the cost and the revenue.
Question
An organization has two projects from which to choose: Project A with an
IRR of 21 % or Project B with an IRR of 15 %. Which one is a better option?
Answer Project A
Payback period:
The number of time periods it takes to recover your investment in the
project before you start accumulating profit. ( Break Even Point )
Question
There are two projects from which to choose: Project A with a payback
period of six months or Project B with a payback period of 18 months.
Which one should the organization select?
Answer Project A
12
Benefit-cost ratio:
Question
What does a benefit cost ratio of 1.7 mean?
A. The costs are greater than the benefits.
Answer B.
The benefits, or revenue, the project brings to the organization are 1.7 times
the cost of the initiative.
13
Question
Project A Project B A OR B
PV 95000 $ 75000 $
IRR 13 % 17 %
Payback Period 16 month 21 month
Cost Benefit Ratio 2.79 1.3
15
Question
Project A Project B A OR B
PV 95000 $ 75000 $
IRR 13 % 17 %
Payback Period 16 month 21 month
Cost Benefit Ratio 2.79 1.3
Project A Project B A OR B
PV 95000 $ 75000 $ A
IRR 13 % 17 % B
Payback Period 16 month 21 month A
Cost Benefit Ratio 2.79 1.3 A
16
Project Selection – Important Terms
Opportunity Cost:
Question
An organization has two projects to choose from. Project A has an NPV of
$45,000. Project B has an NPV of $85,000. What is the opportunity cost of
selecting project B
Answer Project B.
16
Project Selection – Important Terms
Sunk Costs:
Question
An organization has a project with an initial budget of $1,000,000. The
project is half complete, and it has spent $2,000,000. Should the
organization consider the fact that it is already $1,000,000 over budget
when determining whether to continue with the project?
17
Project Selection – Important Terms
18
Project Selection – Important Terms
Working Capital
Depreciation
19
Straight line depreciation
20
Question
Which of the following sequences represents straight line
depreciation?
A. $100,$100,$100
B. $100,$120,$140
C. $100,$120,$160
D. $160,$140,$120
21
Question
Which of the following sequences represents straight line
depreciation?
A. $100,$100,$100
B. $100,$120,$140
C. $100,$120,$160
D. $160,$140,$120
Answer A
Straight line depreciation uses the same amount each time period.
22
Accelerated depreciation
1. Sum of the Years Digits ( for the previous Laptop worth 1000$ )
It essentially front loads what you can deduct instead of spreading it
over the useful life.
First we take the asset's useful life and add together the digits for
each of those years.
We add 1 + 2 + 3 + 4 + 5 = 15.
Each number is then divided by the "sum of years" to determine the
percentage by which the asset should be depreciated each year.
The largest deduction is taken the first year and a lesser amount
each successive year.
23
Accelerated depreciation
2. Facilitation Techniques
Brainstorming, conflict resolution, problem solving, and meeting
25
Develop Project Charter: Outputs
Project Purpose/Justification
Measurable Project Objectives
High-level requirements
Assumptions and Constraints
High level project description
High level Risks
Summary budget & milestones
Initial Stakeholder List
Project Approval Requirements
Assigned Project Manager
Name and Authority of the sponsor
26
4.1- Develop Project Charter: OUTPUTS
Project Purpose/Justification
Measurable Project Objectives
High-level requirements
Assumptions and Constraints
High level project description
Project High level Risks
Charter Summary budget & milestones
Initial Stakeholder List
Project Approval Requirements
Assigned Project Manager
Name and Authority of the sponsor
27
CONTRACT
EEF (IF ANY)
BUSINESS
CASE
OPA
(SOW)
TOOLS &
TECHNIQUES
FACILITATION TECHNIQUES
OUTPUT EXTERNAL SMEs
EXPERTS JUDGMENTS
24
4.2- Develop Project Management Plan
30
31
PROJECT MANAGEMENT INF. SYSTEM ( EEF Page 84 )
32
CHANGE CONTROL SYSTEM ( PMIS / EEF )
34
Develop project management plan: T & T
2. Facilitation Techniques
Brainstorming, conflict resolution, problem solving, and meeting
35
4.2-Develop Project Management Plan OUTPUTS
36
4.2-Develop Project Management Plan OUTPUTS
37
QUALIT
STKHOLD
R
Y
REQUIR MGMT COST MGMT
PROJECT PROCESS
EMT PLAN PRFRMN PLAN
ENTERPRISE CHARTER IMPRVMN
MGMT CE T
ENVIRONMENT SCHEDU
SCOPE PLAN LE BASELIN COMM PLAN
AL MGMT E
FACTOR (EEF) PLAN SCHEDUL BASELIN MGMT
ORGANIZATIONAL E E PLAN
HUMAN PRCRMNT
PROCESS MGMT RESOURCE MGMT
PROJEC
ASSETS PLAN COST PLAN PLAN
T
(OPA) SCOPE
MGMT RISK
MGMT
SCOPE PLAN
STMNT PLAN
BASELIN
E
35
4.3- Direct & Manage Project Work
40
41
4.3- Direct & Manage Project Work
42
1. the performance data collected from various controlling
processes.
• Change Requests
44
Approved change requests
• The approved change requests can also modify the policies, project
management plan, procedures, costs, or budgets or revise the
schedules.
46
PROJECT
MGMT
PLAN APPROVED
EEF
CHANGE
REQUESTS
OPA
TOOLS &
TECHNIQUE
S
WORK PROJECT
CHANGE PROJECT
MNAGEMENT
DELIVERABLES PERFORMANCE DOCUMENTS
REQUESTS PLAN
DATA UPDATES
UPDATES
43
4.4- Monitor & Control Project Work
The process of tracking, reviewing, and regulating the progress to meet the
performance objectives defined in the project management plan.
49
50
51
4.4- Monitor & Control Project Work
52
4.4- Monitor & Control Project Work Inputs
54
Fault tree analysis (is not required for exam )
55
Regression Analysis ( will be explained later )
56
Monitor & Control Project Work T & T
1. Analytical Techniques
Regression
Causal Analysis
Root Cause Analysis
Forecasting methods (time series, scenario building, etc.)
Fault tree analysis (FTA)
Reserve Analysis
Trend Analysis
Earned Value Management
Variance Analysis
Forecasting methods
2. Expert Judgment
4. Meetings
57
4.4- Monitor & Control Project Work OUTPUTS
1 Change requests
2 Work Performance Reports
58
PROJECT VALIDATED
MGMT CHANGES
PLAN
EEF SCHEDULE
FORECASTS
WORK
OPA PERFORMA
COST NCE INFO
FORECAST
T&T
53
4.5- Perform Integrated Change Control
61
Configuration management
Configuration Control is focused on the specification of both of the
deliverables & the processes.
63
Change Control Log Template
64
65
66
67
PROJECT
MGMT
CHANGE
EEF PLAN
REQUESTS
OPA
WORK
PERFORMANCE MANUAL OR AUTOMATED MAY
REPORTS BE USED BASED ON NEEDS
62
4.6- Close Project or Phase
70
71
Administrative Closure
OPA UPDATES
Project files
Project or phase closure documents
Historical information
72
PROJECT
MGMT
PLAN
(OPA)
ACCEPTED • REGRESSION ANALYSIS
DELIVERABLES • GROUPING METHODS
• CAUSAL ANALYSIS
• ROOT CAUSE ANALYSIS
• FORECASTING SCENARIOS
• FAILURE MODE & EFFECT
ANALYSIS
• TREND ANALYSIS
T&T • EARNED VALUE MANAGEMENT
(EVM)
• VARIANCE ANALYSIS
74
Question
ANSWER : B
The lessons learned are project management deliverables, and
therefore must be completed for the project to be complete. 75
Question
A. Making changes.
B. Tracking and recording changes.
C. Informing the sponsor of changes.
D. Preventing unnecessary changes.
76
Question
A. Making changes.
B. Tracking and recording changes.
C. Informing the sponsor of changes.
D. Preventing unnecessary changes.
ANSWER : D
77
Question
3. The customer on a project tells the project manager they have run out
of money to pay for the project. What should the project manager do
FIRST?
A. Shift more of the work to later in the schedule to allow time for the
customer to get the funds.
B. Close Project or Phase.
C. Stop work.
D. Release part of the project team.
78
Question
3. The customer on a project tells the project manager they have run out
of money to pay for the project. What should the project manager do
FIRST?
A. Shift more of the work to later in the schedule to allow time for the
customer to get the funds.
B. Close Project or Phase.
C. Stop work.
D. Release part of the project team.
ANSWER : B
79
Question
A. Procedures.
B. Standards for reports.
C. Meetings.
D. Lessons learned.
80
Question
A. Procedures.
B. Standards for reports.
C. Meetings.
D. Lessons learned.
ANSWER : D
Lessons learned are reviews of the processes and procedures
after the fact, to improve them on future projects.
81
Question
A. Project manager.
B. Team.
C. Sponsor.
D. Stakeholders.
82
Question
A. Project manager.
B. Team.
C. Sponsor.
D. Stakeholders.
ANSWER : A
83
Question
A. Decelerated depreciation.
B. Straight line depreciation.
C. Accelerated depreciation.
D. Life cycle costing.
84
Question
A. Decelerated depreciation.
B. Straight line depreciation.
C. Accelerated depreciation.
D. Life cycle costing.
ANSWER : C
85
Question
7 . A project management plan should be realistic in order to be used to
manage the project. Which of the following is the BEST method to
achieve a realistic project management plan?
A. The sponsor creates the project management plan based on input
from the project manager.
B. The functional manager creates the project management plan
based on input from the project
manager.
C. The project manager creates the project management plan based
on input from senior
management.
D. The project manager creates the project management plan based
on input from the team.
86
Question
7 . A project management plan should be realistic in order to be used to
manage the project. Which of the following is the BEST method to
achieve a realistic project management plan?
A. The sponsor creates the project management plan based on input
from the project manager.
B. The functional manager creates the project management plan
based on input from the project
manager.
C. The project manager creates the project management plan based
on input from senior
management.
D. The project manager creates the project management plan based
on input from the team.
ANSWER : D
87
Question
8 . You are in the middle of executing a major modification to an
existing product when you learn that the resources promised at the
beginning of the project are not available. The BEST thing to do is to:
88
Question
8 . You are in the middle of executing a major modification to an
existing product when you learn that the resources promised at the
beginning of the project are not available. The BEST thing to do is to:
ANSWER : C
89
Question
9 . During a project executing, the project manager determines that a
change is needed to material purchased for the project. The project
manager calls a meeting of the team to plan how to make the change.
This is an example of:
A. Management by objectives.
B. Lack of a change management plan.
C. Good team relations.
D. Lack of a clear work breakdown structure.
90
Question
9 . During a project executing, the project manager determines that a
change is needed to material purchased for the project. The project
manager calls a meeting of the team to plan how to make the change.
This is an example of:
A. Management by objectives.
B. Lack of a change management plan.
C. Good team relations.
D. Lack of a clear work breakdown structure.
ANSWER : B
91
Question
10 . Project A has an internal rate of return (IRR) of 21 percent.
Project B has an IRR of 7 percent. Project C has an IRR of 31
percent. Project D has an IRR of 19 percent. Which of these would
be the BEST project?
A. Project A
B. Project B
C. Project C
D. Project D
92
Question
10 . Project A has an internal rate of return (IRR) of 21 percent.
Project B has an IRR of 7 percent. Project C has an IRR of 31
percent. Project D has an IRR of 19 percent. Which of these would
be the BEST project?
A. Project A
B. Project B
C. Project C
D. Project D
ANSWER : C
93