Activity Activity Orig Rem % Early Early 2018

MAY JUN JUL AUG SEP OCT NOV DEC


ID Description Dur Dur Start Finish 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 1
9009
Subtotal 81 81 66 29MAY18 30AUG18

Unit#1
Subtotal 64 64 66 31MAY18 13AUG18

12 Inlet duct
A01 Marking and cutting duct components 4 0 100 Marking and cutting duct components

A02 Fit-up and welding sub panels 7 0 100 Fit-up and welding sub panels

A03 Fit-up and welding liner pins 3 0 100 Fit-up and welding liner pins

A04 Assembly to duct shape 4 0 100 Assembly to duct shape

A05 Dimension check before welding 1 0 100 Dimension check before welding

A06 Welding 7 0 100 Welding

A07 Finishing and NDT 2 0 100 Finishing and NDT

A08 Sand blasting and primed 2 2 0 11JUN18 12JUN18 Sand blasting and primed

A09 Insulation 2 2 0 13JUN18 14JUN18 Insulation

A10 Install liner plates 2 2 0 15JUN18 16JUN18 Install liner plates

A11 Nuts torque and tack weld 2 2 0 18JUN18 19JUN18 Nuts torque and tack weld
13 diverter damper
Frame
B101 Cutting main parts 4 0 100 Cutting main parts

B102 Folding to shape 7 0 100 Folding to shape

B103 Cutting wall and bottom panel components 3 0 100 Cutting wall and bottom panel components

B104 Fit-up sub-part wall and bottom panels 4 0 100 Fit-up sub-part wall and bottom panels

B105 Welding sub-part wall and bottom panels 2 0 100 Welding sub-part wall and bottom panels

B106 Assembly panels (side, top and bottom) 5 0 100 Assembly panels (side, top and bottom)

B107 Welding panels 4 0 100 Welding panels

B108 Finishing and NDT 2 0 100 Finishing and NDT

B109 Fit-up and welding liner pins 4 0 100 Fit-up and welding liner pins

B110 Sandblasting and primed on main parts 3 0 100 Sandblasting and primed on main parts

B111 Diverter assembly 2 0 98 14JUN18 13JUN18 Diverter assembly

B112 Welding 3 0 98 16JUN18 15JUN18 Welding

B113 Finishing, NDT and primed on weld joints 2 0 80 20JUN18 19JUN18 Finishing, NDT and primed on weld joints

B114 Install landing bars 2 2 0 22JUN18 23JUN18 Install landing bars

B115 Insulation 2 2 0 25JUN18 26JUN18 Insulation

B116 Install liner plate 2 2 0 27JUN18 28JUN18 Install liner plate

B117 Nuts torque and tack weld 2 2 0 29JUN18 30JUN18 Nuts torque and tack weld

Start Date 02MAY18 T-800 bypass 32m Arroyo Seco ARGENT


Early Bar
Finish Date 31AUG18 VPI Date Revision CheckedApproved
Progress Bar
Data Date 09MAY18 06MAY180 S.Prasong
Run Date 16JUL18 21:57 Critical Activity

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early 2018
MAY JUN JUL AUG SEP OCT NOV DEC
ID Description Dur Dur Start Finish 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 1
Blade
B201 Laser cutting blade parts 2 0 100 Laser cutting blade parts
B202 Folding blade main parts 4 0 100 Folding blade main parts
B203 Assembly blade frame 7 7 0 29JUN18 06JUL18 Assembly blade frame
B204 Welding blade frame 4 4 0 07JUL18 11JUL18 Welding blade frame
B205 Fit-up and welding blade skins bed 2 2 0 12JUL18 13JUL18 Fit-up and welding blade skins bed
B206 PWHT ( over 6mm) 2 2 0 14JUL18 16JUL18 PWHT ( over 6mm)
B207 NDT 1 1 0 17JUL18 17JUL18 NDT
B208 Fit-up and welding liner pins 2 2 0 18JUL18 19JUL18 Fit-up and welding liner pins
B209 Install insulation 2 2 0 20JUL18 21JUL18 Install insulation
B210 Install liner plates 2 2 0 23JUL18 24JUL18 Install liner plates
B211 Nuts torque and tack weld 1 1 0 25JUL18 25JUL18 Nuts torque and tack weld
B212 Trial fit with blade main shaft, alignment 1 1 0 26JUL18 26JUL18 Trial fit with blade main shaft, alignment
Fully assemble
B301 Install blade to duct frame 1 1 0 27JUL18 27JUL18 Install blade to duct frame
B302 Install other mechanical parts 2 2 0 28JUL18 30JUL18 Install other mechanical parts
B303 Manual drive test and alignment 2 2 0 31JUL18 01AUG18 Manual drive test and alignment
B304 Install blade seal and bridging seals 2 2 0 02AUG18 03AUG18 Install blade seal and bridging seals
Seal air fan pipe spools
B401 Cutting pipe length 1 0 100 Cutting pipe length
B402 Fit-up weld jonts 3 0 100 Fit-up weld jonts
B403 Welding pipe joints 4 0 100 Welding pipe joints
B404 Sandblast and primed 2 2 0 31MAY18 01JUN18 Sandblast and primed
Miscellaneous machine parts
B501 Turning main blade shafts 7 0 100 Turning main blade shafts
B502 Machining shaft flanges 7 4 50 25JUN18 28JUN18 Machining shaft flanges
B503 Fit-up main shaft flanges 1 1 0 03JUL18 03JUL18 Fit-up main shaft flanges
B504 Welding 2 2 0 04JUL18 05JUL18 Welding
B505 PWHT 2 2 0 06JUL18 07JUL18 PWHT
B506 NDT 1 1 0 09JUL18 09JUL18 NDT
Anchor bolt and support legs
B601 Making anchor bolts 14 0 100 Making anchor bolts
B602 Fabricated embedded plates 4 0 100 Fabricated embedded plates
B603 Galvanizing 7 0 100 Galvanizing
14 Guillotine duct
C01 Marking and cutting duct components 2 0 100 Marking and cutting duct components
C02 Assembly sub-parts 4 0 100 Assembly sub-parts
C03 Welding sub-parts 5 0 100 Welding sub-parts

Start Date 02MAY18 T-800 bypass 32m Arroyo Seco ARGENT


Early Bar
Finish Date 31AUG18 VPI Date Revision CheckedApproved
Progress Bar
Data Date 09MAY18 06MAY180 S.Prasong
Run Date 16JUL18 21:57 Critical Activity

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early 2018
MAY JUN JUL AUG SEP OCT NOV DEC
ID Description Dur Dur Start Finish 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 1
C04 Assembly to duct shape 2 0 100 Assembly to duct shape
C05 Corner welding 2 0 100 Corner welding
C06 Finishing and NDT 1 0 100 Finishing and NDT
C07 Fit-up and welding liner pins 2 0 100 Fit-up and welding liner pins
C08 Sandblasting and primed 2 2 0 29JUN18 30JUN18 Sandblasting and primed
C09 Insulation 2 2 0 02JUL18 03JUL18 Insulation
C10 Install liner plates 1 1 0 04JUL18 04JUL18 Install liner plates
C11 Nuts torque and tack weld 1 1 0 05JUL18 05JUL18 Nuts torque and tack weld
15 HRSG expansion joint
D01 Cutting frame parts 2 0 95 06JUL18 05JUL18 Cutting frame parts
D02 Assembly frame 4 0 95 09JUL18 07JUL18 Assembly frame
D03 Welding frame 3 0 95 13JUL18 12JUL18 Welding frame
D04 Finishing and NDT 1 1 0 17JUL18 17JUL18 Finishing and NDT
D05 Sandblasting and primed 2 2 0 18JUL18 19JUL18 Sandblasting and primed
16 Bypass expansion joint
E01 Cutting frame parts 2 0 95 20JUL18 19JUL18 Cutting frame parts
E02 Assembly frame 4 0 95 23JUL18 21JUL18 Assembly frame
E03 Welding frame 3 0 95 27JUL18 26JUL18 Welding frame
E04 Finishing and NDT 1 1 0 31JUL18 31JUL18 Finishing and NDT
E05 Sandblasting and primed 2 2 0 01AUG18 02AUG18 Sandblasting and primed
23 Packing frame
M01 Fabricated packing frames 7 7 0 03AUG18 10AUG18 Fabricated packing frames
M02 Painting 2 2 0 11AUG18 13AUG18 Painting

Unit#2
Subtotal 66 66 65 29MAY18 13AUG18

12 Inlet duct
H01 Marking and cutting duct components 4 0 100 Marking and cutting duct components
H02 Fit-up and welding sub panels 7 0 100 Fit-up and welding sub panels
H03 Fit-up and welding liner pins 3 0 100 Fit-up and welding liner pins
H04 Assembly to duct shape 4 0 100 Assembly to duct shape
H05 Dimension check before welding 1 0 100 Dimension check before welding
H06 Welding 7 0 100 Welding
H07 Finishing and NDT 2 0 80 13JUN18 12JUN18 Finishing and NDT
H08 Sand blasting and primed 2 2 0 15JUN18 16JUN18 Sand blasting and primed
H09 Insulation 2 2 0 18JUN18 19JUN18 Insulation
H10 Install liner plates 1 1 0 20JUN18 20JUN18 Install liner plates
H11 Nuts torque and tack weld 2 2 0 21JUN18 22JUN18 Nuts torque and tack weld

Start Date 02MAY18 T-800 bypass 32m Arroyo Seco ARGENT


Early Bar
Finish Date 31AUG18 VPI Date Revision CheckedApproved
Progress Bar
Data Date 09MAY18 06MAY180 S.Prasong
Run Date 16JUL18 21:57 Critical Activity

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early 2018
MAY JUN JUL AUG SEP OCT NOV DEC
ID Description Dur Dur Start Finish 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 1
13 Diverter damper
Frame
I101 Cutting main parts 4 0 100 Cutting main parts
I102 Folding to shape 7 0 100 Folding to shape
I103 Cutting wall and bottom components 3 0 100 Cutting wall and bottom components
I104 Fit-up sub-wall wall and bottom panels 4 0 100 Fit-up sub-wall wall and bottom panels
I105 Welding sub-part wall and bottom panels 1 0 100 Welding sub-part wall and bottom panels
I106 Assembly panels ( side, top and bottom) 5 0 100 Assembly panels ( side, top and bottom)
I107 Welding panels 4 0 100 Welding panels
I108 Finishing and NDT 2 0 100 Finishing and NDT
I109 Fit-up and welding liner pins 4 0 100 Fit-up and welding liner pins
I110 Sand blasting and primed on main parts 3 0 100 Sand blasting and primed on main parts
I111 Diverter assembly 2 0 98 26JUN18 25JUN18 Diverter assembly
I112 Welding 3 0 98 28JUN18 27JUN18 Welding
I113 Finishing, NDT and primed on weld joints 2 1 50 02JUL18 02JUL18 Finishing, NDT and primed on weld joints
I114 Install landing bars 2 2 0 04JUL18 05JUL18 Install landing bars
I115 Insulation 2 2 0 06JUL18 07JUL18 Insulation
I116 Install liner plate 2 2 0 09JUL18 10JUL18 Install liner plate
I117 Nuts torque and tack weld 2 2 0 11JUL18 12JUL18 Nuts torque and tack weld
Blade
I201 Laser cutting blade parts 2 0 100 Laser cutting blade parts
I202 Folding blade main parts 4 0 100 Folding blade main parts
I203 Assembly blade frame 7 7 0 02JUL18 09JUL18 Assembly blade frame
I204 Welding blade frame 4 4 0 10JUL18 13JUL18 Welding blade frame
I205 Fit-up and welding blade skins bed 2 2 0 14JUL18 16JUL18 Fit-up and welding blade skins bed
I206 PWHT (over 6mm) 2 2 0 17JUL18 18JUL18 PWHT (over 6mm)
I207 NDT 1 1 0 19JUL18 19JUL18 NDT
I208 Fit-up and welding liner pins 2 2 0 20JUL18 21JUL18 Fit-up and welding liner pins
I209 Install insulation 2 2 0 23JUL18 24JUL18 Install insulation
I210 Install liner plates 2 2 0 25JUL18 26JUL18 Install liner plates
I211 Nuts torque and tack weld 1 1 0 27JUL18 27JUL18 Nuts torque and tack weld
I212 Trial fit with blade main shaft, aligment 1 1 0 28JUL18 28JUL18 Trial fit with blade main shaft, aligment
Fully assemble
I301 Install blade to duct frame 1 1 0 31JUL18 31JUL18 Install blade to duct frame
I302 Install other mechanical parts 2 2 0 01AUG18 02AUG18 Install other mechanical parts
I303 Manual drive test and alignment 2 2 0 03AUG18 04AUG18 Manual drive test and alignment
I304 Install blade seal and bridging seals 1 1 0 06AUG18 06AUG18 Install blade seal and bridging seals

Start Date 02MAY18 T-800 bypass 32m Arroyo Seco ARGENT


Early Bar
Finish Date 31AUG18 VPI Date Revision CheckedApproved
Progress Bar
Data Date 09MAY18 06MAY180 S.Prasong
Run Date 16JUL18 21:57 Critical Activity

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early 2018
MAY JUN JUL AUG SEP OCT NOV DEC
ID Description Dur Dur Start Finish 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 1
Seal air pipe spools
I401 Cutting pipe length 1 0 100 Cutting pipe length
I402 Fit-up weld joints 3 0 100 Fit-up weld joints
I403 Welding pipe joints 1 0 100 Welding pipe joints
I404 Sand blasting and primed 2 2 0 29MAY18 30MAY18 Sand blasting and primed
Miscellaneous machine parts
I501 Turning main blade shafts 7 0 100 Turning main blade shafts
I502 Machining shaft flanges 7 4 50 25JUN18 28JUN18 Machining shaft flanges
I503 Fit-up main shaft flanges 1 1 0 03JUL18 03JUL18 Fit-up main shaft flanges
I504 Welding 2 2 0 04JUL18 05JUL18 Welding
I505 PWHT 2 2 0 06JUL18 07JUL18 PWHT
I506 NDT 1 1 0 09JUL18 09JUL18 NDT
Anchor bolts and support legs
I601 Making anchor bolts 14 0 100 Making anchor bolts
I602 Fabricated embedded plates 4 0 100 Fabricated embedded plates
I603 Galvanizing 7 0 100 Galvanizing
14 Guillotine duct
J01 Marking adn cutting duct components 2 0 100 Marking adn cutting duct components
J02 Assembly sub-parts 1 0 100 Assembly sub-parts
J03 Welding sub-parts 5 0 100 Welding sub-parts
J04 Assembly to duct shape 2 0 100 Assembly to duct shape
J05 Corner welding 2 0 100 Corner welding
J06 Finishing and NDT 1 1 0 20JUL18 20JUL18 Finishing and NDT
J07 Fit-up and welding liner pins 2 1 30 21JUL18 21JUL18 Fit-up and welding liner pins
J08 Sandblasting and primed 2 2 0 24JUL18 25JUL18 Sandblasting and primed
J09 Insulation 2 2 0 26JUL18 27JUL18 Insulation
J10 Install liner plates 1 1 0 28JUL18 28JUL18 Install liner plates
J11 Nuts torque and tack weld 1 1 0 30JUL18 30JUL18 Nuts torque and tack weld
15 HRSG expansion joint
K01 Cutting frame parts 2 0 100 Cutting frame parts
K02 Assembly frame 4 0 95 23JUL18 21JUL18 Assembly frame
K03 Welding frame 3 0 95 27JUL18 26JUL18 Welding frame
K04 Finishing and NDT 1 1 0 31JUL18 31JUL18 Finishing and NDT
K05 Sandblasting and primed 2 2 0 01AUG18 02AUG18 Sandblasting and primed
16 Bypass expansion joint
L01 Cutting frame parts 2 0 100 Cutting frame parts
L02 Assembly Frame 2 0 95 06AUG18 04AUG18 Assembly Frame
L03 Welding frame 3 0 95 08AUG18 07AUG18 Welding frame
Start Date 02MAY18 T-800 bypass 32m Arroyo Seco ARGENT
Early Bar
Finish Date 31AUG18 VPI Date Revision CheckedApproved
Progress Bar
Data Date 09MAY18 06MAY180 S.Prasong
Run Date 16JUL18 21:57 Critical Activity

© Primavera Systems, Inc.


Activity Activity Orig Rem % Early Early 2018
MAY JUN JUL AUG SEP OCT NOV DEC
ID Description Dur Dur Start Finish 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 1
L04 Finishing and NDT 1 1 0 11AUG18 11AUG18 Finishing and NDT
L05 Sandblasting and primed 1 1 0 13AUG18 13AUG18 Sandblasting and primed
23 Packing frame
N01 Fabricated packing frames 7 7 0 03AUG18 10AUG18 Fabricated packing frames
N02 Painting 1 1 0 11AUG18 11AUG18 Painting

FAT
Subtotal 7 7 0 04AUG18 11AUG18

Unit#1
Trial assembly
F01 Trial assembly with other ducts 2 2 0 04AUG18 06AUG18 Trial assembly with other ducts
F02 Final dimension check 1 1 0 07AUG18 07AUG18 Final dimension check
F03 Install hydraulic system 1 1 0 08AUG18 08AUG18 Install hydraulic system
F04 Install seal air fan and pipe spools 1 1 0 09AUG18 09AUG18 Install seal air fan and pipe spools
F05 Ready for FAT 0 0 0 09AUG18 Ready for FAT
Unit#2
Trial assembly
F10 Trial assembly with other ducts 2 2 0 07AUG18 08AUG18 Trial assembly with other ducts
F11 Final dimension check 1 1 0 09AUG18 09AUG18 Final dimension check
F12 Install hydraulic system 1 1 0 10AUG18 10AUG18 Install hydraulic system
F13 Install seal air fan and pipe spools 1 1 0 11AUG18 11AUG18 Install seal air fan and pipe spools
F14 Ready for FAT 0 0 0 11AUG18 Ready for FAT

Packing and deliver


Subtotal 18 18 0 10AUG18 30AUG18

Documents
X01 Prepare packing list 2 2 0 10AUG18 11AUG18 Prepare packing list
X02 Get approved export documents 7 7 0 13AUG18 20AUG18 Get approved export documents
Wooden crate
X10 Prepare export wooden crate 7 7 0 13AUG18 20AUG18 Prepare export wooden crate
X11 Packing and reporting 7 7 0 21AUG18 28AUG18 Packing and reporting
Shipping mark
X20 Final shipping mark check 1 1 0 29AUG18 29AUG18 Final shipping mark check
X21 Issued IRN 1 1 0 30AUG18 30AUG18 Issued IRN
X22 Ready to loadout 0 0 0 30AUG18 Ready to loadout

Start Date 02MAY18 T-800 bypass 32m Arroyo Seco ARGENT


Early Bar
Finish Date 31AUG18 VPI Date Revision CheckedApproved
Progress Bar
Data Date 09MAY18 06MAY180 S.Prasong
Run Date 16JUL18 21:57 Critical Activity