Академический Документы
Профессиональный Документы
Культура Документы
07DKA16S1017
Project can be described as a unique set of coordinated activities, with definite starting
and finishing points, undertaken by an individual or organisation to meet specific
objectives with defined schedule cost and performance parameters. The goal of a
construction project is to build something. What differentiates the construction industry
from other industries is that its projects are large, built on-site, and generally unique.
Time, money, labour, equipment, and, materials are all examples of the kinds of
resources that are consumed by the project.
b) The uniqueness of a project comes together with its objectives. For example, a
company has an objective of constructing the tallest twin tower building in the
world. This non- routine activity to carry out the objective requires some unique
elements in the project.
c) In order to complete the objectives, projects should have a time limit of when the
projects should start and when the projects should be completed. Time duration is
crucial for engineers to plan the work schedule for successful completion of the
project.
1
DCC5183 PROJECT MANAGEMENT FAZLEERAHIM K SUHAILI
07DKA16S1017
d) In addition, engineers or project managers also need to consider the resources, for
example humans, materials and financial that they need for completing the schedule.
e) Unlike much organisational work that is segmented according to functional
speciality, projects typically require the combined efforts of a variety of
specialists. Engineers, marketing professionals, quality control specialists, and
surveyors, who work closely together under the guidance of a project manager to
complete the project.
The time constraint refers to the amount of time available to complete a project. The cost
constraint refers to the budgeted amount available for the project. The scope constraint
refers to what must be done to produce the project's end result. These three constraints
are often competing constraints: increased scope typically means increased time and
2
DCC5183 PROJECT MANAGEMENT FAZLEERAHIM K SUHAILI
07DKA16S1017
increased cost, a tight time constraint could mean increased costs and reduced scope, and
a tight budget could mean increased time and reduced scope. The discipline of project
management is about providing the tools and techniques that enable the project team (not
just the project manager) to organize their work to meet these constraints.
Another approach to project management is to consider the three constraints as finance,
time and human resources. If you need to finish a job in a shorter time, you can throw
more people at the problem, which in turn will raise the cost of the project, unless by
doing this task quicker we will reduce costs elsewhere in the project by an equal amount.
6. Explain the role and relationship of the parties involved during the construction phase of
the project as listed below:-
a) Owner
The owner is the individual or organization for whom a project is to be built under
a contract. The owner owns and finances the project. Depending on the owners’
capabilities, they may handle all or portions of planning, project management,
design, engineering, procurement, and construction.
The owner engages architects, engineering firms, and contractors as necessary to
accomplish the desired work.
Public owners are public bodies of some kind ranging from agencies from the
country level to the municipal level. Most public projects or facilities are built for
public use and not sold to others.
Private owners may be individuals, partnerships, corporations. Most private owners
have facilities or projects built for their own use or to be sold, operated, leased, or
rented to others. In order to achieve success on a project, owners need to define
accurately the projects objectives. They need to establish a reasonable and balanced
scope, budget, and schedule. They need to select qualified designers, consultants,
and contractors.
b) Contractor
A contractor for Civil Engineering works may be an individual person or
group of persons or a company who under takes the construction of the work.
He offers to undertake the construction of the work for given amount of money.
He must have the skill and competence to execute the work properly as per
design and specifications.
The contractor is responsible for procuring of materials not supplied by the
owner, organizing, planning and executing the work as per drawings and
specifications laid down in the contract and as per construction schedule agreed
upon.
c) Consultant
A consultant is specialist in his field.
A consultant may be appointed for highly specialized project to help the owners
3
DCC5183 PROJECT MANAGEMENT FAZLEERAHIM K SUHAILI
07DKA16S1017
d) Project Manager
The project manager is the individual charged with the overall coordination of the
entire construction program for the owner.
His or her duties will vary depending upon the client’s experience and requirements
for the project.
Project manager usually a suitably qualified professional, must be competent
enough to plan, organize, coordinate, monitor and control the project.
The role of a project manager is to lead the project team to ensure a quality project
within time, budget, and scope constraints.
a) Figurehead role – the project manager, is the legal and social head of the project, he
is the single focal point for making decisions, presiding at ceremonial functions and
performing symbolic duties.
b) Leadership role – as a leader, the project manager directs the inter-functional efforts
through a complex web of relationships created in the project organisation by building
a performance-motivated team of skilled and experienced people, who collectively
face challenges posed by environment.
c) Liaisoning role – the project manager maintains contacts outside the organisation,
deals with those activities which may involve correspondence and contact with the
concerned government and non-government officials, contract vendors, professionals
and other senior persons in the industry.
d) Monitoring role – the project manager’s focus is on the baseline plan adopted for
performing and implementing tasks within the time, cost and quality specifications.
He is also responsible for planning and monitoring the entire system with a view to
motivate the project team to provide assured results.
4
DCC5183 PROJECT MANAGEMENT FAZLEERAHIM K SUHAILI
07DKA16S1017
5
DCC5183 PROJECT MANAGEMENT FAZLEERAHIM K SUHAILI
07DKA16S1017
6
DCC5183 PROJECT MANAGEMENT FAZLEERAHIM K SUHAILI
07DKA16S1017
10. List the advantages & disadvantages the concept of construction project below: -
a) Traditional Contract
Advantages
Accountability due to a competitive selection.
Competitive equity as all tendering contractors bid on the same basis.
It allows the Employer to choose Consultants who will be specialists in their field and
among the best available.
Variations/changes to the contract are relatively easy to arrange and manage.
It allows the Employer and his Consultant to pre-qualify and select Contractors and
choose the most economic conforming tender.
A tried and test method of procurement which the market is very familiar with.
Disadvantages
Can be timely process to produce the full contract documentation. Tenders documents
from an incomplete design can be produced but can lead to less cost and time certainty,
and may lead to disputes.
Overall project duration may be longer than other procurement methods as the strategy
is consequential and construction cannot be commenced prior to the completion of the
design.
7
DCC5183 PROJECT MANAGEMENT FAZLEERAHIM K SUHAILI
07DKA16S1017
No input into the design or planning of the project by the contractor as they are not
appointed during the design stage.
Advantages
Client has to deal with one firm and reduces the need to commit resources and time to
contracting designers and contractors separately.
Price certainty is obtained before construction commences as client’s requirements are
specified and changes are not introduced.
Use of a guaranteed maximum price with a savings option split can stimulate innovation
and reduce time and cost.
Overlap of design and construction activities can reduce project time.
Improved constructability due to contractor’s input into the design.
Disadvantages
With design-build, the owner must lock in its requirements much earlier.
Client changes to project scope can be expensive.
Difficulty in comparing bids since each design will be different, project programme will
vary between bidders, and prices for the project will be different for each design.
Client required to commit a concept design at an early stages and often before the
detailed designs are complete.
Design liability is limited to the standard contracts that are available.
c) Turnkey Contract
Advantages
Reduce the of the project implementation. Time savings can be made because the fully
involvement of contractors in the construction process from beginning to the end.
Responsibilities one party
Fixed project cost
Easier and effective communication
Innovation in design and construction because of the early involvement of the
contractor.
Can reduce direct owner involvement on matters related to technical problems, cost,
time and other.
Disadvantages
High cost of project.
Scope of variation is limited.
Wastage will occur during the construction stage.
Affect the participation of local consultants because the contractor will typically hire a
own consultancy.
New contractor and Bumiputera contractors cannot compete to participate due to it is
used for project management and high cost.
8
DCC5183 PROJECT MANAGEMENT FAZLEERAHIM K SUHAILI
07DKA16S1017
11. The implementation of concept project management may apply to various types of
construction project and contract. Explain the concept of construction project below:
a) Traditional Contract
A programme allows sufficient time.
Consultant design is warranted.
A client wishes to appoint designers and contractors separately.
Price certainty is wanted before the start of construction.
Product quality is required.
A balance of risk is to be placed between the client and contractor.
c) Turnkey Contract
Urgent need for a specific project
Owner lack the expert group