Академический Документы
Профессиональный Документы
Культура Документы
It is an organized activity of converting raw materials into useful products. But before
starting the actual production, production planning is done to anticipate possible
difficulties and to decide in advance as to how the production process should be
carried out in a best and economical way to satisfy customers. Since only planning of
production is not sufficient, hence management takes all possible steps to see that
plans chalked out by planning department are properly adhered to and the standard
set are attained. In order to achieve it, control over production is exercised. The
ultimate aim of production planning and control (PPC) is to produce the products of
right quality in right quantity at the right time by using the best and least expensive
methods.
16-2
16-3
Master Production Planning
(MPS)
A timetable that specifies what is to be
made (usually finished goods) and when.
Introduction
Material Requirements Planning (MRP) is a computer-based production planning and
inventory control system. MRP is concerned with both production scheduling and
inventory control. It is a material control system that attempts to keep adequate inventory
levels to assure that required materials are available when needed.
In dependent demand situation, if the demand for an item is known, the demand for other
related items can be estimated. For example, if the demand of an automobile is known,
the demand of its sub-assemblies and sub components can easily be estimated. For
dependent demand situations, normal reactive inventory control systems (i.e. EOQ etc.)
are not suitable because they result in high inventory costs and unreliable delivery
schedules. More recently, managers have realized that inventory planning systems (such
as materials requirements planning) are better suited for dependent demand items. MRP
is a simple system of calculating arithmetically the requirements of the input materials at
different points of time based on actual production plan. OR
RIGHT MATERIAL ON RIGHT PLACE AT RIGHT TIME
MRP can also be defined as a planning and scheduling system to meet time-phased
materials requirements for production operations. MRP always tries to meet the delivery
schedule of end products as specified in the master production schedule.
16-6
Material Requirements Planning (MRP)
MRP Objectives
“To determine when material for production is required.”
16-7
Material Requirements Planning (MRP)
MRP System
A simple sketch of an MRP system is shown in figure below. It can be seen from
the figure that an MRP system has three major input components:
16-8
Material Requirements Planning (MRP)
Inventory Status File: Inventory status file keeps an up-to-date record of each
item in the inventory. Information such as, item identification number, quantity on
hand, safety stock level, quantity already allocated and the procurement lead
time of each item is recorded in this file.
16-9
Material Requirements Planning (MRP)
After getting input from these sources, MRP logic processes the available
information and gives information about the following:
2. Planned Order Release: This is the order quantity of an item that is planned
to be ordered in the planned time period for this order that will ensure that
the item is received when needed. Planned order release is determined by
offsetting the planned order receipt by procurement lead time of that item.
16-10
Capacity Balancing
16-11
What is Scheduling?
16-12
Objectives in Scheduling
16-13
Loading
16-14
Assignment Method
16-16
Sequencing Rules
16-17
Critical Ratio Rule
16-18
Sequencing Jobs Through One
Process
16-19
Simple Sequencing Rules
PROCESSING DUE
JOB TIME DATE
A 5 10
B 10 15
C 2 5
D 8 12
E 6 8
16-20
Simple Sequencing
Rules: FCFS
16-21
Simple Sequencing
Rules: DDATE
16-22
Simple Sequencing A(10-0) – 5 = 5
B(15-0) - 10 = 5
Rules: SLACK C(5-0) – 2 = 3
D(12-0) – 8 = 4
E(8-0) – 6 = 2
16-23
A(10)/5 = 2.00
Simple Sequencing B(15)/10 = 1.50
Rules: CR C (5)/2 = 2.50
D(12)/8 = 1.50
E (8)/6 = 1.33
CR START PROCESSING COMPLETION DUE
SEQUENCE TIME TIME TIME DATE TARDINESS
E 0 6 6 8 0
D 6 8 14 12 2
B 14 10 24 15 9
A 24 5 29 10 19
C 29 2 31 5 26
16-24
Simple Sequencing
Rules: SPT
16-25
Simple Sequencing
Rules: Summary
16-26
Sequencing Jobs Through
Two Serial Process
Johnson’s Rule
1. List time required to process each job at each machine.
Set up a one-dimensional matrix to represent desired
sequence with # of slots equal to # of jobs.
2. Select smallest processing time at either machine. If
that time is on machine 1, put the job as near to
beginning of sequence as possible.
3. If smallest time occurs on machine 2, put the job as
near to the end of the sequence as possible.
4. Remove job from list.
5. Repeat steps 2-4 until all slots in matrix are filled and all
jobs are sequenced.
16-27
Johnson’s Rule
E A D B C
16-28
Johnson’s Rule (cont.)
E A D B C
E A D B C Process 1
(sanding)
5 11 20 31 38
Idle time
E A D B C Process 2
(painting)
5 15 23 30 37 41
Completion time = 41
Idle time = 5+1+1+3=10
16-29
Guidelines for Selecting a
Sequencing Rule
16-30