Вы находитесь на странице: 1из 5

COMPRESSORtech2

Thermal Design Considerations For Centrifugal Compressor Piping


Systems
compressortech2.com/thermal-design-considerations-centrifugal-compressor-piping-systems/2

​October​ ​18​, ​2017

Compressor nozzle loads (API 617)

The piping, restraints and soil stiffness have a direct relationship to the stress in the pipe as well
as the loads on the compressor nozzle. If the nearby restraints are rigid, the piping grows
thermally towards the compressor and increases the nozzle loads. A very flexible system would
result in low compressor nozzle loads, but would be very susceptible to vibration. This balance
between thermal flexibility and mechanical stiffness is a critical factor that should be accounted
for in a station piping design.

Table 1. Compressor nozzle loads for different configurations.

API 617 is commonly used to determine acceptability of the compressor nozzle loads on
centrifugal compressors. The API 617 allowable values are equal to 1.85 * NEMA SM23. Nine
different allowable values are calculated based on the “equivalent” nozzle diameter. An
allowable multiplier is typically applied (often 3.0 * API 617). The calculated moments are
resolved about a common point, which can and does affect the acceptability of the predicted
1/5
loads. The summation of forces and moments are compared to the code allowable values along
with the three combined loads shown below.

Individual Nozzle Loads

• Suction Flange 3 * Fr + Mr

• Discharge Flange 3 * Fr + Mr

Nozzle Load Summations

• SFx, SFy, SFz, SMx, SMy, SMz (six different allowable values)

• 2 * Fc + Mc

Figure 3 presents a sample calculation of the API 617 compressor nozzle allowable values.

2/5
Figure 3. API 617 compressor nozzle calculation.

Oftentimes, resolving the loads about a single point will result in the highest value. This can be
due to high thermal loads that should be lowered to ensure safe operation. For larger diameter
piping, however, resolving the load about the discharge nozzle often results in a large moment
about the X-axis as shown in Figure 4. The weight of the suction flange (FY) is multiplied by the
length between the compressor nozzles (DZ) and creates a high moment about the discharge
nozzle. This is not due to any thermal growth of the piping or unit; it is due to the weight of the
flange.

The predicted loads and code check should be discussed with the original equipment
manufacturer (OEM) to determine if the loads are acceptable to the vendor. A good
3/5
understanding of the loads and their sources is necessary to understand whether the loads are
due to a thermal growth issue or if it is a result of the resolved loads calculation. Good design
practice can often lower nozzle loads to acceptable levels during the design phase and is
preferred to validating high loads and having a review by the OEM.

Figure 4. Compressor nozzle loads.

As discussed later in this paper, improper modeling techniques and temperature range
selection can lead to underpredicting equipment loads. At a new compressor station, large
diameter piping (36 in. [915 mm] suction, 30 in. [762 mm] discharge) and the compressor were
analyzed during the design phase of the project.

The goal of this analysis was to evaluate various pipe routing and ensure that equipment loads
were within acceptable limits. In this case, using 45° elbows on the suction piping was preferred
(in order to keep the centerline of the compressor as low to the ground as possible). A thermal
stress analysis was performed during the design phase and this pipe routing (and the predicted
equipment loads) was deemed acceptable.

4/5
During the commissioning of the compressor package, several issues were noted with the
piping. A new piping thermal model was independently built and followed the modeling
techniques cited herein. These results showed equipment loads in excess of allowable API
values and much closer to those limits established by the OEM. Using this updated model,
design changes were identified that would lower the stresses in the piping as well as lower the
predicted equipment loads. These costly changes were then implemented with much better
results.

Previous articleFERC Approves Two Pipelines


Next articleMechanical Drive Order Survey 2017

5/5

Вам также может понравиться