QUALITY CONTROL & TEST PLAN

FABRICATION & ERECTION QUALITY CONTROL &


TEST PLAN
MQP Number :Indospace/ EXTINCT/QC-001
REV : 0
DATE :
Page No: 1
Class of
SR NO Activity & Operation Characteristics/Instruments Type of Check Quantum of Check Reference Doc.
check

1 Hydrant System

A) PRE-ERECTION &
ERECTION Check of damage Major Visual 100%
Installation/Manu
Rotating Equipment Leveling, Grouting of base frame Major Visual 100% al/drg.
Visual feeler & Installation/Manu
Pumps Alignment of Pump Critical Allign proper 100% al/drg.

Check of Lubrication, free Installation/Manu


rotation Major Visual 100% al/drg.

1b
Motors / Diesel Engine Check for Damage Major Visual 100%

Check for foundation as per Installation/Manu


Drawing Major Visual 100% al/drg.
Visual,spirit
Leveling,Alingment of level feeler & Installation/Manu
motor/Diesel Engine Critical dial gauge 100% al/drg.
Check for earthing,cable Installation/Manu
termination Major Visual 100% al/drg.

Check for lubrication, free


rotation Major Visual 100%

2 Apprd. Drg. /
MS Pipes Fit-up for Pipe joint Major Visual 100% WPS

WPS availabilty/PQR,Welder ASME Sec IX

Qualification
Pipe Alignment,fixing of support
elev. Slope layout Major Visual/Meas do

Inspection of weld joints Major Visual 100% do

Flanges, Fittings

As per drg. / 1.5


times of design
Pressure testing of piping system Major Hydero Test Each lots pressure

Wrapping & coating for U/G


Piping Major Holiday Test 100%
Prepared by
Approved by

Extinct fire engineers Indospace


AN

WORK : FIRE PROTECTION SYSTEM


CLIENT : INDOSPACE
CONSULTANT : ACE
CONTRACTOR : EXTINCT FIRE ENGINEERS PVT. LTD

Format of Record Agency Remarks

Performance witness/Review
( Extinct) ( Indospace )
To be stored in covered
Log Book / register 2 _ area

Record 2 _

Record 2 1

Record 2 _

To be stored in covered
Log Book 2 _ area

Record 2 _

Record 2 1
Record 2 _

Record 2 _

Hyderotest shall be carried


Record 2 _ out in lots

Record to be furnished to
customer
QW 482,483 2 _

484

Record 2 _

Butt welds only, Acceptance


norms as per ASME Sec IX
(10% of each pipe size
Record 2 1 joints)

For above ground


pipes,painting shall be
done as per approved
Record 2 1 painting procedure

For Under ground pipes as


per IS:10221
Record 2 1
Note : Extinct - 1

Indospace- 2