Академический Документы
Профессиональный Документы
Культура Документы
SP-1275
(OLD ERD 17-04)
This document is the property of Petroleum Development Oman, LLC. Neither the whole nor any
part of this document may be disclosed to others or reproduced, stored in a retrieval system, or
transmitted in any form by any means (electronic, mechanical, reprographic recording or otherwise)
without prior written consent of the owner.
Specification for Civil & Building Works – Design Criteria Manual Version 1.0
Signed:............................................................
Ali Nasser Al Jahadhamy, TTO/2 (UEC)
CFDH, Civil Engineering
The following is a brief summary of the recent revisions to this document. Details of all revisions prior
to these are held on file by the issuing department.
Version 1.0 June ‘04 Ali Nasser Al Jahadhamy, Converted to Specification as per PDO
TTO/2 (UEC) policy and minor changes to the text
Contents
Contents ..................................................................................................................................... ii
Appendices .............................................................................................................................104
Appendix A: Glossary of Definitions & Abbreviations.....................................................105
A.1 General Definitions & Terminology .................................................................105
A.2 Abbreviations ....................................................................................................106
A.3 Abbreviations for Building Types.....................................................................110
A.4 Abbreviations for Room Types.........................................................................116
1.0 Introduction
1.1 Purpose
The purpose of this document is to specify the minimum requirements and recommendations
for “Structural Design and Detail Engineering of Civil and Building Works” and is
intended for use by PDO and its nominated Consultants and Contractors for the
development and operation of Company facilities.
- Set the Company standards for facilities along the facilities life cycle.
This Specification supersedes the ERD-17-04 ‘Civil & Building Design Criteria Manual’.
Other than the conversion or formatting, the following are the main changes to this
document.
- Accommodation facility requirements for PDO and Contractors camps in section 2.7
and its subsections are revised
- Staircases & Platforms requirements in section 2.9 revised and added more.
- Mandatory Warning Sign requirement for the Graded/Tarmac Transition are added
as new in section 2.14.3
- Graded Road section details (Fig 4) and its material specifications are revised.
For all HSE requirements, the User should refer the CP-122 ‘Code of Practice for Health,
Safety and Environmental Protection’ and other documents referenced therein.
Custodian of this document is the Corporate Functional Discipline Head (CFDH) of Civil
Engineering. Any User of this document, who encounters an inaccuracy or ambiguity, is
requested to notify the CFDH using the SP user-comment form provided in Appendix-M.
Reviews and modifications or changes to the specification will normally be made by the
CFDH every four years or earlier when justified.
This Specification shall be read in conjunction with the latest revisions of the following
Standards, Specifications and Codes.
PGSC List : Product Group Service Codes List for Civil Products
Any deviations from this part of Specifications shall be subject to Company approval and
shall be advised in writing to the Custodian.
In all cases the Company shall determine the adequacy of the design carried out and Works
executed by the Contractor in accordance with this Specifications.
2.0 Scope
2.1 General
This Specification is an Engineering Guidelines for the Company Civil & Building Facilities
and includes applicable design and detailing data and requirements.
In general the SI Units of Measurements shall apply. In addition, the following are used in
this document.
Frequency : hertz Hz
Refrigeration : : kilowatt kW
Relative Humidity : RH
The Company should provide the information required to carry out the project to the
Consultant in the following form:
- Scope of works
- Project specification
- Location drawing(s)
The information should include, but not be limited to, the following:
- Any information on existing site surveys, site investigations etc. that may be
available.
Building appearance shall conform to established PDO requirements, local customs, and if
applicable, existing buildings.
- Preliminary
- Tender
- Contract
- As built
Building should be designed to allow for future horizontal extension unless specified
otherwise by the Company.
The purpose of soil investigation is to provide information on the soil conditions for design
and construction of civil and structural engineering works. The soil investigation work shall
be carried out in accordance with SP-1278: ‘Specification for Site Selection & Soil
Investigation Works – ‘Engineering Guidelines’.
Depending on the requirements of the project, the investigation may be used to obtain
information on, but not limited to, the following:
- Bearing capacity
The Consultant shall however carefully investigate the necessity for a soil investigation, and
if required, the type of information needed. The Consultant may consider the following:
A study of available information of the area such as geological maps, water and oil well
logs, hydrological data and site investigation reports of adjacent sites.
A site visit shall be carried out to obtain the information on the type and behaviour of
adjacent structures (cracks, sags due to differential settlements, rock outcrops which give an
indication of the presence of the depth of bed rock etc).
For extensions, single storey buildings on raft type foundations, pipelines etc., the
Consultant may consider a site investigation unnecessary based on the information obtained
from above, nevertheless it is the Consultants responsibility to ensure foundations are
suitable for the building/structure and ground conditions.
However, for multi-storey structures, installation of large sized tanks (where settlement
predictions are important) installation of vibrating or rotary equipment (with considerable
dynamic loading) etc, dedicated soils investigations shall be undertaken.
Soil Investigation Reports shall comply with SP-1278 Specification for Site Selection & Soil
Investigation Works – ‘Engineering Guidelines’ and BS-5930: Code of Practice for Site
Investigations.
The report shall provide information on the items noted in section 2.3.2.1 as necessary. The
report shall be factual with engineering recommendations.
The soils report shall clearly state how the recommendations have been arrived at and shall
include copies of the Terzaghi curves used etc, to enable the Consultant to conclude the size
of safety factors used to obtain the allowable bearing pressures, etc.
All reports shall be loaded in electronic form to PDO live link system for reference.
The Consultant shall undertake preliminary designs. During this process, the Consultant
shall advise the Company on alterations considered necessary, if any, regarding orientation,
location etc, in view of local climatic conditions, topography or any other aspects. Such
alternations shall only be implemented if agreed by the Company.
In order to achieve preliminary designs, the Consultant shall be fully acquainted with the
site. To obtain the necessary knowledge the Consultant shall visit the site. The number of
visits, and personnel visiting the site, will be dependent on the project, however the
Consultant shall ensure adequate knowledge is gained.
- Site layout plan(s), showing the location of buildings and plant, and
indicating true North and prevailing wind direction(s).
It shall be noted that locally manufactured materials shall be used wherever possible as long
as such materials are technically acceptable. In support of the Company’s drive to promote
local industry.
The Consultant is required, to some extent, to consider relaxing design specifications (and
hence investigate the financial consequences of the resulting operating and capital costs
associated with such a relaxation). All other civil/building materials shall be chosen out
from the Company PGSC (Product Group Service Codes) list for Civil Products. All of
which (with minor exceptions) have local agents.
Preliminary designs shall include details of alternative construction and cost comparisons in
order to achieve both technically and economically viable solutions.
The Consultant shall obtain, as a minimum, the following information in order to undertake
the final design and details.
- Detailed site surveys including details of all existing services (if applicable)
and likely future building service runs for water, power, sewage disposal,
telephones, etc.
The Consultant shall produce thorough and complete sets of detailed design calculations and
shall be approved by the Company. All calculations shall indicate, clearly and concisely the
output and conclusions of each particular solution.
Calculations shall be preceded with a standard information sheet, containing all of the above
information, plus additional details as shown in the project related drawings and documents.
The following Codes of Practice and British Standards shall be used as a minimum for the
final design, unless alternative codes are agreed and approved by the Company.
- Full working drawings showing the structural and civil designs of the entire
project giving full details of all the elements in the building(s) (refer section
2.3.6).
- Plans of every floor and roof, cross sections through individual floors and
essential elevations of the building. These drawings shall show the position,
form, dimensions and materials of all the various parts of the buildings and
structures.
In the design for structural elements, the load factors, material factors, permissible stresses,
etc. shall be in accordance with the requirements of the design code being applied. Due
consideration shall be given to exceptional load conditions and accident cases for which the
design may be undertaken with reduced load and material safety factors as allowed by the
design code. Refer to Appendix B for Weights of General Building Material and Appendix
C for Live Loads.
2.3.5.1 Steelwork
Deflections due to dead loads, where limits are given for live loads in Table 1, shall not
impair the strength and efficiency of the structure, lead to damage of the finishing or to be
unsightly. Measures to nullify the effects of deflection due to dead loads by adjusting the
casing on cased members or by pre-cambering should be considered.
Horizontal deflections at crane rail level due to spread of the supporting structure shall be
considered and shall not exceed the value in Table 1, the manufacturers recommendations or
affect the performance of the crane. When checking for deflections the most adverse
realistic combination and arrangement of loads should be assumed.
Connections should, whenever possible, avoid the use of high strength friction grip bolts.
However, if used for special technical reasons, the mode of checking tension shall be by the
use of load indicating washers.
Bolt grades on a particular job should be standardised where possible to prevent incorrect
usage of bolt types on site.
2.3.5.2 Concrete
Concrete elements shall contain suitable materials to meet the requirements of both strength
and durability. Consideration to both the levels of chloride and sulphates shall always be
given when specifying cement type.
One of the following three typical land based exposure conditions needs to be stipulated as
the basis of the design criteria of concrete foundations (chemical analysis to be assessed
from the soil investigation report):
When the chlorides or sulphates or both (chlorides & Sulphates) in the soil or ground water,
are not in a significant level or totally free, the recommendation shall be ordinary port land
cement (OPC) to BS EN 197 or ASTM Type I. In addition, the concrete surface shall be
treated with two coats of ‘FOSROC Nitoproof 100’ bituminous paint or any other
approved equivalent.
The membrane system of tanking shall consist of primer, membrane, corner fillet,
reinforcing strip, protection board etc., Typical tanking details for concrete foundations
(above and below grade) are shown in Figure: 1. The tanking system product shall be
‘Schlegel’ or any other approved equivalent. The exposed surface shall be treated with two
coats of ‘FOSROC Dekguard S’ Anti-Chlorides and Carbonation coatings or any other
approved equivalent with a dft of 350 microns. This coating shall be required to protect the
above ground concrete from the atmospheric effects and windborne salts. For more details
of the exposure condition refer SP-1282 Specification for Reinforced Concrete –
‘Production & Construction Guidelines’.
The coating system for tanking shall be two coats of ‘FOSROC Nitocote PE135’ or any
other approved equivalent with a dft of 400 microns.
All membrane or coating system shall be strictly in accordance with the relevant
manufacturers instruction. Covers to all reinforcement including links shall never be less
than the value shown in Table 2.
Internal : 50mm
External : 50mm
Note: The above are minimum nominal covers and shall be increased if required by the
relevant design standard being used.
Reinforced concrete should be general contains aggregates not exceeding 20mm and mass
concrete should in general contain aggregates not exceeding 40mm. The design and details
of concrete and concrete mixes shall be in accordance with SP-1282 Specification for
Reinforced Concrete – ‘Production & Construction Guidelines’.
All structural concrete shall be of Grade C35 (that is, having a characteristic strength of 35
N/mm2 at 28 day), unless specified otherwise. Mass concrete shall be used for general
filling as required. Blinding concrete shall be 50 mm thick. Both Blinding and Mass
Concrete shall have a characteristic strength of at least 10 N/mm2 at 28 days. All edges of
exposed concrete shall have a chamfer of approx. 25 mm.
Note: 1. Product Brand Name: Schlegel for Membrane system and Fosroc for
Exposed surface coating.
Foundation bolts shall be in accordance with the latest revision of PDO Standard
Drawing STD-2-3950-001. Unless stated otherwise, the standard minimum lap
lengths of concrete reinforcement shall be as shown in Table 3.
Tension / Tension /
Size Size
Compression Compression
R6 300 T6 350
R8 350 T8 450
Concrete reinforcement for Hot-Rolled Mild Steel and Hot-Rolled Deformed High-Yield-
Stress Bars, shall be detailed as follows:
12 – R/T 10 – 3 - 200
SPACING OF BARS
BAR MARK
NUMBER OF BARS
REQUIRED
Careful consideration should be given to the partial safety factors used for materials when
designing block work. Details of supervision and quality of blocks required to meet the
design assumptions should be stated on the drawings or in the specification.
Blockwork shall be designed to carry all the applied loading and combinations of loading,
giving due consideration to differential and thermal movements.
All welding symbols used shall comply with BS 449 Part 2C.
Legend / Symbols are given below and for definitions and abbreviations see Appendix A.
Should other symbols or abbreviation be required (excepting welding symbols) a key shall
be provided on the drawing clearly describing their meaning.
Lettering and figures shall be distinct and uniform to ensure the production of good legible
prints. The style should be simple and unaffected. Capital letters should be used for all
titles and sub-titles. Lowercase letters should be used only for notes.
Civil/Structural
Note:
1. Where larger scale details are desirable, the following should be used 1:5,
1:2 or FS.
2. For projects with large foundations a scale of 1:25 may be used when scales
of 1:50 or 1:20 are clearly unsuitable.
All structural slab levels or finished floor levels should be indicated and related to a datum.
Levels shall be expressed in metres. All other dimensions shall be expressed in millimetres.
Structural steelwork working drawings should show details of main connections. For minor
connections all moments, forces and shears shall be required to enable their design by the
contractor. The Consultants scope of work shall include the checking of shop drawings and
connection details designed by the contractor.
The Consultant shall produce a full set of As Built drawings, based on fully marked up
drawings by the contractor, which shall contain all civil, structural, mechanical, electrical
details etc. They shall clearly indicate the true location of all hidden and underground
services, structures and the like.
Complete copy of drawings shall be submitted in electronic form and loaded to PDO live
link system.
Legend / Symbols
The specification gives minimum general requirements for the design and engineering of all
new building, however additional requirements for specific buildings are specified in the
following documents:
The design of Standard Pipe Supports is covered in a separate dedicated document: SP-1187
Specification for ‘Selection of Standard Pipe Supports’.
The design shall take into account all loading conditions foreseen as occurring during the
design life of the structure. If applicable, loading from future extensions shall be allowed
for. These shall include any alterations to wind loading effects due to the change in
structure size. Details of assumptions made in this respect shall be clearly stated in the
design concept section of the calculations.
Loadings that will occur during construction of the structure shall be designed for. Details
of any specific construction procedural requirements such as back propping; de-propping
etc. shall be clearly stated to the contractor in the drawings or specifications as necessary.
The self-weight of all the building elements including services, specific plant etc. shall be
calculated and used in the design of the structure. For proprietary systems, equipment and
machines specific details of loading shall be obtained from the manufacturers and used in
the design. These details shall correspond to the items specified on the contract drawings
and in the specifications.
Where permanent partitions are shown in the plans their actual weights shall be included in
the dead load.
The weights of tanks and other receptacles and of their contents shall be considered as dead
loads. These loads need to be calculated for the cases when a tank or receptacle is full and
when empty.
Dead loads should be calculated from the unit weights given in BS 648 or from actual
known weights of the materials used. For general building materials, however, the values
given in Appendix B may be used.
Live loads for buildings, and method of calculation, shall be in accordance with BS 6399
Part 1, however the live loads shown in Appendix C may be used as a guideline.
For structural steel platforms on Oil/Gas projects, the following live loads shall be used:
Special Cases (e.g. Floors located at the draw end of a : 750 kg/ m2
shell tube heat exchanger).
Under desert conditions roof with a pitch of less than 50 shall be designed for sand loading
and shall be a minimum of 1 kN/m2.
For structural calculations, local codes or regulations, and actual loading situations shall be
adhered to if more stringent than the values obtained from Appendix C.
Where applicable, the weight of vehicles shall be included as live loading and shall be
applied to produce the most critical design cases.
Wind load calculations shall comply with the requirements of BS 6399-2 Loading for
Buildings – ‘Code of Practice for Wind Loads’ and DEP 34.00.01.30-GEN.
Figure 2 specifies highest Mean Hourly Wind Speed, V10 (m/s), at a height of 10 m, which
shall be accounted for in the design.
The Design Wind Speed at any height z above the ground, Vz (m/s), is derived from the
formula below:
Refer Table 4 for the values of F & 1/y and Table 5 for the value of S3.
Figure: 2
F 1/y
Categor
Topography
y
3 sec gust 10 sec gust
Although 3-second gust speeds, are sometimes quoted and certainly of great importance
when dealing with wind forces on structures, the above formula takes this into account.
The values of S3 are shown in Table 5 and shall be used for the various category of structure
as described in section 2.5.
Structure Type S3
Permanent 1.00
Temporary 0.77
Note: The values given above shall not be applicable for Telecom Type Towers and for any
special structures for a particular project and shall be calculated from BS 6399.
The following applies only to single crane operation and to simple forms of crane gantry
construction. Loads for heavy crane, high-speed operation or multiple cranes on a single
gantry have to be specially calculated.
For crane gantry girders, the following allowances can be used to cover all forces set up by
vibration, shock from slipping of slings, kinetic action of acceleration and retardation and
impact of wheel loads:
a. For loads acting vertically, the maximum static wheel loads shall be increased by the
following percentages.
b. The horizontal force acting transverse top the rails, the following percentages of the
combined weight of the crab and the load lifted:
c. The horizontal forces acting along the rails shall be taken as a percentage of the static
wheel loads, which can occur on the rails, as follows:
The forces specified in either (b) or (c) above, may be considered as acting at the rail level
and being appropriately transmitted to the supporting system.
Either of the horizontal forces in (b) or (c) above may act at the same time as the vertical
load on gantry girders and their vertical supports.
The design loadings for Overhead Travelling Cranes and outdoor gantries shall be
determined in accordance with BS 2573.
Where loads arising from machinery, and other plant producing dynamic effects, are
supported by or communicated to a structure, allowance shall be made for these dynamic
effects by increasing the load by an adequate percentage.
Foundations, which directly support vibrating equipment such that the effects need to be
taken account of in the calculations, shall be designed in accordance with BS CP 2012. In
general it is advisable to provide anti-vibration pads.
Load combinations shall be such that both maximum and minimum load cases are checked if
applicable to investigate not only design loadings on particular elements but also stability,
uplift and overturning conditions. Load combinations shall also be in accordance with the
requirements of the particular design code of practice or standard.
Attention shall be paid to the prevailing climatic conditions in various seasons (using
records of local climatic design data), such as air temperature, temperature differences,
saline atmosphere, sand and dust storms, possible sand infiltration of buildings, humidity,
solar influence, wind, micro climatic variations, etc., to arrive at a satisfactory design.
Buildings shall be designed and constructed so that, within operational and physical
constraints, they are able to maintain the necessary internal comfort condition with the
minimum of capital and operations costs over the whole range of external prevailing
conditions.
Outdoor design conditions should be based on the relevant meteorological data for each
project. For further detail refer section 2.16.
1 Residential and If at all possible, camps & housing plots etc., shall be sited up
Housing Areas wind of industrial areas, so that prevailing winds drive smoke &
fumes away from accommodation/residential areas. They shall
also be sited a reasonable distance away from mosques and
recreational facilities.
4 Mosques and All mosques and prayer shelters shall be orientated towards
Prayer Shelters Mecca. Once the building foundation trenches have been
excavated, final approval by the local religious authority shall be
received before further work commences. Mosques shall be
located away from any sources of noise.
5 Outdoor Sports Tennis courts, volley ball courts (and preferably football pitches)
Facilities shall be orientated in the N-S direction because of sun light
problems at dawn and dusk. Care need to be taken in siting these
facilities in relation to problems of night time glare from
flares/burnpits. Shelter is needed from the wind, especially for
badminton or tennis courts. Sports facilities shall not be located
close to areas from which there is high level of noise, for example,
turbines, or close to likely source of fumes/smoke, for example,
fire training ground.
6 Open Air Open Air Cinemas are usually only used at night. Therefore if
Cinemas such a facility has been specified by the Company (no longer
considered a standard facility), their location and orientation shall
depend on problems associated with glare from flares etc., and
noise to accommodation, mosques, etc., or from adjacent plant and
equipment. Prevailing wind problems with fumes, dust, etc., shall
also be taken into account, not forgetting the effects of the glare
from the sun (least important).
7 Power Stations Power Stations are generally very noisy and therefore their
location shall be such as to cause the least amount of discomfort to
occupants of camps, building, potential building plots, etc., still
ensuring cost effectiveness of cable lengths, O/H lines, fuel lines
etc. Gas Turbines have the added hazard of gas explosions (as well
as possible H2S problems). Noise levels are defined in the section
3.0 of SP 1231 and section 4.6 of DEP 34.17.00.32.
(Contd.)
8 Clinics Clinics shall be sited such that easy access to both Residential
and Industrial Areas is achieved. Noise is considered the
major hazard for clinics even though hazards due to
fumes/smoke/flare glare, etc., shall also be taken into account.
9 Schools Schools generally have a certain amount of noise associated
with them, and therefore should not be too close to housing.
A more important factor is the hazard of fast traffic. Speed
bumps shall be located on both sides of the School, with
appropriate traffic warning signs, etc., to control traffic
speeds. All hazard facilities, such as electrical substations,
sewage pumping pits, etc., shall be securely fenced off with
suitable locks.
10 Offices Offices should have an E-W main axis, with the windows
facing either north or south, as the penetrating morning and
evening sun is undesirable. The sun can be kept out by sun
blinds, window U/V film, or roof overhang. Siting is
dependant on client needs but care must be taken against
noise and fume/smoke hazards. Space is needed directly
outside the office space for off loading supplies and adequate
car parks. Natural day light is very desirable but not
necessarily essential. Artificial lighting, to correct levels, may
be used if no other option is available.
14 Airstrips & When siting an Airstrip in the Interior the following points
Air Terminals shall be considered:
(Contd.)
17 Fire Training The Fire Training Area is a source of ignition and a source of
Areas smoke (and possible H2S). These areas shall be located well
away from Residential and Recreational facilities. They
shall also be located well away from any installations, which
have inflammable or hydrocarbon compounds such as oil/gas
installations, fuel stations, explosive stores, laboratories,
warehouses/stores, etc. Building facilities, other than
buildings within the compound itself, shall not be less than
150 m away from a point of ignition in the Fire Training
Area. Prevailing winds and hence the effects of smoke must
be taken into consideration when locating such an area.
(Contd.)
25 Car Parks In the design of car parks particular attention shall be drawn to
save ingress to and egress from the approach roads. In
congested areas right angle parking should be used to maximise
space usage and overall cost. Elsewhere 450 parking is
considered desirable. Whilst it is mandatory in the Interior to
build car parks suitable for Reverse Parking, for the Coast uses
normal drive in parking (see Figure 5 in this document).
26 Shops Shops shall be provided with a storeroom, toilet and wash hand
basin. The store shall be minimum 15% of the shop floor area.
The planning of all buildings shall be in accordance with the BS 5588 Part 1 to 5 Fire
Precautions in the Design & Construction of Buildings and shall comply with the
requirements of Royal Oman Police regulations.
Building layouts and proposed fire protection systems shall be subject to Company
approval.
The layouts shall show safe means of escape routes, protected corridors, travelling distances
to the protected corridors, protected shafts and means of escape exists. A statement shall be
provided specifying the proposed air-conditioning supply and return air systems, and fire
protection systems for the project.
The location of all hand held fire-fighting equipment shall be agreed with the Company.
All matters relating to Fire Detection, Protection and Alarms is covered under Section
2.17.7, 2.19.4 and 2.20 of this document.
These buildings shall be designed with an overall building width of 13 m. One of the centre
corridor walls shall coincide with the centre of the building giving offices of internal
dimensions of:
Provision shall be made for installation of partition walls at approximately 1.69 m intervals
so that following rooms sizes can be formed: 7 m2, 10.5 m2, 14 m2, 21 m2, 31.5 m2 and 42
m2.
All rooms in the PDO sleeping accommodation blocks shall have a bedroom, attached
bath/toilet and storage facilities. Standard room sizes are given in the Table 6. The
accommodation unit allocation shall be one person/room for senior staffs and two
persons/room for junior staffs.
Staff (Grade)
Item
SS JS
En suite En suite
Notes shower/wc shower/wc
In general toilets shall have minimum internal dimensions of 1.0 m x 1.6 m for both SS and
JS. This may be reduced to 0.9 m x 1.3 m in offices.
Showers shall have minimum dimensions of 1.0 m x 1.8 m, divided into a wet area and a dry
area by a simple curtain, the latter area having a seat.
Contractor’s temporary site offices shall have areas as stated in section 2.7.1.1 or to suit the
requirements of a particular contract.
Three persons sharing per room shall be allowed for JE and other staff categories, if the
bedroom size is more than 21 m2 or as stated in Table 6.
The following sanitary ware fittings shall be provided for each bath /toilet unit. Refer Table
7.
Sanitary Fittings
2a SS √ √ √
2b SS √ √ √
2c SS √ √ √
Contractors JS/JE and all other staff’s accommodation units shall have a sleeping room with
attached bath/toilet facilities. The room sizes shall not be less than 13 m2.in case of portable
accommodation units otherwise the size shall be the same as given in Table 6. The
following minimum number of sanitary ware fittings shall be provided for each bath / toilet
unit. Refer Table 8.
Sanitary Fittings
3a JS √ √ √
3b JE √ √ √
3c JE √ √ √
3d Others √ √ √
3e Others √ √
In general, the Kitchen and Associated Facilities should be constructed in block work, and
the use of porta-cabin type kitchens shall be discouraged. The Kitchen and Associated
Facilities for Contractors have been sized using the following design criteria, based on
international norms:
Individual space requirements in the kitchen for the various functions are shown in the
Figure 3.
M2
60
Preparation
40
20
Meals
3.a. Preparation
M2
80
60 Service
40
20
Meals
3.b. Service
M2
60
40 Staff Facilities
20
M2
60
Cooking
40
20
Meals
3.d. Cooking
M2
60
40
Wash-Up
20
Meals
3.e. Wash-Up
M2
60
Storage (total)
40
20
Meals
3.f. Storage (total)
4 Kitchen Area
4a Preparation N/A 10 m2 10 m2 11 m2 15 m2 23 m2
4b Service N/A 18 m2 18 m2 19 m2 22 m2 36 m2
4d Cooking N/A 19 m2 19 m2 20 m2 23 m2 39 m2
4e Wash Up N/A 8 m2 8 m2 10 m2 13 m2 18 m2
180 - 2 No
5b Assumed Average Population N/A 20 40 80 170
Shifts
360 - 2 No
5d Assumed Number of Meals/sitting N/A 20 40 80 170
Shifts
5e Dining Space factor for JS N/A 1.6per’s/m2 1.5per’s/m2 1.4per’s/m2 1.4 persons/m2 07 persons/m2
5f Dining Space factor for SS N/A N/A N/A 1.8per’s/m2 1.7 persons/m2 08 persons/m2
JS Dining Area Space Requirement in m2 N/A 32m2 60m2 93m2 203m2 220m2
JS Servery and Extra Circulation Space N/A 18m2 30m2 47m2 107m2 110m2
5g Total Dining Space Requirement for JS N/A 50m2 90m2 140m2 310m2 330m2
Dining Area Space Requirement for SS N/A N/A N/A 25m2 43m2 36m2
SS Servery and Extra Circulation Space N/A N/A N/A 15m2 27m2 24m2
6 Other Facilities
Building elements shall be designed and detailed to comply with fire regulations as detailed
in the United Kingdom Building Regulations 1985 produced by the Department of the
Environment and the Welsh Office. Designs and details shall also comply with the
requirements of the local fire authorities. Refer Appendix C for the relative values of the
different Building Elements and Finishes of PDO buildings.
2.8.1 Walls
All wall designs and details shall take into consideration the following:
- Economic Aspects
- Finishing Requirements
In addition external walls shall be designed and detailed to resist moisture penetration, to
prevent the occurrence of condensation. Damp proofing is required, as in temperate
climates (regarding the omission of damp proof courses, refer section 2.8.1.5). Termite
barriers are essential in the construction of walls.
Internal walls for wash rooms and other wet rooms shall be designed and detailed to be
moisture resistant and shall contain a damp proof course. Walls for control buildings shall
be solid with no cavities to prevent the possible build up of gases and therefore hollow
blocks shall not be used in these instances. Holes for cable entries in these buildings shall
be sealed with polyurethane foam after cables have been installed.
All load bearing block work walls shall have a minimum compressive strength of 10 N/mm2.
All non - load bearing block work walls shall have a minimum compressive strength of 3.5
N/mm2.
All openings for windows, doors, etc. in hollow block work shall be framed on all sides by
providing a minimum of one T12 reinforcing bar placed centrally in the block hollow
adjacent to the opening. The hollow shall subsequently be filled with concrete as the block
work progresses. The concrete shall be a minimum of grade 20. (Characteristic strength of
concrete shall be 20 N/mm2 @ 28 days with 10 mm aggregate).
The framing bar shall run from the floor below the opening to the ceiling above and where
applicable shall pass through and be cast into the lintels above the opening. It shall also,
where applicable, be cast into the slab below and soffit above the block panel under
consideration.
Walls shall be designed to withstand all vertical, horizontal and longitudinal loads, including
wind and stability loading, as necessary. Due consideration shall be given to the eccentricity
of loading in the design.
Light colour, heat reflecting, thermal qualities and low maintenance shall be the main
considerations in selecting the external finish. ‘U’ values should not exceed 0.6 W/m2 0C for
external walls. Cavity walls with insulation shall be considered in all external wall designs
for air conditioned buildings to help conserve energy. See also section 2.8.1.5.
All walls shall be suitably designed and constructed to ensure compliance with the room
noise ratings specified in Appendix K.
Vertical movement joints in walls shall be placed at intervals not exceeding the following:
Concrete walls 30 m
Parapet walls 5m
All movement joints in buildings shall be sealed to prevent the ingress of water.
Consideration shall be given to exceeding the ‘U’ value of 0.6 W/m2 °C stipulated in section
2.8.1.2 where the environmental condition within the space is not critical.
Non-fair faced un-rendered block work may be used in areas of non-aesthetic importance.
Where wall cladding is used, un-plastered non-fair faced blocks shall be used on faces
covered by the cladding.
External walls constructed on concrete ground beams or slabs which are a minimum of 150
mm above surrounding ground level shall not require a horizontal damp proof cover.
2.8.2 Floors
Where reinforced concrete floors are required externally they should be constructed in bays
not greater than 4.5 m in width, which shall separated by longitudinal construction joints.
Every other longitudinal construction joint shall be formed to allow shrinkage to occur.
Each bay shall be divided into lengths not exceeding 5 m by transverse shrinkage control
joints. Expansion joints shall be provided in both directions every 30 m.
Where mass concrete hard standings are used they shall be formed in bays not exceeding 5
m x 5 m, which shall be separated by isolation joints.
All external floors and hard standings shall be laid with adequate falls (minimum 1:100)
such that, allowing for normal tolerances, there is no possibility of water ponding and to
ensure quick and effective drainage.
Consideration shall be given, particularly with temporary or semi permanent floor to laying
the concrete directly on the ground.
All exposed concrete floors subject to oil/acid spillage shall be treated with a suitable epoxy
based flooring cover.
In workshops, due consideration shall be given to fork lift loading, racking and machine
foundations.
All vibrating and large machine foundations shall be isolated from the ground floor slab by
way of an isolation joint.
For the installation of computers and other instrument or electrical equipment with cable
connecting at the bottom of the equipment cavity floors shall be provided. These shall
comprise a reinforced concrete lower floor and a removable panel upper floor of 600 x 600
module supported on pedestals. The pedestals shall be fixed to the concrete floor in such a
manner as to form a firm bedding and shall be in accordance with the manufacturers
instructions. They shall be adjustable in height and the adjustable section shall have
automatic positive locking. Ensure that the pedestals and the frames, supporting either the
instrument or electrical cabinets, are able to provide independent stability to the structure at
all times. Each floor panel shall be capable of supporting, as a minimum, a concentrated
load of 4450 N, applied on an area of 650 mm2 at any point. The floor shall also be capable
of carrying, as a minimum, 15 kN/m2 with a maximum deflection of 1 mm. The reinforced
concrete floor below the cavity shall be painted with an epoxy paint to prevent formation of
dust.
All pre-cast suspended floors shall be suitably tied to the structure to provide robust and
stable construction.
To all wet areas such as toilets the floor and 200 mm up surrounding walls shall be painted
with two coats of bitumen and sharp sand splattered for key.
At change of finishes line, at all doorways and in bays not exceeding 15 m2 brass dividing
strips finished flush to the surface shall be provided.
2.8.3 Skirting
2.8.4 Ceilings
2.8.5 Doors
All doors shall be either solid teak framed or teak faced solid core flush doors. Where doors
are fire rated their composition shall change accordingly.
2.8.6 Windows
Contractors shall verify the final dimensions at site before making shop drawings. Approval
to shop drawings shall be given prior to commencement of manufacture. All windows to be
silver anodised aluminium with 6 mm thick glazing.
Windows shall be fixed into a timber frame. Glazing to floor level windows shall be armour
plated glass. To bathrooms and toilets shall be rough - cast narrow receded.
2.8.7 Ironmongery
Subject to the building type the quality of fittings to be used shall be determined by the
Company Representative. Generally ironmongery shall be in packs. Ironmongeries pack
and typical requirements are detailed in Appendix J of this document.
All doors shall open in the direction of the escape route and be positioned so as not to block
any stairway.
For steel stairs the minimum width of stairway, walkway & platforms shall not be less than
750mm. Stair treads shall not be made GRP or aluminium and shall be hot-dip galvanised
steel. On platforms, the distance to a stair or ladder shall not be more than 25m.
The Concrete platforms in front of equipment doors shall be calculated to be able to bear the
equipment that will be transported through the doors.
No stairway shall exceed sixteen risers in any one flight, if more are necessary a landing
shall be provided.
For fire safety purposes (fire escapes) a flow capacity of 1.3 persons per second per metre
width shall be used. This is greater than normal use flow capacity which, shall be
determined as shown in Table 14 below:
Free Flow Mean Plan Density <0.6 Full Design Capacity 1-way Plan
persons/m2 Density 2 persons/m2
0.9 27 0.6 60
The following formula shall be used to determine the suitable relationship of riser to going
for normal staircases:
Refer Table 15 for the stairs dimensions, headroom clearances, travelling distances and
other requirements.
Height of handrail above front of treads 900 900 900 900 900 900
Height of handrail above landing 1100 1100 1100 1100 1100 1100
(Contd.)
+ Length of landing shall not be less than width of staircase relevant to location of stairs.
The minimum fire rating values of the building for various purposes and types are indicated in the Table 16, however these shall meet the requirements of the
latest Royal Oman Police regulations.
(Contd.)
(Contd.)
(Contd.)
(Contd.)
Modifications
Any element of structure should have at least the minimum period needed for any other element structure, which it carries or supports (whether that other element
is load bearing or not).
* Increased to 1 hour for separating walls. Reduced to 0.5 hour if the area of the basement is 50 m2 less.
** Reduced to 0.5 hour for any floor (which is not also a compartment floor), but not for any part of floor, which contributes to the support of the
building as a whole and not for any beam, which supports the floor.
Notes: 1. The floor area of each storey in the building or where the building is divided in compartments the floor area of each storey in the compartment of which
the element structure forms part.
2. The cubic capacity of the building or where the building is divided into compartments cubic capacity of the compartment of which the structure forms
part.
3. Where the building is fitted throughout with an automatic sprinkler system meeting relevant recommendations of BS 5306: Part 2.
2.10 Roofs
Due consideration shall be given to the provision of access to roofs, where necessary for
maintenance etc. In situations where required, a safe means of access shall be provided.
Also waterproofing details in these instances shall be such that they will satisfactorily
withstand the likely subsequent wear and tear.
Roofs should have a maximum ‘U’ value of 0.6 W/m2 0C. Insulation should be capable of
withstanding rodent attack in situations where it may be exposed to the same. Roofs are
subject to intense heat and thermal movement and waterproof membranes shall be
adequately protected or detailed to withstand these conditions. It should be possible to
inspect and repair the membrane periodically and consideration should be given to
permanent access. Because of its exposure special care should be taken when specifying
roof insulation for ‘Upside-Down’ roofs, in terms of required insulation characteristics,
durability, water absorption and physical strength.
Rain is infrequent, but when it does occur it can be torrential, consequently, traditional
gargoyles are the preferred method of rainwater disposal from flat roofs and should be
employed. Careful consideration shall be given to the projection of gargoyles and to the
ground treatment where rain water discharges. Gargoyles shall be provided with suitable
drips to prevent water running down the face of the building causing unsightly stains.
Gargoyles shall be sited away from doors, lights and where possible windows.
Flat roofs should be promoted where possible. Pitched roofs, other than for warehouses/
workshops, are not permitted in the Muscat Area. The upside down flat roof has the added
advantage that the roof insulation protects the waterproofing layer from both the intense heat
and puncturing. Extremely careful detailing of such roofs is essential to ensure durability.
Flat roofs shall be provided with a minimum fall of 1.80. Consideration shall be given to
pre-cambering, particularly on long span roofs to prevent ponding. In any case ponding
shall not occur.
Parapets on flat roofs are a natural source of building defects, particularly when of block
work construction.
Parapets shall be carefully detailed to control thermal movement with control joints not
exceeding the spacing in section 2.8.1.4.
Parapets shall be securely fixed to the roof slab and shall be capable of resisting a minimum
horizontal load, on access roofs, of 0.75 kN/m run at the top of the parapet which should be
a minimum of 1.1 m above the roof covering.
Flat roofs cast on load bearing block work should contain a slip plane between the block
work and slab soffit to allow for thermal movement of the slab without distressing the block
work. The roof slab, however, must be suitably held in place to ensure stability criteria are
maintained.
Pitched roofs shall be avoided wherever possible. As a general rule, only flat roof designs
shall be used in the Muscat Area. Pitched roof designs may be considered in the Interior
only if it needs to match existing pitched roofs, or used for warehouses/ workshops and
sunshades. Pitched roofs in the Muscat Area have to be hidden by using appropriate
facades.
When used, pitched roof plan shapes shall be kept as simple as possible, hips and valleys
should be avoided. The construction shall be such as to result in a completely waterproofed
roof.
Consideration shall be given to ridge vents in order to reduce internal design pressures
arising from wind loading and where required to provide natural ventilation.
Gutters and downspouts shall only be provided over entrances and where people have to
pass. However adequate details at ground level shall be provided to prevent erosion and
percolation.
Design of Sunshades and standard details are covered under a separate document: SP-1283
Specification for Standard Sunshades – ‘Design & Standard Drawings’.
It is important to fully specify the roof sheeting requirements on design drawings. The
following minimum requirements shall be used:
4. Not be used in severe marine areas (for example, MAF, RAH, etc.): this is
also in line with the requirements of the Muscat Municipality.
5. Be fixed with stainless steel self-tapping screws and isolated from the
purlins with In-seal Tape.
In addition to the above two materials (but ignoring sheeting materials such as GRP/ GRE/
etc.), a third type of material may be used known as 55%AIZn Coated Steel Sheeting. This
material has an ideal mix of 55% Aluminium, 43.4% Zinc and 1.6 Silicon. The material
shall follow the same requirements as Galvanised Steel (see above), but can be used for
Coastal Areas (MAF, RAH, etc.). There might be problems related to powder coating this
material and therefore colour choices will be limited.
2.11 Built-in-Furniture
All cupboards shall be fitted with shelving to maximise the use of the storage space.
In the layout of kitchens particular attention shall be paid to safe distances between electric
points and the sink. Kitchens shall be designed to be ergonomically and correctly related in
the layout of the parts. In general,
Fitted wardrobes shall be provided in all bedrooms including SS rooms and Clinic wards.
Where rooms are in use by two persons two wardrobes shall be provided.
In each dwelling bathroom, and each room with bed(s) and basin, a bathroom cabinet shall
be provided with mirror front, two sections, shaver point and light.
2. Offices.
To detached and semi-detached accommodation and mess block, curtain pelmets shall be
provided.
To SS Mess firm bar with back display and storage shall be provided.
2.12 Security
All fencing and gates shall comply with the requirements of the Company standard
specification SP-1279-P Specification for Civil & Building Construction – ‘Fencing &
Gates’. The consultants drawing shall make reference to the fencing and gate types
contained therein.
Booster Station B
Explosives Store A
Farms C
Flares – Ground C
Flares – Tower C
Garbage Dumps C
Gathering Station B
H2S Well B
Interior Camps B
Isotope Pit A
Microwave Areas B
Oxydation Ponds C
(Contd.)
Power Station B
Production Station A
Sub Station B
Telecom Centres A
Telecom Towers B
In addition to the above requirements, a standard signboard (refer SP-1284 Specification for
Signs & Signboards – ‘Standard Signs Catalogue’ shall be placed at the entrance of the
fenced compound, indicating the presence of a ‘Restricted Area’ (refer CP-122). It should
be noted that the rationale for installing fences and gates as tabled above, is as a direct result
of having identified Specific HSE Site Hazards and/ or Specific Security related Access
Control Requirements.
The HSE Access Control Procedure (refer CP-122 and the documents referenced therein),
Stipulates that the asset holder (as defined in the Corporate Asset Holder Register) is
required to specify those areas, which need Access Control (based on what hazards and
threats have been identified). It is possible therefore, that asset holders may decide to install
fences/ gates in locations not included in the above table.
Low Pressure Well Heads and Remote Manifolds do not require fencing. For details refer
SP-1127 Plant Equipment & Layout Specification.
Colours shall be to British Standard BS 4800. If specific colours are not requested or
specified, the following colours should be used for:
08-B-15 : Magnolia
10-B-15 : Ivory
06-C-33 : Honeysuckle
00-E-55 : White
For the non-specialised buildings, that is, accommodation, offices, exposed service pipes,
for example water pipes, shall be painted to match their background colour.
All external walls should be 06-C-33 throughout (unless specified otherwise). All exposed
drainage or vent pipes in front of the external wall shall be painted the same colour as the
wall.
All Mess Dining Rooms, Games Rooms, Lounges, Billiards Rooms and TV/Video Rooms
shall be 08-B-17 - Wood Smoke.
Where the soffit of the ceiling is exposed (either exposed concrete or plastered ceilings) use
00-E-55.
The type of paint finish shall be as described in Wall Finishes (Appendix D).
2.14.2 Landscaping
All projects involving landscaping should incorporate the current PDO landscaping
specification SP-1279-Q. Particular attention should be paid to the creation of a localised
microclimate with low, medium or high canopies as appropriate to the particular situation.
For Landscaping Irrigation refer to section 2.17.8.
Soft Landscaping should be designed considering both the aesthetic aims and long term
maintenance requirements.
Consideration should be given to the need to reduce dust nuisance in amenity areas by
landscaping in conjunction with other appropriate means, for example, fabric attached to
fences.
2.14.3 Roads
Where internal access roads are required to serve buildings, car-parking areas etc., the
Consultant must clarify the likely range of vehicles that will be requiring access.
Where the layout is designed for private vehicle usage, mountable kerbs should be provided
where necessary to allow for occasional heavy vehicle passage.
1. Geometric Design:
Typical desirable and minimum standards for internal access roads for both light and
commercial vehicle usage are given in Table 18. It should however be borne in mind that
the dimensional requirements may vary according to the actual size of commercial vehicle
requiring access.
Roads are to be cambered or with cross fall at 1.5% and provided with adequate longitudinal
gradient to ensure dispersal of storm water into the proposed drainage system.
Care shall be taken in the design to avoid flat spots and consequent ponding of storm water.
Care shall be taken to ensure adequate visibility sightlines particularly where buildings are
located adjacent to junctions.
2. Pavement construction
The pavement is to be constructed to suit the future loading over the specified design life.
Where loadings are light, consideration should be given to designing a pavement of granular
material sealed with surface dressing (e.g. “spray and chip”, SPP stabilised and sand sealed
or slurry dressing).
Where roads will be trafficked by commercial vehicles, the anticipated traffic loading should
be predicted and the pavement designed in accordance with the procedure set out in the
latest issue of the “Oman Highway Design Manual”, as well as what is advised in both SP-
1279-R & S (Specification for Civil & Building Construction – ‘Roads & Paving’, and
‘Graded Roads, Rig Locations, Airstrips, Tank Pads & Bund Works).
Road signs and markings should be minimised and yet give clear direction to drivers. Road
signs should be of minimum 600mm size and be in accordance with SP-1284 Specification
for Signs and Signboards – ‘Standard Signs Catalogue’.
Road markings should be either thermoplastic or road marking paint to suit the scale of
works. A mandatory warning sign is required below the danger warnings at all junctions of
the Grades/Tarmac transition to give more information about the dangerous situation.
Where external access roads are required to serve a facility, the road must be designed to
suit the initial level of service and yet allow for future upgrading if required.
1. Geometric Design
Roads are to be designed to the geometric design standards set out in the latest issue of the
“Oman Highway Design Manual”, using an appropriate design speed.
2. Pavement Construction
Figure 4 details standard pavement construction for PDO interior roads, which will allow
progressive development of the standard of road as required. These are further detailed in
SP-1279-S Specification for Civil & Building Works – Graded Roads, Rig Locations,
Airstrips, Tank Pads & Bund Works’. Roads, which are to be adopted by the Ministry of
Communications, are to be constructed with asphaltic concrete overlying granular pavement
layers. The pavement is to be designed in accordance with the latest issue of the “Oman
Highway Design Manual”.
Currently tests are being performed using road material stabilisers. Their performance in
these tests might well promote the use of road stabilisers in the construction of both graded
and paved roads. The road designer shall therefore investigate the status of these tests, and
hence assess their suitability in the design of all roads.
Successful road base stabilisation, say with SPP (Sulphonated Petroleum Product), could
result in CBR of greater than 120, which will in turn allow cheaper road surface dressings to
be used, such as Sand Seal and Slurry. However, the latter road seal thickness is only in the
order of 6 to 8 mm, and therefore road surface finish tolerance (and therefore the road’s
“riding comfort”) is likely to be poor.
Road signs and markings should be provided to suit the scale of the road and shall be in
accordance with the latest issue of SP-1284 Specification for Signs and Signboards –
Standard Signs Catalogue and the “Oman Highway Design Manual”. A mandatory warning
sign is required below the danger warnings at all junctions of the Grades/Tarmac transition
to give more information about the dangerous situation.
Car parks should be provided on-site to cater for employees, operational needs and visitors
typical car park spacing requirements are given in Table 19. Car parks shall be designed so
as to discourage parking in the aisles and access routes. Where parking is designed for
commercial vehicles, the standards to be applied are to suit the particular usage.
Car parking facilities shall be generally designed to the layout standards shown in Figure 5.
Parking bays are based on a 3 m x 6 m module. Where available space permits, parking
areas should be designed for 900angle parking.
Car parks shall be profiled to ensure dispersal of storm water to the proposed drainage
system.
Car parks be surfaced with 80 mm thick interlocking block paving, asphaltic concrete or
surface dressing as appropriate to the scale of construction and required aesthetics.
Pavement construction is to be designed to cater for the relevant loading over the design
period.
Where the construction is in interlocking block work, use should be made of different
colours to clearly distinguish between vehicle routes and parking areas. In general vehicles
routes are to be paved with grey blocks and parking areas with charcoal grey blocks.
Landscaping and street furniture should be set back from kerb lines to allow overhang of
vehicles.
Road signs and markings should be minimised and yet give clear direction to drivers.
Where interlocking block work construction is proposed, use should be made of coloured
blocks for markings and bay divisions. Road signs should be of minimum 600 mm size and
in accordance with the latest issue of SP-1284 Specification for Signs & Signboards –
‘Standard Signs Catalogue’.
(Contd.)
(Contd.)
(Contd.)
Parking Spaces
Facility Type
On Site Off Site
500 – 900 m2 2 1
200 – 400 m2 1 1
Education Kindergarten 14 12
Elementary 16 – 38 24 – 96
Preparatory 23 – 54 22 – 86
Bus Terminus 0 40
Bus Garage 50 0
(Contd.)
Material storage yards should be designed to suit the particular material to be stored.
Particular attention must be made for access and manoeuvre of forklifts and delivery
vehicles.
2.14.6 Footpaths
Footpaths are to be provided, where required, to clearly define pedestrian routes. Analysis
is to be carried out of the desirable walkway routes, bearing in mind that pedestrians tend to
try to minimise the distance walked.
Footpaths are to generally 2 m wide. This may be reduced to 1.5 m minimum where layouts
and volume of pedestrian traffic permits.
Footpath are generally to be surfaced with 60 mm coloured interlocking block work or pre
cast concrete slabs overlying sand laying course and granular base material. Footpaths are
to be bound by kerbs.
In principle, all costs associated with access to wells and routing of flow lines to the
Gathering Station, shall be kept to a minimum. The simplified sketch, shown below (Figure
6), shows how the above may be achieved. Here, the access field roads enter the field from
one side, whilst the services to the wells, as well as the flow lines and/or bulk lines,
enter/exit from the other side of the field. By doing so, the number of road crossing is kept
to a minimum (in this example only one road crossing is required), allowing all power
cables to be routed under roads.
Figure 6: Concept Layout Of Wells, Drilling Locations Flow/Bulk Lines Using Min. Road Crossing
Building services design criteria shall be established in consultation with the Company.
Designs shall be fit for purpose and requirements for economy, reliability, maintainability,
flexibility and life expectancy shall be agreed with the company.
The requirements here described shall apply to the following Sections of this documents.
2.17: Plumbing
2.19: Electrical
One set of the final approved design calculation shall be submitted to the Company for the
record purpose.
Material and equipment shall be selected from the latest PGSC (Product Group Service
Codes) list. .As stipulated, Type A materials, shall be identified by duty and specification
only, not by the manufacturer. In the selection of materials and equipment, building services
designs shall show a preference for the use of local, and GCC, manufacturers.
- Equipment Schedules
- Wiring Diagrams
Building services design should normally include updating the drawings to “As Built”.
Minimum dimensions for depths of cover and for separation between services are shown on
company Standard Drawings STD-2-1404.
The Building Services design shall include, but not be limited to, overall scheme design,
sizing of equipment and pipe work and coordination with other service.
District chilled water service installations should comprise buried mains served from a
chiller compound suitably located to reduce the environmental impact, particularly noise, on
adjacent buildings. The chiller compound pump room may be combined with an electrical
substation in one building. Allowance should be made for future expansion of district
chilled water schemes, and this should be done with minimal costs. For schemes with a high
probability of future expansion, ring main chilled water distribution be provided, with
secondary chilled water pumps at each building. For other schemes, radial distribution may
be appropriate. In any case, the logistic and limits of future expansion should be established
and agreed with the Company.
The interface with the electrical design shall be established with the Company as described
in section 2.19.
The Air-Conditioning & Ventilation system, materials and Equipments shall comply with
the SP-1285-B Specification for Civil & Buildings Utility Services – ‘Air Conditioning
Works’.
Design outdoor conditions should be based on relevant meteorological data for each project
area and shall be subject to Company approval. In the absence of definitive data, the figures
given in Table 20 should be used.
Appendix K includes the following criteria relating to the majority of company facilities.
- Room temperature
- Room humidity
Where criteria are not listed in Appendix K, design indoor conditions should be based on the
CIBSE Guide, Section A1, Environmental Criteria for Design, and shall be subject to
Company approval.
Normally, humidity control should not be necessary. However, the critical psychometrics of
each design should be checked to ensure that reasonable comfort conditions are always
achieved.
With diversity and standby requirements taken into account, air-conditioning equipment
should be sized to have a minimum overcapacity of 15%.
Water chillers shall be outdoor, package units located within a secure enclosure. An access
gate shall be provided for each chiller and external lighting shall be provided for
maintenance purposes.
- Pressurisation unit
Pipe work and cables between chillers and pump room should be directly buried.
2.16.2.2 Controls
In the selection of water chillers, proper account shall be taken of low load operation. In
any case, chillers should be capable of running at 25% full load or less.
One primary pump should be provided to run with each chiller, with one additional pump as
standby. Selector control should be provided for both chillers and pumps so that any pump
may be selected to run with any chiller. The lead pump should also act as jockey pump in
the event that no chiller is required to run.
Pipe work should be set out to facilitate draining down at low points and automatic venting
at high points. Provisions shall be made to allow the flushing of the complete chilled water
circuit.
The design of battery room ventilation system shall fully comply with the requirements of
DIN 57510/VDE 0510.
All cells in which the electrolyte is in aqueous solution give off hydrogen and oxygen during
charging, the major gassing occurring towards the end of the charging or during boost
charging. Typical boost charging cycles are for 8 hours every 6 months. An explosive
mixture is formed when the hydrogen concentration, by volume, in air exceeds 3.8%.
A safe dilution (20% of the above) will be maintained using the following formula.
Q = 0.055 x N x I
Where,
Q = Airflow in m3/h
Inlet air should be introduced at low level, from the building airconditioning system, and
mechanically exhausted to atmosphere at as high a level as possible, to avoid air pockets.
When ventilation is provided as described above, then the battery room shall be classified as
non-hazardous. However, due to possible local concentrations of gas, the exhaust fan
should be suitable for a Zone 2 installation and resistant to the electrolyte.
Substations and switch houses should normally be designed as completely closed structures,
with dust tight construction and cable passages.
The air conditioning design shall include two or more separate installations, which shall be
individually electrically supplied and controlled.
During normal operation, the maximum indoor temperature shall not rise above 350C DB.
In the case of breakdown or maintenance to one of the installations, the maximum indoor
temperature shall not rise above 400C DB.
The maximum supply air relative humidity shall not exceed 90%.
Spare and empty gas bottles shall be separated and stored in an upright-chained position and
housed in a purpose built, well ventilated, shaded and secured enclosure located at least 20
m from combustible materials. Possible air pockets at high level shall be avoided.
Requirements are normally satisfied by the provisions of a cage of tubular frame, chain link
fencing and roof sheeting with an internal separation.
2.16.3.4 Kitchens
The guidelines given below address commercial catering installations, criteria for domestic
kitchens are given in Appendix K.
Often it is not possible to achieve comfort conditions in kitchen cooking areas at all times
because of the extremely high expenditure involved. In such cases, it should be sufficient to
maintain acceptable working conditions.
Generally air should be extracted from cooking and subsidiary areas through double-skin
hoods located over the main cooking and dishwashing equipment. Hoods should be sized to
overlap equipment by 100 mm, to have a minimum face velocity of 0.3 m/s and to have a
minimum clearance of 1900 mm above finished floor level. The hood volume should suit
the equipment covered. 80 – 85% of the replacement air should be provided, as filtered
outside air, at the internal perimeter of the hood. If this part of the replacement air is
supplied outside the hood, it should be 100% outside air-cooled to plenum conditions, say
250C. Ducted, re-circulating systems should not be used because of greasing problems. The
remainder of the replacement air should be drawn from adjacent areas so that a negative
kitchen pressure is maintained to contain odours.
Extract ductwork shall be designed for ease of cleaning, with flanged joints and man-size
access doors, and shall be constructed of galvanised sheet steel, minimum thickness, 1.0
mm. Air velocities should be a minimum of 9 m/s. Extract fans should be treated for
moisture and heat, and attenuators should be avoided.
Comfort air conditioning should be provided by high level fan coil units.
The requirements for fire detection and protection in kitchens are included in SP-1075
Specification for Fire & Explosion Risk Management.
2.16.3.5 Laboratories
Laboratory air conditioning design shall be based on the specific requirements of the
laboratory work. However, the following guidelines should apply.
Laboratory working and solvent storage areas should be provided with an 100% outside air
system, and should be under positive pressure to reduce dust ingress. In interior Oman,
heating should be included for winter morning start up. Ancillary areas, such as offices,
should be provided with separate, re-circulating systems such as fan coil units. Mechanical
exhaust should be provided for chemical and material storage areas, typically at a rate of 6 –
15 air changes an hour, depending on the items stored.
Fume cupboards for use with hydrocarbons should have an acid resistant 18/12 stainless
steel internal fume chamber with integral bench top. The minimum air velocity over a 400
mm deep sash opening should be 0.75 m/s.
Fume cupboards for general use should have 1 mm thick high-pressure plastic laminate on
the sides and solid epoxy resin bench tops. The minimum air velocity over a 400 mm deep
sash opening should be 0.5 m/s.
All fume cupboards should be provided with airfoil sash opening profiles and high-level by-
pass grilles to ensure constant volume airstreams.
Fume cupboard exhaust ductwork shall be constructed of HDPE and shall not contain fire
dampers.
The internal fume chamber, exhaust ducting and exhaust fan shall be classified as Zone 1
hazard. The internal light fittings therefore shall be separated from the fume chamber by an
airtight glass plate. Solvent and gas bottle stores shall be classified Zone 2.
Air conditioning design parameters for temporary buildings, such as transportable units,
should be similar to those for permanent buildings. However, due to inferior thermal
storage characteristics, electric heating may be required.
Condensate drains from indoor terminal units should discharge to wash hand basins, or
sinks, before the trap to ensure that the connection to the drainage system is always sealed.
While drains may discharge into planter areas, the use of soakaways should be avoided.
Pipe work shall not be directly buried, nor chased in floors or walls, but shall be enclosed in
preformed ducts or voids.
Activation of a fire alarm shall cause the shutdown of air conditioning system, unless
continued operation of the system does not cause spread of smoke to outside the area where
the fire has been detected.
Particular attention is drawn to the optimum temperature for multiplication of bacteria and to
the design, operation and maintenance of evaporative water-cooling systems.
2.17 Plumbing
- Potable water,
- Domestic hot and cold water,
- Drainage,
- Liquid petroleum gas,
- Laboratory piped services,
- Fire fighting water,
- Swimming pools,
- Irrigation.
Plumbing installation, materials and equipment shall comply with the following
specifications:
SP-1285-C Specification for Civil & Buildings Utility Services - ‘Plumbing Works’
SP-1285-D Specification for Civil & Buildings Utility Services – ‘Fire Protection Works’
Normally, the primary source of potable water will be provided by the Company, which will
be by outside the scope of the Building Services Project.
The demand, size, location and interface for the potable water main connection(s) should be
established with the Company at preliminary design stage.
Connection to existing potable water mains shall require prior Company approval. The
valve and meter may be supplied and installed, and the service connection made, by the
Company.
Demand will vary with time, location and population. Average and peak consumption
figures should be subject to individual analysis for each system.
However, in the absence of definitive data, the figures in Table 21 should be used for
average demands:
Coast
Interior
- Major intersections,
- Branches off ring mains,
- Regular intervals on distribution mains shall be 400 m maximum spacing.
Valve chambers should be located in areas with easy access but not subject to heavy traffic.
Pipelines shall have facilities for venting air, flushing and cleaning. In secondary
distribution networks, air may be vented through building connections. In pipelines of 300
mm dia or greater, air valves and washouts should be provided at high and low points
respectively.
Water meters shall be provided for each large user, down to and including all Senior Staff
accommodation (married and bachelor), and on the main transmission line for each
distribution network.
Meters should be fitted above ground at building entries, or in valve chambers below
ground.
2.17.1.4 Storage
The capacity and location of main storage tanks should be agreed with the Company. In
general, not less than 24 hours storage should be provided in any distribution system, but
this will depend on the source and location of the water supply.
Main water tanks should be provided with visual level indicators, access ladders, access
manholes, (with adequate provision for safety and lighting) etc. Inlet and overflows should
be close to access points for maintenance purposes.
2.17.1.5 Pumping
Pump sets should be designed to meet forecast peak demands. Constant pressure systems,
with run and standby facility, are preferred.
2.17.1.6 Sterilisation
Potable water systems shall be completely flushed out and sterilised, to the approval of the
Company, before being put into service.
Details of the sterilisation process are given in SP-1285-C Specification for Civil &
Buildings Utility Services – Plumbing Works.
While published data may be used as guidelines, estimated consumption of water should be
based on specific use as well as numbers of consumers and fittings. For example, for Staff
Accommodation Blocks in the Interior, peak demand for HWS is for showers at the end of
shifts.
Number of showers
Section 2.17.1.1 gives typical per capita water demands for different applications.
Systems should be designed for supply directly from the potable water main unless there is a
specific requirement for storage. In any case, drinking water draw offs shall be taken
directly from the main.
HWS/CWS systems shall be vented at all high points and provision for drain-down shall be
provided at all low points.
Treated effluent water may be used to flush toilet in order to conserve water. In such
situation, a separate close system shall be designed to tap from nearest irrigation source.
Refer also 2.17.8.
2.17.2.3 Isolation
The incoming main shall be provided with a stop valve and a drain cock, preferably located
immediately inside the building. The stop valve may be located in a valve chamber adjacent
to the building.
2.17.2.4 Insulation
HWS/CWS pipe work exposed to ambient conditions, concealed in ducts and in false ceiling
voids, and in equipment rooms shall be insulated.
Surface mounted connections to equipment and fittings shall not be insulated but should be
painted.
2.17.2.5 Sterilisation
HWS/CWS systems shall be completely flushed out and sterilised, to the approval of the
Company, before being put into service (see section 2.17.1.6).
All urinal cisterns, and other automatically flushed devices, shall be fitted with a flush
control valve to limit the waste of water.
Control should be by provision of push button flush pipe valves or may be by cistern cold
feed control valves.
Spray assemblies shall be provided for all AWC’s, and for EWCs in public toilets, located
on the right hand side of the pan.
Water to showers should be taken, by a dedicated gravity feed, from a cold water storage
tank. However, if insufficient head is available or the water temperature may exceed 35 0C,
then a connection should be taken directly off the incoming main, immediately after the
main stop valve.
Eye wash stations shall be self-contained units, mounted on wall brackets, located within 10
sec or 30 m of the hazard and such that the water temperature shall not exceed 40 0C.
Units shall flush both eyes simultaneously and deliver not less than 1.5 1/min.
HWS deadlegs shall not exceed the lengths listed in Table 22. When dead legs do exceed
these length secondary HWS pumps shall be installed.
15 mm 12 m
22 mm 8m
28 mm 3m
2.17.3 Drainage
Design of above ground drainage systems shall comply with the requirements of BS EN
12056 ‘Gravity Drainage Systems inside buildings’
2.17.4 Sewerage
This section covers domestic sewage systems that discharge into treatment plants. Sewage
treatment is addressed in section 2.18 of this specification.
Systems should be designed in accordance with BS EN 752 Drain & Sewer Systems Outside
buildings and the following Company Standard Drawing STD-2-1030 Typical Manhole
Details.
Rates of sewage flow vary with time, location and population. Average and peak flow rates
should be subject to individual analysis for each system. However, in the absence of
definitive data, the figures in Table 23 should be used for average dry weather flows
(DWF):
Coast
Interior
Similarly, in the absence of definitive data, peak flows may be taken as 3 times DWF.
Between manholes : 60 mm
Manholes shall be provided at all changes of direction and at all junctions. For straight runs
of pipe work, the maximum distance between manholes shall be 45 m.
2.17.4.4 Interceptors
Grease traps shall be provided at connections from catering installations and should be
located indoors. The use of enzyme dosing shall be considered during design.
Petrol/oil interceptors shall be provided at connections from vehicle workshop and fuel
stations.
The placing of drainage pipe work under buildings shall be avoided wherever possible.
Where unavoidable, pipes shall be laid in straight lines at one gradient. Access shall be
provided to all parts of the drain and flexible joints used at entry and exit to/from the
building.
Pipework passing through retaining walls, footings, ground beams etc., shall be sleeved,
with the same material, and packed with polystyrene or similar. Flexible joints shall be
provided at exits from buildings.
Pumping of sewage should be avoided where possible since, in addition to the extra cost, it
also forms the weakest link in the operation of a sewage system.
While the sewage pumping station design must take account of peak flows, the emphasis on
sizing pumps and the sump together with the levels of the flow switches should be on
keeping the sewage flowing so that potential problems of septicity in the sump and hydraulic
shock at the treatment plant are avoided. A typical flow rate would be 4 times DWF.
Design of LPG systems should follow the recommendations of the following BS Standards:
- BS 5482: Code of Practice for Domestic Butane and Propane Gas Burning
Installations &
Refer section.2.16.3.3.
2.17.5.2 Regulators
Secondary regulators should normally be supplied with each appliance, be fitted after the
appliance isolating valve, be adjustable, and be capable of reducing the gas pressure from
approximately 345 mb to the appliance operating pressure at maximum demand.
For catering and industrial systems, an emergency shut-off fire valve, normally of the
deadweight type, shall be provided in the main supply, upstream of the high-pressure
regulator(s). The valve should be operated manually, from exits, and automatically by the
fire detection system.
Cable or electrically activated systems may be used. Electrically operated actuators shall be
suitable for hazard Zone 1.
The following are accepted temperature ratings for deadweight gas valve fusible links.
Domestic LPG installations shall be carried out strictly in accordance with Company
Standard Drawing PDO-STD-2-1403.
Design of laboratory service should follow the BS 3202: Laboratory furniture & Fittings.
All main distribution pipe work supplying laboratories should be exposed, wall or ceiling
mounted. Branches to fume cupboards, hoods and benches shall be provided with stop
valves within easy reach. Individual ranges of pipe work may be concealed in service ducts,
but should be separated from electrical services. Flammable gas pipe work shall be
accessible over the full length.
The use of demineralised water from plant utilities may also be appropriate, in which case
an ion exchange unit may be required.
Dry and oil free compressed air shall be supplied from a compressor located in separate
equipment room of the laboratory. The compressor should be rated against 7 bar(g) and the
system should include a refrigerated air dryer, a pressure relief valve, regulators, filters and
pressure gauges.
2.17.6.5 Vacuum
The vacuum pump shall be located as directed by the Laboratory custodian. Unless directed
otherwise, the pump should be rated at 1.9 kPa(a). A buffer vessel and/or liquid catcher
shall be provided between pump and suction point.
Typical special gases to laboratory areas are listed in Table 24, which includes hazard
categories and typical off-take pressures.
Butane and Propane and system guidelines are given in section 2.17.5.
Gas cylinders shall be stored in a purpose-built compound, located in an area free from fire
risk and away from sources of heat or ignition, which shall be well ventilated, preferably by
natural means, and protected from direct sunlight and rain by a sloped canopy without air
pockets. Full and empty cylinders shall be stored separately. Inert, flammable and oxidising
gas cylinders shall be segregated.
Oxidising gas cylinders shall be separated from flammable gas cylinders by a minimum
distance of 7 m or by a 1 hr fire barrier. Gas cylinders shall be stored in special racks.
A manifold set shall be provided complete with isolating valves, regulators and safety valves
which shall discharge to open air. Changeover should be manual with an electrically
operated alarm cabinet to give remote warning of cylinder exhaustion.
Electrical supply emergency shut down (ESD) switches shall be provided at each laboratory
room exit. ESD shall be provided for flammable gasses, activated either by gas ESD
switches and/or by the fire alarms.
Piping for flammable and for toxic gases shall include excess flow check valves.
Acetylene, hydrogen and oxygen piping shall include a flashback arrestor. Acetylene piping
shall be so positioned or protected so as not to be exposed to any source of heat.
Hydrogen piping shall include flow-limiting devices, and switch off devices functioning
when higher-pressure drops occur.
Company fire fighting design parameters are set out in SP-1075 Specification for ‘Fire &
Explosion Risk Management’. Brackish water should normally be considered too corrosive
for use as fire fighting water in buildings.
The Company standards for fresh water system materials and equipment shall comply with
the following: SP-1285-D Specification for Civil & Buildings Utility Services – ‘Fire
Protection Works’ and the Company Standard Drawing STD-2-1402: Typical Fire Water
Details.
Hose reels installations should be designed so that the whole of each floor area is protected,
and no part of the area protected is more than 6 m from a hose nozzle, hose extended. Water
supply should cater for a minimum of 3 hose reels operating at any time, with a total flow
rate of 2.3 1/s, at a working pressure of 2.1 bars (g) at the furthest reel.
The firewater installation should be an extension of the firewater mains. Where firewater
mains are not available, connection may be made to the domestic water supply. In such
cases, the connection shall be made before the incoming water main valve and be dedicated
to the hose reel installations, and fitted with an isolation valve a lockable devise. In
installations where the incoming main pipe work is UPVC, the service pipe work is copper,
and the hose reel pipe work is GI, then the GI branch shall be from the UPVC before the
change to copper.
Office areas hose reels should be automatic, swinging, recess type with 25m of 19mm hose.
Industrial area hose reels should be automatic, swing open, wall type with 30m of 25mm
hose.
2.17.7.2 Hydrants
Tanks shall store water for both hydrant and hosereel supply, and should be sized to hold
sufficent water to supply 3 fire fighting jets, 19 mm nozzles, at 8.3 l/s for 45 minutes, i.e.
67.5m3 minimum. Tanks used for combined storage shall have a dedicated firewater outlet,
and a dedicated and secure firewater storage volume.
Below ground storage, such as swimming pools, with suction hose hydrants may be
appropriate.
Package fire pump sets shall be sized to supply 41.5 l/s with a minimum 4 bar(g) pressure at
the farthest hydrant.
2.17.8 Irrigation
Treated effluent (TE) from sewage treatment plants should be used for the irrigation of
Company community area soft landscaping.
TE irrigation applications shall comply with the requirements of the Ministry of Regional
Municipalities and Environment.
For some applications, it may be necessary or desirable to use potable water (PW). It is
therefore necessary to check directly with MRME Engineers on all such issues. In addition,
irrigation for Company residences should be taken off the dwelling PW supply, after the
water meter. In either case, the irrigation system demand should match the quality and
quantity of water available. The irrigation system shall comply with SP-1285-C
Specification for Civil & Buildings Utility Services – Plumbing Works & the following
Company Standard Drawings STD-2-1400: Typical Irrigation Details & STD-2-1401:
Typical Potable Water Details.
2.17.8.1 Demand
Irrigation water demands should be determined for individual schemes taking account
evaporation rates, soil conditions, salinity and consequent leaching requirements and the
method of irrigation.
Table 25 sets out typical figures for the maximum water required for mature planting in the
summer based on automatic or semi-automatic drip irrigation systems. Demands would
increase markedly if non-automatic irrigation were employed during daylight hours when
evaporation rates are very high. The figures given do not include for leaching.
Further details of planting requirements are given in SP-1279-Q Specification for Civil &
Building Construction – ‘Landscaping Works’.
Shrubs 16 litre/shrub/day
Hedges 12 litre/m/day
Grass 10 litre/m2/day
System Components
Distribution pumps
Filters
Control panel
Washouts
Sub mains
Pressure regulators
Isolating valves
(Contd.)
Laterals
Spray sprinklers
2.17.8.3 Storage
TE should be held in storage tanks similar to what is described in section 2.17.1.4. For large
TE irrigation systems, it may be preferable to provide more than one tank, strategically
located. Tanks should be sized to hold two days demand.
Storage tanks for TE shall be identifiable as not containing drinking water. Signage should
be in Arabic and English and the tanks should be painted green (even if they are constructed
of concrete).
Systems should be designed to operate 8 h a day in two equal periods, morning and evening.
A run and a standby pump and pressure vessel should be provided together with a stainless
steel core filter with a fine-hole element.
Pump power and auto-changeover control should normally be incorporated in a main Motor
Control Panel such as that provided for a sewage treatment plant. Pump auto-start should be
initiated by a relay in the Irrigation Control Panel described in section 2.17.8.5.
External irrigation control systems should comprise electro-mechanical zoned control panels
and zone solenoid valves. Controls for local small irrigation systems, such as those in
Company residences, may comprise similar solenoid valves controlled by a local timer.
Drip systems generally operate best under pressure of 1 to 3 bars. Pressure regulators,
before the zone solenoid valves, may be required to maintain these limits.
TE irrigation water pipe work shall be pigmented green to distinguish from PW.
2.17.8.7 Sprinklers
Since spray sprinklers normally require PW irrigation (refer section 2.17.8.), and incur
higher evaporation losses compared with drip emitters, their use should be avoided where
possible. However, sprinklers should be used for lawn irrigation since emitter systems often
leave blemishes.
Table 26 sets out typical emitter allocations for different plants, designed to apply the
quantities of water given in Table 25.
For Swimming Pools refer SP-1280 Specification for Swimming Pools – ‘Design &
Construction Guidelines’.
Installation shall comply with the regulations of the Ministry of Regional Municipalities and
Environment – MRME – which will normally require an Environmental Impact Statement.
The Company focal point for liason with the MRME is the Environmental Advisor,
Corporate HSE department.
This section primarily covers treatment of domestic, biodegradable, sewage. The treatment
and controlled disposal of industrial, non-biodegradable, waste shall be determined in
conjunction with the Company in each case. The preferred process shall be by sewage
treatment plant with all the treated effluent used for irrigation purposes. For temporary
facilities, facultative ponds may be provided. In remote locations, with population
equivalent up to 100, septic tanks with soakaways may be provided, subject to Company
approval. In specific cases, holding tanks and sludge gulpers may be appropriate. For very
low population equivalents, chemical toilets may be appropriate.
STD-2-1034: Soakaways
The location of sewage treatment plant should take the following factors into account.
Treatment plant throughout and peak flows should be determined as detailed in section
2.17.4.1.
Treatment should be by the activated sludge process with extended coarse bubble aeration,
chlorination and tertiary filtration, should be collected in a holding tank, and be used for
irrigation purposes. Water retaining structures of epoxy painted reinforced concrete, above
ground, should be preferred.
Control panels, pumps, filters and blowers should be housed in a naturally ventilated block
work with a telephone and external visual fault alarm.
An overflow pond should be provided for start-up, while process biology is being
established, and for maintenance purposes. Sludge should be collected in drying beds.
Potable water should be provided to a hand-wash trough and to a shower Hose bib taps,
which may supply treated effluent, should be provided at strategic locations for general
cleaning purposes. Treated effluent outlets shall be labelled “NOT DRINKING
WATER”, in Arabic and English.
Provision should be made for maintenance vehicle access and the whole of the sewage
treatment area should be secured within a Type of C fence. Photocell activated external
lighting should be provided around the main plant.
The sewage treatment plant should include, but not be limited to, the following components.
System Component
(Contd.)
Walkway lighting
Auto-reset
PH
Chlorine
Measuring cylinders
(Contd.)
9. Test kit (contd.) BOD5 should normally be measured at the Company facilities
The sewage treatment process and control philosophy should be agreed with the Company
during the preliminary design of each plant.
Sewage treatment plant shall comply with the regulations of the Ministry of Regional
Municipalities and Environment Table 27 gives current requirements in mg.l or ppm (unless
otherwise stated). For definition of A and B, refer Table 28.
(Contd.)
Table 28, below, provides details of the re-use of wastewater from a sewage treatment plant.
Wastewater quality shall at all times be within the limits that are set out in Table 27.
Area A B
Method of Spray or any other method of arial irrigation not permitted in areas
Irrigation with public access unless with timing control.
Facultative Ponds shall require special permit from MRME and PDO Corporate HSE
department. All Facultative pond shall be lined.
Facultative ponds should be sized on the basis of 2 months holding excluding losses. The
maximum holding level should be at a depth of 800 mm to achieve a reasonable balance of
aerobic and anaerobic action.
Bunds should be constructed of late-rite fine grade, maximum 40µm, in layers of 150 mm,
well compacted up to 95% modified AASHTO. The internal bund gradient should be 1:1.5
maximum, top bund widths should be 1000 mm minimum and the external bund gradient
should be 1:2 maximum. The external bund face may have riprap. The height of the bund
should be 1200 mm above the floor of the pond.
The whole of the evaporative pond area should be secured within a Type G fence.
The design of septic tanks with soakaways should comply with the Company Standard
Drawing listed in section 2.18.
The design of pits for the collection of hydrocarbon waste shall comply with the Company
Standard Drawing STD-2-4025 and other standards listed in section 2.18.
This section covers the design of building services low voltage (LV), 415V/3ph/50Hz,
electrical distribution installations and extra low voltage (LLV), 30V and below,
instrumentation installations. High voltage (HV), rated above 415V, installations are not
part of the building services design scope nor are LV vital supply installations. The scope
of, and interface between, LV and HV electrical designs shall be established with the
Company at preliminary design stage. Electrical building services installations include:
- LV Electrical Supply
- Small Power
- In-door Lighting
- Emergency Lighting
- Outdoor Lighting
- Lightning Protection
- Telecoms
- Datacoms
- Audio
- Nurse Call
The entire electrical installation shall be designed to be suitable for the environment and
climatic conditions prevailing in the Sultanate of Oman.
Building services electrical supply design should normally comprise input to the design of
the LV main switchboard and earth bar, which should be part of the HV design scope,
together with the design of the LV electrical installation from the LV main switchboard
outgoings and the earth bar.
Vital service supply by no-break set (UPS) or emergency generator set shall not be part of
building services design, which shall be confined to local battery backup packages.
Electrical equipment shall be selected to comply with the following rated voltages and
frequencies.
415V/3ph/50Hz, 240V/1ph/50Hz
2.19.1.2 Loads
The electrical design shall include a schedule of connected and instantaneous loads, which
shall be updated during the design process to form the basis of the power supply and
distribution capacity. The figures given in Table 29 may be used for estimating purposes.
The power supply and distribution system should be designed with minimum 25% spare
capacity to accommodate changes and future expansion.
The overall system power factor, inclusive of reactive power losses in transformers and
distribution system equipment, shall not be less than 0.8 lagging at rated design load.
The voltage drop in cables between LV main switchboard outgoings and consumer terminals
shall not be more than 5%, based on continuous maximum current loading and rated voltage.
Moreover, during the starting and stopping of heavy loads, such as chiller compressors, the
transient voltage depression at the terminals of any motor shall not be more than 20% of the
rated equipment voltage.
Contractor Facility
While the sizing of above ground cables shall be in accordance with the IEE Regulations
(refer section 1.4.3 for the IEE), a basic de-rating factor, depending on cable size and type,
shall be used for underground cables. The figures given in Table 30 shall be used a catchall
factors.
Table 30: Overall De rating Factors for Underground LV Cables (Note: Not
applicable to cable groups)
LV cables sizes 16 mm2 and above shall be copper conductor, cross-linked polyethylene
insulated, steel wire armoured, polyvinyl chloride sheathed (XLPE/SWA/PVC).
LV cables sizes 2.5 mm2 to 10 mm2 may be PVC insulated, copper braid armoured, PVC
sheathed, (PVC/SWB/PVC).
2.19.1.6 Earthing
Earthing systems shall be provided in accordance with SP-1099 Specification for Electrical
Installation Practice section 2.3, ‘Earthing Systems’. The system of earthing shall be TN-S,
that is, protection against indirect contact obtained by earthed equipotential bonding and
automatic disconnection of supply.
Minimum ring cable size shall be 70 mm2, minimum radial cable size shall be 25 mm2.
Appendix L includes the following small power requirements relating to Company facilities.
- Power outlets
- Shaver outlets
- Hand dryers
- Airconditioners
- Ventilation fans
- Water heaters
- Cookers
- Refrigerators
- Insectocutors
SP-1099 Specification for Electrical Installation Practice, gives the Company Electrical
Standards for the following.
- General Requirements
- Cable Installation
- Earthing Systems
- Hazardous Area
- Equipment Installation
The Company Electrical Standard Drawings lists are contained in SP-1105 Specification for
Electrical Standard Drawings List.
Electrical designs shall include distribution board and feeder pillar single line diagrams
showing:
- Sub circuit ways, outgoing feeders, MCB/RCD/ELCB protection ratings, wire sizes
and sub areas served.
Distribution boards shall incorporate residual current type earth leakage circuit breakers to
provide discriminatory protection as follows.
Distribution boards shall not be located within toilets or ablutions. Neither power outlet nor
switch shall be located within 1 m of a water source, or under a water pipe.
A means of identifiable local isolation shall be provided for each connection to electrical
equipment.
All single-phase loads shall, as far as is practically possible, be evenly distributed over the
phases.
2.19.2.4 Cables
Cables in conduit or trunking shall be copper conductor, PVC insulated. Minimum size
shall be 2.5 mm2.
PVC conduit shall be used only inside buildings in locations not liable to mechanical
damage. Only GI conduit shall be used for external work. Minimum conduit size shall be
20 mm. Design drawings should indicate the number and use (line, neutral and protective
earth) of cables in each conduit.
GI trunking should be used instead of multiple conduit runs. Trunking that is intended for
the accommodation of different services shall be divided into separate compartments to
provide complete cable separation.
Steel conduit and trunking shall be electrically and mechanically continuous throughout.
Earthing and bonding installations shall be shown on the electrical design drawings. All
metallic electrical equipment enclosures shall be earthed as described in section 2.19.1.6.
Exposed metalwork of all conduits, trunking, ducts, sheaths and armouring of cables, and all
fixed metalwork which is in reach of electrical apparatus, shall be bonded and earthed. Such
other fixed metalwork required, to be bonded and earthed shall include exposed metal pipes,
sinks and tanks.
The earth bonding connection to any water services entering a building shall be as near as
possible to the point of entry, after the isolation valve.
Minimum cable size for bonding metal pipes, sinks and the like shall be 6 mm2.
General requirements for the illumination of Company facilities are given in Appendix L.
Where requirements are not listed in Appendix L, illumination levels should follow the
standards listed below: Indoor lighting design should comply with the recommendations of
the following.
2.19.3.1 Luminaries
As well as first cost, lamps should be selected for long life, giving reduced maintenance and
replacement costs, and low energy consumption. Where special requirements for colour
rendering exist, they should be met. Incandescent lamps should only be used for decorative
purposes. Low pressure sodium discharge lamps should not be used since they represent a
fire hazard in the event of breakage. Table 31 gives typical lamp selections for standard
applications.
Application Lamp
Fluorescent Ex e
Zone 1 & 2
HP discharge Ex d
Luminaries located in ablution and toilet areas shall be protected to IP54, in special cases,
for example, where cleaning is by water hose, IP55 may be required. Light switches in
ablution and toilet areas shall be pull cord operated.
Emergency lighting systems cover escape route lighting, exit sign indication and vital
lighting.
- Provide illumination along such routes to allow safe movement towards and through
the exits provided.
Ensure that the fire alarm call points and fire fighting equipment provided along escape
routes can be readily located.
Escape route and exit lighting shall be located at each exit door, emergency exit door, and
where necessary to identify potential hazards, that is,
- At corridor intersections
- At stair flights
General requirements for escape route and exit lighting are given in Appendix L.
An un-switched power supply shall be provided to keep the battery backup packs on charge,
and to sense mains failure.
Emergency lighting system design, installation and implementation shall confirm to the
requirements of BS 5266, Emergency Lighting.
Fixed escape route lighting shall actuate within 5 sec of normal lighting failure.
Illumination should be not less than 0.2 lux.
Exit light fittings should be maintained, self-contained slave units, with 3 hour battery
backup.
In cases where vital lighting is required for operational purposes, battery backup conversion
kits should be used in a proportion of the standard light fittings.
Appropriate vital illumination levels should be calculated in each case, but in the absence of
definitive data, the number of vital lamps as part of the total number of lamps may be
determined using Table 32.
Administrative Area 5%
Outdoor lighting installations shall comply with SP-1099 Specification for Electrical
Installation Practice section 2.5.5 Lighting.
Outdoor lighting fixtures shall be located a minimum distance of 0.5 m from the face of
roadway kerbs and a minimum 1.5 m from the face of car park kerbs.
Polycarbonate diffusers shall not be used unless they are certified as UV resistant.
Table 33 also gives minimum maintained illumination levels for outdoor lighting.
The Company fire detection and alarm design parameters are set out in SP-1075
Specification for Fire, Explosion & Risk Management. General requirements are given in
Appendix L. For the fire detection and alarm equipment and materials shall comply with
the requirements as given in SP-1285-D Specification for Civil & Buildings Utility Services
– ‘Fire Protection Works’. The above are considered as being the minimum standard,
however each project shall be reviewed for particular requirements at the design stage.
Power supplies for fire detection and alarm systems shall include a standby battery and
automatic charger, and shall be designed so as not to become inoperative in the event of
failure of the power supply. In general, stand by power supply shall be designed in
accordance with DEP 33.65.50.31-Gen. ‘Static DC Uninterruptible Power Supply (DC UPS)
Units’.
The main supply feeding the local annunciator panel shall be connected to a dedicated
circuit way on a distribution board which is part of the main switch panel. No other service
shall be connected to this circuit way and, where MCBs are used, the one serving the fire
protection system shall be coloured red and labelled, white/red/white, FIRE ALARM-DO
NOT SWITCH OFF (consideration should be given to providing a key switch; the key
being held by the fire officer). The main supply cable should follow the least hazardous
route available.
The battery backup power supply shall provide at least 24-hour of system operation plus 15-
minute of full alarm.
The battery charger shall be capable of restoring the battery to full capacity within 8 hours
from fully discharged condition. Fault monitoring and alarm indication shall be provided
for:
A closed circuit principle shall be used, and all wiring shall be continuously monitored such
that any of the following conditions cause a FAULT indication at the local annunciator
panel.
c. Earth fault.
The control circuitry shall be so arranged such that none of the above conditions cause the
fire alarms to sound. Monitoring of the system shall be intrinsic in the control circuit design
and shall be automatic in operation, and shall not require manual operation of switches or
other apparatus.
Large buildings shall be suitably zoned in accordance with BS 5839 Fire detection and
Alarm system for buildings.
The local annunciator panel shall be located at the building main entrance and shall be
visible from outside the building. The panel shall indicate zone FAULT, and zone FIRE
which shall be activated by manual call points and automatic detection systems. Activation
of one zone alarm shall operate audible alarms on all zones. Activation of one zone alarm
shall also shutdown airconditioning systems in all zones except for systems that do not cause
the spread of smoke outside the area of the fire. FAULT and FIRE alarm shall be relayed
to a central mimic panel, at a location specified by the Company.
2.20.2 Cables
Fire alarm and detection cables shall be segregated from other electrical services, including
those of similar voltage and frequency.
Cables shall be protected by armour, conduit or trunking. Buried cables shall have steel
wire armour and cables encased within building fabric may be in PVC conduit. Cables
should be exposed only in industrial applications.
Cables should be single copper conductor, minimum size 2.5 mm2 for low voltage (240v)
and minim size 1.13 mm2 for very low voltage (to 30v).
Mineral insulated cable should not normally be required for fire detection and alarm
systems.
Lightning protection requirements, if any, should be based on the factors listed below and
shall be agreed with the Company.
- Exposure risk
- Use of structure
- Type of construction
- Location topography
Lightning protection system designs should follow the requirements of BS 6651, Code of
Practice for Protection of Structures Against Lightning.
The design of telephone distribution systems shall be agreed with and approved by the
Company Telecommunications Projects Department (TCT). The building services design
shall include, but not be limited to, allocation of reserved rights of way, external layouts,
internal layouts and schematics. A key sheet may also be required.
The project scope of work, and the interface between the building services contractor and
the telecoms contractor, shall also be agreed with TCT. Normally, this will exclude the
pulling and the terminations of external telephone cable but will include the distribution
points, telephone outlets, and terminations at the distribution points, conduit and wiring, and
terminations at the outlets.
Company supplied materials, which are free issue to the building services contractor, shall
be specified by TCT. Normally, they will include:
- Underground ducting
- Distribution boxes
- Manhole accessories
The Company Standards for cable laying, manhole construction, duct installation and for
installation within buildings is given in PDO-ERD-71-01, Installation of Underground and
Internal Telephone Cable Networks.
The scope of building services design should normally be confined to the provision of
distribution ways, conduit, trunking or trays, and outlet points together with spatial
requirements for equipment.
The scope and design shall be agreed with approved by the Company Telecommunications
Department (TCT).
Normally, provision for TV shall be confined to built-in conduit and outlet points.
However, in cases where reception for individual buildings is not possible, a central antenna
system may be provided. For camps in the Oman Interior, a VCP system, as well as a
satellite dish, may also be included.
Concept design shall be part of the building services scope with detail design provided by a
Specialist Vendor. Both concept and detail design shall be subject to Company approval.
Concept and detail design scopes shall be as described in section 2.22.2. General
requirements for Nurse Call systems are given in Appendix L.
Appendices
Appendix A: Glossary of Definitions & Abbreviations
Appendix F: Skirting
Appendix G: Ceilings
Appendix J: Ironmongeries
For the purposes of this document, the following definitions, terminology and abbreviations
shall apply.
the : The party with which the Company has entered into a Contract
Contractor
Manufacturer : A Party responsible for the manufacture of equipment and services to
perform the duties specified by the Consultant or the Company.
Worksite : The land and other places on, under, in or through which the Works
are to be executed.
the User : The Company, and/or Consultant, designate using this document.
Temporary : Any member or structure which needs to withstand loads and forces
Structures of a temporary nature, such as scaffolding, erection bracing, steel
props, commissioning facilities, etc. The word ‘temporary’ shall be
understood as a short period, limited to maximum of 2 years.
A.2 Abbreviations
B : Bottom
BS : British Standard
BWK : Brickwork
CP : Code of Practice
DIA : Diameter
DRG : Drawing
EF : Each Face
EW : Each Way
FF : Far Face
FS : Full Size
GI : Galvanised Iron
HOR : Horizontal
HP : High Pressure
HW : Hardwood
HV : High Voltage
(Contd.)
JE : Junior Employee
JS : Junior Staff
LV : Low Voltage
MAX : Maximum
MIN : Minimum
N : Neutral
NF : Near Face
No. : Number
PE : Protective Conductor
PW : Potable Water
RC : Reinforced Concrete
(Contd.)
SP : Specification
SS : Senior Staff
STD : Standard
T : Top
TE : Treated Effluent
UV : Ultra Violet
VERT : Vertical
The abbreviations used in this document for different building types are given in Table 34.
ABL : Ablutions
ACC : Accommodation
(Contd.)
(Contd.)
KIT/1 : Kitchen – SS
KIT/2 : Kitchen – JS
KIT/3 : Kitchen – JE
LAB : Laboratory
LAU : Laundry
MOS : Mosque
(Contd.)
OFF : Office
SCH/2 : Kindergarten
SHO : Shop
(Contd.)
STO : Store
(Contd.)
WOR : Workshop
The abbreviations used in this document for different room types are given in Table 35.
BATH : Bathroom
BED : Bedroom
BAKE : Bakery
BAR : Bar
CANT : Canteen
CLRM : Classroom
CORR : Corridor
(Contd.)
KTCH : Kitchen
LDRY : Laundry
LESR : Leisure
LBRY : Library
LIFT : Elevator
MORT : Mortuary
PTRY : Pantry
RECP : Reception
RSNT : Restaurant
(Contd.)
SH : Shower
SL : Sluice
SHOP : Shop
STWL : Stairwell
TV : TV / Video Room
(Contd.)
WARD : Ward
WC : Toilet
WKSP : Workshop
25 mm thick 0.58
(Contd.)
Boards
6 mm 0.14
Glass Fibre
Roof Boarding
25 mm thick 0.12
32 mm thick 0.14
(Contd.)
Steel 77.22
Tiling, Roof
0.48
Redwood 5.50
Note: For Abbreviations of Building Types & Room Types refer Tables 34&35 in Appendix B.
DUCT 1.5 W7 F8 S7 C2 D9
ELEC 2.0 W7 F8 S1 C2 D9
ENTR 2.5 W1 F3 S1 C3 D9
EXTR 2.5 W3 F6 S8
ST/K 2.5 W1 F3 C2 D9 G6
STWL 3.0 W1 F1 S1 C3
ACC/1
WC 1.5 W2 F4 S4 C3/5 D9 G10
BATH 1.5 W2 F4 S4 C3 D9 G5
DINE 2.0 W1 F3 S1 C3 D9 G6
DUCT 1.5 W7 F8 S7 C2 D9
ELEC 2.0 W7 F8 S1 C2 D9
EXTR 3.0 W3 F6 S8
ST/K 2.5 W1 F3 S1 C2 D9 G6
STWL 3.0 W3 F8 S7 C3
BED 1.5 W1 F3 S1 C3 D9 G7
ENTR 3.0 W1 F3 S1 C3 D9
AA/3
EXTR 3.0 W3 F6 S8
STWL 3.0 W3 F8 S7 C3
WC 1.5 W2 F4 S4 C3 D9 G5
EXTR 3.0 W3 F6 S8
SH 2.0 W6 F7 S4 C3 D11
STWL 3.0 W3 F8 S7 C3
WC 1.5 W2 F4 S4 C8 D11
BED 1.5 W1 F3 S1 C8 D9 G8
ELEC 2.0 W7 F8 S7 C2 D9
EXTR 3.0 W3 F6 S8 C8
ST/G 3.0 W1 F3 S1 C3 D9
EXTR 3.0 W3 F6 S8
ST/B 7.5 W1 F8 S1 C2 D9
ST/D 7.5 W1 F4 S1 C2 D9
ST/G 5.0 W1 F4 S1 C2 D9
ST/K 7.5 W1 F4 S1 C2 D9
ST/P 5.0 W1 F4 S1 C2 D9
WC 2.0 W1/2 F4 S4 C8 D9 G5
EXTR 7.5 W3 F6 S8
EXTR 7.5 W3 F6 S8
EXTR 7.5 W3 F6 S8
OFF 3.0 W1 F3 S1 C3 D9 G-
WC 2.0 W1/2 F4 S4 C2 D9 G5
EXTR 5.0 W3 F8 S8
WC 2.0 W1/2 F4 S4 C2 D9 G5
WC 2.0 W1/2 F4 S4 C2 D9 G5
WC 2.0 W1/2 F4 S4 C2 D9 G5
WC 2.0 W1/2 F4 S4 C2 D9 G5
EXTR 2.0 W3 F6 S8
WC 2.0 W1/2 F4 S4 C3 D9 G6
OFF 2.0 W1 F3 S1 C3 D9 G5
HOS/1 &
HOS/2
ST/H 2.0 W1 F7 S7 C3 D9 G5
MORT 2.0 W1 F3 S1 C3 D3
BED 1.5 W1 F3 S1 C3 D9 G9
RECP 2.5 W1 F3 S1 C3 D2 G-
SL 2.0 W1/6 F4 S4 C3 D9 G6
WC 2.0 W2 F4 S4 C3 D9 G6
WC 1.5 W1/2 F4 S4 C3 D9 G6
EXTR 3.5 W3 F6 S8
CLNR 2.0 W1 F3 S3 C3 D9
CORR 4.0 W1 F5 S4 C5 D1
DINE 4.0 W1 F3 S3 C5 D1 G1
EXTR 5.0 W3 F6 S8
ICE 3.0 W1 F5 S4 C3 D9
ST/G 4.0 W1 F8 S4 C3 D9
TV 2.0 W1 F10 S3 C3 D3 G1
WC 2.0 W1/2 F4 S4 C3 D9 G6
EXTR 4.0 W3 F6 S8
ICE 3.0 W1 F5 S4 C3 D9
ST/G 4.0 W1 F8 S4 C3 D9
TV 2.0 W1 F3 S3 C3 D3 G1
MES/2 &
WC 2.0 W1/2 F4 S4 C3 D9 G6
MES/3
MOS/1 DOME W5 C2 G7
EXTR 2.0 W3 F6 S8
WC 2.0 W1/2 F4 S4 C3 D9 G3
CORR 4.0 W1 F3 S1 C4 D1 G-
OFF/1 &
OFF/2
ELEC 3.5 W1 F8 S1 C2 D9
ENTR 4.0 W1 F3 S1 C5 D1
EXTR 5.0 W3 F6 S8
PROJ 2.5 W1 F3 S1 C3 D9 G7
WC 2.0 W1/2 F4 S4 C3 D9 G6
DINE 4.0 W1 F3 S1 C3 D1 G-
FILE 5.0 W1 F3 S1 C3 D9
EXTR 7.5 W3 F6 S8
WC 3.0 W1/2 F4 S4 C5 D9 G6
WKSP 10.5 W1 F8 S7 C2 D1
EXTR 4.0 W3 F6 S8 C3
WC 2.0 W1/2 F4 S4 C3 D9 G6
EXTR 4.0 W3 F- S8
WC 2.0 W1/2 F4 S4 C3 D9 G6
WC 2.0 W1/2 F4 S4 C3 D9 G6
ST 5/m W1 F4 S4 C2 D3
EXTR 5.0 W3 F6 S8
WC 2.0 W1/2 F5 S4 C3 D9 G5
EXTR 5.0 W3 F- S8
WC 2.0 W1/2 F4 S4 C3 D9 G5
FILE 4.0 W1 F8 S2 C3 D9
ST 2.5/m W1 F8 D9
WARE 2.5/m W7 F8 D3
WC 2.0 W1/2 F4 S4 C3 D9 G5
Type Description
15mm cement/sand render applied in two coats. Primed with one coat PVA
primer/seal and two coats PVA copolymer based putty filled, rubbed down
with fine sandpaper to completely even surface and painted with two coats of
washable and steam resistant emulsion paint – Vinyl Silk finish. (It should
be noted that while Vinyl Silk finish is specified here this may not be always
the case: sometimes Gloss Oil to Dado is required; or Matt finish; or Gloss
finish all over, etc., if in doubt check with the Company and hence the
Client).
Fair faced blockwork and fair faced in-situ concrete. Cleaned down and
flush pointed. Cement/Sand wash bag rubbed, applied over entire surface
and finished to 4.5mm overall thickness with one coat of PVA Copolymer
emulsion paint. Emulsion paint priming coat and one coat roller applied
heavy texturised external copolymer emulsion paint finish coat. Final
texture by sponge or spatula.
Fair faced blockwork walls cleaned down and dampened. Finished to 15mm
overall thickness with two coats trowel. Fibrous Epoxy Plaster applied in
accordance with manufacturer’s printed instructions. Surface blemishes
sanded down with fine sand paper. For Squash courts the wall court
markings are to be made with polyurethane paint.
W5 Mosque Dome
Rendering with steel float finish. One coat of primer sealer, two coats PvA,
two undercoats and two coats of full gloss.
Type Description
Fair faced blockwork cleaned down and flush pointed. Cement/sand wash,
bag rubbed applied over entire surface and finished with 1 coat PVA
Primer/sealer and 2 coats washable and steam resistant emulsion.
Stainless steel angle corner guards 2.0m long to protect all external angles of
walls, including door jambs. Bottom edge level with top of skirting.
Note: Refer Appendix C for wall finishes in different buildings and rooms.
Type Description
Size 150mm x 150mm x 12.5mm shot faced clay floor quarry tiles (BS
6431 type A). Bedded and jointed in cement/sand mortar (1:4) on
cement/sand floor screed. Overall thickness of tiles and screed 50mm or
laid to falls as required.
F6 PC Interlocking Tiles
Type Description
Size of tiles 500mm x 500mm x 7.3mm. Laid with medium stick latex
anti-slip solution on 50mm cement/sand screed, sealed with anti-dust
compound.
Two pack high build epoxy coating. Applied onto 50mm cement/sand
screed. Wire brushed to remove laitence and filled with solventless filter.
Note: Refer Appendix C for floor finishes in different buildings and rooms.
Type Description
S5 Wall tiles with right angle butt to floor with 3mm mastic pointed abutment.
S6 Trunking skirting.
Appendix G: Ceilings
Type Description
C6 Softwood ‘T’ and ‘G’ chamfered match boarding with secret fixing and
clear matt finish (all as detailed).
C11 Metal lay-in ceiling with exposed grid and bagged sound insulation over.
Note 1. Access panels shall be provided and coordinated into ceilings and
: allow proper access to equipment over.
Type Description
D5 As D1 and HW louvres.
D6 As D4 single door.
D7 Flush door with flush side panel for wide furniture access.
D8 As D7 with HW louvres.
D12 By Specialist.
Note: 1. Doors will vary in width to suit the plan, also where required
frames may be storey height and ventilation grilles may be set
into the doors.
Type Description
G1 Low-level fixed lights with high level bottom hung ventilator (1450mm
high, 1250mm wide).
G9 Mid height, fixed light with bottom hung over (800mm wide).
G13 Low level, one sliding, one fixed (2000mm wide) patio door.
Note: Refer Appendix C for window types in different buildings and rooms
Appendix J: Ironmongeries
Pack A B C D E F G H J K L M N O
Mortise latch
Pack A B C D E F G H J K L M N O
(Contd.)
Pack A B C D E F G H J K L M N O
Limit stays
Push plate 1
Note: All Cylinder locks to have 5 individual keys, 3 Sub-Master keys per block/ floor, 2 Builders Master key, and 1 Grand Master.
Building Room A B C D E F G H J K L M N O
ACC/1 BATH a
BED a
DINE a
DUCT a
ELEC a
EXTR
KTCH a
LNGE a
ST/K a
ACC/2 BATH a
BED a
DUCT a
ELEC a
(Contd.)
Building Room A B C D E F G H J K L M N O
ACC/2 EXTR
ST/K a
ACC/4 BATH a
BED a
ELEC a
EXTR
SERV a
ST/K a
STWL
WC a
ACC/5 BATH a
BED a
ELEC a
(Contd.)
BUILDING ROOM A B C D E F G H J K L M N O
ACC/5 EXTR
KTCH
LNGE a
SERV a
ST/K a
WC a
CON/1 - 3 CLNR a
ELE/3 ALL a
EXTR
OFF a
WC
(Contd.)
BUILDING ROOM A B C D E F G H J K L M N O
GAR/1 EXTR
WC a
GAR/2 EXTR
OFF a
WC a
GAR/3 EXTR
ST/F
WC a
GUA/1 ALL a
EXTR
WC
HOS/1 BATH a
ST/M
(Contd.)
BUILDING ROOM A B C D E F G H J K L M N O
HOS/1 EXAM a
OFF a
ST/H a
MORT a
BED a
PTRY a
RECP a
SL a
WC a
TRMT a
HOS/2 REDX a
WC a
(Contd.)
BUILDING ROOM A B C D E F G H J K L M N O
KIT/1/2/3 EXTR
KTCH a
OFF a
MES/1 BAR a
ST/L a
CLNR a
CORR a
DINE a
EXTR a
ICE a
KTCH a
(Contd.)
BUILDING ROOM A B C D E F G H J K L M N O
LNGE a
RECP a
SERV a
MES/1
ST/K a
WC a
TV a
DINE a
EXTR a
ICE a
KTCH a
LNGE a
(Contd.)
BUILDING ROOM A B C D E F G H J K L M N O
RECP a
SERV a
TV a
MOS/1 DOME
ENTR a
EXTR
PRAY a
WC a
MOS/2
OFF/1 To CORR a
OFF/3
ELEC a
(Contd.)
BUILDING ROOM A B C D E F G H J K L M N O
OFF/1 TO ENTR a
OFF/3
EXTR a
OFF a
ST/G a
WC a
REC/5 ELEC a
PROJ a
STND a
WC a
REC/6 EXTR a
SCH/1 To ALL a
SCH/4
EXTR a
KTCH a
(Contd.)
BUILDING ROOM A B C D E F G H J K L M N O
SCH/1 TO SERV a
SCH/4
ST/G a
WC a
WKSP a
EXTR a
SPO/1 ELEC a
EXTR a
SQCT a
WC a
VIEW
SPO/2 ALL a
EXTR a
WC a
(Contd.)
BUILDING ROOM A B C D E F G H J K L M N O
EXTR a
WC a
WC a
WC a
WAR/1 To EXTR
WAR/4
OFF a
WARE
Room Temp Relative Min Fresh Air Min Air Max Noise Min Illumination
Building Room 0
C Humidity %RH l/s Change Per h Rate NR Lux
Project Specific * * * * * *
Standard Rooms
BATH “ “ No 6 40 150
BED “ “ “ No 30 150
CLNR No No No “ 45 100
CONF “ “ “ 6 35 300
CORR No “ No No 40 150
(Contd.)
Room Temp Relative Min Fresh Air Min Air Max Noise Min Illumination
Building Room 0
C Humidity %RH l/s Change Per h Rate NR Lux
Project Specific * * * * * *
Standard Rooms
DARK “ “ No 6 35 *
ALL
DINE “ “ Std 8 40 200
ENTR “ “ No No 40 300
FILE “ “ “ “ 40 300
ICE “ “ “ “ 45 150
OFF1 “ “ “ 4 35 500
OFF2 “ “ “ 4 35 500
(Contd.)
Room Relative Min Fresh Air Min Air Max Noise Rate Min Illumination
Building Room
Temp 0C Humidity %RH l/s Change Per h NR Lux
Project Specific * * * * * *
Standard Rooms
OFF3 “ “ “ 4 35 750
PRAY “ “ “ No 35 150
PROJ “ “ No * 35 150
ALL
RECP “ “ “ No 40 300
SHOP “ “ No No 40 300
SQCT “ “ “ “ 40 500
SERV “ “ “ “ 45 150
SH No No “ 6 45 150
ST/O “ “ “ No 45 150
(Contd.)
Room Relative Min Fresh Air Min Air Max Noise Rate Min Illumination
Building Room
Temp 0C Humidity %RH l/s Change Per h NR Lux
Project Specific * * * * * *
Standard Rooms
TLET No No No 6 45 150
UTIL “ “ No No 45 150
ALL
VIEW “ “ “ “ 40 150
WAIT “ “ “ “ 40 200
WC No No “ 6 45 150
-18± 1??
DPFZ “ “ “ 45 150
(depends)
(Contd.)
Room Relative Min Fresh Air Min Air Max Noise Rate Min Illumination
Building Room
Temp 0C Humidity %RH l/s Change Per h NR Lux
Project Specific * * * * * *
Standard Rooms
ST/P “ “ “ “ 40 150
MORT “ “ No “ 40 150
RECP “ “ “ “ 40 300
ST/M “ “ No “ 40 150
TRMT “ “ “ “ 35 300
(Contd.)
Room Relative Min Fresh Air Min Air Max Noise Rate Min Illumination
Building Room
Temp 0C Humidity %RH l/s Change Per h NR Lux
Project Specific * * * * * *
Standard Rooms
WARD “ “ Std “ 35
HOSP (ALL)
XRAY “ “ “ “ 35 200
ST/K “ “ “ No 45 150
ST/B “ “ * * 45 150
ST/F “ “ * * 40 500
(Contd.)
Room Relative Min Fresh Air Min Air Max Noise Rate Min Illumination
Building Room
Temp 0C Humidity %RH l/s Change Per h NR Lux
Project Specific * * * * * *
Standard Rooms
REC2 “ “ “ “ 40 500
MES (ALL)
ST/E “ “ No “ 40 150
ST/L “ “ “ “ 40 150
SCHO
KTCH Std Std No 6 40 300
(ALL)
ST/B No No * * 45 150
STO (ALL)
ST/C * Std No * 40 150
ST/H “ “ “ * 40 150
ST/M “ “ “ 6 40 150
(Contd.)
Room Relative Min Fresh Air Min Air Max Noise Rate Min Illumination
Building Room
Temp 0C Humidity %RH l/s Change Per h NR Lux
Project Specific * * * * * *
Standard Rooms
Y = qty as rqd
ROOM = internal
A = automatic
E5 FIRE ALARM
M = manual
DRINKING WATER
E13 Qty Y = qty as rqd
COOLER
Standard Rooms Y
ALL BAR Y Y M Y 1 Y Y
BTRY Y A * Y Y
CANT Y Y M Y Y Y
CHRM Y Y Y Y
CLNR Y Y Y
CLRM Y Y Y
CONF Y Y M Y Y Y
CORR Y Y A Y Y
CTRL Y Y M Y Y
DARK Y Y Y Y * Y
DINE Y Y M Y Y
ENTR Y Y A
FILE Y Y Y
GYM Y Y Y Y
ICE Y Y Y
ALL
LBRY Y Y Y Y
LDRY Y Y M Y Y Y Y
LNGE Y Y M Y Y Y 1
OFF1 4 Y 1 1
OFF2 4 Y 2 1
OFF3 Y Y Y Y
PRAY Y Y Y
PROJ Y Y Y Y Y
RECP Y Y M Y Y Y 1
RSNT Y Y M Y 1 Y Y Y
SHOP Y Y 1 Y 1
SQCT Y Y 1 Y 1
SERV Y Y Y
(Contd.)
ALL SH Y Y
ST/O Y Y Y
TLET Y Y Y Y
TV Y Y Y Y
UTIL Y Y
VIEW Y Y
WAIT Y Y Y
WC Y Y
ABL BLD Y M Y
BED 4 Y 1 1 Y
KTCH Y Y Y Y * 1
(Contd.)
ACC/3 BLD Y M Y Y
BATH Y Y Y
BED 1 Y 2 1 1 1
BED 1 1 Y 2 1 1 1
AIR/1 BLD Y M
BAKE Y Y A Y Y Y ?
CDST Y Y * Y *
DPFZ Y Y * Y *
LDRY Y Y Y Y
ST/K Y Y Y
ST/P Y Y Y *
(Contd.)
AUX Y Y Y
CTRL Y Y Y Y
EXP BLD Y * Y
GUA/1 BLD Y
BATH Y 1 Y
BED 3 Y Y 2 2 1 1
EXAM 2 Y Y 1 1
MORT 2 Y 1
RECP 2 Y M Y Y 1 Y 1
REDX Y Y Y
(Contd.)
ST/M 1 Y Y Y
TRMT Y Y Y 1 Y
HOS/ALL WARD Y Y M Y Y 1 1 Y
WC Y 1 Y
XRAY Y Y 1 Y
KTCH Y Y A Y Y * * * Y
PTRY Y Y Y
PREP Y Y M Y
ST/K Y Y
CORR 1 Y A Y
LABO Y Y * Y Y *
LABW Y Y * Y Y *
(Contd.)
ST/F Y A Y Y
REC Y Y Y Y
ST/E Y Y
ST/L Y Y
REC/1-/4 BLD Y M
REC/5 BLD Y M
REC/7 AREA Y M Y
ROS AREA Y
SCH/1-/3 BLD Y M Y
SHO/1 BLD Y M
SHO/2 BLD Y Y
SPO/1-/3 BLD Y M Y
SPO/5 AREA Y Y
(Contd.)
SPO/6 BLD Y M Y Y
SPO/7 AREA Y
STO/1 BLD Y A Y
STO/2 BLD Y M
STO/3 BLD Y A
STO/4 BLD Y M
STO/5-/7 BLD Y M
STO/8 AREA Y
SP User-Comment Form
If you find something that is incorrect, ambiguous or could be better in an SP, write your
comments and suggestions on this form. Send the form to the Document Control Section (DCS).
They make a record of your comment and send the form to the correct CFDH. The form has
spaces for your personal details. This lets DCS or the CFDH ask you about your comments and
tell you about the decision.
Number:
Comments:
Suggestions:
Phone:
CFDH Actions
Comments: