Вы находитесь на странице: 1из 25

NATIONAL INSTITUE OF CONTRUCTION

MANAGEMENT AND RESEARCH, PUNE

SCHOOL OF DISTANCE EDUCATION


 

Post Graduate Programme in Construction Management (PGP CM)


 

Module : 12

Course No. : PGCM 21

Course Title : PROJECT MANAGEMENT SYSTEMS & TECHNIQUES

Assignment No : 1

Registration No: 217-06-11-50971-2191

Submitted by

SRINATH SRINIVASAN

 
SRINATH SRINIVASAN        1                                                 217-06-11-50971-2191

                
 
ASSIGNMENT
 

A New International cricket facility is to be constructed outside a mega city over a 

piece of land. Facility to include:

     1. Capacity of Spectators: 80,000 

     2. Day/Night play facility 

     3. TV Camera platform in six directions 

     4. Safety of players from spectators 

     5. Pavilion for VIPs to sit: 300 seat 

     6. Parking (adequate space for all above)

Time  available  is  16  months  including  monsoon.  Cost  of  construction  need  to  be 

recovered in 5 years. Average cost of Ticket is 100/‐. Approximate 4 matches per year. 

Submit the Project Report:

    1. Identification of Project 

    2. Stages in development of Project 

    3. Work break down structure to undertake the project 

    4. Milestone & CPM chart for corporate control 

    5. Cost of project. 

   

SRINATH SRINIVASAN        2                                                 217-06-11-50971-2191

                
 
PROJECT IDENTIFICATION & FEASIBILITY:-

The primary thing about the any project is its necessity as well as its feasibility. Now 

the necessity of the project like a cricket stadium is created by the people of the city 

as well as a mega city demands a cricket stadium in its vicinity. The feasibility demands 

a deep thought like for a location of stadium i.e. 

 Where can the plant be located? 

 What is the present and future projected cost of resources? 

 The sources for Financing of the project? 

 Are there enough raw materials as well as skilled and productive labour 

available in the area or can be created? 

 Are there adequate electricity and communication facilities available? 

 What political or institutional factors may cease or impede the development 

and operation of the facility? 

Most  projects  start  with  a  need  to  have  a  new  facility  long  before  designers  start 

designs and drawing of the projects and certainly before field construction work can 

commence. Elements of this phase include: 

 Conceptual analysis 

 Technical and feasibility studies and 

 Environmental impact reports 

   

SRINATH SRINIVASAN        3                                                 217-06-11-50971-2191

                
 
FEASIBILITY STUDY OF THE PROPOSED STADIUM

It is abundantly clear that the stage of conceptualization and initial planning is when 

there is maximum flexibility and that this flexibility must be utilized to the fullest to 

achieve maximum benefits in terms of cost saving s and quality. The feasibility study 

would broadly consist of: 

 Identifying and the need for a Stadium 

 The projected cost and long term financial viability of the Stadium

The need for the stadium is obvious and clear. The popularity of the sport and the level 

of matches will ensure high patronage at all times. The stadium should not present 

any  real  pollution  related  or  other  political  &  economic  problems  at  the  outset. 

However, traffic studies should be undertaken to validate the selection of the site for 

the stadium. Thus, the project needs to be defined only in terms of financial viability.  

The projected earnings are as follows: 

1. Stadium Capacity       ‐  80,000 (100% attendance is the norm) 

2. Assuming 95% Capacity    ‐   76,000 

3. Average price of attendance  ‐  INR 100 

4. Income from tickets per match  ‐  INR   7,600,000 

5. @4 matches per year    ‐  INR   30,400,000 

6. For 5 years        ‐  INR   15,20,00,000  

SRINATH SRINIVASAN        4                                                 217-06-11-50971-2191

                
 
It is clear from the above that the revenue from tickets alone will not be sufficient to 

fund and sustain the stadium. Additional sources of income will have to be utilized and 

some of the options are as follows: 

1. Advertising/sponsorship revenue @ 50 lakhs per match 

2. Grants from BCCI & State Cricket Assoc. @ 30 lakhs per match

3. Income from lending out ancillary Grounds / halls for gatherings                       

@ 10 lakhs per year 

4. Income from cricket coaching clinics @ 05 lakhs per year 

5. Income from club house @ 10 lakhs per year 

6. Therefore income from above would be 3.45 crores per year.  

7. Over a 5 year period these earnings would be 17.25 crores 

Therefore the stadium can generate approximately 32.5 crores over a 5 year period. 

Additionally,  it  is  common  practice  for  the  BCCI  to  give  out  additional  grants  for 

construction of such stadiums. The state cricket association (SCA) and the Ministry of 

Sports and Youth affairs could also be approached for additional funds. Local corporate 

bodies could also be approached for funds.  

The  comparative  cost  of  constructing  a  world‐class  facility  is  US$  50  to  60  million. 

Therefore it can be assessed that the project is a commercially viable one and will be 

able to recover the investment over a period of 5 years.  

   

SRINATH SRINIVASAN        5                                                 217-06-11-50971-2191

                
 
PROJECT REPORT

Project report is a basis for communicating what has been planned for the project. In 

this project I have assumed the site in Madurai as there is no other such type of facility 

is  available  yet.  The  city  is  developing  very  fast  in  respect  to  the  social  as  well  as 

economical aspects. The city is well planned and itself is an attractive place with its 

rich cultural heritages. 

CONCLUSION: After going through all these aspects we can conclude that building a 

cricket stadium outside the megacity will be beneficial project not to the cricket lovers 

only but as a profit making business also. 

PROJECT DEVELOPMENT PROCESS

From  conceptualization  to  implementation  the  stages  in  the  development  of 

construction  project  fall  into  broadly  consistent  patterns  but  time  and  degree  of 

emphasis each project takes on its own a unique character. 

An idea of a project passes through six phases before it become a reality: 

 Conceptualization 

 Engineering and design 

 Procurement 

 Construction  

 Commissioning 

 Operation and maintenance 

SRINATH SRINIVASAN        6                                                 217-06-11-50971-2191

                
 
Conceptualization

Most projects start with a need to have a new facility long before designers start 

preparing  designs  and  drawings  of  the  projects  and  certainly  before  field 

construction  work  can  commence.  Considerable  thought  goes  into  broad  scale 

planning. Elements of this phase include

a.  Conceptual analysis 

b. Technical and feasibility studies

c. Environmental impact reports

Engineering and Design

Architects and design engineers primarily handle these phases. Increasingly, however, 

the client operation and utilization of Knowledge and field constructors’ experience 

are  more  strongly  injected  at  this  stage  through  direct participation and  stringent 

review procedures. There are two phase of engineering and design: 

    (i) Preliminary engineering and design  

    (ii) Detailed engineering and design 

PROJECT MANAGEMENT ORGANIZATION

The  basic  ingredients  for  a  project  management  framework  may  be  represented 

schematically  in  Figure‐1.  A  working  knowledge  of  general  management  and 

familiarity with the special knowledge domain related to the project are indispensable. 
SRINATH SRINIVASAN        7                                                 217-06-11-50971-2191

                
 
Supporting disciplines such as computer science and decision science may also play an 

important role. The representation in Figure‐1 reflects only the sources from which 

the project management framework evolves.  

Figure 1:  Basic Ingredients in Project Management

Specifically,  project  management  in  construction  encompasses  a  set  of  objectives 

which  may  be  accomplished  by  implementing  a  series  of  operations  subject  to 

resource constraints. There are potential conflicts between the stated objectives with 

regard  to  scope,  cost,  time  and  quality,  and  the  constraints  imposed  on  human 

material and financial resources. These conflicts should be resolved at the onset of a 

project by making the necessary tradeoffs or creating new alternatives. Subsequently, 

the functions of project management for construction generally include the following:  

SRINATH SRINIVASAN        8                                                 217-06-11-50971-2191

                
 
 Specification  of  project  objectives  and  plans  including  delineation  of  scope, 

budgeting, scheduling, setting performance requirements, and selecting project 

participants.  

 Maximization  of  efficient  resource  utilization  through  procurement  of  labor, 

materials and equipment according to the prescribed schedule and plan 

 Implementation of various operations through proper coordination and control 

of  planning,  design,  estimating,  contracting  and  construction  in  the  entire 

process 

 Development  of  effective  communications  and  mechanisms  for  resolving 

conflicts among the various participants 

The  Project  Management  Institute  focuses  on  nine  distinct  areas  requiring  project 

manager knowledge and attention: 

1. Project integration management to ensure that the various project elements are 

effectively coordinated. 

2. Project scope management to ensure that all the work required (and only the 

required work) is included.  

3. Project time management to provide an effective project schedule 

4. Project  cost  management  to  identify  needed  resources  and  maintain  budget 

control.  

5. Project quality management to ensure functional requirements are met.  
SRINATH SRINIVASAN        9                                                 217-06-11-50971-2191

                
 
6. Project human resource management to development and effectively employ 

project personnel.  

7. Project communications management to ensure effective internal and external 

communications 

8. Project risk management to analyze and mitigate potential risks 

9. Project procurement management to obtain necessary resources from external 

sources 

PROJECT PLANNING & CONTROL

Planning is the basic function of the management. Planning is concerned with ‘how 

and when’ to achieve the predetermined objectives. Planning sets all other functions 

of management viz. organizing, staffing, directing, motivating, coordinating & etc. The 

main objectives of planning are listed below: 

 Analysis 

 Anticipation 

 Scheduling resources 

 Co‐ordination and control 

 Production of data 

The basic components of the project, according to Hallows, are laid out in the figure 

below. 

SRINATH SRINIVASAN        10                                                 217-06-11-50971-2191

                
 
1. Planning is the creative and demanding mental activity of working out what has 

to be done, how, by when, by whom and with what – doing the job in the mind. 

Plans are not just pieces of paper. Plans represent the result of careful though, 

comprehensive  discussions,  decisions  and  actions,  and  commitments  made 

between people and contractual parties. 

2. Planning techniques form the planner’s toolbox. They assist in the analysis of 

the  plan,  organizing  the  information,  and  have  a  crucial  effect  on  the  way  in 

which the plan is communicated to others. Taken together, these two elements 

of planning produce “the plan” a strategy and tactics for the execution of the 

project. In terms of activities, time quantities, resources and perhaps costs and 

values,  now  the  point  is  how  and  by  whom  this  planning  and  planning 

techniques use to convert all these theories of planning and planning techniques 

in to a practical shape. 

SRINATH SRINIVASAN        11                                                 217-06-11-50971-2191

                
 
CONTROL

Planning  can  be  described  as  a  process  of  thinking  in  advance.  It  is  based  on 

experience,  sound  judgment  and  some  quantitative  techniques.  It  deals  with  the 

future and as such there are bound to be uncertainties, which may cause deviations 

from the target proposed to be achieved. So, one should not hope that everything will 

be fine, because plans and schedules do not work by themselves. It is rightly said that 

we  must  plan  the  work  first  and  then  work  the  plan.  So  for  working  the  plans  and 

schedules  effective  controlling  is  necessary.  “Planning  is  looking  forward  while 

controlling is looking back.” 

PROJECT CONTROL COVERS

While doing original planning and scheduling activity duration might have been over 

estimated or under estimated. 

1. Some activities are delayed due to reasons beyond control like change in foundation 

condition, bad weather, monsoon as in this case, non‐availability of certain resources, 

labor  strike,  break  down  of  equipment  etc.  So  covering  these  risks  the  total  time 

allotted  to  complete  the  cricket  stadium  is  16  months. 

2.  Natural  calamities  like  floods,  earthquakes,  epidemic  etc.,  festivals  etc.  

3. Addition deletion or major modification in the work by client.

4. Introduction of new material, equipment or construction techniques. It is necessary 

to review the actual progress against the predetermined targets.  
SRINATH SRINIVASAN        12                                                 217-06-11-50971-2191

                
 
UPDATING NETWORK

It consists of review of the planning and scheduling at regular intervals. But for that 

updating, the information required will be, period at which review is taken either in 

terms of days or weeks. List of activities completed and partially completed with the 

period  required  to  complete  the  balance  of  the  activity  etc.  Now  after  getting  the 

required updating should be done at regular intervals, which depends upon magnitude 

of  work,  rate  of  progress  etc.  At  short  intervals  as  the  scope  of  absorbing  delays  is 

limited as the period advances, for small projects. At certain stages such as foundation 

level, plinth level, sub structure and super structure etc. Whenever new techniques or 

equipment are available , when work has stopped for a long period for some reasons 

the updating of a project also helps in rescheduling of the activities which are delayed 

or lagging behind so that the project can be completed within the stipulated time.  

Calendaring the Network

While preparing the network we consider the working days while on work sits there 

will be holidays such as weekly of day, festivals etc. these holidays have therefore to 

be incorporated in calendaring the network.  

Cost control

Project control must be linked up with the cost. The objectives of the cost control are 

the method must give the program of expenditure so that requirements of fund can 

SRINATH SRINIVASAN        13                                                 217-06-11-50971-2191

                
 
be assessed. At the time of review we should have a clear picture of actual expenditure 

incurred (vs) program expenditure and actual expenditure (vs) the expected returns. 

In  case  deviations,  what  are  the  reasons  and  what  will  be  the  estimated  cost  of 

remaining  portion  of  the  work.  Improper  Cost  estimation  &  Controlling  can  bring  a 

project to a standstill, if the project is under budgeted the project will be stopped mid‐

way, similarly proper planning is to be done stage wise requirement of the funds for 

the various stages of the project & the sources for the same. Without control planning 

loses much of its value. It must be applied continuously to update the plans and to 

enable reconsideration of the workload in the light of what has already taken place. 

PROJECT WORK BREAKDOWN

The project work breakdown process involves splitting of the project works into its 

manageable  constituents  arranged  in  a  hierarchical  order  till  the  desired  level.  The 

work‐breakdown  levels  are  categorized  into  sub‐projects,  tasks,  work  packages, 

activities  and  operations.  These  levels  depend  upon  the  plan  type,  the  nature  and 

complexity of the project and the expected degree of control. The work‐breakdown 

levels for various types of plans are given in the figure below. It may be noted that the 

levels classification is a broad concept and, at times, overlapping of levels may become 

unavoidable. 

These  activities  are  also  called  as  levels,  which  can  be  classified  very  well.  For 

instance the activities of the cricket stadium are:  
SRINATH SRINIVASAN        14                                                 217-06-11-50971-2191

                
 
 Site consolidation 

 Line out and marking  

 Foundation Works 

 Erecting Super Structure  

 Erecting ancillary structures  

 Services – Electrification, Illumination, Plumbing, HVAC, Fire Fighting 

 Finishing Works 

 Pitch development 

 Parking layout and demarcation 

 Clearance, Testing and Handing Over 

 Maintenance (may not be a part of main WBS but should be) 

MODELING AND ANALYZING NETWORKS

The  three  commonly  used  techniques  this  family  are  Critical  Path  Method  (CPM), 

Program  Evaluation  and  Review  Techniques  (PERT)  and  the  Precedence  Network 

Analysis (PNA) Technique. The common features these techniques are that they make 

use of network model for depicting time‐plan of project, apply critical path concept 

for determining project duration and identifying critical activities, and employ network 

analysis  techniques  for  controlling  project  time  object  but  each  technique  has  a 

distinct model and its field of application varies.  

 
SRINATH SRINIVASAN        15                                                 217-06-11-50971-2191

                
 
Network analysis procedure the modeling and analysis of a network involves following 

steps: 

 Defining scope of network 

 Determining activities 

 Developing network logic diagram 

 Structuring model 

 Incorporating activity durations 

 Numbering events/activity 

 Computing critical path 

Criteria for selection of network technique Experience shows that: 

 CPM is best suited for developing sub‐project/task/work package sub‐networks 

having activities with deterministic single‐time duration. 

 PERT is useful for work packages, tasks or sub‐projects involving uncertainties. 

In  such cases, probabilistic approach  of  three‐times (or a mathematical time‐

related function) is used for assessing activity duration.  

 Precedence Network is the most commonly used technique for time planning of 

construction sub‐projects and projects. 

SRINATH SRINIVASAN        16                                                 217-06-11-50971-2191

                
 
COST OF OUR PROJECT

1. Capacity of spectators      =   Rs. 80000 

2. Time limit                =  16 months 

3. Average cost of ticket                          =  Rs. 100 

4. Per year matches                                    =   04 

5. Assuming One match avg spectators  =   Rs. 60000 

6. Earning from match tickets    =   Rs.100 x 60000   

=  Rs. 6000000 

7. Per year earning through matches  =   Rs.6000000 x 4   

=   Rs.24000000 

8. In 5 years earning through matches  =   Rs.24000000 x 5   

=   Rs. 12,00,00,000 

9. Say the built up area for the stadium  =   20000 Sq. m 

10.Cost of construction per Sq. m    =   Rs. 6000 

11.Therefore, Total cost of construction  =   20000 x Rs. 6000   

=  Rs.120,0,00,000 

This cost will be covered in 5 years exactly. 

   

SRINATH SRINIVASAN        17                                                 217-06-11-50971-2191

                
 
CPM/ NETWORK ANALYSIS

Network is defined as the pictorial representation of the activities of a given project in 

the form of arrows, which form an essential element of network. Arrow represents an 

activity, task of operation of the work since activity consumes resources. Arrow has a 

directional sense, which can be represented by an arrow head it is used to indicate the 

general direction of flow of work. It is conventional to show arrows directing from left 

to  right.  Tail  of  arrow  indicates  the  start  of  the  activity  and  it’s  had  indicates  the 

completion  of the activity.  Beginning of completion  of an activity marks a phase or 

stage of work. This is represented by a suitable geometrical figure like circle, triangle 

and rectangle. This is known as event. Events naturally do not consume any resource 

by itself. There is another type of activities, which do not require any resources and 

which  are  basically  imaging  activities  called  dummy  activities,  these  activities  only 

show the interdependency of the activities but doesn’t consume any resource. 

Development of network

Network can be developed in two ways, 

1. Preceding and following activities 

some activities cannot be started unless certain activities are completed. For 

e.g. excavation of foundation must be completed before foundation concrete 

is poured. These types of activities are known as sequential activities 

SRINATH SRINIVASAN        18                                                 217-06-11-50971-2191

                
 
2. Concurrent activities 

A few activities can be carried out concurrently. For e.g. excavation for 

foundation of four walls of a room can be started simultaneously. Let us take 

the case of erecting steel framework (for lightning) on cement concrete 

foundation in a cricket ground, the following operations are identified in the 

network.  

Clearing  and  levelling  the  site,  giving  lineout,  Procuring  material  for  concrete, 

Procuring  steel  for  foundation,  excavation,  formwork  foundation  steel,  Concreting, 

Backfilling, Erection & painting of steel work, Clearing & levelling site, Preparation of 

ground& pitch  

These  are  the  general  activities  for  the  development  of  Master  Control  Network 

(MCN), however we can divide each activity in to sub activity to develop a sub‐ network 

.e.g.  concreting  can  be  divided  as  conc.  In  foundation,  in  boundary  wall,  in 

superstructure etc. the activities of excavation, formwork, concreting and backfilling 

are divided in to two parts to make these activities concurrent to further reduce the 

time of completion and thus cost. 

SRINATH SRINIVASAN        19                                                 217-06-11-50971-2191

                
 
Activity Activities Duration Preceding Following Concurrent
no description
activity activity Activity

Site clearing & 30


A B C
leveling

B Layout 15 B D C

Procurement of 180
C V
material

Excavation for 45
D B E,L
foundation

E Foundation work 60 D F,H,I,J L

F Waterproofing 21 E G H,I,J,M

G backfilling 15 F X

Construction of 90
H E S F,I,J
boundary walls

Construction of 150 K,N,P,R,T,


I E F,H,J
super structure U

Construction of 60
J E Q
toilets

Services work 90 G,N,P,R,T,U,


K I V
Q

Foundation for 25
L D M E
light structure

SRINATH SRINIVASAN        20                                                 217-06-11-50971-2191

                
 
Activity Activities Duration Preceding Following Concurrent
no description
activity activity Activity

Fabrication of 90
structure for
M L V F,H,I,J
lights for d/n
facility

Construction of 100 G,K,P,R,T,U,


N I O
drains Q

Construction of 120
O N S V
Roads

Construction of 90 G,K,N,R,T,U,
P I S
parking area Q

Finishing works 50 G,K,N,R,T,U,


Q J S
in toilets P

M/S railing works 60 G,K,N,R,T,U,


R I S
P

Painting work 90 H,K,N,P,R,T,


S V O
U,Q

Structure of 60
welded wire
G,KN,P,R,U,
T mesh around the I S
Q
Ground for
safety of players

Preparation of 150
U I X G,KN,P,R,T,Q
Ground and pitch

Installation of 15
V S,C W
Gadgets

Commissioning 20
W V X
of Services

X Handing over 5 W

SRINATH SRINIVASAN        21                                                 217-06-11-50971-2191

                
 
ANALYSIS PROCEDURE

The  project  can  be  analyzed  in  a  no.  of  ways,  through  precedence  network  and 

PERT/CPM  networks.  Precedence  network  is  the  way  of  representing  the  project 

through the activity‐on‐node approach. In precedence network, an activity is shown 

on the node, which is represented by a box. The precedence diagram is shown as a 

straight line, called connectors, if an activity a is followed by another activity B, it is 

known as 

Sequential Activity

Sequential activity and it will be represented in CPM/PERT network as in the figure 

given below. However if the some activity A is followed by another activity B, then it 

will be represented in precedence diagram as: 

Sequential Activity

Precedence network is easier to understand than arrow networks to draw as well as 

to understand. It is also easier to explain to a non‐technical person who does not have 

much knowledge about a network.  
SRINATH SRINIVASAN        22                                                 217-06-11-50971-2191

                
 
Now time analysis in both the networks (precedence and PERT/CPM) is done on the 

same lines. Every event is associated with two timings, 

Earliest occurrence (ET) and Latest occurrence (LT) Similarly each activity is associated 

with four times: 

1. Earliest start time (EST)   = Earliest time by which an activity can start. 

2. Latest start time (LST)   = Latest time by which an activity must start. 

3. Earliest finish time (EFT)  = Earliest time by which an activity can be finished. 

4. Latest finished time (LFT) = Earliest time by which an activity must be finished. 

So,  activities  have  to  be  planned  and  schedule  in  such  a  way  as  to  satisfy  these 

constraints without extending the project duration: however if the constraints are of 

critical nature even project duration has to be altered to satisfy them. In the end let us 

give a look at step –by – step procedure for large network, 

1. Prepare project network.

2. Calculate event timings, activity timings & Floats 

3. Prepare a bar chart to suitable scale. List the activities in a proper scale.

a. The activities should be listed in increasing tail event number. 

b. If there are more activities with the same tail event number they should be 

so arranged that head event numbers in increasing numbers
4. First schedule all activities at EST and work out resource requirements. If the 

distribution is not satisfactory find out sum of the squares.
5. Reschedule the activities. Start with the last activity. It should be shifted towards 

LST stage by stage 

SRINATH SRINIVASAN        23                                                 217-06-11-50971-2191

                
 
6. Next activity is then taken up and same procedure is followed till we finish all 

the activities.
7. While  scheduling  activity  from  whose  head  event  more  than  one  activity  is 

emanating, care is necessary. The latter are rescheduled; hence the preceding 
activity  must  be  over  by  the  earliest  time  worked  out  by  rescheduling.  Of 
subsequent activities.

CPM NETWORK

Essentially it was a problem concerned with obtaining tradeoff between completion 

time  of work  and the  cost.  The method  known as  critical  path  method  is  therefore 

based on the assumption that the time required by various activities is known. It is 

deterministic in nature and is not concerned with uncertainties. CPM is more suitable 

in construction situation where some experience in handling similar activities in the 

past is available. 

Critical  Path  Method  is  capable  of  serving  on  the  basis  of  an  integrated  company‐

worldwide management, ranging from pre bid feasibility studies though estimating, 

planning, cost accounting, progress control and financial control. 

Critical Path Method is the path of events having longest duration i.e. A‐B‐D‐E‐I‐N‐O‐

V‐W‐X having duration 482 days=16 months, which is required completion time. 

   

SRINATH SRINIVASAN        24                                                 217-06-11-50971-2191

                
 
CONCLUSIONS & RECOMMENDATIONS

 Successful  pre  construction  planning  and  scheduling  will  go  a  long  way  in 

ensuring that the product is of the desired quality and meets all expectations 

with respect to cost, time and quality. 

 Due to both financial and time constraints, it is essential that thorough control 

be maintained throughout the duration of the project. 

 A conscious effort to adopt sound quality practices must be undertaken. This is 

deemed to be a world class facility. The quality objective is apparent and must 

be adhered to. 

 Adequate  allowance  for  stoppage/slowing  of  work  must  be  made  during 

monsoons. 

REFERENCES

I. NICMAR Lesson Book ‐ Project Management Systems & Techniques 

II. Lt. Col. K.K. Chitkara “Project Management” Tata Mc. Graw,1998 

SRINATH SRINIVASAN        25                                                 217-06-11-50971-2191

                
 

Вам также может понравиться