Time Schedule

NO. Item Start Time Completion Time Duration


1 Construction preparation 28 d 2018/11/22 2018/12/20
1.1 Mobilization 14 d 2018/11/22 2018/12/5
1.2 Construction of Temporary Facilities & warehouse 28 d 2018/11/22 2018/12/20
2 PV field construction 165 d 2018/12/1 2019/5/14
2.1 Civil work 165 d 2018/12/1 2019/5/14
2.1.1 Site leveling 20 d 2018/12/1 2018/12/20
2.1.2 Fencing work 20 d 2018/12/1 2018/12/20
2.1.3 Drilling 62 d 2018/12/21 2019/2/20
2.1.4 Pouring concrete foundation 70 d 2018/12/31 2019/3/10
2.1.5 Equipment foundation construction 71 d 2019/1/10 2019/3/21
2.1.6 Cable trench excavation 70 d 2019/1/10 2019/3/20
2.1.7 Road,drainage and Other civil works 24 d 2019/4/21 2019/5/14
2.2 Electrical & Installation work 80 d 2019/1/21 2019/4/10
2.2.1 Photovoltaic modules support installation 55 d 2019/1/21 2019/3/16
2.2.2 Solar PV modules installation 55 d 2019/1/25 2019/3/20
2.2.3 Inverters and transformers installation 26 d 2019/3/16 2019/4/10
2.2.4 Cablecasting 56 d 2019/2/14 2019/4/10
2.2.5 Grounding 56 d 2019/2/14 2019/4/10
2.2.6 Other equipment installation 30 d 2019/3/12 2019/4/10
3 110KV substation construction 131 d 2018/12/21 2019/4/30
3.1 Civil work 120 d 2018/12/21 2019/4/19
3.1.1 Building construction 90 d 2018/12/21 2019/3/20
3.1.2 Equipment foundation construction 56 d 2019/1/5 2019/3/1
3.1.3 Cable trench excavation 30 d 2019/1/10 2019/2/8
3.1.4 Road,drain and Other civil works 60 d 2019/2/19 2019/4/19
3.2 Electrical & Installation work 61 d 2019/2/9 2019/4/10
3.2.1 Electrical circuit installation 31 d 2019/2/9 2019/3/11
3.2.2 Transformer installation 21 d 2019/3/21 2019/4/10
3.2.3 Miscellaneous equipment installation 26 d 2019/3/16 2019/4/10
3.2.4 Pre-commissioning 10 d 2019/4/11 2019/4/20
3.2.5 Commissioning and ready for power energizing of the substation 10 d 2019/4/21 2019/4/30
4 Transmission line 147 d 2018/11/25 2019/4/20
4.1 Survey,design,approval and Purchase 61 d 2018/11/25 2019/1/24
4.2 Pole and tower foundation construction 30 d 2019/1/25 2019/2/23
4.2 Tower erection 30 d 2019/2/24 2019/3/25
4.2 Pull the electric wire 26 d 2019/3/26 2019/4/20
5 Substantial Completion 1d 2019/5/1 2019/5/1
6 Testing and Commissioning for PV Modules and Whole Plant 60 d 2019/5/2 2019/6/30