DESIGN SUBMISSION PROGRAM (On 05/02/2019)

No. Description Status Revision Planned date Submission date


1) KALUPUR STATION
A Roof slab
1 grid 1-7 GFC 28-11-2018 28-11-2018
2 grid 7-14 CRD R0 13-11-2018
CRD R1 17-11-2018 20-11-2018
CRD R2 29-11-2018
CRD R3 29-12-2018 29-12-2018
3 grid 14-16 CRD R0 24-12-2018 24-12-2018

B Concourse slab
1 grid 1-3 CRD R0 17-11-2018
CRD R1 30-11-2018
CRD R2 10-12-2018 10-12-2018
2 grid 3-7 CRD R0 21-01-2019 24-01-2019
3 grid 7-14 CRD R0 10-02-2019
4 grid 14-16 CRD R0 28-02-2019
5 grid 16-19 CRD R0 28-02-2019

C Base slab
1 grid 1-4 CRD R0 17-11-2018
CRD R1 26-12-2018
CRD R2 11-01-2019
CRD R3 15-02-2019
2 grid 4-7 CRD R0 30-03-2019
3 grid 7-14 CRD
4 grid 14-16 CRD
5 grid 16-19 CRD R0 30-01-2019
6 Temp. base slab CRD R0 12-01-2019 14-01-2019

D Miscellaneous
1 RCC details for OTE CRD R0 03-11-2018
CRD R1 30-11-2018
CRD R2 24-12-2018
CRD R3 14-01-2019
CRD R4 29-01-2019
2 SEM drawing (Concourse & roof) CRD R0 15-12-2019 15-12-2019
SEM drawing (Platform & undercroft) CRD R0 28-02-2019
3 Framing plan & sections CRD R0 29-12-2018 29-12-2018

E Arch. Drawing
1 BIM model CRD R0 29-09-2018 24-09-2018
CRD R1 30-11-2018 29-11-2018
CRD R2 26-12-2018
CRD R3 07-01-2019

2) KANKARIA STATION
A D-walls
1 grid 9-14 CRD R0 20-01-2019
2 grid 4-9 CRD R0 01-03-2019
3 grid 1-4 CRD R0 15-03-2019
4 grid 14-19 CRD R0 30-01-2019
5 grid 19-22 CRD R0 15-02-2019

B Arch. Drawing
1 Drawing CRD R0 07-12-2018 07-12-2018
2 BIM model CRD R0 07-12-2018 07-12-2018

3) NATM SHAFT
A D-walls
1 D-walls on side CRD R0 25-02-2019
2 D-walls on NATM face CRD R0 10-03-2019
3 Strut and waler CRD R0 15-03-2019
4 Base slab CRD R0 30-03-2019

4) CROSS PASSAGE
1 Launch shaft- Kankaria 2 Nos. CRD R0 09-10-2018
CRD R1 10-12-2018
CRD R2 first week of jan-19
CRD R3 20-01-2019
2 Kankaria - Kalupur 3 Nos. CRD R0 30-01-2019

5) NATM
1 Kalupur - contract boundary CRD R0 30-01-2019

6) DBR
1 Station and cut cover CRD R0 06-12-2018 06-12-2018
2 NATM & tunnel CRD R0 12-01-2019 09-01-2019

7) Ancillary building
1 Framing plan Submitted
2 Temp. structure CRD R0 15-02-2019
3 Reinforcement drawing CRD R0 28-02-2019

8) Ramp cut/cover
1 GAD/ Framing plan Submitted
2 Temp. structure R0 01-03-2019
3 Reinforcement drawing - ramp R0 27-12-2018
R1 15-03-2019
4 Reinforcement drawing - ramp 20-05-2019

9) Entry/Exit
A Entrance A
1 GAD/ Framing plan R0 10-02-2019
2 Temp. structure R0 05-02-2019
3 Reinforcement drawing R0 20-04-2019

B Entrance B
1 GAD/ Framing plan R0 10-02-2019
2 Temp. structure R0 15-03-2019
3 Reinforcement drawing R0 30-04-2019
SUBMISSION PROGRAM (On 05/02/2019)
Remarks

Delayed by 7 days

Delayed by 3 days

Delayed by 6 days
Delayed by 2 days

Delayed by 95 days

Delayed by 29 days

Delayed by 15 days
Delayed by 6 days

Delayed by 120 days


Delayed by 7 days

Delayed by 6 days