Вы находитесь на странице: 1из 4

CUSTOMER:

REV.# DATE DESCRIPTION SIGN BILL


Thursday, January 17, 2019 VERSI 7

Pembuatan Resto Bhinneka Bandung

DEPARTEMEN/UNIT KERJA: PMD

BOBOT TOTAL
17% NO. DESKRIPSI / ITEM PEKERJAAN VOL. SAT. PROGRESS %
PEKERJAAN PROGRESS

A Pekerjaan Persiapan
1 Penerangan kerja OP 1.00 ls 0.20% 100% 0.20%
2 Scaffolding pekerja OP 1.00 ls 0.49% 100% 0.49%
3 Keamanan OP 1.00 ls 0.30% 100% 0.30%
4 Pembersihan selama pekerjaan OP 1.00 ls 0.20% 100% 0.20%
5 Akomodasi & Mobilisasi OP 1.00 ls 0.39% 100% 0.39%
6 As Build Drawing OP 1.00 ls 0.20% 0.00%

1.77%

B Pekerjaan Shop Front (A/B)

1 3D ACRYLIC "BHINNEKA RESTORAN PADANG & KAFE" DD 1.00 ls 3.92% 50% 1.96%

Canopy awning DEXSON WATERPROOF(SETARA


2 SUNBRELLA) rangka pipa hollow 4" fin. Spray paint black VR 56.16 m2 8.09% 50% 4.05%
size 15.60x3.60M, SABLON LOGO BHINNEKA

2a Tutup rangka canopy (Mode Ceiling) DEXSON VR 35.20 m2 2.23% 50% 1.12%

Single door alum frame glass non tempered 8mm +


4 VR 3.00 unit 1.24% 0.00%
accessories size 90 x 210 cm

Cover column existing with GRC + pipa hollow + fin paint


5 AP 1.00 unit 0.28% 0.00%
ex dulux cream color

Cover column all wall fin paint (refinish only) with dulux
5a CVL 2.00 unit 0.55% 0.00%
paint

16.31%

C Pekerjaan Palung Area

1 Dinding celcon VR 6.60 m² 0.91% 100% 0.91%

2 Kaca tempered palung 1.00

Drop Ceilling area palung from gypsum fin emultion


3 AP 19.80 m² 1.14% 100% 1.14%
paint with led

Partisi Cover Table Bar for palung with plywood fin.


4 AP 1.00 l.s 2.54% 0.00%
Wooden HPL + ornamen Plywood

4.59%
D Pekerjaan Cashier Area

Table cashier bentuk L dari plywood fin WOODEN HPL


1 AP 1.00 unit 1.50% 0.00%
motif kayu

1.50%

E Pekerjaan Cafe Bar Area

1 Ceilling area (existing) café Bar refinish paint ex dulux CVL 20.00 m² 1.15% 100% 1.15%

Door for Café bar from glass + kusen list frame pipa
2 VR 1.00 unit 1.52% 50% 0.76%
hollow

3 Dinding Partisi GRC t. 1,2 cm + keramik putih VR 15.00 m² 0.78% 70% 0.54%

4 Dinding Partisi Celcon CVL 6.00 m² 0.34% 100% 0.34%

5 Partisi kaca 8mm + frame list VR 15.00 m² 1.90% 50% 0.95%

6 BAR Chair (kaki besi, soft foam) AP 6.00 unit 1.04% 100% 1.04%

6.73%

F Pekerjaan Dining Area

1 Artificial Plants

1a area pilar OP 22.00 m 0.51% 100% 0.51%


CUSTOMER:

REV.# DATE DESCRIPTION SIGN BILL


Thursday, January 17, 2019 VERSI 7

Pembuatan Resto Bhinneka Bandung

DEPARTEMEN/UNIT KERJA: PMD

1c pot bulat + artificial plants OP 10.00 pcs 0.81% 100% 0.81%

1d dudukan pot bulat (besi) OP 2.00 pcs 0.14% 100% 0.14%

Wall partisi area dining with list paint + wash paint ex.
2 AP 77.83 m² 2.69% 50% 1.35%
Dulux

3 Ceilling fin. Emultion paint CVL 165.00 m² 3.80% 50% 1.90%

4 Cover Column structure fin paint only ex dulux CVL 6.00 unit 0.33% 0.00%

7 PLINT AP 46.80 m 1.29% 0.00%

9 Treatment dinding, cat biru ex: DULUX CVL 146.00 m² 3.03% 0.00%

10 Lease plafon profil AP 46.80 m 1.29% 100% 1.29%

10 Ambalan pilar (plywood 18mm, finish wooden HPL) AP 25.00 unit 1.04% 100% 1.04%

11 Pek. Flooring Vinyl (Wooden Vinyl) OP 146.52 m² 4.90% 0.00%

19.84% 0.00%
0.00%
G Pekerjaan Toilet 0.00%

1 Pekerjaan lantai fin keramik ex. Roman CVL 6.00 m² 0.33% 0.00%

Wall partisi toilets area from celcon + dinding keramik


2 CVL 5.85 m² 0.55% 100% 0.55%
ex. Roman

Door for Toilet with solid wood fin. Paint + accessoris


3 CVL 2.00 unit 0.56% 0.00%
(ruko baru lt.1 dan lt.2)

4 Water profing toilets area ex. Casali CVL 5.85 m² 0.14% 0.00%

5 Treatment dinding bata tempel + Cermin AP 1.00 l.s 0.56% 0.00%

6 Wastafel + cabinet AP 2.00 unit 0.88% 0.00%

7 Closet ex. Toto + acesories + pekerjaan CVL 2.00 set 1.83% 0.00%

8 Exhaust uk 30x30 ex. Panasonic FV-30RUN5 CVL 2.00 unit 0.35% 0.00%

Partisi multi kotak kotak area washtafel, finish white


9 AP 1.00 unit 0.69% 0.00%
duco

5.88% 0.00%
0.00%
H Pekerjaan Washing Area 0.00%

43 1 Pekerjaan lantai fin keramik ex roman texture 60 x 60 CVL 18.81 m² 1.19% 0.00%

2 Wall partisi washing area, kontruksi + fin. Paint CV m² 0.00% 0.00%

- Dinding celcon, kolom beton , piping pembungan 4",


CVL 56.43 5.14% 100% 5.14%
lantai beton

Door for washing area size w. 1 m ex. Solid wood +


3 CVL 1.00 unit 0.58% 0.00%
kusen + daun pintu + accessoris

4 Water proofing washing area ex. Casali CVL 18.81 m² 0.45% 0.00%

Jendela awning dari aluminium + glass + accessoris size


5 VR 2.00 set 0.69% 0.00%
60 x 60

8.04% 0.00%
0.00%
I Pekerjaan Kitchen Area 0.00%
CUSTOMER:

REV.# DATE DESCRIPTION SIGN BILL


Thursday, January 17, 2019 VERSI 7

Pembuatan Resto Bhinneka Bandung

DEPARTEMEN/UNIT KERJA: PMD

1 Pekerjaan lantai fin keramik ex roman CVL 78.21 m² 4.96% 0.00%

2 Water proofing kitchen area ex casali CVL 78.21 m² 1.86% 0.00%

3 Ceilling fin.paint CVL 78.21 m² 1.80% 100% 1.80%

4 Peninggian with hebel t.10 cm CVL 78.21 m² 0.90% 0.00%

9.52% 0.00%
0.00%
J Pekerjaan Struktur Storage LT.2 0.00%

Pembuatan partisi storage plywood with fin. paint area


1 CV m² 0.00% 0.00%
storage

- Dinding celcon, kolom beton , piping pembuangan 4",


CVL 56.43 9.10% 100% 9.10%
lantai beton + paint

2 Lantai area Storage keramik ex roman 60 x 60 CVL 18.81 m² 1.19% 0.00%

3 Ceilling fin.paint CVL 18.81 m² 0.50% 100% 0.50%

4 Door ex solid wood + accessories + daun pintu + kusen CVL 1.00 set 0.58% 0.00%

Jendela awning dari aluminium + glass + accessoris size


5 VR 1.00 set 0.35% 0.00%
60 x 60

11.72% 0.00%
0.00%
K Pekerjaan Struktur Mess Karyawan LT3 0.00%

Pembuatan partisi storage plywood with fin. paint area


1 storage '- Dinding celcon, kolom beton , piping m² 0.00% 0.00%
pembungan 4", lantai beton + fin paint+ tangga

CVL 35.00 5.65% 100% 5.65%

2 Lantai area Storage keramik ex keramik roman 60 x 60 CVL 18.81 m² 1.19% 0.00%

3 Ceilling fin.paint CVL 12.52 m² 0.33% 100% 0.33%

4 Door solid wood fin paint natural + accessories CVL 1.00 set 0.58% 0.00%

7.75% 0.00%
0.00%
L Pekerjaan Struktur Area Tandan Air/Toren 0.00%

1 Door from plat besi + daun pintu + kusen + accessoris CV 1.00 set 0.00% 0.00%

Kanopi kecil rangka besi hollow 4" + upvc + fin spray


2 CV 8.00 m² 0.00% 0.00%
paint

3 Reilling tandon pipa besi hollow 4" + fin spray paint CV 11.40 m 0.00% 0.00%

4 Tangga monyet dari aluminium + fin spray paint p.2.5 m CV 1.00 unit 0.00% 0.00%

0.00% 0.00%
0.00%
M Pekerjaan Dudukan Tabung Gas 0.00%
1 Cor pile cap 80 x 80 20 CVL 0.38 m³ 0.35% 0.00%
2 Cor sloof 20 x 50 CVL 2.02 m³ 1.86% 0.00%
3 Cor kolom CVL 2.34 m³ 2.15% 0.00%
4 Cor pelat lantai CVL 1.13 m³ 1.04% 0.00%

5.41%

GRAND TOTAL
99.1% 45.64%

FORM/TLI-PMD/002, Rev.03 Tgl. terbit:


CUSTOMER:

REV.# DATE DESCRIPTION SIGN BILL


Thursday, January 17, 2019 VERSI 7

Pembuatan Resto Bhinneka Bandung

DEPARTEMEN/UNIT KERJA: PMD

1 .

Вам также может понравиться