CRONOGRAMA VALORIZADO DE OBRA

OBRA : “CREACION DE UN PARQUE RECREATIVO EN EL SECTOR VIRGEN PURISIMA EN EL CENTRO POBLADO DE PICHIU QUINHUARAGRA-DISTRITO DE SAN MARCOS-HUARI-ANCASH”

LUGAR : PICHIU QUINHUARAGRA


COSTO DIRECTO: 4,875,911.96
PLAZO DE EJECUCION DE OBRA
PRESUPUESTO
ITEM ACTIVIDADES MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08 PARCIALES S/.
DE OBRA
30 DIAS 60 DIAS 90 DIAS 120 DIAS 150 DIAS 180.00 210 DIAS 240 DIAS

01 ESTRUCTURAS 539,913.82 539,913.82 539,913.82


01.01 OBRAS PROVISIONALES 16,724.65 16,724.65 16,724.65
01.01.01 CARTEL DE OBRA DE 3.60 X 2.50 m 1,729.45 1,729.45 1,729.45
01.01.02 ALMACEN Y OFICINA 4,400.00 4,400.00 4,400.00
01.01.03 CERCO DE OBRA CON POSTES DE MADERA Y TRIPLAY 10,595.20 10,595.20 10,595.20
01.02 OBRAS PRELIMINARES 45,472.80 45,472.80 45,472.80
01.02.01 LIMPIEZA DE TERRENO MANUAL 11,790.00 11,790.00 11,790.00
01.02.02 TRAZO Y REPLATEO INICIAL 11,400.00 11,400.00 11,400.00
01.02.03 TRAZO DURANTE LA EJECUCION DE LA OBRA 10,592.80 10,592.80 10,592.80
01.02.04 SERVICIO DE AGUA PARA LA OBRA 2,240.00 2,240.00 2,240.00
01.02.05 FLUIDO ELECTRICO PARA LA OBRA 1,600.00 1,600.00 1,600.00
01.02.06 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIA 7,850.00 7,850.00 7,850.00
01.03 MOVIMIENTO DE TIERRAS 287,735.90 143,867.95 143,867.95 287,735.90
01.03.01 EXCAVACION MASIVA CON EQUIPO PESADO 11,427.45 5,713.73 5,713.73 11,427.45
01.03.02 EXCAVACION EN ROCA MACIZA CON EQIPO Y EXPLOSIVOS 48,400.82 24,200.41 24,200.41 48,400.82
01.03.03 EXCAVACION MANUAL DE ZANJAS PARA ZAPATAS 14,396.00 7,198.00 7,198.00 14,396.00
01.03.04 EXCAVACION DE ZANJAS PARA CIMIENTOS 4,988.21 2,494.11 2,494.11 4,988.21
01.03.05 NIVELACION DE TERRENO MANUAL 71,820.00 35,910.00 35,910.00 71,820.00
01.03.06 RELLENO COMPACTADO CON MATERIAL PROPIO 44,495.35 22,247.68 22,247.68 44,495.35
01.03.07 ELIMINACION MATERIAL EXCEDENTE MANUAL A D=15M 10,863.89 5,431.95 5,431.95 10,863.89

01.03.08 ELIMINACION DE MATERIAL EXCEDENTE CON TRANSPORTE 81,344.18 40,672.09 40,672.09 81,344.18

01.04 CONCRETO SIMPLE 189,980.47 94,990.24 94,990.24 189,980.47


01.04.01 CONCRETO f'c = 100 kg/cm2 PARA SOLADOS DE ZAPATAS DE E=4" 6,889.60 3,444.80 3,444.80 6,889.60
01.04.02 CONCRETO CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HOR 32,722.07 16,361.04 16,361.04 32,722.07
01.04.03 CONCRETO f'c=175 kg/cm2 PARA SOBRE CIMIENTO 12,692.11 6,346.06 6,346.06 12,692.11
01.04.04 CONCRETO f'c=175 kg/cm2 PARA VEREDAS 18,121.83 9,060.92 9,060.92 18,121.83
01.04.05 CONCRETO f'c=175 kg/cm2 PARA SARDINELES 7,607.96 3,803.98 3,803.98 7,607.96
01.04.06 CONCRETO f'c=175 kg/cm2 PARA LOSAS 101,872.44 50,936.22 50,936.22 101,872.44
01.04.07 ENCOFRADO Y DESENCOFRADO NORMAL EN SOBRECIMIENTOS 10,074.46 5,037.23 5,037.23 10,074.46
02 CONCRETO ARMADO 1,041,681.58 260,420.40 260,420.40 260,420.40 260,420.40 1,041,681.58
02.01 ZAPATAS 20,271.10 5,067.78 5,067.78 5,067.78 5,067.78 20,271.10
02.01.01 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 EN ZAPATAS 4,176.06 1,044.02 1,044.02 1,044.02 1,044.02 4,176.06
02.01.02 ENCOFRADO Y DESENCOFRADO NORMAL EN ZAPATAS 1,737.92 434.48 434.48 434.48 434.48 1,737.92
02.01.03 CONCRETO f'c= 210 kg/cm2 EN ZAPATAS 14,357.12 3,589.28 3,589.28 3,589.28 3,589.28 14,357.12
02.02 VIGAS DE CIMENTACION 94,036.91 23,509.23 23,509.23 23,509.23 23,509.23 94,036.91
02.02.01 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 EN VIGAS DE C 16,214.27 4,053.57 4,053.57 4,053.57 4,053.57 16,214.27
02.02.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE CIMENT 26,429.76 6,607.44 6,607.44 6,607.44 6,607.44 26,429.76
02.02.03 CONCRETO f'c=210 kg/cm2 EN VIGAS DE CIMENTACION 51,392.88 12,848.22 12,848.22 12,848.22 12,848.22 51,392.88
CRONOGRAMA VALORIZADO DE OBRA

OBRA : “CREACION DE UN PARQUE RECREATIVO EN EL SECTOR VIRGEN PURISIMA EN EL CENTRO POBLADO DE PICHIU QUINHUARAGRA-DISTRITO DE SAN MARCOS-HUARI-ANCASH”

LUGAR : PICHIU QUINHUARAGRA


COSTO DIRECTO: 4,875,911.96
PLAZO DE EJECUCION DE OBRA
PRESUPUESTO
ITEM ACTIVIDADES MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08 PARCIALES S/.
DE OBRA
30 DIAS 60 DIAS 90 DIAS 120 DIAS 150 DIAS 180.00 210 DIAS 240 DIAS
02.03 COLUMNAS 157,232.58 39,308.15 39,308.15 39,308.15 39,308.15 157,232.58
02.03.01 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 EN COLUMNAS 91,912.10 22,978.03 22,978.03 22,978.03 22,978.03 91,912.10

02.03.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS 24,912.92 6,228.23 6,228.23 6,228.23 6,228.23 24,912.92

02.03.03 CONCRETO f'c=210 kg/cm2 PARA COLUMNAS 40,407.56 10,101.89 10,101.89 10,101.89 10,101.89 40,407.56
02.04 VIGAS 157,885.99 39,471.50 39,471.50 39,471.50 39,471.50 157,885.99
02.04.01 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 EN VIGAS 64,450.65 16,112.66 16,112.66 16,112.66 16,112.66 64,450.65
02.04.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS 51,120.72 12,780.18 12,780.18 12,780.18 12,780.18 51,120.72
02.04.03 CONCRETO f'c=210 kg/cm2 EN VIGAS 42,314.62 10,578.66 10,578.66 10,578.66 10,578.66 42,314.62
02.05 ESCALERAS 11,039.54 2,759.89 2,759.89 2,759.89 2,759.89 11,039.54
02.05.01 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 EN ESCALERAS 1,061.66 265.42 265.42 265.42 265.42 1,061.66

02.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN ESCALERAS 5,665.44 1,416.36 1,416.36 1,416.36 1,416.36 5,665.44

02.05.03 CONCRETO f'c=210 kg/cm2 PARA ESCALERAS 4,312.44 1,293.73 1,293.73 1,293.73 431.24 4,312.44
02.06 MUROS DE CONTENCION 433,748.86 130,124.66 130,124.66 130,124.66 43,374.89 433,748.86
02.06.01 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 EN MUROS DE 123,027.76 36,908.33 36,908.33 36,908.33 12,302.78 123,027.76
02.06.02 ENCOFRADO Y DESENCOFRADO NORMAL EN MUROS DE CONT 60,966.45 18,289.94 18,289.94 18,289.94 6,096.65 60,966.45
02.06.03 CONCRETO f'c=210 kg/cm2 EN MUROS DE CONTENCION 249,754.65 74,926.40 74,926.40 74,926.40 24,975.47 249,754.65
02.07 LOSA ALIGERADA 124,798.27 37,439.48 37,439.48 37,439.48 12,479.83 124,798.27
02.07.01 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 EN LOSA ALIGE 9,089.82 2,726.95 2,726.95 2,726.95 908.98 9,089.82
02.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN LOSA ALIGERADA 48,873.81 14,662.14 14,662.14 14,662.14 4,887.38 48,873.81
02.07.03 CONCRETO f'c=210 kg/cm2 PARA LOSAS ALIGERADAS 22,492.52 6,747.76 6,747.76 6,747.76 2,249.25 22,492.52
02.07.04 LADRILLO DE ARCILLA HUECO 15X30X30 cm PROVEIDO Y COLO 44,342.12 13,302.64 13,302.64 13,302.64 4,434.21 44,342.12
02.08 GRADAS DE TRIBUNA 42,668.33 12,800.50 12,800.50 12,800.50 4,266.83 42,668.33
02.08.01 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 EN GRADAS DE 5,411.75 1,623.53 1,623.53 1,623.53 541.18 5,411.75
02.08.02 ENCOFRADO Y DESENCOFRADO NORMAL EN GRADAS DE TRIB 11,380.40 3,414.12 3,414.12 3,414.12 1,138.04 11,380.40
02.08.03 CONCRETO f'c=210 kg/cm2 EN GRADAS DE TRIBUNA 25,876.18 7,762.85 7,762.85 7,762.85 2,587.62 25,876.18
03 ARQUITECTURA 3,069,229.60 920,768.88 920,768.88 920,768.88 306,922.96 3,069,229.60
03.01 ALBAÑILERIA 451,532.45 135,459.74 135,459.74 135,459.74 45,153.25 451,532.45
03.01.01 MURO LADRILLO K.K. DE ARCILLA 18H (09x013x24) AMARRE DE 65,197.58 19,559.27 19,559.27 19,559.27 6,519.76 65,197.58
03.01.02 MURO LADRILLO K.K. DE ARCILLA 18H (09x013x24) AMARRE DE 117,927.57 35,378.27 35,378.27 35,378.27 11,792.76 117,927.57
03.01.03 MURO DE BLOQUE DE VIDRIO 268,407.30 80,522.19 80,522.19 80,522.19 26,840.73 268,407.30
03.02 REVOQUES ENLUCIDOS Y MOLDURAS 131,728.67 39,518.60 39,518.60 39,518.60 13,172.87 131,728.67
03.02.01 TARRAJEO DE MUROS EXTERIORES 16,749.99 5,025.00 5,025.00 5,025.00 1,675.00 16,749.99
03.02.02 TARRAJEO DE MUROS INTERIORES 62,754.72 18,826.42 18,826.42 18,826.42 6,275.47 62,754.72
03.02.03 TARRAJEO EN COLUMNAS 6,931.05 2,079.32 2,079.32 2,079.32 693.11 6,931.05
03.02.04 TARRAJEO EN VIGAS 15,015.16 4,504.55 4,504.55 4,504.55 1,501.52 15,015.16
03.02.05 TARRAJEO EN PARAPETO 3,591.19 1,077.36 1,077.36 1,077.36 359.12 3,591.19
03.02.06 TARRAJEO EN CIELORASO 20,613.78 6,184.13 6,184.13 6,184.13 2,061.38 20,613.78
03.02.07 TARRAJEO EN DERRAMES 6,072.78 1,821.83 1,821.83 1,821.83 607.28 6,072.78
CRONOGRAMA VALORIZADO DE OBRA

OBRA : “CREACION DE UN PARQUE RECREATIVO EN EL SECTOR VIRGEN PURISIMA EN EL CENTRO POBLADO DE PICHIU QUINHUARAGRA-DISTRITO DE SAN MARCOS-HUARI-ANCASH”

LUGAR : PICHIU QUINHUARAGRA


COSTO DIRECTO: 4,875,911.96
PLAZO DE EJECUCION DE OBRA
PRESUPUESTO
ITEM ACTIVIDADES MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08 PARCIALES S/.
DE OBRA
30 DIAS 60 DIAS 90 DIAS 120 DIAS 150 DIAS 180.00 210 DIAS 240 DIAS
03.03 CIELO RASOS 4,833.89 1,450.17 1,450.17 1,450.17 483.39 4,833.89
03.03.01 CIELORRASOS CON FIBRO DE CEMENTO E=4MM, SS.HH. JUEGO 3,554.10 1,066.23 1,066.23 1,066.23 355.41 3,554.10
03.03.02 ALERO CON FIBRO DE CEMENTO E=4MM, SS.HH. JUEGO DE NIÑ 1,279.79 383.94 383.94 383.94 127.98 1,279.79
03.04 PISOS Y PAVIMENTOS 450,103.77 135,031.13 135,031.13 135,031.13 45,010.38 450,103.77
03.04.01 CONTRAPISO DE 2" INCLUYE FALSO PISO 38,175.02 11,452.51 11,452.51 11,452.51 3,817.50 38,175.02
03.04.02 PISO CERAMICO 30x30 PEGADO Y FRAGUADO 20,964.27 6,289.28 6,289.28 6,289.28 2,096.43 20,964.27
03.04.03 PISO DE MADERA MACHIEMBRADO DE 4"x4" SOBRE DURMIENTES 2 9,122.88 2,736.86 2,736.86 2,736.86 912.29 9,122.88
03.04.04 PISO DE CEMENTO ACABADO PULIDO 9,072.00 2,721.60 2,721.60 2,721.60 907.20 9,072.00
03.04.05 PISO DE JEBE 11,485.60 3,445.68 3,445.68 3,445.68 1,148.56 11,485.60
03.04.06 PISO DE GRASS SINTETICO 361,284.00 108,385.20 108,385.20 108,385.20 36,128.40 361,284.00
03.05 CONTRAZOCALOS 11,543.98 3,463.19 3,463.19 3,463.19 1,154.40 11,543.98
03.05.01 CONTRAZOCALO DE CEMENTO PULIDO ENCASTRADO H=20 cm 980.88 294.26 294.26 294.26 98.09 980.88
03.05.02 CONTRAZOCALO DE CERAMICA 30x30 cm ENCASTRADO H=10 cm 4,748.10 1,424.43 1,424.43 1,424.43 474.81 4,748.10
03.05.03 CONTRAZOCALO DE MADERA DE 2" CON RODON 2,907.50 872.25 872.25 872.25 290.75 2,907.50
03.05.04 CONTRAZOCALO DE MADERA DE 1:2M + 1/4 RODON 2,907.50 872.25 872.25 872.25 290.75 2,907.50
03.06 REVESTIMIENTOS 22,130.19 6,639.06 6,639.06 6,639.06 2,213.02 22,130.19
03.06.01 REVESTIMIENTO DE PASOS Y CONTRAPASO CON CEMENTO PUL 22,130.19 6,639.06 6,639.06 6,639.06 2,213.02 22,130.19
03.07 COBERTURAS 953,826.88 286,148.06 286,148.06 286,148.06 95,382.69 953,826.88
03.07.01 COBERTURA CON TEJA ANDINA 2,740.58 822.17 822.17 822.17 274.06 2,740.58
03.07.02 CUMBRERAS DE TEJA ANDINA 1,595.66 478.70 478.70 478.70 159.57 1,595.66
03.07.03 COBERTURA CON CALAMINON 949,490.64 284,847.19 284,847.19 284,847.19 94,949.06 949,490.64
03.08 CARPINTERIA DE MADERA 33,432.00 10,029.60 10,029.60 10,029.60 3,343.20 33,432.00
03.08.01 PUERTAS DE MADERA CEDRO DE TABLEROS REBAJADOS 17,400.00 5,220.00 5,220.00 5,220.00 1,740.00 17,400.00
03.08.02 PUERTAS CONTRAPLACADAS DE 35mm CON TRIPLAY 4mm 11,856.00 3,556.80 3,556.80 3,556.80 1,185.60 11,856.00
03.08.03 VENTANA DE MADERA CEDRO CON HOJAS 4,176.00 1,252.80 1,252.80 1,252.80 417.60 4,176.00
03.09 CARPINTERIA METALICA 37,890.00 11,367.00 11,367.00 11,367.00 3,789.00 37,890.00
03.09.01 PASAMANOS METALICOS 27,950.00 8,385.00 8,385.00 8,385.00 2,795.00 27,950.00
03.09.02 PUERTA PRINCIPAL DE INGRESO METALICA 9,940.00 2,982.00 2,982.00 2,982.00 994.00 9,940.00
03.10 CERRAJERIA 6,976.80 2,093.04 2,093.04 2,093.04 697.68 6,976.80
03.10.01 BISAGRA ALUMINIZADA CAPUCHINA DE 31/2" X 31/2" 2,738.00 821.40 821.40 821.40 273.80 2,738.00
03.10.02 CERRADURA PARA PUERTAS CONTRAPLACADA 816.40 244.92 244.92 244.92 81.64 816.40
03.10.03 CERRADURA PARA PUERTAS APANELADAS 3,422.40 1,026.72 1,026.72 1,026.72 342.24 3,422.40
03.11 VIDRIOS, CRISTALES Y SIMILARES 4,135.41 1,240.62 1,240.62 1,240.62 413.54 4,135.41
03.11.01 VIDRIO SEMIDOBLE INCOLORO CRUDO 4,135.41 1,240.62 1,240.62 1,240.62 413.54 4,135.41
03.12 PINTURA 181,784.60 54,535.38 54,535.38 54,535.38 18,178.46 181,784.60
03.12.01 PINTURA LATEX EN MUROS EXTERIORES 63,828.87 19,148.66 19,148.66 19,148.66 6,382.89 63,828.87
03.12.02 PINTURA LATEX EN MUROS INTERIORES 83,588.36 25,076.51 25,076.51 25,076.51 8,358.84 83,588.36
03.12.03 PINTURA LATEX EN CIELO RASO 28,896.01 8,668.80 8,668.80 8,668.80 2,889.60 28,896.01
03.12.04 BARNIZ EN PUERTAS DE MADERA 563.10 168.93 168.93 168.93 56.31 563.10
CRONOGRAMA VALORIZADO DE OBRA

OBRA : “CREACION DE UN PARQUE RECREATIVO EN EL SECTOR VIRGEN PURISIMA EN EL CENTRO POBLADO DE PICHIU QUINHUARAGRA-DISTRITO DE SAN MARCOS-HUARI-ANCASH”

LUGAR : PICHIU QUINHUARAGRA


COSTO DIRECTO: 4,875,911.96
PLAZO DE EJECUCION DE OBRA
PRESUPUESTO
ITEM ACTIVIDADES MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08 PARCIALES S/.
DE OBRA
30 DIAS 60 DIAS 90 DIAS 120 DIAS 150 DIAS 180.00 210 DIAS 240 DIAS
03.12.05 BARNIZ EN VENTANAS DE MADERA 1,499.18 449.75 449.75 449.75 149.92 1,499.18
03.12.06 BARNIZ EN PISO MACHIEMBRADO 2,955.12 886.54 886.54 886.54 295.51 2,955.12
03.12.07 BARNIZ EN CONTRAZOCALO DE MADERA 453.96 136.19 136.19 136.19 45.40 453.96
03.13 VARIOS 654,886.30 196,465.89 196,465.89 196,465.89 65,488.63 654,886.30
03.13.01 FLETE TERRESTRE 210,000.00 26,250.00 26,250.00 26,250.00 26,250.00 26,250.00 26,250.00 26,250.00 26,250.00 210,000.00
03.13.02 EQUIPAMIENTO 82,257.80 41,128.90 41,128.90 82,257.80
03.13.03 BUTACAS DE FIBRA DE VIDRIO 362,628.50 181,314.25 181,314.25 362,628.50
03.14 INSTALACIONES ELECTRICAS 124,424.66 62,212.33 62,212.33 124,424.66
03.14.01 SALIDA PARA CENTROS DE LUZ 28,515.12 14,257.56 14,257.56 28,515.12
03.14.02 SALIDA PARA INTERRUPTOR SIMPLE 2,529.60 1,264.80 1,264.80 2,529.60
03.14.03 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE + LINEA A TIER 6,598.56 3,299.28 3,299.28 6,598.56
03.14.04 ARTEFACTO FLUORESCENTE RASE-E CON EQUIPO Y LAMPARA D 9,872.16 4,936.08 4,936.08 9,872.16
03.14.05 ARTEFACTO DE ALUMBRADO CON REFLECTOR DE 500W 18,107.00 9,053.50 9,053.50 18,107.00
03.14.06 ARTEFACTO PARA ALUMBRADO PUBLICO DE VAPOR DE SODIO 1 6,376.08 3,188.04 3,188.04 6,376.08
03.14.07 ARTEFACTO PARA LUZ DE EMERGENCIA CON EQUIPO Y LAMPARA 2,716.08 1,358.04 1,358.04 2,716.08
03.14.08 TABLEROS DISTRIBUCION CAJA METALICA CON 04POLOS 239.83 119.92 119.92 239.83
03.14.09 POSTE DECORATIVOS DE FIERRO DE 6.5m 25,938.96 12,969.48 12,969.48 25,938.96
03.14.10 CABLE THW CABLEADO DE 10mm2 22,485.00 11,242.50 11,242.50 22,485.00
03.14.11 POZO CONEXION A TIERRA 1,046.27 523.14 523.14 1,046.27
04 INSTALACIONES SANITARIAS 80,177.84 40,088.92 40,088.92 80,177.84
04.01 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO 4,976.15 2,488.08 2,488.08 4,976.15
04.01.01 SALIDA DE AGUA FRIA TUBERIA PVC C-10 o 3/4" 4,058.81 2,029.41 2,029.41 4,058.81
04.01.02 RED DE DISTRIBUCION INTERNA TUBERIA PVC C-10 O 3/4" 158.94 79.47 79.47 158.94
04.01.03 VALVULA COMPUERTA DE 3/4" 758.40 379.20 379.20 758.40
04.02 SISTEMA DE DESAGUE 16,242.84 8,121.42 8,121.42 16,242.84
04.02.01 SALIDA DE DESAGUE EN PVC SAL 2" 390.96 195.48 195.48 390.96
04.02.02 SALIDA DE DESAGUE EN PVC SAL DE 4" 2,898.00 1,449.00 1,449.00 2,898.00
04.02.03 SUMIDERO DE BRONCE ROSCADO 2" 835.12 417.56 417.56 835.12
04.02.04 SUMIDEROS DE BRONCE ROSCADO 4" 429.56 214.78 214.78 429.56
04.02.05 CAJA DE REGISTRO DE DESAGUE 12" X 24" 11,689.20 5,844.60 5,844.60 11,689.20

04.03 SISTEMA DE DESAGUE PLUVIAL 19,662.56 9,831.28 9,831.28 19,662.56

04.03.01 TUBERIA DE BAJADA PVC SAP 3" INCL ACCESORIOS DE FIJACION 3,436.16 1,718.08 1,718.08 3,436.16
04.03.02 REJILLA METALIICA PARA CANAETAS A=0.30m 16,226.40 8,113.20 8,113.20 16,226.40
04.04 ACCESORIOS SANITARIOS 39,296.29 19,648.15 19,648.15 39,296.29
04.04.01 TOALLERO DE LOSA BLANCO 1,012.52 506.26 506.26 1,012.52
04.04.02 ESPEJO EMPOTRADO DE 2.5x1.2 968.04 484.02 484.02 968.04
04.04.03 INODORO NACIONAL ONE PIECE ADVANCE PLUS 7,569.20 3,784.60 3,784.60 7,569.20
04.04.04 PAPELERA DE LOZA BLANCA 9,615.20 4,807.60 4,807.60 9,615.20
04.04.05 SECAMANOS ELECTRICO 1,344.08 672.04 672.04 1,344.08
CRONOGRAMA VALORIZADO DE OBRA

OBRA : “CREACION DE UN PARQUE RECREATIVO EN EL SECTOR VIRGEN PURISIMA EN EL CENTRO POBLADO DE PICHIU QUINHUARAGRA-DISTRITO DE SAN MARCOS-HUARI-ANCASH”

LUGAR : PICHIU QUINHUARAGRA


COSTO DIRECTO: 4,875,911.96
PLAZO DE EJECUCION DE OBRA
PRESUPUESTO
ITEM ACTIVIDADES MES 01 MES 02 MES 03 MES 04 MES 05 MES 06 MES 07 MES 08 PARCIALES S/.
DE OBRA
30 DIAS 60 DIAS 90 DIAS 120 DIAS 150 DIAS 180.00 210 DIAS 240 DIAS
04.04.06 BEBEDERO DE AGUA 1,626.12 813.06 813.06 1,626.12
04.04.07 DISPENSADOR DE JABON 432.16 216.08 216.08 432.16
04.04.08 LAVATORIO OVALIN MINBELL TREBOL 13,225.32 6,612.66 6,612.66 13,225.32
04.04.09 URINARIOS BAMBI (TREBOL) 3,503.65 1,751.83 1,751.83 3,503.65
05 PLAN DE CONTROL DE CALIDAD 8,940.39 4,470.20 4,470.20 8,940.39
05.01 DISEÑO DE MEZCLAS 1,525.41 762.71 762.71 1,525.41
05.02 ENSAYO A COMPRESION DEL CONCRETO 2,542.00 1,271.00 1,271.00 2,542.00
05.03 ENSAYO PROCTOR 847.46 423.73 423.73 847.46
05.04 ENSAYO DENSIDAD EN CAMPO 1,483.05 741.53 741.53 1,483.05
05.05 COSTO PLAN DE CONTROL 2,542.47 1,271.24 1,271.24 2,542.47

06 PLAN DE MITIGACION AMBIENTAL 123,816.69 61,908.35 61,908.35 123,816.69

06.01 PLAN DE MITIGACION AMBIENTAL 4,237.29 4,237.29 4,237.29


06.02 CONSTRUCCION DE SERVICIOS HIGIENICOS 92,317.65 92,317.65 92,317.65
06.03 LIMPIEZA FINAL DE OBRA 7,650.00 7,650.00 7,650.00
06.04 ROCIADO DE AGUA ANTIPOLVO 13,140.00 13,140.00 13,140.00
06.05 PREPARACION DE TIERRA P/SEMBRIO DE PLANTAS HORNAMENTA 672.83 672.83 672.83
06.06 MACETEROS PARA PLANTAS ORNAMENTALES 1,500.25 1,500.25 1,500.25
06.07 SEMBRIO DE PLANTAS HORNAMENTALES 1,157.93 1,157.93 1,157.93
06.08 APLILAMIENTO DE DESECHOS FINALES DE OBRA Y TRASLADO A 3,140.74 3,140.74 3,140.74
07 PLAN DE SEGURIDAD 4,237.29 4,237.29 4,237.29
07.01 COSTO PLAN DE SEGURIDAD 4,237.29 4,237.29 4,237.29
08 PLAN DE MONITOREO ARQUEOLOGICO 5,084.75 5,084.75 5,084.75
08.01 PLAN DE MONITOREO ARQUEOLOGICO 5,084.75 5,084.75 5,084.75
09 TALLER Y CAPACITACION 2,830.00 2,830.00 2,830.00
09.01 TALLER DE MOTIVACION 1,392.50 1,392.50 1,392.50
09.02 CAPACITACION Y ASISTENCIA TECNICA A LOS POBLADORES EN 1,437.50 1,437.50 1,437.50
COSTO DIRECTO 601,822.17 260,420.40 1,181,189.28 1,181,189.28 1,181,189.28 306,922.96 44,559.12 118,619.50 4,875,911.96