Cover-Note/ Sheet for any SFC/EFC Proposal PACKAGE-I

Main Part Sub-Part Details/Particulars

Rehabilitation and Up-gradation of NH-63 Renapur at Design Km. 6.000 to Astha at Km.
24.030 (Design length is 18.030 Km) Part of the Renapur - Ashtamode (NH-361) – Udgir -
Name of the Project Deglur (NH101) – Adampur Phata (NH101) -Khatgaon– Sagroli – Bodhan-Nizamabad
(NH6) project to Two/Four lane with paved shoulder configuration in the state of
Maharashtra on Engineering, Procurement & Construction (EPC) Basis Contract.

Mode of Implementation EPC


Length of Project 18.030 Kms
Specification of the project . * 18.030 Kms
2-Lane with PS (With or with out service Road
in any Stretch)

. 4-Lane with or (with out service Roads) -


-
. 6-Lane with or (with out service Roads)
Pavement Flexible/ Rigid Rigid
Traffic (No. of PCUs) Toll able Non-Toll able Total
1047 2005 3052
ROW Details Existing ROW (in Mtrs) 30
Land area under the Existing ROW 72.090 Ha
Existing Carriageway 5.5m
(ROW acquired during earlier up-gradation Encroachment on the already acquired
project (e.g for 4-laning project, ROW ROW Yes
acquired for earlier executed 2-Laning
work should be mentioned) 30m (Except Curve Improvements & Toll
Proposed ROW Plaza & Bus laybay & Truck Laybay
Locations)

Additional land Required for the proposed 4.959 Ha


ROW
Of which
Government Land Nill
Forest Land Nill
Private Land 4.959 Ha
Estimated Land Acquisition Cost 1.160 Cr
Rate of Administrative Charges for LA, if
Applicable -
Status of Acquisition of Private Land Section 3A Submitted to CALA
Section 3D -
Section 3G -
Possession taken
Contiguous length of encumbrance-free
availble ROW
Status of Availablity of ROW 16.16 Kms
for approach to the structures 1.72 Kms

Time by which complete ROW would be Existing ROW on Appointed date and
availble Balance ROW 150 days from Appointed
Date
Status of other pre-conditions
Completed
Status of Tree-felling permission, if required
Status of other pre-conditions
Main Part Sub-Part Details/Particulars

Nill
Area of Forest Land Diversion and status
Wild-life Clearance, if Required Not Required

Electrical utility Shifting -estimated costs. 1.77 Cr

Water Supply line shifting- Estimated Costs 1.06 Cr


Any other Utilities to be shifted -
Status of GAD approvals in case of In Progress
ROB/RUB
Additional Project Features Major Bridges 01 Nos
Minor Bridges 04 Nos
Culverts 09 Nos Box Culverts
Flyovers Nill
RoB/RuB 01 No ROB & 01 No RUB
VUP Nill
FOB Nill
Major Junctions 01 Nos
Minor Junctions 16 Nos

5.130 x 2 = 10.260 Kms BHS Service Road


Length of Service Road/ Slip Road & 0.906 X 2 = 1.812 Kms Slip Road

14.10 Kms
Length of RCC Rectangular/ RCC Toe Drain
Bypass (No. & Length) Nill
Realignment - (Length) Nill
Bus-bays/ Shelters 8 Nos
Truck Lay-bayes Nill
Rest Area/ Way side Amenity Nill
Any other, Specify Nill
Toll Plaza Location of Toll Plaza Nill

Distance from the Muncipal Limits/ area Nill


Distance from the pending Toll Plaza Nill
Distance from the subsequent toll plaza Nill
Any deviation from the Toll-fee Rules
-anlong with Justification Nill
No. of Lanes proposed Nill
Estimated Project Cost Cost of Addl. Land 1.16 Cr
Cost of other Pre-construction activities 5.05 Cr
Civil Construction Cost (Road stretch) 118.680 Cr
Total Civil Construction Cost 151.040 Cr
Centages
24.880 Cr
(Refer to the Break-up)
Total Estimated project Cost 182.13 Cr
Project Completion Schedule Date by Which Tenders to be invited 12/8/2017
Proposed date of LoA -
Project Completion Schedule
Main Part Sub-Part Details/Particulars
Proposed date of declaration of 'Appointed
Date'

Project Completion Time (no. of months) 18