PRESUPUESTO

OBRA: AMPLIACIÓN DE TALLER UBICACIÓN: CIRCUNVALACIÓN 289. SURCO-LIMA


PROPIETARIO: PQRT FECHA: ABRIL-2013
CONTRATISTA: CLAUDIA FEBRES ÁREA GEOGRÁFICA. 02

ITEM DESCRIPCIÓN UND. CANT. P.UNIT. PARCIAL TOTAL


1.00 TRABAJOS PRELIMINARES 6,235.00
1.01 LIMPIEZA DE TERRENO M2. 500.00 2.81 1,405.00
1.02 TRAZOY REPLANTEO M2. 500.00 9.66 4,830.00
2.00 MOVIMIENTO DE TIERRA 5,892.72
2.01 EXCAVACIÓN DE ZANJA M3. 90.00 30.11 2,709.90
2.02 RELLENO M3. 8.00 22.58 180.64
2.03 ELIMINACIÓN DE MATERIAL EXCDENTE M3. 98.40 30.51 3,002.18
3.00 CONCRETO SIMPLE 27,440.80
3.01 CIMIENTO CORRIDO 1:10 +30%P.G. M3. 80.00 142.00 11,360.00
3.02 SOBRECIMIENTO
3.02.01 CONCRETO 1:8+25%P.M. M3. 30.00 216.95 6,508.50
3.02.02 ENCOFRADO-DESENCOF. M2. 80.00 27.36 2,188.80
3.03 FALSO PISO, E=4" M2. 300.00 22.68 6,804.00
3.04 SOLADO 1:12 M2. 50.00 11.59 579.50
4.00 CONCRETO ARMADO 56,629.17
4.01 ZAPATA 4,689.60
4.01.01 CONCRETO F'C=210 KG/CM2. M3. 10.00 239.36 2,393.60
4.01.02 ACERO FY=4,200KG/CM2. KG. 560.00 4.10 2,296.00
4.02 COLUMNA 12,359.40
4.02.01 CONCRETO F'C=210 KG/CM2. M3. 20.00 325.93 6,518.60
4.02.02 ENCOFRADO-DESENCOF. M2. 60.00 42.68 2,560.80
4.02.03 ACERO FY=4,200KG/CM2. KG. 800.00 4.10 3,280.00
4.03 VIGAS 8,659.93
4.03.01 CONCRETO F'C=210 KG/CM2. M3. 10.00 293.14 2,931.40
4.03.02 ENCOFRADO-DESENCOF. M2. 69.00 47.37 3,268.53
4.03.03 ACERO FY=4,200KG/CM2. KG. 600.00 4.10 2,460.00
4.04 LOSA ALIGERADA 23,123.55
4.04.01 CONCRETO F'C=210 KG/CM2. M3. 15.00 274.17 4,112.55
4.04.02 ENCOFRADO-DESENCOF. M2. 300.00 33.69 10,107.00
4.04.03 ACERO FY=4,200KG/CM2. KG. 690.00 4.10 2,829.00
4.04.04 LADRILLO 0.15X0.30X0.30 2500.00 2.43 6,075.00
4.05 ESCALERA 7,796.69
4.05.01 CONCRETO F'C=210 KG/CM2. M3. 11.00 298.11 3,279.21
4.05.02 ENCOFRADO-DESENCOF. M2. 48.00 52.26 2,508.48
4.05.03 ACERO FY=4,200KG/CM2. KG. 490.00 4.10 2,009.00
5.00 MUROS 8,783.00
5.01 LADRILLO KK 18HCO. SOGA M2. 55.00 49.00 2,695.00
5.02 LADRILLO KK 18HCO. CABEZA M2. 80.00 76.10 6,088.00
COSTO DIRECTO 104,980.69
GASTOS GENERALES (10%) 10,498.07
UTILIDAD (12%) 12,597.68
SUBTOTAL 128,076.45
IGV 23,053.76
TOTAL 151,130.21