Вы находитесь на странице: 1из 14

SUMMER INTERNSHIP REPORT

APOLLO PROTON THERAPY AND CANCER CARE HOSPITAL


(20-06-2016 to 05-07-2016)

Submitted to

Larsen & Toubro Limited


L & T Construction
Buildings & Factories, Independent Company,
Mount Poonamalle Road,
Manapakkam,
Chennai

Submitted by

Iyyappan R
Third year under graduate student,
Department of civil engineering,
Bannari amman institute of technology,
Sathymangalam, Erode District.

1
Acknowledgement

I am very thankful to LARSEN & TOUBRO CONSTRUCTION


BUILDINGS & FACTORIES INDIPENDENT COMPANY for having
given me the opportunity to undertake my internship at their APOLLO
PROTON THERAPY AND CANCER CARE HOSPITAL PROJECT
SITE, OMR PROJECT. This internship has been an excellent experience. I
have been able to meet so many people it will help me with opportunity in the
future. It is important to say that I have learned time management and self-
motivation through this internship. I thank Managing director of L&T for giving
opportunity to students to allow them to undertake training at their prestigious
company. At this juncture I feel deeply honoured in expressing my sincere
thanks to Mr.R.Gokulan, B&F HR - CNCL for giving me this wonderful
opportunity to do my summer at in plant training at L& T. I would like to thank
Mr Pandari S, DGM – Contracts & Commercial Dept., who provided me the
path to take training at their company. I would also like to give my heart-felt
thanks to Prabakaran L (project manager) who supported me during my
internship. Furthermore I want to tank Environmental Health Safety Engineer,
quality engineer who guided me during my internship. At last I would like to
thank all staff at L&T construction, for their help during my training.

2
CONTENT

Chapter Topic Page no.

1 Introduction 4

2 Details of the project

2.1
Project 5

2.2
Building details 5

2.3
Safety and quality 6

2.4 Field study 7

3 Conclusion 14

3
CHAPTER 1
Introduction

This report is a short description of my fifteen days internship carried out at


Apollo proton therapy and cancer hospital project site, OMR. Since the project
was hospital building L&T construction B&F IC, undertakes project with
greater care. The safety measures that were provided during construction were
really good to my knowledge. At the beginning of internship I had several
goals, which I wanted to achieve through this internship i.e., to enhance my
communication skills, to get field experience, to know what are the knowledge I
still need to develop in future.

About company
Larsen & Toubro limited (L&T) has its headquarters in
Mumbai, Maharashtra, India. The company has business interest in engineering,
construction, manufacturing goods, information technology, and financial
services. L&T is the largest engineering and construction company in India.
VISION
L&T shall be a professionally-managed Indian multinational, committed to total
customer satisfaction and enhancing shareholder value. L&T shall be an
innovative, entrepreneurial and empowered team constantly creating value and
attaining global benchmarks. L&T shall foster a culture of caring, trust and
continuous learning while meeting expectations of employees, stakeholders and
society
MISSION
To achieve excellence in the field of engineering, procurement and construction
through world class practice and standards in quality, safety and project
management

4
CHAPTER 2
Details of the project
2.1 PROJECT:
Apollo proton therapy and cancer hospital is located at OMR Road, Tharamani
Rd, near SRP Tools bus stop, Chennai.
The project is the prestigious project of L&T since it has proton therapy block
along with the cancer hospital.
 Client – Apollo hospital enterprise limited.
 Contract Type – Design and Built Lump Sum Contract.
 Contractor: Larsen and Toubro Ltd.
 Consultant : Engineering Design And Research Center (EDRC), L&T
Construction – Buildings & Factories
 Built up Area – 3.92 Lakhs square feet.
 Project duration – 30 Months
 Project value – 242.50 cr
 Number of beds – 160 beds

2.2 BUILDING DETAILS


 Cancer Hospital - 2B + G+ 6
 Proton Therapy – G + 1st Floor (service floor)
 MLCP (Multi Level Car Parking) – 2nd to 7th Floor in proton therapy
building
 Service Building – B + G +2
 Number of beds – 114
PROTON THERAPY:
 It consist of
1. 2 gantries
2. FBTR (Fast Bread Test Reactor)
3. Cyclotron
 Shear wall was adopted for building
 Maximum wall thickness adopted was 4.6m in the place where cyclotron
is located
 Greater thickness was adopted to prevent the radiation emission to
outside atmosphere
 It consist of removable pre cast beam at level +3.83m to +5.63m

5
2.3 SAFETY & QUALITY:
 L&T provides Personal protective equipment’s (PPE) to all the workers
who are involved in different stages of works in construction site. PPE
includes,
 Safety helmets
 Eye protection (Glasses)
 Ear protection
 Nose masks
 Reflective jackets ( High visibility cloth )
 Safety belt (fall protection)
 Hand protection (Protective gloves)
 Foot protection (safety shoes)
 Quality control (QC) is a procedure or set of procedures intended to
ensure that a manufactured product or performed service adheres to a
defined set of quality criteria or meets the requirements of the client or
customer.
 Once the material comes to the site, inspection for various
characteristics of the material as per IS code specification is done.
 A separate quality lab is provided at the site for the testing of materials
and the tests are recorded.
 Materials such as cement, concrete, solid blocks, aggregates etc., are
tested to find its durability.
 For example, If RMC is brought to the site, flow of concrete is
checked and cubes are casted to check the compressive strength after 7
and 28 days.
SAFETY & QUALITY POLICY:
 L&T has various safety norms as per ISO standards.
 High priority is given for Health & Safety (EHS).
 They are accredited to the International Standards of ISO 14001:2004
and OHSAS 18001:2007.
 EHS (Environmental Health Safety) office is present in project site and
they provided and monitored the safety aspects in the site. The safety
engineer with green cap was appointed by project manager for monitoring
purpose.
 L&T has quality policy.
 L&T are also accredited to the International Standards of ISO 9001:2008.

6
2.4 FIELD STUDY
2.4.1 SOIL: Soil was found to be a clayey soil during excavation
2.4.2 WATER TABLE: Water table was very high
2.4.3 SURVEYING:
 Equipments used for survey are Total Station, Auto-Level, Theodelite
and other measuring tools
 Masonry pillars was constructed for permanent bench mark and its top
surface was finished neatly
 Survey layout was prepared showing permanent benchmark and points
were set out for pillars and other individual structure
2.4.4 SHOWRING:
 Sheet piling (yield stress not less than 295 N/mm2) was adopted with
help of vibro hammer to prevent the sliding of surrounding soil and strut
arrangement along with king post was made for its stability purpose.

2.4.5 PILE:
 BCIS - Bored Cast In-Situ Pile (IS 2911: Part I Sec: 2 1979) i.e end
bearing pile is used in project for foundation and the pile was lowered up
to 1m below the rock strata.
 Totally 730 number of pile is adopted for project
 Termination of pile was depend on PPR value derived from SPT ‘N’
value

7
PILING OPERATION:
 Auger cutting tool was attached to Kelly and pre-boring was done
 Casing was driven into ground the verticality was stage wise checked.
 During the process of boring the bentonite solution was circulated from
bentonite tank.
 Rebar cage was lowered after termination of bore. Rebar was lowered
with the help of crane.
 Then bentonite water was used to remove all lose materials from bore.
Bentonite slurry:
 Viscosity 30 - 60 seconds
 PH value 9 - 11.5
 Density 1.03 - 1.12 gm/cc
 Flushing was done until slurry specific gravity not exceed 1.12
 Concreting was stopped if specific gravity exceeds 1.12
 M30 grade of concrete was used in pile.
 Slump range 150 – 180 mm
 Tremie pipe was been used while concreting.
 Top level of concrete was brought up to cut off level, empty bore was
then filled with sand
LOAD TEST ON PIPE:
 Vertical pile load test
 Lateral pile load test
 Dynamic load test
 Integrity test
2.4.6 VARIOUS TEST CARRIED OUT ARE
 Cement - Normal Consistency Test
 Aggregate - Sieve Analysis Test
 Concrete -Slump Cone Test for Wet Concrete
Compression Test for Casted & Cured Concrete
 Steel - Tension Test
2.4.7 EXCAVATION AND PILE HEAD PREPARATION:
 After completion of piling work excavation was carried out for purpose
of providing pile cap
 Excess harden concrete in pile cap was chipped using jack hammer and
other equipments
 Projecting reinforcement was bent and accommodated into pile cap

8
2.4.8 MATERIALS USED:
 Cement used: OPC 53 grade
 Temperature controlled concrete (ice concrete) – They have used mass
concrete for greater depth (1.2m and above) in proton therapy building
 50% of mineral admixer (GGBFS- Slag) was added to replace cement
and make it as eco friendly building
GGBFS was used to reduce high temperature of concrete due to cement
 Reinforcement bars used – Fe500D (D-ductility)
 Thermocouple was used to check the temperature of outer face and core
of concrete and the difference was maintained less than 19 deg C
 Water proofing admixture – penetron
 Hy-rib sheet MS Plate for construction joint
 Grade of concrete – For PCC – M7.5
For Raft – M30 TCC (Temperature Controlled
Concrete)
For Pile & wall– M30
For beam – M50
For Column – M40
2.4.9 MOCK UP TEST:
 Test was made on separate concrete block to check the temperature
variation inside and outside the block using thermocouple
 Thermocouple was place at middle, side, top and bottom of block
 If the inside temperature is too hot and outer is cold due to temperature
gradient crack is formed
2.4.10 REINFORCEMENT:
 Reinforcement was laid in sequential layers
 First layer of rebar was placed above clear cover (cement or PVC cover
block) on PCC
 After that chair bars were provided for top layer
 Then top layer of reinforcement was provided above the chair bar after
which other vertical bars for wall were placed
 Construction joint were provided with shear reinforcement
 After fixing wall reinforcement cover blocks were provided with
formwork supported using push and pull props
 Water stoppers were fixed and supported the bars using additional
reinforcement

9
2.4.11 FORM WORK:
MATERIALS USED IN FORM WORK:
 For shuttering 12mm plywood was adopted
 H16 Timber beam
 50mm thick PUF Foam
(NOTE:
PUF sheet was used to control temperature variation between inner core
and surface)
 Rebar
 Standard steel waler (ISMC 100 B/B Channels)
 Flange claw assembly
 Props to align the shutters to the required angle
 EPS was used with formwork to reduce concrete surface from high
temperature
TYPES OF FORM WORK:
 For wall – wall form work system

 For column – column form work system


 For slab – flex form work system
 For beams – HDT (Heavy Duty Tower) form work system
DE SHUTTERING:
 De shuttering was done after the variation of temperature between inner
core and surface was 19 deg C

10
2.4.12 CONSTRUCTION JOINT:
 To join the two mass concrete placed at different time construction joint
was used to make it as single load bearing element
 Hy-rib sheet were been at junction of construction joint (vertical)
 To avoid radiation leak MS plate 300mm wide and 6mm thick was
provided in joints
 MS plate 150mm either side of the joint

2.4.13 TEMPERATURE CONTROL CONCRETE & CONCRETING:


 Placing temperature was maintained less than 25deg C
 Maximum allowable temperature 70 deg C
 Temperature variation was maintained less than 19 deg C
 temperature is monitored using thermocouples
 Concreting was done during night time to maintain low temperature
 Water proofing admixer was added to concrete in transit mixer
2.4.14 CURING:
 Chemical curing was adopted
 Covered with plastic sheet 1mm thick over which 40mm thermocol was
placed
 Thermocol covering was protected by taupaulin sheet to protect from
rain until temperature reduces to 40 deg C

11
2.4.15 TRANSPORTATION OF CONCRETE:
 RMC of capacity 1cum to 3 cum was used for concrete production
 Concrete was transported by transit mixer
2.4.16 PCC & MASS CONCRETING FOR FOUNDATION:
 Mat or Raft foundation was adopted for project
 The Raft foundation was made above the PCC which was made for
75mm thick
 The depth of Raft foundation was higher to 1.2m and above hence raft
foundation was made using TCC

2.4.17 PLANT & MICHINARIES (P&M):


The machineries that are used in site are Crane and DG (Diesel Power
Generator)
CRANE:
 Tower crane was used in project
 The length of jib(working arm) is 65m
 Jib has a lifting capacity of 1.75tone at its free end
 For every 17m from operating platform the lifting capacity of jib was
decreases by 8tone
 16mm wire rope is used to lift materials which was driven using gear
arrangement in motor which is below the drum or working platform
 The rope fixed with pulley was checked frequently using vernier for its
diameter variation if less then rope was replaced

12
DIESEL POWR GENERATOR:
 Diesel power generator of 180KV was used for entire project
 DG efficiency was 200litre/day and the DG operated for15-17 hours daily
therefore it consumes 14 litre of diesel per hour
 For every 300 hours change was made for engine oil, fuel filter,
lubrication filter
 After 1000 hours air filter was changed
 Standard engine oil 15w40 shell amala engine oil was used for generator
POWER FROM EB:
 power from EB was kept as backup which has capacity of 96KW
 MCCB circuit breaker was used in circuit
 Change over switch was there to change supply from DG to EB and vice
versa

13
CHAPTER 3
Conclusion
This internship was very useful for my carrier, through this internship I found
out what my strengths and weakness are. I have gained new knowledge, and
met many people who teach me many skills. On the whole this internship was a
good and useful experience.

14

Вам также может понравиться