REFERENCE NO: CMB /OP /PGE /43.

MEETING TYPE: SITE MEETING

DATE: 17 /07 /2018

VENUE: SITE OFFICE (PGE)

TIME: 12:00PM.

ATTENDANCE

JAN KAPUSKA ADETUNJI OLUYINKA

OPEYEMI OMOLE ALEXANDER N, OKORIE

CHARLES IJASAN ANYATONWU MARTINS

BOLAJI ABUBAKAR OJO OLAOLU

AHUNANYA CHIBUEZE EMMANUEL JUSTICE

OSOKOMAIYA OLUWABUMI AZEEZ LAWAL

THOMAS MOSES OMOSEBI ISAAC

GEORGE M. L. ENDURANCE I. O.

IBIYEMI M. A.

GENERAL DISCUSSION.

 Mr. Laide is absent and sent a representative. The pail loader has been fixed and available for
use. The truck is still not working, serving of the truck has been done already, awaiting funds to
continue repair of the Truck and hopefully by weekend the truck should be ready.
 As regards movement of POP materials to the store for safe - keeping and avoid wastage, Arch
Opeyemi Reported that the POP materials were rather moved to sites where they are needed.
i.e B/ 13a, Engr. Jan Emphasized that material remains should either be moved to sites where
they are most needed or returned to the store. Engr. Jan also emphasized that actions should be
taken on anyone found wanting on wastage of materials. Engr. Jan also mentioned Placement of
tiles on designated projects, he emphasized that tiles must be placed accordingly and correctly
and this includes a proper communication, supervision and briefing of artisans daily.
 Engr. Bolaji Abubakar raised the motion of instability of mixer machines on casting days. Arch
Opeyemi suggested that mixer machines be rented in order to curb machine breakdowns and
avoid casting delays. Engr. Jan emphasized that Pearl expeditors should up their game in time and
deal with equipment subs-tandardness.
 Mr. Jan Stressed the need for Engineers to take up projects accordingly. Although Engr.
Emmanuel Justice was mentioned for Pearl Audaces, Mr. Jan moved the motion to sit out the
matter with Mr. Dariusz Adekoya.
 NLNG Representatives came in to give samples of fittings to be used in the projects.

PEARL GARDENS
B/1A (JOSHUA OHIELEI) : ARCH OPEYEMI OMOLE
WORK (PROGRESS/PLAN) TASK COMPLETION MILESTONE
o 90% done with POP N/A HANDOVER
works, remaining the
masters bedroom.
o Tiling to wet areas still
ongoing, awaiting funds to
completion.
o Housekeeping has been
done, except the
entrance area, debris
areas have been cleared.
ACTION POINT

1/9 (SAMSOM OLUWOLE) : ENGR. JIMOH


WORK (PROGRESS/PLAN) TASK COMPLETION MILESTONE
N/A N/A
ACTION: Balustrades were delivered yesterday evening, and should be installed tomorrow.

1/11,12,45-46 (PATRICK ILODIANYA) : ARCH OPEYEMI OMOLE


WORK (PROGRESS/PLAN) TASK COMPLETION MILESTONE STATUS
 Setting out for kerbs and
paving stone has been
done.
 reinforcement to septic
tank ongoing.
 issues with architectural
drawing not matching
with what we have on
site.
 Erected perimeter fence
is low and should be raise
a little.
ACTION POINT

2/33A (THOMAS) : ARCH OLAOLU


WORK (PROGRESS/PLAN) TASK COMPLETION MILESTONE STATUS
o Formwork has completed PROJECT HAND OVER
for cesspool.
o Reinforcement to
cesspool completed.
o Awaiting funds.
o A request was made for
materials for nogging and
PVC.
ACTION POINT

2/33B BUBA SULAIMAN : ARCH OLAOLU


WORK (PROGRESS/PLAN) TASK COMPLETION MILESTONE STATUS
Project completed, Snag List has HAND OVER
been attended to awaiting
handover. clients services are to
come for the key.
Action Point: Mr. Jan emphasized that a statement be written and signed by the structural engineer in
charge, to certify the building is safe for handover during and beyond its defect liability period. The
building should also be properly monitored to check if cracks are live or dead cracks.

4/12 OBOH: ARCH OLAOLU


WORK (PROGRESS/PLAN) TASK COMPLETION MILESTONE STATUS
 Entrance door has been HAND OVER
replaced.

D/15B SAMSON TELSOLA : ARCH OLAOLU


WORK (PROGRESS/PLAN) TASK COMPLETION MILESTONE STATUS
N/A N/A Tiling and POP works

4/18B SOLA BETIKU : ARCH OLAOLU


WORK (PROGRESS/PLAN) TASK COMPLETION MILESTONE STATUS
Snag list is still pending HAND OVER
Issues with the Tiller
ACTION POINT

5/19 (FRANCIS DWELLER) : ENG EMAMOKE


WORK (PROGRESS/PLAN) TASK COMPLETION MILESTONE STATUS
Reinforcement to fence N/A
stem is ongoing. Blocks
are available, slight issues
with block dimentions.
8/36A NICHOLAS ODIETTE : ENG EMAMOKE
WORK (PROGRESS/PLAN) TASK COMPLETION MILESTONE STATUS
 Tiling to stair case  Tiling to staircase Tiling and POP works
 POP works on ground completed
floor.  POP works on ground
 Roof piping. floor completed.
 internal PVC works  Electrical Roof piping
 External PVC works still completed.
ongoing  Internal PVC works
 cesspool has been casted completed.
and sunk remaining the
casting of the top slab.
ACTION POINT

B/6B CHRIS OFODILI : ENG EMAMOKE


WORK TASK COMPLETION MILESTONE STATUS
(PROGRESS/PLAN)
N/A N/A

ACTION POINT

7/40B (ELIZEBETH USEN): ENG EMAMOKE


WORK (PROGRESS/PLAN) TASK COMPLETION MILESTONE STATUS
 Casting of first floor  Casting of first floor
lintels has been lintels.
completed.  Wall piping.
 wall piping has been
completed.
 Block setting above lintel
is underway and
rendering is ongoing as
well.

ACTION POINT

D/13A (FUNMI ALE): ENG EMAMOKE


WORK (PROGRESS/PLAN) TASK COMPLETION MILESTONE STATUS
 External plastering has  External Plastering.
been completed.  Noggins and PVC
 internal and external installation.
noggings as well as PVC
installation has been
completed.
 Awaiting tiles from the
client to proceed with
installation of tiles due to
her preference of tiles.

ACTION POINT: POP works are ongoing.

D/13B (DAPO AGBOOLA): ENG EMAMOKE


WORK (PROGRESS/PLAN) TASK COMPLETION MILESTONE STATUS
 Tiling maintenance as N/A
well as skirting to be
commenced.
ACTION POINT
D/11A (UGOCHUKWU OTUONYE) : ENG EMAMOKE
WORK (PROGRESS/PLAN) TASK COMPLETION MILESTONE STATUS
 Plastering to ground floor Plastering to Ground floor.
completed.
 Clock setting on first
floor still ongoing.

9/5A (AMOS OLOGUNLEKO): ENG EMAMOKE


WORK (PROGRESS/PLAN) TASK COMPLETION MILESTONE STATUS

 Tiling is ongoing External Plastering.


 External plastering has
been completed.
C/4A: (CHARLES OKENWA) ENG WANDE
 Expecting PVC Materials N/A
today.
 Expecting Tiles for
Staircase
2/43 (PROF AYORINDE) ARCH OLAOLU OJO
WORK (PROGRESS/PLAN) TASK COMPLETION MILESTONE STATUS
 Fence work on going. Reinforcement to fence base.
 Dressing of window
frames ongoing.
 Expecting window
merchant.
 Reinforcement to fence
base has been
completed.

ACTION:

8/49 (DAYO): ARCH OLAOLU


WORK(PROGRESS/ PLAN) TASK COMPLETION MILESTONE STATUS

 Internal plastering
ongoing.
 Windows have been
delivered.
ACTION:

A/7 (TOSAN TONYE) ARCH OLAOLU OJO


WORK TASK COMPLETION MILESTONE
(PROGRESS/PLAN)
 Tiling to wet
areas still
ongoing.
 Issues with tiller,
a new tiller was
engaged.
ACTION

PEARL (NLNG/NUGA)
B2
 concrete to upstand beams has been completed. Expecting 9 inches blocks to commence
block setting.

B3
 Burglary bar has been received and installed in all openings.
 Snaglists is being attended to.
B4
 Installation of burglary bars completed.
 All masonry works has been completed as well.

B5
 Installation of burglary bars ongoing. Issues with fabrication sizes.

B6 window hood dressing completed.


B7 N/A
B8
 Formwork to soffit of suspended beams ongoing.

5/2A
 Painting is still ongoing.
 Tiling maintenance to wet areas is ongoing.
 Waiting for M&E to carry out testing before covering of the chambers.
 Electrical functionality test, done and certified okay.

A2
 Internal Plastering is ongoing and should be completed this week.
 External plastering is to commence accordingly.

A3
 M&E completed.
 First floor beams /slab casting completed.

A4
 N/A.

PEARL COOPERATIVE
ROAD 4
 Blinding to base is ongoing for culvert.
 Issues with payment.

PEARL AUDACES
 Gatehouse stopped due to wrong positioning.
 Awaiting supply of blocks to commence with fence erection.
 Marking out of plots is ongoing.