TIME: 12:00PM.
ATTENDANCE
GEORGE M. L. ENDURANCE I. O.
IBIYEMI M. A.
GENERAL DISCUSSION.
Mr. Laide is absent and sent a representative. The pail loader has been fixed and available for
use. The truck is still not working, serving of the truck has been done already, awaiting funds to
continue repair of the Truck and hopefully by weekend the truck should be ready.
As regards movement of POP materials to the store for safe - keeping and avoid wastage, Arch
Opeyemi Reported that the POP materials were rather moved to sites where they are needed.
i.e B/ 13a, Engr. Jan Emphasized that material remains should either be moved to sites where
they are most needed or returned to the store. Engr. Jan also emphasized that actions should be
taken on anyone found wanting on wastage of materials. Engr. Jan also mentioned Placement of
tiles on designated projects, he emphasized that tiles must be placed accordingly and correctly
and this includes a proper communication, supervision and briefing of artisans daily.
Engr. Bolaji Abubakar raised the motion of instability of mixer machines on casting days. Arch
Opeyemi suggested that mixer machines be rented in order to curb machine breakdowns and
avoid casting delays. Engr. Jan emphasized that Pearl expeditors should up their game in time and
deal with equipment subs-tandardness.
Mr. Jan Stressed the need for Engineers to take up projects accordingly. Although Engr.
Emmanuel Justice was mentioned for Pearl Audaces, Mr. Jan moved the motion to sit out the
matter with Mr. Dariusz Adekoya.
NLNG Representatives came in to give samples of fittings to be used in the projects.
PEARL GARDENS
B/1A (JOSHUA OHIELEI) : ARCH OPEYEMI OMOLE
WORK (PROGRESS/PLAN) TASK COMPLETION MILESTONE
o 90% done with POP N/A HANDOVER
works, remaining the
masters bedroom.
o Tiling to wet areas still
ongoing, awaiting funds to
completion.
o Housekeeping has been
done, except the
entrance area, debris
areas have been cleared.
ACTION POINT
ACTION POINT
ACTION POINT
ACTION:
Internal plastering
ongoing.
Windows have been
delivered.
ACTION:
PEARL (NLNG/NUGA)
B2
concrete to upstand beams has been completed. Expecting 9 inches blocks to commence
block setting.
B3
Burglary bar has been received and installed in all openings.
Snaglists is being attended to.
B4
Installation of burglary bars completed.
All masonry works has been completed as well.
B5
Installation of burglary bars ongoing. Issues with fabrication sizes.
5/2A
Painting is still ongoing.
Tiling maintenance to wet areas is ongoing.
Waiting for M&E to carry out testing before covering of the chambers.
Electrical functionality test, done and certified okay.
A2
Internal Plastering is ongoing and should be completed this week.
External plastering is to commence accordingly.
A3
M&E completed.
First floor beams /slab casting completed.
A4
N/A.
PEARL COOPERATIVE
ROAD 4
Blinding to base is ongoing for culvert.
Issues with payment.
PEARL AUDACES
Gatehouse stopped due to wrong positioning.
Awaiting supply of blocks to commence with fence erection.
Marking out of plots is ongoing.