Вы находитесь на странице: 1из 2

DPR (Daily Progress Report)- Electrical

Project UG+G+2P+9F Typ+RF MIXED USE RESIDENTAL BUILD (102)


Client MR. AHMED AL ZAROONI
Consultant KAIZEN ARCHITECTS & ENGINEERING
Main Contractor FLAMINGO CITY BUILDING CONTRACTING LLC
Date 1/21/2019
SNO Activity Description % of Total Progress

First Floor
Installation of GI Box Inside Flats(Bedroom,Living
1 Room) 100%
2 PVC Conduits on Block wall 100%
3 Installation of DB&ONU Enclosure 100%
4 PVC Conduits on Floor 100%
5 Wiring -Lights 100%
6 Wiring -Power 98%
7 Wiring -Data,Tele,TV 98%
8 Wiring -FCU & W/H 100%
9 Installaion of Cable Tray 15%
Second Floor
Installation of GI Box Inside Flats(Bedroom,Living
1 Room) 100%
2 PVC Conduits on Block wall 100%
3 Installation of DB&ONU Enclosure 100%
4 PVC Conduits on Floor 98%
5 Wiring -Lights 100%
6 Wiring -Power 98%
7 Wiring -Data,Tele,TV 98%
8 Wiring -FCU & W/H 100%
9 Installaion of Cable Tray 60%
RJ 45 Keystone Termination (Outlet ELV-Sub Contractor
10 side.Data/TV/Tele ) IIS 88%
3rd Floor
Installation of GI Box Inside Flats(Bedroom,Living
1 Room) 100%
2 PVC Conduits on Block wall 100%
3 Installation of DB&ONU Enclosure 100%
4 PVC Conduits on Floor 96%
5 Wiring -Lights 100%
6 Wiring -Power 96%
7 Wiring -Data,Tele,TV 96%
8 Wiring -FCU & W/H 100%
9 Installaion of Cable Tray
RJ 45 Keystone Termination (Outlet ELV-Sub Contractor
10 side.Data/TV/Tele ) IIS 30%
4th Floor
Insatallation of GI Box Inside
1 Flats(Bedroom,Living Room) 100%
2 PVC Conduits on Block wall 100%
3 Insatallation of DB&ONU Enclosure 100%
4 PVC Conduits on Floor 95%
5 Wiring -Lights 100%
6 Wiring -Power 95%
7 Wiring -Data,Tele,TV 95%
8 Wiring -FCU & W/H 100%
9 Installaion of Cable Tray 0%
5th Floor
Installation of GI Box Inside Flats(Bedroom,Living
1 Room) 100%
2 PVC Conduits on Block wall 100%
3 Installation of DB&ONU Enclosure 100%
4 PVC Conduits on Floor 95%
5 Wiring -Lights 100%
6 Wiring -Power 91%
7 Wiring -Data,Tele,TV 91%
8 Wiring -FCU & W/H 0%
9 Installaion of Cable Tray 0%
6th Floor
Installation of GI Box Inside Flats(Bedroom,Living
1 Room) 100%
2 PVC Conduits on Block wall 100%
3 Installation of DB&ONU Enclosure 100%
4 PVC Conduits on Floor 94%
5 Wiring -Lights 100%
6 Wiring -Power 91%
7 Wiring -Data,Tele,TV
8 Wiring -FCU & W/H
9 Installaion of Cable Tray
7th Floor
Installation of GI Box Inside Flats(Bedroom,Living
1 Room) 100%
2 PVC Conduits on Block wall 100%
3 Installation of DB&ONU Enclosure 100%
4 PVC Conduits on Floor 88%
5 Wiring -Lights 100%
6 Wiring -Power 88%
7 Wiring -Data,Tele,TV
8 Wiring -FCU & W/H
9 Installaion of Cable Tray
8th Floor 100%
Installation of GI Box Inside Flats(Bedroom,Living
1 Room) 100%
2 PVC Conduits on Block wall 100%
3 Installation of DB&ONU Enclosure
4 PVC Conduits on Floor
5 Wiring -Lights
6 Wiring -Power
7 Wiring -Data,Tele,TV
8 Wiring -FCU & W/H
9 Installaion of Cable Tray
9th Floor
Installation of GI Box Inside Flats(Bedroom,Living
1 Room) 50%
2 PVC Conduits on Block wall 45%
3 Installation of DB&ONU Enclosure 100%
4 PVC Conduits on Floor
5 Wiring -Lights
6 Wiring -Power
7 Wiring -Data,Tele,TV
8 Wiring -FCU & W/H
9 Installaion of Cable Tray
Roof
1 Conduiting &box fixing parrepet wall 55%

AC-CU wire pull rope pulling Eatch Floor Flats to


2 Roof 30%
Prepared by Checked by
Elect ENG. Anwar MEP MANAGER