Академический Документы
Профессиональный Документы
Культура Документы
Anthony Bowen
Consultant, AB Measurement & Control Solutions
T
he first oil well structures to be installed in open
waters were in the Gulf of Mexico, in water depths of
up to 100 metres, in 1955. Oil exploration in the
North Sea began in the 1960s with little early success. It
was 1969 when the first oil discovery was made and new
fields have been found since then to the present time.
Prior to that time there had been little interest in the use
of load cells in marine applications - following their intro-
duction on to the market largely - because at the time they
were somewhat prone to the ingress of moisture. Then the
major use of load cells was for the continuous determina-
tion of load on a winch, to protect the towline and winch
against overload or for testing following installation.
A similar application was developed with the support of
the Fisheries Research Organisation to measure the ten-
sion in the trawl warp. The aim was to ensure that the Figure 1: Cable laying offshore – typical of the numerous appli-
cations for load cells in the marine environment.
warp was not overloaded resulting in the cable breaking
maybe causing damage or steerage problems to the light mud products and four-point mounting for the larg-
trawler and the loss of very expensive trawling equip- er silos. Material transfer from dockside to the supply
ment. Finally, a major application was, and still is, The boat is by pneumatic conveying. The traditional oil
Tanker Mooring Load System, on which more informa- industry storage silo is mounted on a square, two-part
tion is given below. steel beam structure, a skid, utilising a hinged weighing
In addition to oil related applications, the rapidly system only partly supported by load cells. The silo is
increased demand for communication channels has installed on the upper part and this is connected to the
spawned advanced technologies for sub-sea cable laying lower part, “at the back”, via two plummer block bear-
and these applications are also reviewed. ings. In the case of the three-point mounting silos a sin-
gle load cell is installed, “at the front”, centrally between
Onshore and offshore mud and cement the upper and lower parts of the skid; on a four-point
weighing applications. mounting silo two load cells are installed, similarly, at
the corners between the two parts of the structure.
Drilling mud and cement are standard consumables used Electronic signal conditioning units are installed on one
in the exploration, development and operation of an oil- of the silo legs, and often included is a permanently
field; separate companies generally supplied the two installed printer or connection to be used by a portable
commodities. The American companies had a standard unit.
hydraulic load cell and indicator for this silo weighing The complete silo is placed on a concrete hard stand-
application. However, the purchasers wanted some trace- ing. These silos are not permanent installations and are
ability for the quantity of mud and cement supplied to moved from one supply base to another, depending on
their rigs. The oil companies wanted the supplier to pro- the oil company’s operations base. Good batch weighing
vide a printed ticket for the quantity of material supplied accuracy is achieved for this type of installation as the
to the supply boat; this was more easily achieved using material is aerated to assist in the pneumatic transfer.
strain gauge load cells and electronic signal processing The mud and cement silos installed on production plat-
with a printer interface. Furthermore, the development forms are similar to the land-based units though capaci-
phase required large quantities of these products to be ties are smaller and hold product in store for use as
supplied to the platforms and this led to silos with capac- required. The complete system includes cement and mud
ities up to 400 tonnes and high-capacity strain gauge surge tanks; these tanks monitor the flow of material into
load cells were less expensive than the equivalent the pumps to ensure that feed of mud and cement down
hydraulic unit. These two factors resulted in a greater hole is continuous. A single tension load cell is normal-
number of strain gauge than hydraulic systems being ly used to suspend tanks, which are around 5 to 10
installed. tonnes capacity; frequently these tanks are installed in
The mud and cement silos, holding stock onshore, the mudroom, a flammable hazardous area, and require
ready for use offshore, are of the vertical cylindrical an appropriate interface electronics to guard against
type, usually incorporating three-point mounting for the explosion risk. Complete mud and cement control sys-
Feature
Feature
non-hardening sealant.
Mooring monitoring systems were originally designed for
oil and LPG tankers mooring at loading facilities and, conse-
quently, were and still are available certified for use in haz-
ardous areas. Instrumentation is available for installation in
the control room and on the vessel’s bridge. Following load
cell signal processing via an intrinsically safe amplifier, the
signal is input to a computer-based data acquisition system
incorporating graphical user interfaces, signals being dis-
played on screens.
Similar systems are used on Floating Production Storage
and Offloading vessels (FPSOs) in which the mooring is
on a turret, which allows the vessel to drift in wind and
tide, or in spread mooring configurations similar to a
tanker mooring system. Technology has facilitated sub-sea
completions in which some processing of the crude output
of the well takes place on the sea bed. These have an
undersea storage facility for gas/oil which has a pipeline
terminated at the surface on a buoy. The tensions on the
tethers of the buoy are often measured using load cells.
When drilling oil or gas extraction wells offshore, the Figure 4: The shaft bracket of a crown block supported by two
driller’s prime objective is to drill a straight hole at the shear load cells – the opposite support is similar.
optimum rate. To help him in this task, measurements of directly behind the drill bit are regularly employed, there is
the total weight of the drill string as well as the weight on still the need to measure the string weight supported by a
the drill bit at the bottom of the hole need to be made. crane hook at the wellhead.
The driller needs to maintain at least enough weight in the A traditional way to determine the weight on the crane
bottom hole assembly – known as ‘The Weight on Bit’ – to hook is by measuring the tension forces in the deadline.
allow the ever-increasing length of drill pipe in the string to This is fairly simple to engineer and enables smaller capac-
remain in tension. This also helps to ensure that some of the ity load cells to be used as they are measuring only a pro-
buckling and corrosion fatigue effects are reduced. portion of the total load. Such systems suffer from errors
Although force measuring systems down the hole and due to friction present in the various sheave bearings that
constitute the crown and travelling blocks and associated
pulleys. The construction of these crane assemblies has
increased in complexity, as holes have become deeper and
consequent loads increased. As the loads have increased,
more lines are strung between the crown and travelling
blocks, causing these friction effects - which can be very
variable with age and environment - to multiply accordingly.
From a weighing point of view, the ideal solution would
be to install a load cell in the hook assembly, but the engi-
neering of such a system where exposure of the transducer
to the environment, structural safety issues and the need
for vulnerable cable disposal systems at the support loca-
tion makes such a solution less than attractive. An alterna-
tive is to install load cells in the structural support for the
crown block. The use of specially designed double-shear
type load cells makes such a support possible. The load
cells become structural pins that can support the entire
crown block, which being at a fixed and high level location
simplifies both the mechanical modification required as
well as providing a fixed cabling location away from the
rigours of the working environment. The load cells are
usually required to be compliant with safety standards for
use in flammable hazardous area as well as being approved
as safe structural components. The instrumentation com-
prises conventional weight transmitters with hazardous
area interfaces that can output the conditioned load cell
signals to communicate with a control system and/or the
rig operating staff.
Figure 3: Schematic of a Rig Hoist System.
Feature