Вы находитесь на странице: 1из 4

Dashengguan Bridge—The Largest Span Steel Arch Bridge

for High-Speed Railway


Zongyu Gao, Chief Eng.; Lunxiong Yi, Vice Chief Eng.; Hai Zhu Xiao, Design Manager; China Railway Major Bridge
Reconnaissance & Design Institute Co., Ltd., Wuhan, China. Contact: gaozy@brdi.com.cn

Abstract Wuhan–Chengdu railway and two heavy live load, large span and width.
tracks for the Nanjing metro); the If the design adopts a conventional
The Nanjing Dashengguan Bridge is a south approach is 3,674 km long while double-plane truss, the maximum
key project on the Beijing–Shanghai the length of the north approach, which force of members will be as much as
high-speed railway; it is designed to is designed to accommodate four-track 150 MN. Because of the constraints in
handle a speed of 300 km/h. The main railways, is 5,599 km. the thickness and strength of the steel
bridge has a large-span continuous plate, the cross section of the members
steel arch truss structure with a total had to be designed to be large enough
length of 1615 m. The two main spans The Main Bridge to withstand such a big force. This
over the main navigation channels of would result in difficulties in manufac-
the Yangtze River are steel arch trusses, Arrangement of Bridge Spans turing, transportation and installation.
each of which is 336 m long. The arches At the same time, the lateral distance
comprise three truss planes above the The main bridge adopts a large-span
between the two truss planes would
orthotropic deck. Erection of the steel continuous steel arch truss structure
be too wide, making the traverse
arch truss adopted the double cantile- with a total length of 1615 m, cover-
beams and bracing members very big
ver method with auxiliary cables sup- ing nearly the entire water zone. The
and more steel would be consumed.
ported by towers on piers. approach spans consist of simply sup-
Therefore, three truss planes at 15 m
ported PC box girders, each of which
Keywords: high-speed railway bridge; spacing were adopted. The four rail-
is 32 m long. Other spans across the
Dashengguan Bridge; steel arch truss way tracks are arranged between the
embankment and the drains of a power
bridge; three-plane trusses; railway trusses. Shanghai–Wuhan–Chengdu
generation plant use continuous pre-
orthotropic deck; stiffened hanger. railway is on the upstream side, while
stressed concrete box girders.
Jinghu high-speed railway is on the
The main bridge comprises two parts: downstream side. Nanjing metro lines
Introduction the first part, across the south bank are on the cantilevers of the deck on
and the deep water channels of the both sides. The cross section of the
The Nanjing Dashengguan Bridge is a Yangtze River, uses continuous steel trusses and railways is illustrated in
key project on Beijing–Shanghai high- arch trusses with spans of 108 + 192 Fig. 2.
speed railway (hereafter referred to as + 336 + 336 + 192 + 108 m. The sec-
The bottom chord of the steel arch
Jinghu high-speed railway); it is also ond part, across the north part of the
truss takes the shape of a parabolic
the main component of the Shanghai– main channels, is a parallel chord of
curve. The depth of the truss at the
Wuhan–Chengdu railway and the rail- continuous steel truss with two units
crown of the arch is 12 m, and the total
way system in Nanjing as well. Two of 2 × 84 m. The general arrangement
tracks of monorails are reserved for of the main bridge is shown in Fig. 1.
the Nanjing metro system. The bridge is straight on plane draw-
ing, and has a longitudinal slope of
The Nanjing Dashengguan Bridge is
5,9% on both ends along the profile
located 20 km upstream of the exist-
line. The main span is designed on
ing Nanjing Yangtze River Bridge and
the vertical curve with a radius of
1,5 km downstream of the Third
35 000 m.
Nanjing Yangtze River Bridge with Nanjing Beijing–Shanghai Shanghai–Wuhan Nanjing
a total length of 9,273 km. The main Metro HSR HSR Metro
The Steel Truss
bridge accommodates six-track rail-
ways (two tracks for Jinghu high-speed The bridge accommodates six-track
railway, two tracks for the Shanghai– railways and is characterized by its Fig. 2: Arrangement of the railway tracks

Beijing Shanghai
84 84 84 84 108 192 336 336 192 108
7 x 12 7 x 12 7 x 12 7 x 12 9 x 12 11 x 12 4 x 15 4 x 15 18 x 12 4 x 15 4 x 15 18 x 12 4 x 15 4 x 15 11 x 12 9 x 12
16

16

0 1 2 3 5 9
4 10
6 7 8

Fig. 1: Arrangement of the main bridge spans (Units: m)

Structural Engineering International 3/2010 Technical Report 299

x021.indd 299 7/21/10 2:41:03 PM


depth from arch spring to the crown is extended 400 mm more than the chord mm, respectively, and correspond-
96,2 m. The 240 m long parallel chord width, which extended through the ingly the deflection to span ratios are
trusses at the two ends of the main vertical plate of bottom chord and then 1/1581, 1/1073 and 1/2137. The verti-
bridge have a constant depth of 16 m. butt-welded with a deck of different cal angular rotation of the truss end
An N-type truss panel of length 12,0 m thickness.At the joint of the main truss, a is 1,9%.
is used for the structure. The transi- rabbet was cut in the top flange of
tion zone between the parallel and the bottom chord; the distance from the Methods of Pre-Camber Setting
arch trusses is realized by a variable end rabbet to the starting point of the
depth truss. Because of the small angle cambered plate was more than 100 mm; In order to achieve vertical curved pre-
between the diagonals and the verti- the nodal plate is a monolithic plate camber, the upper chords of the end
cal members of the arch truss near the going through the rabbet. Both sides span and the side span were length-
pier four panel lengths are extended to of the nodal plate and the end rabbet ened or shortened, and the length
15 m on both sides of the three main were connected with the top flange of of hangers in the middle span was
piers with the aim to minimize the size the upper chord by penetrating weld- adjusted. Different methods of pre-
of the nodal plate. ing joints, and the deck then combined camber were adopted for the parallel
the nodal plate and bottom chord chord trusses and arch trusses. For the
The main truss has a welded, mono- parallel chord trusses, the length of
effectively. A typical bottom chord is
lithic joint. The members and gusset the bottom panel remained constant
shown in Fig. 3.
plates were welded together in the and the length of the top panel was
fabrication yard and then transported adjusted. For the steel arch truss, there
to the site and spliced outside the joint Fabrication and Installation of Deck
is no pre-camber in the arch; the pre-
with high-strength bolts. The axial Components
camber was directly set by adjusting
force of the members differs greatly: Each deck of the panel length is the hanger length.
the maximum axial force is 93,3 MN divided into five components travers-
whereas the minimum is only 1,73 ally, namely, the deck ends welded to
MN. In order to reduce consumption Axial Force and Deflection of the
the bottom chords of triple main truss Three-Plane Trusses
of steel, the design uses main truss and the other two decks between the
members of three widths—600, 1000 adjacent bottom chords. The widths of Under dead load, the maximum ten-
and 1400 mm—and four depths—1000, the bottom chords in the side and mid- sile and compressive axial forces of
1200, 1400 and 1820 mm—to resist dif- dle spans are 2,52 and 3,24 m, respec- middle truss members are 34 163 kN
ferent forces. tively, and the panel length of the side and −69 141 kN. The members subject
span is the same as that of the middle to maximum tensile force are those in
Steel Type and Thickness span. The width of the deck between the upper chord at the transition of
the adjacent truss planes is 11,76 m. the truss and the arch truss, while the
The steel type was determined accord-
The traverse girder and deck of each members subject to maximum com-
ing to the axial force of the members.
panel length were fabricated and pressive force are those in the bot-
The recently developed Q420qE grade
installed separately along the bridge’s tom chord of the arch truss. Under the
steel was utilized for arch rib mem-
longitudinal directions, each member most unfavorable six-track live loads,
bers that are subjected to a compres-
sive force of more than 40 MN and and deck being fabricated by welding
for the gusset plate; Q370qE grade in the yard. The longitudinal and tra-
for other main truss members and the verse girders were connected at the
deck system; Q345qD grade for the site by using high-strength bolts while
bracing system and longitudinal gird- the deck connection was by penetra-
ers of the metrorail and brackets; and tion welding. The bridge deck compo-
Q235B grade for the auxiliary mem- nent layout is shown in Fig. 4.
bers.The maximum thickness is 68 mm
for the gusset plate and 52 mm for the Deflection and Pre-Camber
members.
Under the most unfavorable six-
track railway live load conditions, the
The Deck System deflections of end span, side span and
The running of the train on the high- middle span are 68,3, 178,9 and 157,2 Fig. 4: Bridge deck component
speed railway requires a higher stiff-
ness for the bridge deck and more
linear rails, so an orthotropic deck was
chosen for the bridge. The orthotropic
deck was welded to the bottom chord
of the steel truss. The deck and the bot-
tom chord of the truss formed a com- 1180 3000 2350 650 3000 1800
posite slab-truss structure to resist the
load.

Detailed Design of the Deck


11980
The horizontal top plate width of
the box-sectioned bottom chord was Fig. 3: Bottom chord of the main truss (Units: mm)

300 Technical Report Structural Engineering International 3/2010

x021.indd 300 7/21/10 2:41:06 PM


the maximum tensile axial force of spliced on site. The hanger is of a method using brackets supported
middle truss members is 15 157 kN in rectangular section, whose longitudi- on the pier, and inclined cables pass-
the upper chord of the truss on pier nal and traverse lengths are 1000 and ing through or attached to towers
numbers five and nine. The axial force 1398 mm, respectively, and has cham- located at the pier head. The mem-
of the upper chord in the transition bers with size 150 × 230 mm, as shown bers of the arch were installed using a
zone of the arch truss and on the truss in Fig. 5. In order to restrain the vibra- crawl crane. The deck segments were
is high. The maximum compressive tion induced by wind, the following shipped by barges and were verti-
axial force of members is −22 019 kN, measures were adopted: cally lifted into position, as shown in
which occurs near the intersection of Fig. 6. The parallel chord trusses were
the bottom chord and the tied mem- 1. The design uses a box section instead erected using the full cantilever con-
bers of the arch. At the same location, of the conventional H section to struction method with a temporary
the total axial force of the middle truss achieve the required rigidity and to pier.
span is bigger than that of the side truss enhance the natural frequency.
span. The normal force is less than 2. The aerodynamic outline is opti-
5%, but the maximum force differ- mized by cutting the four angles of Design Speed of the Railway Lines
ence is about 10%. Under dead load, the cross section. The octagon shape on the Bridge
the maximum difference between the can increase wind speed induced by
The design speed of Jinghu high-
joint deflections at the bottom chord the vortex.
speed railway is 350 km/h. According
(tied member of the arch) of side and 3. Provision for dampers is made so
to the general static analysis result,
middle spans is about 10 mm, which that they can be added where nec-
under the six-track railway live load,
occurs near the mid-span of the arch essary according to the frequency
the most unfavorable condition, the
truss. and results of the damper test on the
deflections of all spans are less than
completed bridge.
1/1000, and the vertical angular rota-
The Steel Hanger tion of the truss end is less than 2%.
The Concrete Ballast Trough for the The results of the simulated vibra-
The longest hangers are about 52 m;
Railway tion analysis show that when the
they were fabricated as three com- train passes through the bridge at a
ponents at the workshop and were The net width of the ballast trough speed of 350 km/h, both the safety
on the Shanghai–Wuhan–Chengdu and comfort indexes match the
Railway is 9,0 m and that of the Jinghu requirements outlined in the design
Railway is 9,4 m. specification.
233

The ballast trough is an RC structure, Because the bridge is near the South
150 mm thick, and the ballast wall is Railway Station of Nanjing, according
1,235 m high. φ19 × 100 mm column to the results of train analysis report,
150 shear studs are welded to the steel the maximum speed of the train,
bridge deck. There is no expansion assuming the train berthed at the
joint in the ballast trough, and a 60 South Railway Station, is 343 km/h,
mm thick waterproof and anti-wearing
1398

nearly equal to the speed envisaged at


layer is applied to the bottom of the time of design.
the trough. The maximum potential
crack width of the concrete trough is Although the results indicate that
about 0,17 mm under the combined the static and dynamic performance
action of concrete shrinkage, creep, conform to the specification, con-
dead load, live load and temperature sidering that nowhere in the world
variation. trains run at 300 km/h on a bridge
whose span is larger than 300 m to
date, the target speedwas set as 300
Construction Method km/h. Any required adjustment of the
1000
The erection of steel arch truss fol- speed will be based on a period of trial
Fig. 5: Cross section of hangers (Units: mm) lowed a double cantilever construction operation.

Tower crane Tower crane


Shanghai
Temporary tower Temporary tower
Beijing Crane 3 Crane 5 Crane 6 Crane 4
4# pier lift station Temporary cable
A37 A37′

Crane 1 S37 S37′ 10# pier lift station


Platform of
E37 E37′ member
7# pier lift station Pier bracket assembly

0 1 2 3 4 5 6 7 8 9 10

Fig. 6: Erection of the steel truss girder

Structural Engineering International 3/2010 Technical Report 301

x021.indd 301 7/21/10 2:41:07 PM


Fig. 7: The photo of Nanjing Dashengguan Bridge after closure

SEI
EI Data Block

Conclusion Yangtze River Bridge, the Zhengzhou Owner:


Yellow River Bridge and the Jinan Beijing–Shanghai High-speed Railway
A bridge is an important structure for Yellow River Bridge. All the four Company Limited
any high-speed railway. It influences large-span bridges adopt steel trusses Structural design:
the vehicle stability, safety and comfort as stiffening girders. The Wuhan China Railway Major Bridge
level of passengers greatly. At present, Tianxingzhou Yangtze River Bridge Reconnaissance & Design Institute
the Jinghu High-Speed Railway and was closed on 10 September 2008. The Co., Ltd.
the dedicated Beijing–Guangzhou Nanjing Dashengguan Bridge was Main contractor:
Railway Line are both under con- closed in July 2009 (Fig. 7 shows the China Railway Major Bridge
struction. There are four large-span photo after closure) and will be was Engineering Co., Ltd.
high-speed railway bridges across the opened to traffic in December 2010.
Yangtze River and the Yellow River The steel truss installations of the Steel (t): 200 000
and also on the two lines, namely, the Zhengzhou Yellow River Bridge and Concrete (Mm3): 12,2
Wuhan Tianxingzhou Yangtze River the Jinan Yellow River Bridge have Total cost (USD million): 738,8
Bridge, the Nanjing Dashenguan already begun.
Service date
(expected): December 2010

302 Technical Report Structural Engineering International 3/2010

x021.indd 302 7/21/10 2:41:08 PM

Вам также может понравиться