VAN SEUMEREN GROUP worldwide specialists in heavy lifting and transport

Larissa van Seumeren


Manager Corporate Communications
Corporate Communications
New corporate campaign
Do what you say and say what you do. That’s our
company culture. And we want our communica-
tion to be just as direct. The basic idea of our new
corporate campaign can be encapsulated in three
words, and it can be given shape in a stamp.
Because Mammoet literally and figuratively places
its stamp on projects in a wide range of sizes, on
every solution that we design, and on the appear-
ance of our entire industry. ‘Moved by Mammoet’
symbolises quality in accomplishments, safety and
added value for the customer.

Our new campaign was launched at the offshore


means via video, photo, text and oral explanation.
A bar in the middle of the stand, on revolving
SPMT wheels, acts as the central meeting place.
Visitors who used the taxis bearing our logo were
literally ‘Moved by Mammoet’.

Another development worth mentioning is our


updated website at www.mammoet.com.
Comprehensive content and navigation options
allow visitors to discover exactly what being
‘Moved by Mammoet’ means with just a few
mouse clicks.
3 MAMMOET
WORLD
O
trade fair (ONS) in Stavanger (end of August 2002) Besides our new corporate campaign, we’ve also
where we exhibited with our new stand. Its flexi- made a start on merchandising activities so as to
ble design allows it to be used for various kinds of retain and strengthen our image and create a cor-
presentations. The stand, whose shape is derived porate brand. We’re increasingly noticing that
from our head office ‘De Bolder’, shows real-life people want to have closer contact with our com-
examples of what being ‘Moved by Mammoet’ pany, they want to be kept informed about our
activities and they want to identify with everything
that Mammoet stands for. Mammoet Store signi-
fies heavy work, endurance, adventure, strength,
safety and teamwork. Mammoet Store gives you
the opportunity to join the world of Mammoet.
Visit us at www.mammoetstore.com

Mammoet Holding B.V. Mammoet Road Cargo B.V. Italy ASIA MIDDLE EAST Canada
Phone +31 (0)10 204 2424 Phone +31 (0)16 53 19 650 • Mammoet Italy Mammoet Canada Eastern Ltd.
Fax +31 (0)10 204 2442 Fax +31 (0)16 53 15 535 Phone +39 02 9552 9521 China United Arab Emirates • Montreal QC
Fax +39 02 9573 1216 Shenyang Mammoet Heavy • Mammoet Dubai Phone +1 450 923 9706
Mammoet Global B.V. Mammoet Van Oord Windmills B.V. Transport & Lifting Co. Ltd. Phone +971 (0)4 333 1252 Fax +1 450 923 1815
Phone +31 (0)10 204 2614 Phone +31 (0)10 204 2549 • Mammoet Palumbo Phone + 86 (0) 24 231 80 456 Fax +971 (0)4 333 1366 • Cambridge ON
Fax +31 (0)10 204 2455 Fax +31 (0)10 204 2696 Phone +39 02 577 777 Fax + 86 (0) 24 231 80 457 Phone +1 519 740 0550
Fax +39 02 57777471 Fax +1 519 740 3531
Mammoet Trading Belgium Japan AMERICA’S • Halifax NS
Phone +31 (0)10 204 2424 Mammoet Belgium N.V. Norway Mammoet Transport Japan Phone +1 902 450 0550
Fax +31 (0)10 204 2442 Phone +32 (0)93 459 891 Mammoet Norge Phone +81 (0)3 3280 6671 USA Fax +1 902 450 0545
Fax +32 (0)93 455 376 Phone +47 (0)35 505 950 Fax +81 (0)3 6408 0722 Mammoet USA, Inc Mammoet Canada Western Ltd.
Fax +47 (0)35 505 960 Phone +1 281 369 2200 • Calgary AB
EUROPE Croatia Malaysia Fax +1 281 369 2178 Phone +1 403 252 0551
Mammoet Croatia Russia Mammoet Romstar SDN BHD • South El Monte CA Fax +1 403 258 3846
The Netherlands Phone + 385 (0)1 2306 243 Mammoet Moscow Phone +60 (0)679 932 00 Phone +1 626 442 5542 • Edmonton AB
Mammoet Europe B.V. Fax + 385 (0)1 2341 491 Phone +7 095 956 0838 Fax +60 (0)679 932 20 Fax +1 626 442 0841 Phone +1 780 449 0552
Phone +31 (0)10 204 2614 Fax +7 095 956 0738 • Greens Bayou TX Fax +1 780 417 9623
Fax +31 (0)10 204 2455 Denmark Singapore Phone +1 713 422 8850 • Ft. McMurray AB
KRW Spain Mammoet (S) Pte Ltd. Fax +1 713 422 8880 Phone +1 780 791 5049
Mammoet Nederland B.V. Phone + 45 98 17 74 33 Mammoet Spain Phone +65 (0)686 11 638 • Atlanta GA Fax +1 780 791 5035
Phone +31 (0)10 204 2424 Fax + 45 98 17 28 07 Phone +34 (0)91 372 8473 Fax +65 (0)686 12 718 Phone +1 404 696 4982
Fax +31 (0)10 204 2442 Fax +34 (0)91 372 9433 Fax +1 404 696 4984 Trinidad
Egypt Thailand • Charlotte NC PTM Limited
• Mammoet Geleen / Elsloo Mammoet Fostrans Egypt Southern Africa Mammoet Banchang Phone +1 704 331 4749 Phone + 1 (868) 653 3802
Phone +31 (0)46 477 1802 Phone +20 (0)2 519 5919 Mammoet Southern Africa Phone +66 (0)38 882 556 to 882 560 Fax +1 704 331 2672 Fax + 1 (868) 652 8030
Fax +31 (0)46 476 8114
• Mammoet Pernis / Moerdijk
Fax +20 (0)2 519 6519 Phone +27 (0)11 882 4499
Fax +27 (0)11 882 4422
Fax +66 (0)38 603 800 • Tranco Mammoet
Phone +1 414 475 3180 Mexico Running up the hill page 4
Phone +31 (0)10 472 0374 France Indonesia Fax +1 414 475 3256 Mammoet Mexico S.A. de C.V.
Fax +31 (0)10 416 48 85
• Mammoet Velsen-Noord
Mammoet Fostrans Marseille
Phone +33 (0)495 06 14 74
United Kingdom
Mammoet UK Ltd.
P.T. Mammoet Nusatama • Mammoet USA NE Phone +(52) 81 83-782029
Fax + (52) 81 83-782170
UK’s biggest bridge slide page 10
Phone +62 (0)21 829 1864 Phone +1 860 443 0451
Phone +31 (0)25 122 9341 Fax +33 (0)495 06 14 75 Phone +44 (0)191 263 9222 Fax +62 (0)21 830 5114 Fax +1 860 442 9565

Kizomba
Fax +31 (0)25 122 4488 Fax +44 (0)191 263 9333 Venezuela
• Mammoet Terneuzen Germany Korea Mammoet Seattle Mammoet Venezuela Ca
Phone +31 (0)11 564 8050 • Mammoet Deutschland GmbH - Mammoet Korea Phone +1 425 258 1135 Phone +58 281 274 4866
Fax +31 (0)11 563 0724 Leuna Phone +82 (0)2 420 7791 Fax +1 425 258 1171 Fax +58 281 275 0539
Phone +49 (0)3461 4326 81 Fax +82 (0)2 420 7790
Mammoet Aannemingsbedrijf B.V. Fax +49 (0)3461 4326 88 AVS Services Brazil

on wheels
Phone +31 (0)10 204 2400 o Mammoet Deutschland GmbH - Australia Phone +1 281 369 3900 Mammoet Irga Brazil
Fax +31 (0)10 204 2415 Halle Mammoet Australia Pty Ltd Fax +1 281 369 2178 Phone +55 (0)11 3942 8100
Phone +49 (0)345 5755 673 Phone +61 (0)7 3010 9424 Fax +55 (0)11 3942 8150
Fax +49 (0)345 5755 677 Fax +61 (0)7 3010 9828

New York…New York… page 16


Colophon Photography Design & Layout Copyright
Local alliances create added value page 18
Aad van Leeuwen, Employees Mammoet, De Telegraaf Graphic Invention bv, De Meern Texts and photos can only be reproduced
after permission from the editor
Editor Mammoet Holding B.V., Text Mammoet Holding B.V., Printing
Corporate Communications Corporate Communications, De Spil B.V. Threels & Partners, De Meern
Crane rental is core business
A characteristic of Mammoet is the diversity of Wouter van Noort, member of the board of Mana- Sander Splinter, also member of the board of
activities, ranging from huge one-of-a-kind pro- gement Cranes Benelux, explains: “The establish- Management Cranes Benelux adds; “Within the
jects with high end equipment, to daily operations ment at such base industries serves as a home on-site concept and contracts for day-to-day
for almost any contractor on a rental base. base, from which additional activities in the area rental, Mammoet offers flexibility. Although most
are supported. For instance, customers in civil pro- equipment is rented with operators, certain areas
The rental activities are based on a clear concept. jects that require crane assistance for just a couple prefer the rental of equipment as such.

Adapting to a changing playing field Wouter van Noort


Mammoet joins so called base-industries, such as
large petrochemical plants, steel production compa-
nies or offshore industries. At these locations, there
of days or even hours, may call upon the resident
Mammoet fleet. This ensures quick and tailor made
services with a high degree of flexibility”.
Likewise, at some sites Mammoet offers services
in competition with others, but at other sites the
customer likes to be assured of high quality levels
Manager Cranes Benelux is a continuing flow of activities deployed by a large and safety, and orders all its subcontractors to
What the past year has clearly Seumeren to become COO and to In the USA, the management team regions. In particular, the slowdown number of subcontractors. They are often involved This concept has been adopted already in The use Mammoet services. Together with 24-hours
shown is that the times are chang- intensify his productive cooperation has been strengthened with Darren in the power industry and the post- in maintenance jobs, extension plans and the Netherlands, Belgium, Germany, the UK, Canada services, the in-house training of operators and
ing faster than ever before. The col- with Siem Kranenburg, who has Adams as COO, and Piet Nooren ponement of several large orders in renewal of existing facilities. In many cases, these and South Africa, and is being expanded to other riggers, that is also open to third parties, obviously
lapse of the stock exchange, the fall remained as CFO. Both of them and Bernadette Coney have been America and Canada impacted neg- subcontractors require temporary support with lifting areas. Examples of base industries are Shell, Dow, encourages the latter viewpoint”.
of the dollar against the euro and have been appointed representative appointed Board members at atively last year. However, there are and transport equipment, for instance cranes from DSM, Suncor and Leuna. The on-site establishment
the threat and then execution of war directors of Mammoet. In addition, Mammoet USA. Hans van Breukelen also new challenges, especially in 30 up to 650 t capacity. Mammoet offers a unique serves as gateways to other customers in their sur-
in Iraq have all had a serious impact Patrick Freericks has joined the is the new President of AVS and, last China and Russia. concept of on-site presence, with guaranteed avail- roundings. The economics of scale leads to attractive
on international companies such as team, taking over Roderik’s former but not least, Ton Bakker has been ability of equipment, to the benefit of these subcon- propositions, both for the on-site customers and
Frans van Seumeren Mammoet. When it comes to reces- responsibilities as Managing Director appointed Mammoet’s Regional The competition in our industry is Sander Splinter tractors and their common customer alike. others. It is a good example of win-win situations.
President & CEO sion and hardship, it’s best to antici- of Mammoet Global. Neil Birkbeck Manager for South America. very fierce but our customers Manager Cranes Benelux
pate them as soon as possible. has been appointed Managing choose Mammoet for our worldwide
Director of the South East Asia and The second vital measure to adapt equipment coverage, our local
So what have we done to ensure the Middle East Region. Tim Sittler to the world’s changing playing field knowledge in the various countries Versatile equipment for new construction
Mammoet stays at the front and has been appointed CEO Mammoet is to make better and more efficient and, in particular, the quality of our
continues to offer customers the Canada, with Russ Watters becom- use of the huge resources of the two work thanks to the continuous atten- Project PO-11
Location ABB Lummus Global B.V.
services they demand? The first act ing Vice President Mammoet former merger partners, Van tion we pay to it.
Customer Rotterdam, The Netherlands
was to make sure we had the right Canada responsible for Canada Seumeren and Mammoet. Roderik
Main equipment Hydraulic cranes, crawler cranes, SPMTs, CC 2800
skills in the right management posi- West and Mark Metcalfe responsible will address this special challenge. When asked what my deepest feel-
tions. We asked Roderik van for Canada East. Under his leadership, our organiza- ings about Mammoet are, I reply that
tion will be tailored even more close- I am “moved by Mammoet”, so are
Highlight
ly to the customers’ needs, while all our employees. And they are not
organizational effectiveness will be the only ones. The award by His The PO-11 project is an example of Mammoets storage and retrieval, positioning, shimming and
boosted by shorter lines of commu- Royal Highness Prince Willem van support during the construction of a new petro- alignment. A steel plate road of 950 meters long
nication and a stronger emphasis on Oranje of The Netherlands of the chemical plant. The complex project, for which and 7 meters wide eased the SPMT moves, while
the personal responsibilities of all King Willem I Prize, the most presti- ABB Lummus Global B.V. is prime responsible, a CC 2800 erected a 165 meter high flare stack.
our staff. gious prize in country for interna- called for various contracts to supply cranes,
Our pay-off Moved by Mammoet tional business success built on the transport equipment and rigging crews. These
certainly applies to our customers twin pillars of creativity and innova- supported the construction of foundations, the
and relations but it also symbolizes tion, was tangible evidence that we installation of pipe racks, of steel constructions,
our perseverance, personal commit- are on the right course. and of storage tanks. The special Equipment
ment and dedication to keeping Erection Contract covered the complete logistics
Mammoet at the forefront of market Mammoet is a corporation to be for handling more than 400 items up to 390 t.
developments. proud of. It is a unique company The logistics included offloading, site transports,
that controls and manages a wide
A third aspect is an on-going call to range of expertise and enjoys a
improve the quality of everything we prominent market position thanks
do. Above all, customers expect us to the dedication of its board, staff,
to work safely, on time and within operators, riggers and all who
cost limits. Jan van Seumeren Jr. belong to our Mammoet family.
will consider this aspect elsewhere I share this feeling with you and
in this issue. hope you will enjoy reading in this
The fourth element is that, even
in an economic downturn, well-
reasoned investments can make all
issue what we have achieved, with
you, in the recent past. Concrete Solutions
the difference between winning or
losing market share. This is why we Aannemingsbedrijf Mammoet B.V., formerly years Mammoet has acquired a reputation such ing from sub-contractor to main contractor. One
are investing in new solutions such Van Driel, is Mammoet’s concrete-assembly that the very name is reason enough for many recent example which clearly demonstrates this
as the Jumping Jack, our newly division. Aannemingsbedrijf Mammoet B.V. is an clients to opt for us. In actual fact this is only logi- evolution is the construction of a warehouse in
developed Jack-Up Vessel for exe- entirely autonomous company which is special- cal, since clients who are confronted with projects Groot-Ammers. In addition to the construction of
cuting projects at sea, in particular ized in the total assembly of concrete elements that require a great deal of lifting expertise – and all the concrete required for this project we also
the installation of windmills, and sal- for structures such as prefab offices, multi-storey that’s often the case – consider our in-house bear the ultimate responsibility for the construc-
vage and decommissioning jobs. car-parks, and viaducts. The company is also access to Mammoet’s knowledge to be a great tion of the steelwork and the entire finishing of the
active in the petrochemical industry, for which it benefit offered by our company. Moreover during building – and all to the client’s full satisfaction."
It is of great importance that we Frank Melse installs concrete structures such as piperacks. the past few years we have developed into a full
closely monitor economic develop- Managing Director of service provider in concrete assembly. In addition The ‘Beam in abundance’ project photo shows
ments and trends in the various Aannemingsbedrijf Mammoet B.V. Mammoet World requested Mr Frank Melse, to the installation of prefab elements, such as for three contracts to which Aannemingsbedrijf
Managing Director of Aannemingsbedrijf the HST line, we have also focused on what is Mammoet contributed its knowledge and exper-
Mammoet B.V., to indicate his company’s percep- referred to as "wet concrete" – i.e. the pouring of tise: the Arena Stadium (1995-1996); Offices,
tion of the added value it offers to its clients. the foundations and cellars for buildings, but also stores and car-parking facilities for Lots 4&6
"We changed our name from Van Driel to Mammoet the on-site pouring of floors and walls. By virtue of (2000); and the recent expansion of Station Bijlmer.
one year ago, and it has since become evident the experience we have acquired in a wide variety
that this has further increased our clients’ confi- of fields in the construction industry the role we

Moved by Mammoet’s winning team dence in our company. Over the course of the play in construction projects is increasingly shift-

Getting the best out of our employees first devices that make it easier to solve complex pro- “Driver number three is our complete dedication to Beams in abundance
requires Mammoet to offer a challenging work blems. Our equipment fleet has been standardized working safely, on time and within cost limits. This
environment with lots of opportunities for per- and designed so that even the most remote parts is supported in part by the SAP data and in part Project Amsterdam-Utrecht elevated railway track
Location Amsterdam, Netherlands
sonal development and career planning. of the globe are within reach at short notice.” by in-depth investments in training, courses, job
Customer Betonson
In addition, the Board of Management should rotation and other activities that increase quality
Main equipment Extendible trailers, prime movers, 300 t hydraulic cranes
have adequate tools at its fingertips to manage “The second driver in our organization is direct awareness and skills. Scheduled maintenance, of
and steer the organization effectively and in line access to all relevant information. We already course, also contributes to preserving our high
with the corporate strategy. make extensive use of our Enterprises Resources quality standards.”
Highlight
Roderik van Seumeren, Program supported by SAP software and will con-
COO. COO Roderik van Seumeren reflects on his recent tinue to explore its facilities more widely and more “Finally, the focus is directed at all times at offer- Redevelopment work has already been under The concrete beams for this project are being
assignment. “The streamlining of our organization deeply. It enhances the transparency of our orga- ing quality at a fair price. It means that internal way in Amsterdam’s South-East district for some manufactured by Betonson, near Eindhoven.
is facilitated by four key drivers. I’m pleased to nization by keeping the entire chain from ‘first overheads are subject to continuous scrutiny in years. The new offices, shops, apartments and Aannemingsbedrijf Mammoet B.V. transports the
share these with our readers because I am con- contact’ to ‘final invoicing’ under control. order to identify potential savings. Our attitude is places for entertainment constructed during the beams to Amsterdam using Mammoet trailers.
vinced they will add to an even better understand- Moreover, SAP provides an insight into the current to search for an optimal balance between high project are to be linked by a long boulevard. The beams vary in length between 2 and 30
ing of each other.” and future availability of equipment and personnel quality performance and limited cost. The However the Amsterdam – Utrecht railway line meters, with weights of between 75 and 144 t.
and lets us analyze various logistics scenarios to economies of scale realized by pursuing market currently transects the site of the planned boule- On their arrival in Amsterdam two 300 t cranes
“The first driver is our attitude, our ability to listen execute the contracts we are awarded. In addition, leadership offer the greatest benefits in terms of vard, and consequently it was decided that the unload the beams and bring them into position
carefully to what customers say. The sooner we by keeping formalized records of our past cost reduction for our customers.” necessary free passage would provided by the in the new viaduct. On the completion of the
get involved in the preparation of their plans and achievements, project governance is a valuable construction of a new concrete viaduct for the project in 2004 Aannemingsbedrijf Mammoet B.V.
schedules, the better we can anticipate what asset to develop new solutions that draw directly railway track 7 meters above the boulevard. will have transported a total of 192 beams.
equipment will be required or develop special on our experience.”

Mammoet World 2003 Page 2 Mammoet World 2003 Page 3


Trends in the market

The first trend One-way ticket to Pembroke


possibly worthy of
notice is the Asian Project Boiler for Texaco
Location Germany
region’s continual-
Customer Winkels
ly important role

Petrochemical
Main equipment SPMTs, conventional trailers, prime mover, LTM 1500’s, barges, tugs
in the world’s
energy market.
Although it is
Highlight
expected that the needs for import-
ed energy in United States of On the instruction of boiler con- attempt to push the boiler onto the


America, Canada and Europe will structor Winkels of Kleve, Germany, barge using two prime movers did
increase in the next two decades, MAMMOET Columns for Shell Moerdijk Mammoet collected a boiler with a not work and it was decided to
the largest increase will neverthe- diameter of over 9 meters, a length place a prime mover in front of the
less probably be focused on Asia.
EUROPE Project Exchange columns C101 of over 26 meters and a weight of boiler in order to drive it on board
Location Shell Chemicals Moerdijk
In fact, whilst the Asia Pacific 320,000 kg. Using combined water safely in a pull-push combination.
Customer ABB Lummus Global B.V.
region’s net imports of oil & gas are and road transport, Mammoet car-
Main equipment Floating derricks, conventional trailers, SPMTs and CC/PC 4200 and LR 1250 cranes
currently 30 percent lower than ried it from Germany to the Texaco At the Mammoet premises in
those of Europe and North site in Pembroke, Wales. Schiedam, the conventional trailers
America, by 2020 they could were removed but not before
Highlight
exceed the latter regions’ needs by superlift ballast, was set up with the Engineering had calculated that the Mammoet employees had raised the
more than 10 percent. Although oil Mammoet was contracted for the assistance of an LR 1250. This crane object had to be loaded onto 18 boiler to a height of 2 meters, using
still plays the leading role, the transport and installation of three was later used as a tailing crane. The lines of conventional trailers, con- the built-in vehicle hydraulics.
demand for and supply of natural columns for an extension at Shell largest column, 74 meters long with a sisting of 4 x 3 lines and 1 x 6 lines. This meant that for the last stage in
gas continues to grow; this Moerdijk. The work included the diameter of 5 meters, was driven After both the combinations had Pembroke, the SPMTs could easily
increased demand is due to the inland water transport from under the crane hook using SPMTs. been formed, the boiler was loaded be positioned under the boiler. After
need for clean fuel required by the Rotterdam to the Shell site at The 271 t tower was erected and onto the trailer by two LTM 1500 the boiler was raised to the required
power stations to meet the enor- Moerdijk. The columns were trans- placed on the foundation in a swift cranes. After securing it, the team height in two strokes, it was
mous growth in capacity. Since the ferred by two floating derricks onto and safe lifting operation. The two had to wait for nightfall because secured for its sea passage.
largest gas reserves are below the six-lines single and six-lines double other columns were subsequently oversize transport by day is not With this, the Dutch part of the job
South China Sea the majority of the conventional Scheuerle trailers. The placed in the following days. allowed in Germany. The transport was finished. It was now over to our
new scheduled LNG trains, GTL columns were transported to a dress- to the banks of the Rhine took English colleagues who installed the
plants and gas plants required to ing area where additional steps and The client’s response: “Certainly a place without any hitches. The first boiler carefully on its final location.
meet the growing demand for ener- platforms were mounted. In the successful operation, but we didn’t
gy will be located in the Middle meantime, a path and a plateau were expect anything else from Mammoet!
East/Asia Pacific regions. prepared for the lifting using 718 Thank you for your effort and a per-
The downstream developments in Azobe mats and 20 steel bulkheads. fect round-up of this project”.
the Oil & Gas sector are essentially Inventive use of SPMTs

similar in nature; several new petro- The lifting crane, a CC/CP 4200 with
chemical complexes are scheduled an 84-meter main mast and 300 t of Project Nanticoke refinery
MAMMOET Location Canada
for construction in China, Indo-
china, Australia, the Caspian Sea AMERICA’S Customer Fluor Daniel
Main equipment SPMTs, steel supports
area, and several Middle Eastern
countries.
Mammoet’s major strength in this
Highlight
segment of the market has always
been the concern’s easy access Fluor Canada awarded Mammoet a contract to transport several large
to local knowledge – by virtue of its pipe-rack modules to the site of a refinery in Nanticoke, Ontario,
offices in most countries in the Canada. The modules, each weighing more than 460 t, were trans-
world – in combination with ported using two 12-axle SPMTs. The shape of the modules made it
Mammoet Global’s powerful inter- necessary to use support steel between the SPMTs and the structure.
national backup and experience. With this simple yet clever solution, the modules could be lifted safely
Consequently Mammoet is in a by means of the hydraulics of the SPMTs prior to their transportation.
position to provide optimum ser-
vice to its Asian customers in the
Americas, and to its European/
American customers in Asia.
Although some plans in the Middle
East and Asia Pacific have incurred “Mammoth” project at Syncrude Canada
a delay it is nevertheless clear that
both regions will continue to offer Syncrude UE-1 reactor transport
Project

an enormous potential for Canada


Location
Syncrude
Customer
Mammoet’s versatile equipment,
Main equipment Railcars, SPMTs, strand jack lifting gantry, Gottwald RG-912, Demag CC 2800 and other cranes.
fleet and services during the com-
ing twenty-year period.

Ton Bakker, tions constitute an especially chal- (‘Hydrogen Generation’), where the
Regional Director Mammoet Asia lenging task, since engineering and crane lifted a turbine, a generator,
operations need to co-operate in and three modules. The Liebherr
deciding on the lifting material to LR1350 began its duties by provid-
be used on the basis of schedules, ing assistance in moving a 300 t
logistics and availability. column; the crane will subsequently
Consequently any amendments to be deployed in a variety of lifts at
the overall schedule will affect the different locations on the site.
availability of the rigging equipment.
Warehousing set up for the rigging To date more than 15 cranes have
equipment will provide for the con- been shipped from all over the world
trol and management of the requi- for this project, one of the biggest
site logistics. Additional prepara- upgrade projects in Mammoet’s his-
Running up the hill tions include the implementation of tory. Work on the UE-1 Project will
QC procedures and control proce- continue well into 2004.
Project DEA Wesseling refinery
dures for all the documentation, the
Location Mondorf
majority of which pertains to the
Customer Escher B.V.
maintenance and certification of all
Main equipment SPMTs, conventional trailers, prime movers
the cranes and rigging equipment.

In early May 2003 Mammoet lifted


Highlight
Mammoet reached the ferry quay at Mondorf, where the the last of a series of four reactors
A 550 t reactor, 34 meters long and with a diameter of ro-ro operation would take place at night. To overcome (of which the heaviest weighed 650 t).
5 meters, kept everyone at Mammoet busy for a week. the 12% gradient, four prime movers were placed in A Gottwald RG912 served as the
The whole structure had to be transported by road from front of the trailer combination. There must have been main crane for all the reactor lifts,
the sprayer to the manufacturer, Escher. The reactor then an article in the local paper because there were lots of with a Demag CC2800 as the tailing
had to be carried by water to its final destination at the onlookers. There was also a large police presence to crane. In the mean time a Demag
Highlight
DEA Wesseling refinery in Germany. make sure everything went smoothly. The audience north of Fort McMurray. approximately 1300 objects. CC4800 began lifting the vertical
applauded loudly when the engines started and they Fort McMurray is a small village in The lifting operations required for the The engineering of all lifts prior to pipe rack modules of Unit 8-3, also
First, the reactor was transported using a 20-line SPMT. probably thought the whole operation would be complet- the northern region of the Canadian UE-1 project involved two main oper- the actual operations is a major referred to as the ‘Fluid Coker Unit’.
The reactor was then put on saddles and moved by a ed in five minutes. Unfortunately they did not know that Province of Alberta. The ‘Upgrader ations, i.e. Heavy Lifts and General task; in addition to individual A Sennebogen SL5500 series crane
pair of 18-liner conventional Scheurle trailers. A prime a ro-ro operation takes some time. The final climb was Expansion 1 (UE-1)’ project is to be Cranes. At present the Heavy Lift approved lift studies, approved rig- was used for the tailing work
mover and the necessary ro-ro doors were used to drive spectacular… burnt rubber and all! carried out at the Syncrude Canada work encompasses the engineering, ging studies are required for the lift involved in these lifts. The Liebherr
the reactor onto the pontoon. After three days’ sailing Ltd refinery located about 50 km scheduling, transport and lifting of of each object. The rigging prepara- LR1550 began its work at Unit 9-4

Mammoet World 2003 Page 4 Mammoet World 2003 Page 5


500 kilometers in 10 days!
Project Suncor 5C-99 fractionator replacement project
MAMMOET
MIDDLE EAST
 Giant columns in Middle East
Aromatics 3 and 4
Project
Middle East
Location Canada Location
J.K.T.
Customer Suncor Customer
SPMTs, conventional trailers, PTC crane, Manitowoc 999, Demag
Main equipment Conventional trailers, prime movers, 2,000 t Heavy Duty Platform Ring Main equipment
CC3800
crane, Liebherr LR 1400

Highlight Highlight

Mammoet Canada Western was awarded the loading, could be brought underneath. The trailer configuration New records were set in the Middle East when pontoons
transport and unloading of a large diameter fractionator consisted of two double 18-line Inter-combi Scheuerles carrying two gigantic vessels weighing more than 900 t
vessel. The vessel had to be transported over a distance with turntables. A number of axles were removed to and with a length of 95 meters arrived in the harbor of
of over 500 km from Edmonton, Alberta, to the Suncor reduce the weight and spread the load when crossing Assaluyeh.
plant, north of Fort McMurray. bridges. The total transport unit was around 10 meters The columns were destined for the Aromatics 4 Project,
high and weighed 700 t. It was pulled by four prime which Mammoet Middle East is carrying out for J.K.T.
The vessel had a diameter of over 8 meters, was approx- movers. The transport operation was completed in ten Mammoet mobilized 48-axle lines of SPMTs and 18-axle
imately 60 meters long and weighed around 400 t includ- days, two days ahead of schedule. The vessel was off- Cometto trailers for the transport of the enormous
ing the transport saddles. Hurdles that had to be overcome loaded in a temporary storage yard, where it was fitted towers. Once they had reached their final destination
included strict government axle-loading regulations, with insulation, cladding, ladders and platforms. The the vessels were lifted into position by a PTC crane,
crossing more than 20 bridges and removing street fur- completed vessel was then driven under the lifting hook. a Manitowoc M999 and a Demag CC 3800.
niture, such as traffic signs and lights. This demanded
coordination, with 30 wire-lifting crews from five separate With the aid of the 2,000 t Heavy Duty Platform Ring, At the same time, Mammoet erected eight columns at
utility companies. the fractionator was pulled upright and successfully set the Third Aromatics plant in Bandar Imam Khomeiny. was preparing the column for the upper part, Mammoet
Mammoet jacking crews installed the saddles at the on its foundations. A new Liebherr LR 1400 was used The weights ranged from 210 to 520 t. For this particular installed another 210 t tower at a radius of 78 meters.
Cessco factory and raised the vessel so that the trailers as the tailing crane. job, Mammoet used a PTC with a 75-meter main boom A few days later the 500 t top section was successfully
and 69-meter jib and for the tailing an LR 1400. Once placed at a height of 80 meters. The PTC was relocated
set up, the base (520 t) and the center unit (510 t) were to a second position where four additional vessels
successfully erected and positioned. While client J.K.T were lifted.

Pascagoula revisited
Project Clean Fuels Project
Location USA
Customer Fluor Daniel
Main equipment SPMTs, pontoons, ro-ro ramps, CC 12600, CC 2800, LR 1450 MAMMOET 
ASIA
LNG 4 new building in Australia
Project LNG 4
Location Australia
Highlight Customer Kellogg Joint Venture
Main equipment Demag cranes CC4800, CC2800
Recently, Mammoet USA has successfully completed down yard, where they were temporarily stored.
the Clean Fuels project.The project involved heavy Phase 2 began while Phase 1 was still in progress; Reactor on the motorway
lifting and transport activities for the upgrading of the it entailed lifting the Vacuum Tower into position using
Chevron oil refinery in Pascagoula and was divided into a CC 2800 with a 72 meter main boom and superlift. Project Asian Silicone Monomer for lifting items of over 50 t and for
Location Thailand
three different phases. An AVS Services LR 1450 was used as the tailing executing 150 dual crane lifts. The
Customer Sankyu
crane. Even though the indicator was positioned lifts of the cryogenic heat exchang-
Main equipment Conventional trailers, prime movers
Phase 1 was subdivided into a number of separate virtually on the limit, there was only minimal clearance ers were very impressive.
stages. The first tank, the Feed Surge drum, was trans- between the platforms and the main boom.
ported to the plant by using a total of 34 axle lines The Tower was lifted into position on the 18 meter The delivery, lifting and positioning
Highlight
Goldhofer trailers. The Vacuum Tower was unloaded in tall concrete foundation without any problem. in a very confined area left no room
the Port of Pascagoula using the M4600 ringer. The unit B&J Mammoet won a contract to transport a number of for error. Mammoet was warned of
was then placed on a pontoon, unloaded at Chevron’s In the final phase Mammoet replaced six Coke drums reactors with a total weight of 12,500 t from the port of an imminent cyclone when it still
dock and driven into the plant with just a few centime- and three derricks using the CC 12600. This crane lifted Maptaput to the Asian Silicone Monomer site. Sankyu, had 20 booms to lift. But thanks to
Highlight
ters’ clearance. In the same week, the first shipload of the 300 t units and positioned them at a working radius a company with operations all over the world, is special- hard, steady work the last boom
Coke drums arrived at the port. After that the Coke of some 70 meters, overhead of three smoke stacks, ized in logistics and engineering solutions and has The LNG 4 project in western was soon removed.
drums were safely transported to the lay- each of which was 75 meters high! assumed overall responsibility for the project from JGC. Australia is the largest project of its
The largest reactor was 61 meters long and 5 meters expressed in centimeters than in meters. Mammoet kind undertaken on the continent. The cyclone, however, never mate-
wide and weighed more than 200 t. The 12-kilometer delivered the cargo safely and subsequently lifted it into Mammoet had a large part to rialized and in the end we had only
route brought Mammoet along such roads as the position. The distillation reactors will be used to convert play in the construction, using a a few inquisitive kangaroos to deal
famous Sukhumit No. 3 motorway, where Mammoet was crude oil into finished products such as petrol. CC 2800, a CC 4800 and a crew with.
confronted by obstacles with clearances that are better of 25. Mammoet was responsible

Many roads lead to Jose


Hamaca Crude Upgrader Project
Project
Venezuela
Location
Fluor Daniel/Grupo Alvica
Customer
Conventional trailers, SPMTs, pontoons,
Main equipment
Demags CC 1400, CC 2600 and CC 12600.
Heavy Lifting on the sunny island of Trinidad
Highlight Project Atlas Methanol Plant and Hydro Agri
Location Trinidad
The Hamaca Crude Upgrader Project in Jose, Venezuela, involves the con-
Customer Paramount and Lurgi
struction of a completely new refinery. Mammoet’s contribution to this pro-
Main equipment Conventional trailers, MSG-50, Portal gantry crane
ject was to receive all the heavy lift items in the port of Guanta, transport
them to the Jose industrial estate some 50 km away and then lift and install
them. The heaviest items were two 250 t reactors, a 660 t vacuum tower, a
Highlight
700 t reactor, various reformer modules, two 500 t coke structure decks and the site. Two 900 t strand jacks lift-
four 320 t cylinders. They were transported in three ways: items up to 70 t Mammoet was contracted to carry ed the vessels and installed them
were transported by road, items between 70 and 350 t were transported out the heavy lifting operations on their foundations – whilst the
using a small pontoon (50 x 15 m) and items over 350 t were transported required during the construction of plant was on-stream.
using a large pontoon (90 x 30 m). a new methanol plant in Trinidad.
A MSG-50 was used to lift and
When the equipment arrived at the quay at the refinery, it was stored tem- erect three vessels varying in weight
porarily near the foundations. Various cranes were mobilized for the lifting between 209 to 600 t. The MSG’s
and installation, including a Demag CC 1400, a Demag CC 2600 and a 102 meter main boom provided
Demag CC 12600. 48 lines of SPMT trailers, 16-axle Goldhofer trailers and ample outreach for the positioning
additional equipment was used for the transport. of the columns on the foundations.
A portal gantry crane was used to
install a 600 t reactor vessel and a
490 t boiler in a confined area. At
the same time a 365 t reactor was
placed on its foundations at the
nearby Hydro Agri plant. The reac-
tor had been manufactured in Italy;
it was loaded onto an ocean-going
vessel at Porto Maghera and trans-
ported to Point Lisas, in Trinidad,
where the reactor was collected on
conventional trailers and brought to

Mammoet World 2003 Page 6 Mammoet World 2003 Page 7


Trends in the market

In a world where Mammoet and FC Utrecht: a perfect match


time is of the
essence, a con- Project FC Utrecht Stadium
Location Utrecht, Netherlands
tinuous process
Customer Hardstaal b.v.
is underway to

Civil
Main equipment Demag CC2800, Liebherr LR-1450HD and Sennebogen S-5500SL
find ways of
saving construc-
tion and/or instal-
Highlight
lation time. Besides improving
the efficiency of existing methods, Mammoet recently played a nostal- the load, along a levelled track
new construction and installation gic home match in FC Utrecht’s paved with steel mats to the loca-
procedures are being developed. HST line in Belgium “Galgenwaard” soccer stadium. The tion in the stadium where the steel

One of these new developments


is the procedure to build the com-
MAMMOET
EUROPE
 Project High Speed Line
Location Antwerp, Belgium
stadium is currently being renovat-
ed; during the construction work a
135 meter and 220 t support beam
construction was to be positioned
on the some 30 meter tall supports.
The complicated lifting/transport
Customer Herrenknecht
plete structure near to the final had to be lifted into place for the operation proceeded without a
Main equipment Conventional trailers, prime mover, 650, 400 and 120 t hydraulic cranes
location. This procedure minimizes new roof on the south side of the hitch. A S-5500SL crane placed the
disturbance of normal processes pitch. The lifting plan included the supports for the truss. The specta-
and decreases the total construc- use of three lattice boom cranes. tors invited to watch the proceed-
Highlight
tion time. A good example of this The CC 2800 and the LR 1450 HD, ings watched open-mouthed from
method is a project in the UK, The construction of the high-speed train (HST) line in Belgium both fitted with a superlift, lifted the the grandstand on the north side,
where Mammoet transported into included the construction of two bored tunnels for the subterranean futuristic roof truss to a height of and applauded once the beam was
position a complete railway bridge “Koningin Astrid” roundabout and the “Dam” roundabout section of approximately 20 meters. Next, the in position on the supports.
of 10,000 t using the hydraulic the line in Antwerp. crane masts were then swivelled to A Spiering crane was used to
skidding system. manoeuvre the truss into the assemble the roof construction for
required orientation. Both cranes the tribune on the south side of
The railway bridge was construct- were then moved, whilst carrying the stadium.
ed near to the existing railway.
Due to this installation procedure
the railway was only blocked for
4 days. Mammoet is increasingly
involved in projects based on this
principle. To enable our clients to
derive the maximum advantage
from this procedure, it is very
important that Mammoet is Herrenknecht supplied the tunnelling Portugal, here we are
involved at an early stage. In this machines; Mammoet was requested to
way our clients should be able to transport the various sections of the Project Pier removal
Location Oporto, Portugal
optimise their construction method drilling machines from the factory to the
Customer Nesco Entrecanates Cubiertas
based on the transportation/instal- site. Seven sections were too large for
Main equipment Strand jack system, jacking towers,
lation possibilities that Mammoet road transport, and consequently they
skidding system
can provide, combined with the had to be moved over water. These sec-
knowhow of the Mammoet tions varied between 70 and 140 t in
Highlight
employees. weight, with dimensions of up to 4.15 m
in height, 8.28 m in width, and 14.2 m in After the completion of the new bridge over
Jan Kleyn length. the river Douro in the city of Oporto, Portugal,
Director Operations Mammoet was awarded the contract to
Projects Europe An inland vessel brought the drilling sec- remove the two 800 t auxiliary piers. The first
tions to the port of Antwerp, where they task involved the use of the auxiliary crane on
were unloaded using a 650 t hydraulic the site to insert the lifting axle through the
crane. Three sections were temporarily pier and the rotation point for the tailing oper-
stored on supports in the harbour; the ations. The next phase was comprised of the
remaining four were transported directly High and Mighty assembly of the skidding system and the con-
to the construction site by 9 and 12 axle- struction of the lifting towers.
line trailers. At the site a 400 t crane lift- Project Renovation overhead crane at the Oxys Steel plant
Location IJmuiden
ed the various sections into the entry pit. Once the strandjacks were under tension the
Customer Corus
The remaining four sections of the auxiliary pier was cut free at the base and
Main equipment Gantry lifting system, SPMTs
drilling machine were assembled using a lowered to the bottom. However the entire
650 t and a 200 t crane. Once the first operation needed to be repeated on the other
tunnel had been completed the sections bank of the river – where there was no space
Highlight
of the drilling machine were lifted from 21, which was shifted outwards over the first whatsoever. A 45 t Liebherr crane lowered 65
the exit pit and then lowered and assem- Mammoet was contracted for the lifting and crane and lowered onto SPMTs. The crane meter from the bridge was used to assemble
bled in the entry pit ready for the drilling transport operations involved in the renovation beam was then transported by land and water the jacking towers, which were then skidded
of the second tunnel. of Loading Crane 21 in the Oxys Steel Factory to Messrs Duyvis, in Koog a/d Zaan, for reno- into their final position.
2 at Corus’ IJmuiden plant. Since Loading vation. The crane, weighing about 850 t, was
Crane 21 was located in between two other subsequently returned to IJmuiden in the The greatest problem confronting the team
overhead cranes it was necessary to disman- same manner. On its arrival Loading Crane 21 was the complete lack of clearance between
tle one of the outermost cranes to gain access was lifted with the strandjacks and returned to the lifting tower and the existing rock-face.
The right equipment for the right job to the overhead crane. Mammoet constructed its position using the temporary beams. The However once rock had been cut away from
an extension comprised of two beams bearing three cranes have since returned to full opera- the surface at several locations it was never-
Project Transport of concrete fly-over eight 900 t strand jacks to remove the outer- tion, whereby they are used to transfer the theless possible to lower the second pier
Location Badhoevendorp, The Netherlands
most crane and lower it outside the mill. Free pots carrying iron melt from one location to using the jacks in the appropriate – and safe –
Customer Combinatie kunstwerken A5
access was then available to Loading Crane another in the mill. manner.
Main equipment SPMTs

Highlight

Mammoet transported and positioned a concrete fly-over of 120 meters A ‘cast-iron’ performance…
long with a weight well over 3,300 t. This giant links a newly constructed
highway in one of the busiest traffic centers of The Netherlands. In total Project Dismantling a steel railway bridge
Location Brussels, Belgium
134 axle lines of SPMTs transported the fly-over to the foundation in two
Customer Campenon Bernard SGE-BPC-Abeb
hours. Because of the extensive pre-engineering the applied solution
Main equipment PC 4200
called for closing the surrounding highway just for one weekend instead
of almost a year, initially scheduled by our customer.

Highlight
were attached to the railway bridge. tional models the bridge would be
Mammoet deployed a PC-4200 in The parallelogram-shaped bridge very rigid – but in practice it twisted
Brussels to dismantle a steel railway sections had already provided for to an extent such that it was not
bridge dating from 1926. The job the necessary brainwork, whereby a safe to continue. After some discus-
involved the removal of a bridge variety of computational models had sions between the parties involved a
with a span comprised of four fields, been employed to determine the solution was found: additional slings
with a total weight of 750 t. A num- correct location of the lifting points. and shackles were fitted to the two
ber of railway tracks alongside and At 10.30, Mammoet began the lifting outermost corners, and at 12.15
under the bridge were subjected to operation at 10.30; once some 150 t Field one was lifted in a safe and
intensive daily use, and consequent- were pulling on the 190 t section of responsible manner. The other three
ly lifting was permitted solely during the bridge it became apparent that fields were lifted out of the way in
specified periods in the weekends. theory and practice could occasion- the same manner, and to everyone’s
Mammoet’s time-window began at ally be quite remote from each full satisfaction – all in all, a ‘cast-
09.00. A total of 8 demolition chains other. According to the computa- iron’ performance.

Mammoet World 2003 Page 8 Mammoet World 2003 Page 9


Skidding a railway bridge
Project Positioning railway bridge
Sporting Lisbon Stadium
Project Construction of Sporting Lisbon Stadium
MAMMOET
AMERICA’S
 TITAN System Meets Interstate 76
Project Removal of railway bridge
Location Sachsen-Anhalt, Germany Location SIMI, Portugal Location Pennsylvania, USA
Customer Industriemontagen Leipzig GmbH Customer Lisbon, Portugal Customer Alan A. Myers
Main equipment Skidding system, telescopic boom cranes Main equipment LR 1250, M 888 Main equipment TITAN lifting system, SPMTs

Highlight Highlight
The bridge was ‘launched’ using Mammoet’s skidding contracts for the new-building at all
system. This involved the use of an inverted skid con- In Portugal there are currently three three stadia, which includes the Mammoet’s TITAN Lifting System recently Mammoet prepared for the lift by assembling a
struction between the rails, whereby the skid shoes stadiums being built for the 2004 Sporting Lisbon stadium. Activities proved to offer the perfect solution for the relatively short TITAN tower (just 4 meters tall)
were fixed in place and the bottom girder of the bridge European soccer championship. comprise the lifting of more than removal of a railway bridge in Philadelphia, on SPMTs. Once the highway was closed the
served as the skidding track. To achieve the correct Mammoet has been awarded the 1000 roof sections ranging from 35 Pennsylvania, USA. Subsequent to a meeting SPMTs were moved under the bridge – and just
height the skid shoes were mounted on boom sections ton to 45 t. A Liebherr with the client Mammoet proposed that the two hours later the bridge had been lifted,
and load spreaders designed especially for the purpose. 1250 with a 46 meter highway be closed completely in the middle of moved 100 meters from the road, and offloaded
A skid plate fitted with Teflon blocks was mounted on main boom, a 47 meter the night, when traffic would be lightest. It ready for demolition in complete safety. The
the skid shoes. Once the actual transport began the luffing jib and a would then be possible to lift the entire bridge client was extremely satisfied with the new,
bridge was skidded from boom to boom; the lateral Manitowoc 888 are cur- and move it to one side of the road, where the rapid demolition technique.
Highlight
guides fitted to the skid plate provided the necessary rently working for a peri- bridge could be dismantled without causing any
Mammoet was contracted to move a 680 t bridge over means to make any corrections to the transverse move- od of 12 months to inconvenience to traffic. In contrast, several
nine railway tracks at Dessau, Germany. The short time ment of the bridge that were required. The bridge was complete this massive weeks are required when cranes are used for
spans during which the railway tracks were free of trains moved to the other side of the railway tracks in a three- task. Once finished, the conventional on-site disassembly of bridges
rendered this an extremely demanding job for the night period (10 hours) with an accuracy of 5 mm. 70,000 spectators will over roads.
Mammoet specialists assigned to the project. be able to watch their
favourite team playing.

Engineering on a high level


Project Central Artery/Tunnel project

UK’s biggest bridge slide Location Massachusetts, USA


Customer SIWP
Project Channel Tunnel Rail Link (CTRL) Main equipment TITAN gantry system, SPMTs
Location Northfleet, UK
Customer Rail Link Engineering ( RLE)
Main equipment SPMTs, skidding system Highlight
system. Two towers were built on 44 axle
For the construction of the second level of lines SPMT. The launching girder, which has
concrete viaducts, a huge overhead crane the ability to move by cantilevering itself over
Highlight
length of the bridge. Compliance needed relocation to a 8 meters higher posi- larger distances, was then “launched” onto
Mammoet was awarded the con- with this stringent tolerance was tion. SWIP considered the full disassembly of Mammoets towers. Finally, the cargo was
tract for the transport of a newly- achieved by the computerization of the launching girder and re-assembly at the moved sideways onto the concrete piers. The
constructed railway bridge in the entire skidding operation. A test higher elevation. However, since this process complete operation, including the (de) mobi-
Northfleet near London. Inclusive of slide was performed to verify the was estimated to take 3-4 months. SWIP lization of equipment, was completed in less
the abutments and piers this 9,500 t system, and to demonstrate to RLE needed a quicker alternative. Mammoet than three weeks.
giant bridge was 100 meter long, that transport within the stringent explored the possibility of lifting it in one
15 meter high and 15 meter wide. tolerance was a feasible proposi- piece. Since the available space was very
Mammoet carried out this challeng- tion. Once the last train had passed limited, Mammoet applied its TITAN jacking
ing contract by the use of its skid- the rail track was closed and demo-
ding system, comprised of 30 skid lished. When the “ready to go” sig-
shoes each with a capacity of 600 t. nal was given the complete bridge
was jacked up and then transported
During the transport only a very over a distance of 50 meter to its
limited deflection in the deck was final position. The first trains ran
permitted – just 16 mm over the full again on Tuesday.
Houses on the run
Project Home delivery project
Location Cambridge
Customer Mattamy homes
Main equipment Skidding system, SPMTs

Highlight
weather. Moreover overhead cranes will allow
Mammoet Canada Eastern was recently building materials of larger dimensions to be
RLE stated: “We congratulate every- During this same weekend entailed the use of standard CSC- awarded a contract for the transport and posi- used during the construction work. Once the
one involved for an extraordinary Mammoet also installed Bridge certified containers as packing tioning of 1000 houses. A major local real- houses have been completed they are trans-
engineering achievement. This was Structure N-160. Mammoet engi- between the SPMT bed and the roof estate developer, Mattamy Homes, is building ported to their final location, and placed on
a highly complex job performed neered another solution for the of the bridge structure, inclusive of the new homes in a new district in Cambridge. the foundations using Mammoet’s skidding
under intense time pressure and in transport of the bridge (65 meter the transport beams at both ends. Mattamy decided that the company would not system. Each house is 15 meter long, 12 meter
physically constrained worksites. It long and 2250 t). This solution These containers made it possible use the conventional construction method, wide, 15 meter tall, and weighs 60 t.
goes to show what can be achieved employed 88 axle-line SPMTs. to use much lighter steel support whereby houses are built on their foundations; At a rate of about one house a day the project
through preparation and partnering.” The preparations for the transport structures. instead it would build them indoors in a will extend over a period of several years.
special construction facility, where the work
would be unimpeded by cold and/or wet

Ship extension MV! Gariep


Project Ship lengthening
MAMMOET 
ASIA
Location Hebburn, UK
Customer A&P Tyne
Main equipment Jacking and skidding system, SPMTs
Precision skidding operation
Project MV Ross Sea Project
Highlight Highlight Location Malaysia
Customer MSE
Mammoet was awarded a contract to assist in Skidding System. This jacking and skidding pro- The MV ROSS SEA project in
Main equipment SPMTs, skidding system
the transport operations involved in the length- cedure was required since the building’s layout Malaysia was comprised of the FSO
ening of the mv Gariep during a complete over- precluded the use of wheeled transport. Once (Floating Storage) conversion of a
haul of the vessel. The first phase entailed cut- outside the building SPMTs were positioned tanker – a project which entailed
ting through the vessel to separate the two underneath the middle section so that it could lengthening the vessel by the under the new mid section of the of the vessel was positioned against
halves. The 3000 t bow section of the vessel be moved to a temporary location in the dry ‘simple’ insertion of an extra section. ship and then moved as close as the stern section, whereby the maxi-
was then repositioned using SPMTs with 118 dock. During the intervening period SPMTs had Mammoet was requested to carry possible to the existing mid section. mum tolerance was 3 mm. In the
axle-lines. Next, 24 axle-lines were temporarily been positioned in the dry dock ready for the out the transport involved in the fourth and final phase Mammoet’s
relocated to the yard’s construction facility for lifting of the 400 t middle section onto the trail- project. The second phase involved moving Skidding System was used to posi-
the transport of the new middle section from the ers. The middle section was then transported the stern section of the vessel 50 tion the bow section of the vessel
building. The middle section was rotated and fitted to the vessel’s stern section. The pro- On the client’s request the vessel meters from the stern section ready against the new mid section.
through 90 degrees and transported to the other ject was successfully completed when SPMTs was lengthened in a procedure com- for the insertion of the new 4000 t
side of the construction facility, where it was with 118 axle-lines positioned the bow section prised of four separate phases. In mid section. During the third phase
then positioned above Mammoet’s Jacking and against the new middle section. the first phase SPMTs were located of the project the new mid section

Mammoet World 2003 Page 10 Mammoet World 2003 Page 11


Trends in the market

In the offshore Kizomba on wheels


market we are
currently complet- Project Kizomba-A
Location Zwijndrecht
ing an extremely
Customer Heerema Zwijndrecht
busy first half of

Offshore
Main equipment SPMTs, jacking, weighing and ballast systems
2003, involving
some fairly heavy
load outs – inclu-
Highlight
sive of one operation in which we each module onto the barges. Since the
almost broke our own world record The Kizomba A project constitutes the first barges were to be loaded at high tide both
on the load out of the 10,500 t phase of the development of four West load-outs began early in the morning.
Kvitebjorn main deck. However African oil fields discovered in Block 15, off Mammoet cranes also assisted in the com-
although we have been remained
fully occupied to date, we have
nevertheless observed an overall
MAMMOET
EUROPE
 Angola’s coast. This phase includes the
installation of a surface wellhead platform
(SWHP) linked to a floating production, storage
pletion of the topside modules, which were
moored alongside the yard.

slow-down in the offshore market, and offloading (FSPO) vessel. The Kizomba-A
especially in North-Western Europe. SWHP is comprised of six separate modules
This is a somewhat surprising manufactured at various locations around the
development in view of the current world. The two topside modules were manu-
oil prices, since at their present factured by the Heerema Fabrication Group,
level they render the development in Zwijndrecht.
of even marginal fields a viable
proposition. We have also observed Mammoet was contracted to transport the
a trend towards subsea develop- topside modules, each weighing some 6000 t,
ment and large floating units. To from the construction hall onto the ocean-
date subsea development has pro- going barges. Mammoet used SPMTs with
vided some work for Mammoet; 240 axle-lines for these two spectacular oper-
however the units are often small, ations, which were performed in a number of
and the work is carried out off- phases. Once the modules had been weighed
shore, and at great depths. and jacked up the SPMTs were moved under
Unfortunately for Western Europe, the units in the construction hall and coupled
most of the huge floating units are together. Some 5 hours were required to load
built in the Far East. Nevertheless
some companies have been suc-
cessful in ordering the steel in the
East and having the mating work
and detailed outfitting carried out in Kvitebjorn
Europe; examples are the Kizomba
and Bonga projects. Project Kvitebjorn Field
Location Haugesund, Tonsberg and Stord
In a favourable development in
Customer ABB Offshore systems, Heerema Tonsberg and Leirvik Module technology
Norway some huge projects for on-
Main equipment SPMTs, Jacking, weighing and ballast systems
land modular plants have now been
commenced. These projects gener-
ate work for our wheels/cranes and Lifting operation at sea Highlight
our special techniques. Moreover Mammoet crew was hard at work on had carried out a final check the
the time is approaching when off- Project Burlington Calder Project UK The Norwegian Statoil oil and gas the unloading and assembly of the green light was given to start the
Location Irish Sea
shore structures will need to be company has constructed a large axle lines. Mammoet’s ballast sys- transport. Within two days the enor-
Customer Suction Pile Technology
removed, although it is difficult to production platform for the develop- tem was also required for the job, mous platform had been loaded
Main equipment SPMTs, eight 900 t strandjacks
estimate the timetable for the actu- ment of the Kvitebjorn field. The and consequently pumps, water safely on the pontoon. Once again,
al work. Fortunately we can sections of the platform were con- pipes and power packs were Haugesund’s ABB had completed
observe that essentially the same structed by different yards; the installed on the pontoon. In the final yet another eye-catching offshore
Highlight
engineering and construction com- the ability of the entire platform to drop into position; the suction- drilling modules were manufactured stage of the preparations all 48 axle structure – safely moved by
panies play an important role in the The project involved the installation install itself using the double-action anchor technology ensured that by Heerema Tonsberg, and the living lines were coupled in long rows and Mammoet.
new remote developments. of the “Rivers Field Calder Platform” strandjacks modified especially for they became anchored in the sea- accommodation by Leirvik Module, a total of 1664 wheels were moved
Mammoet, as a solutions provider, in the Irish Sea, some 40 km from the purpose. SMPTs had already bed. The strandjacks were then in Stord. Mammoet transported all under the platform. Once the client
can offer the expertise it has Holyhead. Since the work was unloaded the 650 t wellhead plat- used to lift the entire deck up the the sections to Haugesund. In
acquired in developing into an largely dependent on the tide the form; once the four legs had been legs, and in the final phase the deck Haugesund, the largest section of
international global player in trans- project was executed according to collected from Genius Vos in was firmly secured in position. This the production platform was manu-
port and lifting work. a tight time schedule. Fortunately IJmuiden and lifted into the module new method of securing offshore factured by ABB offshore systems
the weather co-operated, and the the journey to the final location at platforms on the seabed does not and consequently the completed liv-
Frans Segeren, oil and gas platform was installed in sea could begin. On arrival at the require the use of divers to release ing accommodation was fitted to the
Market Segment Manager Offshore a record time of 40 hours. The ultimate destination Mammoet used the pilings – consequently resulting production platform at this location.
unique feature of this project was the strandjacks to allow the legs to in a much safer procedure.
Before the enormous structure
could be moved out of the con-
struction hall Mammoet’s computer-
ized weighing system verified the
pre-calculated weight of the plat-
form; the precise weight was 10,500
t. In the mean time a 20-man

Conversion of MS Rocknes
Project Ship lengthening
Location Botlek, Rotterdam
Customer Keppel-Verolme
Main equipment Conventional trailers, two AC 650 cranes
12,000 t Murphy Medusa loadout
Project Murphy Medusa
Location Middle East
Highlight Customer McDermott
Main equipment Strandjacks, skidding system
MS Rocknes, a ship owned by Van Oord, was dry-
docked at Keppel-Verolme for a large-scale conver-
sion. One of the sections for this conversion was
Highlight
fabricated in Poland and subsequently shipped by
pontoon to Rotterdam. On instructions from McDermott Middle East, The total sliding distance was about 200 meters.
Mammoet undertook a load-out of a buoy. It The average speed was about 10 meters per
Once there, it was offloaded with a floating crane. was a floating oil storage buoy, with a length hour. The job was completed successfully in
It was then placed onto a Keppel-Verolme trailer, of 180 meter, a diameter of around 30 meter three days, resulting in two further orders for
which was moved alongside the MS Rocknes. and a weight of no less than 12,000 t! Mammoet from Mc Dermott.

Mammoet was contracted to position the 120 t Mammoet’s instructions were to pull the buoy
weighing section from the quay onto the ship. After onto a pontoon using four 900 t strand jacks.
a thorough preparation by the staff of both Keppel- The client provided the sliding system. First,
Verolme and Mammoet’s Technical Sales dept., the the buoy was released and pulled to the
task was completed to everyone’s satisfaction using quayside, from where it could be pulled onto
two AC 650 cranes. the pontoon.

Mammoet World 2003 Page 12 Mammoet World 2003 Page 13


Trends in the market

Completing a puzzle…. The global power


segment has
Project SNEPO Bonga Project undergone an
Location Nigeria & The Netherlands
overall market
Customer Amec, Heerema Fabrication Group
correction during

Power
Main equipment SPMTs, Jacking, weighing and ballast systems
the past 12 - 18
months, largely
due to the severe
Highlight
and centers of gravity. The work was carried cutbacks in the construction of new
The Bonga oil and gas field, which was dis- out in severe weather conditions – a very high power generation plants in the


covered in 1995, is about 120 km South West humidity, and average temperatures of 35 North American market. The phe-
of the Niger Delta and at a depth of in excess degrees. On the successful conclusion of the nomenal growth experienced in the MAMMOET Farming the wind
of 1000 meters below sea level. Shell will job Amec thanked the Mammoet team for their fossil-fuel arena from the late
extract oil and gas extraction from the Bonga excellent, professional and safe completion of 1990s until early 2001 has come to
EUROPE Project Wind Farm project
Location Rotterdam Europoort
field using a FPSO (Floatable Production the load outs. a virtual standstill. Although this
Customer Nordex Energy GmbH
Storage and Offloading facility). Most of the slow-down in the industry has had
Main equipment CC 2800 lattice boom crane, 300 and 120 t hydraulic cranes
construction work for the FPSO has been con- Mammoet also worked on the Bonga project an impact on the volume of pro-
tracted to Amec, a large offshore construction in the Netherlands, where Mammoet trans- jects, it has nevertheless opened
company in Wallsend, UK. The various sec- ported seven modules with weights varying the doors to other opportunities
Highlight
tions of the structure were manufactured by from 500 to 2200 t for the Heerema within the segment, such as stor-
and collected from countries around the Fabrication Group at Zwijndrecht. age sites, plant relocations, service, The Wind Farm Project is the first substantial deploy-
world. On the completion of a number of the repairs and replacements of ment of wind-turbine technology by both BP and
sections of the FPSO in Nigeria Mammoet was machinery. Mammoet has been ChevronTexaco. Mammoet’s share in this project was
requested to ensure for the load out of three highly active in these markets, and comprised of the provision of the cranes and staff
sections. Each section first needed to be although the concern has been required for the installation of nine wind turbines with
weighed to determine its precise weight; the unable to maintain the rate of an 80 m tower. Mammoet used a CC2800 (96 meter
SPMTs also had to be coupled in a specific growth of the past 5 to 6 years main boom and 100 t superlift) in combination with
configuration for each section to accommo- Mammoet has nevertheless been a 120 t hydraulic crane as the tailing crane for the
date the differences in weight, dimensions, able to focus its energy on the tower sections. A 300 t hydraulic crane was deployed
retention of the concern’s market for the installation of the individual vanes. To minimize
share within this segment. the risks involved in the installation Nerefco imposed
a requirement on Mammoet stipulating that the
The continued growth of Green CC2800 crane should be dismantled prior to each
Innovative and safe in Louisiana Power in the USA, Canada and relocation. However subsequent to the installation of


Mexico offers another major oppor- some turbines Nerefco permitted Mammoet to move
Project Falcon Nest tunity to Mammoet. Green Power is the complete crane with boom, subject to the proviso
MAMMOET Location Iberia, USA
extremely environmentally-friendly, that this took place outside the perimeter fence and
AMERICA’S Customer Omega Natchiq Inc
since it involves the use of sustain- that the boom was directed away from the plant.
Main equipment Gantry lifting system, weighing system, SPMTs
able sources of energy such as
wind, thermal, and hydro resources The project will result in the generation of an amount
in the generation of power. of electricity equivalent to the needs of 20,000
Highlight
Mammoet has been highly active households – and reduce CO2 emissions by 20,000 t
The Falcon Nest project is a classical exam- in the transfer of the concern’s per annum.
ple of innovation, whereby Mammoet and knowledge of Wind Power Farm
Omega Natchiq Inc. drew up proposals for an development from Europe to the
alternative lifting procedure for the Falcon Americas. Mammoet continues to
Nest Platform, carried out the engineering, cooperate with wind-turbine manu-
and then implemented the method. In the first facturers in the development of
phase the production deck and the main deck new and cost-effective transport
frame were stacked on each other using concepts for the continually
Omega cranes. In the second phase the two increasing size of the equipment –
stacked decks were completed and fitted with not to mention our innovative lifting
the necessary equipment and piping. The final concepts used during the erection
phase involved lifting the entire 1,500 t of the turbines. Mammoet has also
assembly using Mammoet’s mast system; commenced the development of


whilst the entire unit was lifted from the the installation of wind turbines to
ground SPMTs positioned the cellar deck, of the maximum load for each lift point – mechanical completion.
MAMMOET
inclusive of the legs and load spreaders, thereby minimizing the risk of torsion or over- The Mammoet Power Segment
under the deck. The two sections were then loading. Team has made use of the opportu- AMERICA’S
mated together. nities offered by the correction in
Once the deck was finished and ready for the fossil-fuel plants to expand the
The advantage offered by this new procedure load out Mammoet used its electronic weigh- concern’s wind-power knowledge Turbine runners for China
is the ability to work at reduced heights. This ing system to weigh the entire 2,772 t deck, base and increase its market
obviates the need for large cranes, since the involving the use of measurements at 16 loca- share in the global Green-Power Project Three Gorges Power Project
Location Montreal, Canada
structure can be manipulated using smaller tions. The job was completed once the industry; nevertheless Mammoet
Customer G.E. Hydro
lifting equipment. Work at lower heights is SPMTs had moved the whole combination has also simultaneously been
Main equipment SPMTs, conventional trailers, pontoons
also beneficial to safety; this issue also onto the pontoon – in just 4 hours. preparing for the initiation of new
played a key role in the decision to employ fossil-fuel projects in late 2004 and
towers rather than cranes, since this provides early 2005.
for the pre-programming and synchronization local road-transport
Jim Hamilton, requirements and
Account Manager Mammoet USA consequently were
permitted to travel 3
km through the city
of Lachine. At the
Building a 800MW power plant end of the journey
by road the runners
Project Rijnmond Energy Center were loaded onto
Location Rotterdam, the Netherlands
pontoons for a 20-
Customer Bechtel-Enka Holland VOF, Siemens Power Generation AG
km transport along
Main equipment Floating derrick, pontoon, SPMTs, sliding gantry system
the St Lawrence
River to the Port of
Montreal.
Highlight
shipped via inland waterways to the Mammoet Yard in
Highlight
Mammoet Europe was contracted to provide for the trans- Schiedam, The Netherlands. A floating derrick was used The cost of the entire Chinese pro-
port and installation of two 310 t combustion turbines and to lift the two sets of turbines and generators onto a Mammoet was awarded a contract ject is estimated to amount to USD
two 302 t generators. second barge for transport to a ro/ro jetty near the for the transport of two large 25 billion; the work is comprised of
Rijnmond Energy Center site. The turbines and genera- hydro-electric turbine runners in the construction of a 2-km dam
Both sets of turbines and generators were loaded onto tors were then loaded onto a 12-axle conventional trailer Montreal, Canada; the runners are with a height of 185 meters across
barges at the Siemens factory in Germany, and then and transported to the construction site. two of a total of 14 that will gener- the Chang River to form a 19 trillion
Mammoet had installed a sliding gantry system with a ate electricity for the Three Gorges liter water reservoir over a distance
total lifting capacity of 400 t at the site, and consequent- Power Project in China. of 600 km upstream. The project is
ly after only a few hours the turbine was in position on scheduled for completion in 2009.
its foundations. The job was completed once the genera- Once the runners were ready for On its completion the new facility
tor was in place. transport they were moved from will be the world’s largest and most
the factory using 2 x 12 axle-line powerful hydro-electric power sta-
In between times Mammoet has installed one of two SPMTs, and then transferred onto tion, generating the equivalent of
200 t transformers; a 325 t steam turbine generator will conventional trailers with 2 x 16 the combined output of no less
be positioned at a later date. axle-lines that complied with the than 15 nuclear power stations!

Mammoet World 2003 Page 14 Mammoet World 2003 Page 15


Powered by Mammoet! Lifting through the dome
Project Hanging Rock Project
Location Ohio, USA Project Exchange of generators
Customer Duke Fluor Location Tennessee, USA
Main equipment Rail cars, mobile lifting/sliding system, Main equipment Platform Twin Ring
Liebherr LR-1450, Manitowoc M250

Highlight
was unload and transport the machinery trans- Mammoet was awarded the contract for the replace-
Mammoet was requested to transport and ported by a maximum of 15 to 20 wagonloads ment of two 350 t steam generators at the Sequoya
install 94 items of machinery and equipment per week – with just one team! nuclear power plant in Chattannooga, Tennessee.
(generators, turbines, transformers, HRSG In preparation for the job a Platform Twin Ring lattice
modules, steam cylinders and capacitors) Mammoet completed the job by installing the boom crane with a 66 meter main mast and 35 meter fly
required for a large power station south of machinery and equipment on the foundations jib was erected in a protected area. Pursuant to a strin-
Ohio, about 150 km east of Cincinnati. The using its sliding or mast systems. The HRSG gent safety policy all parts of the crane were required to
majority of the machinery and equipment was modules were installed using an AVS Liebherr undergo an inspection prior to admission to the plant. Beach Power
transported in seventy-six rail wagons. LR-1450 caterpillar crane as the main crane,
and a Maxim Manitowoc M250 as the auxil- The first phase of the work involved cutting openings in Project Brighton Beach Power
Location Ontario, Canada
Mammoet designed and constructed a unique iary crane. the dome to gain access to the containment; the con-
Customer Brighton Beach Power
mobile hoist for use in lifting the machinery from crete slabs were removed using the PlatformTwin Ring.
Main equipment Sliding system, SPMTs
the wagons onto trailers. Each unit was lifted In the second phase the existing generators were lifted
and positioned sideways on the trailer using through the dome and positioned horizontally on the
hydraulic bogies. The mobile hoist was built site using a specially fabricated tailing frame. During
Highlight
above the rail track; each unit was unloaded the third and final phase the tailing frame was used to erators and HRSG equipment. The
within an hour, irrespective of the geometry, erect the new generators, which were then lifted and Brighton Beach Power – a joint turbines and generators were built
the weight, or the number of hoisting points. carefully passed through the openings in the power venture between Ontario Power by General Electric and transported
By virtue of this procedure, ever day Mammoet station’s dome. Generation and ATCO Power – has to Windsor by rail. Mammoet
begun construction work on a new unloaded the freight using a skid
550 MW power station in Windsor, system and transported the equip-
Ontario, Canada. Mammoet was ment to the site.
awarded the contract for the trans-
The Full service providers port and lifting work required for
the installation of the turbines, gen-
Project Bethlehem Power Station
Location Pennsylvania, USA
Customer Alstom Power
Main equipment Railcars, SPMTs, weighing system, strandjack lifting system.

The looooong, narrow and winding road


Highlight Project New Power Station
access opening in the wall of the building. In
Location Connecticut, USA
Mammoet recently transported and installed the final phase of the job an overhead crane
Customer Dick Corporation
two steam turbine generators required for a lifted the generator from the sliding equipment
Main equipment Pontoon, conventional trailers, transport frame,
power station in Bethlehem, Pennsylvania. and placed it on its foundations. The same
strand jack lifting system
The generators were manufactured in Germany, procedure was used for the second generator.
and were transported to the Port of Baltimore The client contracted Mammoet to provide a
Highlight
harbour over sea. The first generator was load variety of services. Mammoet Netherlands frame. This impressive vehicle, with a length of
ed onto a railcar for the 200-km journey to the was requested to weigh the generators; Mammoet has completed the first of several 80 meters, was required for permission from
power station; on its arrival the 165 t generator Mammoet USA railway transportation group, shipments to a new power station near the Connecticut Department of Transportation
was unloaded by a portal crane, and then of the Greens Bayou branch in Houston, was Hartford, Connecticut, USA. Mammoet was to cross a long-span bridge along the route.
transported to a temporary storage location at responsible for the collection of the generator requested to transport all the heavy cargo The transports took place at night so as to
the site using 2 x 6 axle-line SPMTs. in the Port of Baltimore and its further trans- to the facility by the plant’s EPC contractor, minimize the disruption they caused to traffic
port by rail; and Mammoet Canada Eastern Dick Corporation. over the 25 km route, which passed through a
The generators were to be installed on a floor was responsible for the lifting and transport highly urbanized area. The greatest challenge
in the new steam-turbine building at a height work on site. Consequently this project con- The first phase of the project involved the confronting Mammoet was the final entrance
of 10 m above ground level. The first genera- stitutes a supreme example of the total – and transport and installation of the steam turbine to the job site – a narrow and winding road of
tor was lifted to the required height using worldwide – service package Mammoet can and generator that had been manufactured in approximately 1.5 km, and with grades of as
Mammoet’s strandjack tower lifting system, offer its clients! Japan. Mammoet collected the equipment on much as 12%. On their arrival at the site
where it was skidded 30 m through a small a barge at the Port of Newport News, Virginia, Mammoet’s 400 t capacity strand jack lifting
and then towed them north along the American system was used to lift the turbine and gener-
East Coast to a beach near Hartford, a distance ator to the required height.
of over 800 km. On arrival the equipment was
New York…New York… rolled off the barge and transported to the
construction site on a low-height transporter
Project Mirant Bowline Project comprised of conventional Scheuerle trailers
Location New York, USA
with 24 axle-lines coupled to a 450 t transport
Customer Mirant Power
Main equipment Pontoons, SPMTs, floating crane

Highlight
floating crane lifted the load onto a It ain’t half hot mum…

Mammoet was contracted for the pontoon, which was then towed to
transport of 59 items of machinery the power plant. SMPTs with 24 MAMMOET Project Various power stations
and 26,000 cubic meters of other
equipment required for the con-
axle-lines were used to unload the
turbines and transport them to their
MIDDLE EAST Location Oman, Qatar, United Arab Emirates
Main equipment Cometto trailers, prime movers, skidding- and jacking systems
the Qida power station in the United Arab
Emirates, where Mammoet had been awarded
struction of a large power station foundations. the contract for the transport and installation
on the Hudson River in the State of all the heavy machinery and other equip-
of New York. During the second phase of the pro- ment required for the expansion.
Highlight
ject Mammoet was responsible for
The combustion turbines for the the transfer and transport of a fur- In a contract awarded via Mammoet’s Italian The generators, turbines and transformers
power station were manufactured in ther six steam drums and 16 HRSG joint venture partner, Mammoet Palumbo, were transported using Cometto trailers and
Greenville, South Carolina. In the modules with weights of up to 190 t. Mammoet Gulf was requested to install all the then installed using Mammoet’s skidding and
first leg of the transport the turbines heavy machinery required for a new power jacking equipment. The work was carried out
were moved by rail to the port at station in Barka, Oman. The machinery was in the power station whilst it continued to
Newport News, Virginia, where they delivered to the port of Mina Qabooz, in generate electricity; consequently on occasion
were transferred onto pontoons by Muscat, and was then transported over a there was very little clearance for the trans-
a port crane prior to their 550-km distance of 60 km to the site. ports under the existing pipelines that were
journey over sea to New York. On still in operation! Moreover the work was car-
their arrival the combustion turbines All transports, which took place at night, ried out during the hottest period of the year,
were unloaded from the pontoons made use of 14 and 16-axle Cometto trailers. when temperatures could reach as high as 53
using SPMTs with 12 axle-lines, and The route included a steep hill just outside the degrees Celsius.
were then transported to the power port, as a result of which Mammoet had to
station. The steam turbine and the make use of 8x8 MAN and 6x4 Mack prime In Qatar Mammoet is currently engaged in
steam turbine generator, with a movers to tow the trailers. work on the expansion of a gas factory which
weight of 370 t, were manufactured During the same period Mammoet was also involves the transport and installation of a
in Albany, New York State. A 500 t occupied with work on a major expansion of total of 60,000 t of equipment.

Mammoet World 2003 Page 16 Mammoet World 2003 Page 17


Market Developments EMD
Local alliances create added value Quality in everything we do
Patrick Freericks recently became Local regulations, difficult accessibil- permanent basis, for instance a 500 the Rio Polimeros project I men- Over the whole range of horizontal We employ highly rated engineers,
a member of Mammoet’s Board of ity, language and culture differences t hydraulic crane. The same develop- tioned. Or take Mammoet Palumbo. and vertical transport work, the designers and operators who know
Management. He has succeeded all pose special challenges. Another ment can be seen in Denmark. We It started with 24 axle lines of quality of the services provided is exactly what the equipment perfor-
Roderik van Seumeren in charge of area of expansion I would briefly satisfy customer requirements either SPMTs. They have been fully booked of profound importance. Any mis- mance is and where the safe-opera-
Mammoet Global and thus the compa- mention is Brazil. We won a very directly or in joint ventures and and we are planning to expand the handling or serious delay could tions envelope is. Even if new
ny’s overall commercial operations. large lifting contract from ABB / strategic alliances with local service fleet. A last example is our joint ven- have an enormous impact on the equipment is being commissioned,
He shares some of his visions with us. Snam Progretti there that will be providers.” ture with Kranringen Wind. It was customers’ investments and pro- we know exactly what to expect.
executed by our joint venture, established in 2001 and now oper- ductivity. Jan van Seumeren Jr. This is because we maintain strong
Patrick Freericks Although these are hard times in eco- Mammoet Irga. The contract is an Do you foresee any special ates two CC 2800 cranes, one TC Jan van Seumeren Jr. explains that Mammoet’s outstand- relationships with our equipment
Managing Director nomic terms, can you identify areas in important boost to the joint venture’s developments that customers want 2800, one TC 2000 and a 500 t Managing Director EMD ing track record is founded on the providers. In many cases, we are an
Mammoet Global which Mammoet can expand? further successful development.” to be achieved? hydraulic crane. This reflects the professional skills and training of integrated part of the design
“There are certainly areas that are “The general trend is to increase growth in activity for the installation its operators and the well-managed process. The direct involvement in
truly emerging markets. Examples Are there any opportunities for the number of solution options from of wind farms. Combining the best maintenance of its equipment. the design process also makes it
are Australia, China, the Sakhalin expansion in established markets, which customers can choose. that the parties have to offer in a easier to standardize our equipment.
Island area in Russia and the such as Europe? To do so, we have to use a versatile, joint venture is an essential part of Quality of service is certainly a com- The fewer different types of equip-
Caspian Sea area. We have already “There certainly are. In Scandinavia, young equipment fleet. Take our strategy to stay successful. By petitive edge that drives Mammoet’s ment there are, the more effective
concluded contracts in these regions the activities in the offshore market Mammoet Irga for instance. We entering into strategic alliances with success. But how do you manage to our maintenance and management
and work is in progress to expand do continue and onshore activities started this joint venture in 2001 with local partners, the local content cre- preserve the high quality level? can be. Our Equipment Manage-
our activities quickly. However, these are even increasing in that area. five cranes. In 2002 we increased ates added value for our customers.” “Our world of heavy lifting and ment Department (EMD) does a great
are not the easiest parts of the globe That is why we have allocated more this resident fleet with an LK 1400/1, transport is chiefly one in which pro- job to combine ‘keep it simple’ with
to do business in. equipment to Northern Europe on a which today enables us to execute fessional skills and in-depth know- ‘go for the best possible quality’.”
ledge of equipment are mandatory.
What about the maintenance proce-
Mammoet Van Oord dures to prevent any technical flaws
in the equipment’s performance? applied for all vehicles, auxiliary fore kept to a minimum. As a result,
“It is just as important as the knowl- equipment and cranes with capaci- our procurement policy can concen-
Subsequent to the North Sea’s heavy-lifting boom the miles from Esbjerg, Denmark. The project was brought to edge about the equipment. At the ties of 14 t and up.” trate on buying the best equipment
1990s marked the return to a more rational view of the a successful completion well before the scheduled date. heart of our maintenance manage- and we have precise records of the
use of installation equipment designed for specific jobs. ment is our Enterprise Resources What is the added value of keeping technical state of the equipment we
Super-large capacity vessels were no longer regarded as Mammoet Van Oord has been recently been awarded two Program, supported by SAP soft- such records? sell through Mammoet Trading.
the solution for all offshore installation work, and conse- other challenging projects for the 2003 season. The first ware. We keep records of equip- The records are an asset for fleet
quently increasing use was made of smaller, more flexi- project, for GE Wind, entails the installation of seven 7 x ment assignments, the maintenance management. The complete mainte- This illustrates just how seriously
ble and less expensive equipment – a trend which ulti- 3.6 MW wind turbines, inclusive of the monopile founda- history, erratic behavior reported by nance history is recorded worldwide, Mammoet takes quality and under-
mately resulted in Mammoet Van Oord’s "Jumping Jack". tions, required for the pilot-trial phase of the Arklow Bank operators and other data. For each both in the management information pins our competitive edge. In addi-
Offshore Wind Project off the coast of County Wicklow, major piece of equipment, we define system and at the cranes them- tion, all our operators are trained to
A special jacking system provides for a rapid transition Ireland. The second project, for Vestas-Celtic, entails the in advance the future maintenance selves. The track records are there- think in terms of quality and safety
from a floating to a standing platform, and vice versa. installation of 30 sets of foundations for the Scroby Sands activities and integrate them with fore available to everyone at all and they know that the equipment
This, in combination with a 2500 m2 deck area and 4000 Offshore Windfarm Project on the Middle Scroby Shoal the availability schedules. SAP times. This enables us to identify behavior will be recorded. This
ton payload, renders multiple transport and installation located off the coast of Great Yarmouth, United Kingdom. warns us in good time to prepare for trends in particular machines, to makes them even more aware of the
trips within a single project a cost-effective proposition. During this latter project Mammoet will supply the onshore maintenance set-up and execution, respond accurately to repairs and importance of working with dedica-
Last year Mammoet Van Oord was responsible for the services (crane and SPMTs) in Great Yarmouth required to which is carried out at Mammoet’s faults and to buy components cen- tion and commitment.
successful installation of the foundations for 80 wind tur- unload the foundations and load the monopiles, whilst Van own facilities. This procedure is trally and on time. Downtime is there-
bines for The Horns Rev Windfarm Project. The Horns Oord ACZ will lay the offshore export cables in the sea
Rev Offshore Windfarm (Elsam A/S) is located in North bed and construct the scour protection required around
Sea waters of about 15m in depth some 20 nautical the foundations.

Mammoet Palumbo Increasing power to erect extremely heavy loads


Mammoet Fostrans
Last year Mammoet began its new Shell, as well as a 1300 t offshore The offshore sector is witnessing 35 x 25 meters is no exception development of special devices at fore fitted with a smart mechanical
Mammoet Palumbo joint venture, module for Petrobras. an exciting and challenging trend: today. Mammoet, states that the solution device that accommodates jacking
with offices in Livorno and Milan. In March a 700 t yacht with a length In the southern countries, our joint the rapid increase in the weight of These enormous constructions are was found by using existing, stan- columns of about 1 meter. These
The company is now in full opera- of 56 m was loaded out for Benetti, venture partner Mammoet Fostrans offshore module fabrication. assembled on the ground. But when dardized equipment. "We widely have clamp holes for the jacking
tions and, according to Davide whilst four 200 t ship sections were specializes in large projects in ready, they have to be raised, load- apply standard hydraulic skid shoes mode and after each stroke, the
Andreani, Managing Operations, has loaded out and transported by barge Portugal. In addition to having Due to a different installation method out onto a barge and shipped to with a capacity of 600 t. The trick is platform rises another half meter.
already completed some spectacular from Ancona to Riva Trigoso for assisted in the building of the (float-over instead of lifting) heavier their final position where a float over to combine four of these skid shoes By inserting jacking columns, the
projects – with plenty of work in the Fincantieri (navy division). A job car- Istanbul and Tunis stadia, the com- and bigger pieces can be installed. operation will take place. To do this, and integrate their systems, stack gradually rises to 12 meters."
pipeline. In preparation for the ried out for the cruise passenger pany was also awarded the contract John Vermeeren, It is also understandable from an a special loadout truss must be hydraulics and electronics so that
Canadian Syncrude project division involved the transport of a carry out a complete factory-to- to lift the roof sections of two Manager Operations Special Devices economic point of view. Reducing the installed underneath which requires they act as one giant 2,400 t jacking An advantage of using standard
Mammoet Palumbo was requested 300 t ship section from the yard to foundations transport on the transfer Portuguese stadiums, where the number of components that have to the stack to be lifted off the ground. system. Using this system, we can equipment is that it fits into normal
to transport several exchangers from the quay, after which it was loaded of a 930 t reactor from Italy to 2004 European soccer champi- be mated in the final assembly cuts In the current jobs this elevation provide virtually any jack capacity containers and thus this super jack
the Italian factory to the quay. out and transported by barge from France. On its arrival Mammoet will onships will be held. Large projects Fostrans wants to get established in the production time and the costs height is 12 meters. How can this be that is required. For this job, we solution is easy to dispatch to any
Moreover the company has also Porto Marghera to Venice. Within the erect and position the reactor on its indeed, which, it must be added, the Mediterranean basin and is set- involved. But the technical challenges achieved? Multiple crane systems constructed eight of these giants place in the world. Once again, it
loaded out two 750 t modules for near future Mammoet Palumbo will foundations. also involved a partnership with a ting off to conquer the Maghreb are breathtaking. Can these are costly and do not offer sufficient with a total jacking capacity of illustrates Mammoet’s dedication to
local company, which enabled markets. With that in mind, commer- leviathans be manipulated and trans- capacity in cramped working 20,000 t. The stroke of the standard offering customers solutions that
Mammoet Fostrans to have access cial or representative agents are ported? Mammoet has addressed spaces. This leaves the jacking jacks is 60 cm and this will not let work safely and quickly while keep-
to any projects requiring a heavy lift. handling North Africa. Projects are these challenges with unprecedented option as a perfect alternative. us reach 12 meters high directly. ing cost within acceptable limits.
Mammoet Irga do Brasil The aggressive policy aimed at being executed, such as one in flair and is developing a jack up sys- John Vermeeren, in charge of the The four-clustered jacks are there-
entering this particular market is Algeria to transport and set down a tem to have these "supermodules"
being reinforced by the presence of 300 t reactor for the account of ABB jacked up to the required heights.
Since its incorporation in 2001 Mammoet At Usiminas, in the state of Minas Gerais, a sales correspondent agent based Company. The job involves carrying
Irga do Brasil has achieved a substantial Mammoet Irga was awarded a rental con- in Portugal. that load (27 meter length and 300 t Half a decade ago, installing an
growth by virtue of the high quality of its tract for 15 cranes required for the expan- weight) over 1800 km in the south of 11,000 t offshore platform deck rep-
work. Mammoet Irga currently employs sion of a steel mill. Greece and Spain are other markets Algeria, which is 43 days’ trans- resented the limit of the technical
cranes from 200 to 450 t lifting capacity; in Southern Europe where Mammoet portation. In Libya, gas and oil pro- ability. Today, we are carrying out a
during the course of this year the fleet will Consequently Mammoet Irga has been able Fostrans has got established. In jects are being studied that require job to lift a 14,500 t deck to a height
be supplemented by a 600 t capacity crane. to laid solid foundations for the further de- Greece, works are in progress at crawler cranes of heavy capacity of 12 meters, while an even bigger
Major projects carried out at two Petrobras velopment of Mammoet’s operations in the Titan Cement (Thessalonica), while (400,600,800 t). In Egypt, Mammoet challenge is looming: decks of over
refineries involved the replacement of a 240 t South American region, especially with res- in Spain Mammoet Fostrans has Fostrans has a contract to build a 25,000 t that need to be erected up
reactor at Minas Gerais and the lifting of pect to the major projects planned in Brazil. built a new LNG (liquefied natural gas-processing plant at Damiette. to 25 meters are already scheduled
two 270 and 230 t units at Sao Paulo. gas) plant in Bilbao. Mammoet for manufacturing at various yards
around the world. A deck of 100 x

Mammoet World 2003 Page 18 Mammoet World 2003 Page 19