SL NO Task Duration

Start of Project
Design Stage
Architectural
Concept Drawings
Design Brief Report
BOQ
Tender Drawings
GFC Drawings
Structural
Tender Drawings
GFC Drawings
Electrical
GFC Drawings
Plumbing
GFC Drawings
Firefighting
GFC Drawings
HVAC
GFC Drawings

Statutory Approvals

Tender Stage
Civil
GCC & SCC
Tender Document
Floating of Tenders
Submission of quotes
Negotiation Meeting
Submission of final quotes
Award of package
Electrical
GCC & SCC
Tender Document
Floating of Tenders
Submission of quotes
Negotiation Meeting
Submission of final quotes
Award of package
Plumbing
GCC & SCC
Tender Document
Floating of Tenders
Submission of quotes
Negotiation Meeting
Submission of final quotes
Award of package
Firefighting
GCC & SCC
Tender Document
Floating of Tenders
Submission of quotes
Negotiation Meeting
Submission of final quotes
Award of package
HVAC
GCC & SCC
Tender Document
Floating of Tenders
Submission of quotes
Negotiation Meeting
Submission of final quotes
Award of package
Lifts
GCC & SCC
Tender Document
Floating of Tenders
Submission of quotes
Negotiation Meeting
Submission of final quotes
Award of package
Execution Stage
Shell and Core
Site Clearance and Marking 2d
Proposed Bridge
Foundation
Excavation 1d
PCC 1d
Reinforcement tying 4d
Shuttering 2d
Concrete 1d
Columns
Reinforcmenet tying 2d
Shuttering 2d
Concrete 2d
Beam & Slab
Shuttering for Beam and Slab 7d
Reinforcement tying for Beam & Slab 4d
Concrete for Beam & Slab 1d
Kitchen Block (Ground Floor)
Foundations
Excavation for Footings 7d
Anti termite Treatment 6d
PCC 6d
Footing Reinforcement Tying 14d
Shuttering for Footing 6d
Footing Concrete 2d
Columns upto Plinth level
Reinforcement Tying 1d
Shuttering 6d
Column Concrete 6d
Plinth Beam
excavation 1d
pcc 2d
Shuttering 2d
Reinforcement Tying 2d
Plinth Beam Concrete 2d
Staircase GF to 1st Floor
Staircase Shuttering 2d
Staircase Reinforcmenet Tying 1d
Staircase Concrete 1d
Ground Floor
Columns
Columns Reinforcement tying 7d
Columns Shuttering 7d
Columns Concrete 7d
Beam & Slab
Slab & Beam Shuttering 20d
SlaB & Beam Reinforcment Tying 5d
Services 2d
Slab & Beam Concrete 2d
GF SLAB DE-SHUTTERING 3d
Dummy Columns @ GF slab level
Reinforcemnet tying for Columns 3d
Shuttering for Columns 4d
Column Concrete 4d
Office/Admin Block (First Floor)
Columns
Reinforcemnet tying for Columns 7d
Shuttering for Columns 7d
Column Concrete 7d
Beam & Slab
Slab & Beam Shuttering 14d
SlaB & Beam Reinforcment Tying 3d
Services 1d
Slab & Beam Concrete 1d
Staircase Head Room
Columns
Reinforcemnet tying for Columns 1d
Shuttering for Columns 1d
Column Concrete 1d
Beam & Slab
Slab & Beam Shuttering 4d
SlaB & Beam Reinforcment Tying 2d
Services 1d
Slab & Beam Concrete 1d
Dummy Columns @ FF slab level
Reinforcemnet tying for Columns 1d
Shuttering for Columns 1d
Column Concrete 1d
UG TANK
Foundations
excavation for UG TANK 1d
PCC 1d
Reinforcemen tying for UG TANK Foundation 1d
Shuttering for UG TANK Foundation 1d
Foundation Concrete 1d
Retaining wall
Retaining wall reinforcmenet tying 1d
Retaining wall shuttering 2d
Retaing wall concrete 2d
UG TANK Top Slab
Slab Shuttering 2d
Slab Reinforcement 1d
Slab Concrete 1d
Utility Block
Foundations
Excavation for footings 1d
PCC 1d
Reinforcement tying for Footings 3d
Shuttering 2d
Concrete 2d
Columns
Reinforcement tying 2d
Shuttering 2d
Concrete 2d
Beam & Slab
Shuttering 3d
Reinforcement tying 2d
Services 1d
Concrete 1d
Boiler Room
Foundations
Excavation for footings 1d
PCC 1d
Reinforcement tying for Footings 2d
Shuttering 2d
Concrete 1d
Columns
Reinforcement tying 2d
Shuttering 2d
Concrete 2d
PEB Roof
Fabrication and errection of Truss 7d
Installation of GI Sheet Roof 3d
Chimney Foundation
Excavation for footings 1d
PCC 1d
Reinforcement tying for Footings 2d
Shuttering 1d
Concrete 1d
Security Room
Foundations
Excavation for footings 1d
PCC 1d
Reinforcement tying for Footings 2d
Shuttering 1d
Concrete 1d
Columns
Reinforcement tying 1d
Shuttering 1d
Concrete 1d
Beam & Slab
Shuttering 2d
Reinforcement tying 2d
Services 1d
Concrete 1d
Compound wall
Excavation 7d
PCC 7d
Foundation for columns 15d
Columns casting 15d

Finishes
Kitchen Block (Ground Floor)
Initial works
Blockwork 25d
Electrical Conduiting 15d
Plastering 25d
Wet Works
Waterproofing and antifungal treatment 5d
VDF Flooring 7d
MEP First Fix
Plumbing lines 7d
Sanitary lines 7d
Firefighting lines 7d
Draw wire in Elect Conduits and clearing 2d
Pressure Testing 7d
Flooring Works
Granite/Vitrified Flooring 7d
Wall dado 4d
Fabrication works
Installation of SS Railing 7d
Installation of Rolling Shutters 2d
Installation of MS Doors 2d
Finishing works
Putty 1st Coat- Ceiling & Walls 7d
Putty 2nd Coat- Ceiling & Walls 7d
Boxing/Cornice works 7d
windows & Doors 7d
Painting 1st Coat ( Ceiling , Walls & MS works) 7d
Electrical Wiring 7d
DBs, switches & Sockets 2d
FINAL WORKS
False ceiling 7d
Fix all Hardware fixtures 7d
Plumbing fixtures Toilets (CP & Sanitary) 2d
Sink & CP fixtures in kitchen and utility 2d
Switch & Socket face plates 2d
FPS- Sprinkler Head 2d
Painting 2nd coat 7d
Test & check all functional points 2d
Desnagging 2d
Painting Final Coat 7d
Cleaning works 3d
Office Block (First Floor)
Initial works
Blockwork 15d
Electrical Conduiting 7d
Plastering 15d
Wet Works
Waterproofing and antifungal treatment 5d
VDF Flooring 2d
MEP First Fix
Plumbing lines 5d
Sanitary lines 5d
Firefighting lines 3d
Draw wire in Elect Conduits and clearing 7d
Pressure Testing 5d
Flooring Works
Granite/Vitrified Flooring 2d
Wall dado 1d
Fabrication works
Installation of SS Railing 2d
Installation of Rolling Shutters 2d
Installation of MS Doors 2d
Finishing works
Putty 1st Coat- Ceiling & Walls 2d
Putty 2nd Coat- Ceiling & Walls 2d
Boxing/Cornice works 2d
windows & Doors 2d
Painting 1st Coat ( Ceiling , Walls & MS works) 2d
Electrical Wiring 3d
DBs, switches & Sockets 1d
FINAL WORKS
False ceiling 5d
Fix all Hardware fixtures 5d
Plumbing fixtures Toilets (CP & Sanitary) 2d
Sink & CP fixtures in kitchen and utility 2d
Switch & Socket face plates 1d
Wooden Flooring 1d
FPS- Sprinkler Head 1d
Painting 2nd coat 2d
Test & check all functional points 1d
Desnagging 1d
Painting Final Coat 2d
Cleaning works 2d
Utility Block
Initial works
Blockwork 7d
Electrical Conduiting 2d
Plastering 5d
Wet Works
Waterproofing and antifungal treatment 5d
VDF Flooring 1d
MEP First Fix
Plumbing lines 2d
Sanitary lines 2d
Firefighting lines 1d
Draw wire in Elect Conduits and clearing 1d
Pressure Testing 2d
Flooring Works
Granite/Vitrified Flooring 1d
Wall dado 1d
Finishing works
Putty 1st Coat- Ceiling & Walls 1d
Putty 2nd Coat- Ceiling & Walls 1d
windows & Doors 1d
Painting 1st Coat ( Ceiling , Walls & MS works) 1d
Electrical Wiring 2d
DBs, switches & Sockets 1d
FINAL WORKS
Fix all Hardware fixtures 3d
Switch & Socket face plates 1d
FPS- Sprinkler Head 1d
Painting 2nd coat 1d
Test & check all functional points 2d
Desnagging 2d
Painting Final Coat 1d
Cleaning works 2d
Boiler Room
Initial works
Blockwork 5d
Electrical Conduiting 2d
Plastering 5d
Wet Works
Waterproofing and antifungal treatment 5d
VDF Flooring 1d
MEP First Fix
Plumbing lines 2d
Sanitary lines 2d
Firefighting lines 1d
Draw wire in Elect Conduits and clearing 1d
Pressure Testing 2d
Flooring Works
Granite/Vitrified Flooring 1d
Wall dado 1d
Finishing works
Putty 1st Coat- Ceiling & Walls 1d
Putty 2nd Coat- Ceiling & Walls 1d
Painting for Roof 1d
windows & Doors 1d
Painting 1st Coat ( Ceiling , Walls & MS works) 1d
Electrical Wiring 2d
DBs, switches & Sockets 1d
FINAL WORKS
Fix all Hardware fixtures 5d
Switch & Socket face plates 2d
FPS- Sprinkler Head 1d
Painting 2nd coat 1d
Test & check all functional points 1d
Desnagging 1d
Painting Final Coat 1d
Cleaning works 1d
Security Room
Initial works
Blockwork 4d
Electrical Conduiting 2d
Plastering 4d
Wet Works
Waterproofing and antifungal treatment 3d
MEP First Fix
Draw wire in Elect Conduits and clearing 2d
Flooring Works
Granite/Vitrified Flooring 1d
Wall dado 1d
Finishing works
Putty 1st Coat- Ceiling & Walls 1d
Putty 2nd Coat- Ceiling & Walls 1d
windows & Doors 1d
Painting 1st Coat ( Ceiling , Walls & MS works) 1d
Electrical Wiring 1d
DBs, switches & Sockets 1d
FINAL WORKS
Fix all Hardware fixtures 1d
Switch & Socket face plates 1d
Painting 2nd coat 1d
Test & check all functional points 1d
Desnagging 1d
Painting Final Coat 1d
Cleaning works 1d
Compound wall
Initial works
Blockwork 15d
Electrical Conduiting 7d
Plastering 15d
MEP First Fix
Draw wire in Elect Conduits and clearing 3d
Finishing works
Primer Coat 15d
External Texture 15d
Painting 1st Coat 10d
Electrical Wiring 3d
FINAL WORKS
Painting 2nd Coat 7d
Desnagging 1d
Painting Final Coat 1d
Cleaning works 1d

Structural Glazing
Finalization of Structural Glazing 2d
Procuement 7d
Installation 15d
Lifts
Procuremnet 7d
Installation 7d
Testing & Commissioning 2d
Transformer, RMU & Electrical Panels
Procurmeent 7d
Installation 2d
Testing & Commmissioning 1d
Main Gate
Procurement 7d
Fabrication and Installation 7d
Testing & Handing Over 1d
CCTV
Wiring 7d
Installation of CCTV 2d
Testing & handing Over 2d
External Plumbing & Sewage 15d
External Firefighting 7d
External Electrical 7d
HVAC 7d
Kitchen Block
Office Block
Landscape 7d
Hardscaping 2d
SoftScaping 2d
DG
Procurement 7d
Installation 7d
Exhaust Piping 2d
Testing and commissioning 2d

Roads & Pathway


Execution
Roadwork
Earthwork in Cutting & Filling 2d
Subgrade preparation 7d
Sub-base preparation 7d
Base course 2d
Wearing Course 2d
Pathways
Earthwork in Cutting & Filling 2d
Subgrade preparation 2d
Sub-base preparation 2d
Base course 2d
Laying of Pathway as per Specs 2d
Road signs
Installation of Roadsigns 1d
External Lighting
Laying of Underground conduting 7d
Wiring 2d
Installation of light fixtures 2d
76