Вы находитесь на странице: 1из 64

67.

4 Republic of the Philippines a Writ of Possession on the subject property5 consonant with Presidential
SUPREME COURT Decree (PD) No. 42.6
Manila
On January 24, 1997, the Writ of Possession7 was issued in favor of
THIRD DIVISION NPC.8

G.R. No. 158609 July 27, 2007 On May 25, 2000, the RTC issued an Order9 appointing three (3) new
Commissioners to appraise the value of the subject property. They were
SPOUSES MARIAN B. LINTAG and ANGELO T. ARRASTIA, directed to take their oath within five (5) days from receipt of said Order,
represented herein by Attorney-in-Fact REMEDIOS BERENGUER to notify the parties and their respective counsels as to the date of the
LINTAG, Petitioners, conduct of ocular inspection of the subject property, and to submit a
vs. report within fifteen (15) days from the completion of the ocular
NATIONAL POWER CORPORATION, Respondent. inspection.

DECISION On June 15, 2000, two commissioners filed a motion praying that the
RTC use the previous Commissioners' Report as basis in determining the
NACHURA, J.: amount of just compensation.10

This is a Petition for Review on Certiorari1 under Rule 45 of the Rules of On July 11, 2000, petitioners filed a Motion11 asking the Court to order the
Civil Procedure seeking the reversal of the Court of Appeals (CA) NPC to pay them or their Attorney-in-Fact Remedios Berenguer Lintag
Decision2 dated November 29, 2002 and praying that the Order3 of the (Remedios Lintag) the amount of ₱49,665.63, as the tentative value of
Regional Trial Court (RTC) of Sorsogon, Sorsogon, dated July 10, 2001, the damaged improvements.
be reinstated and affirmed in toto.
On August 28, 2000, the RTC directed Field Personnel Wenifredo A.
The Facts Halcon, Jr. and Augusto V. Ramos, Jr. to confirm that the damage to the
improvements in the subject property amounted to ₱49,665.63.12 NPC
paid the said amount.
Petitioners-spouses Marian Berenguer-Lintag and Angelo T. Arrastia
(petitioners) are the registered owners of a property with an area of
80,001 square meters, covered by Transfer Certificate of Title (TCT) No. On September 13, 2000, pre-trial was held and a pre-trial Order13 was
T-24855 and located at Barangay Bibincahan, Sorsogon, Sorsogon. issued. The case was set for trial on the merits on November 15, 2000.

On December 4, 1996, respondent National Power Corporation (NPC) However, on November 7, 2000, Republic Act (RA) No. 8974 entitled "An
filed a Complaint4 for Eminent Domain against petitioners in order to Act To Facilitate The Acquisition Of Right-Of-Way, Site Or Location For
acquire an easement of a right of way over a portion of the said property, National Government Infrastructure Projects And For Other Purposes"
consisting of 8,050 square meters (subject property) with an initial was approved.
assessed value at ₱2,468.09. NPC averred that such acquisition was
necessary and urgent for the construction and maintenance of NPC's 350 On February 14, 2001, petitioners filed a Motion14 asking the RTC to
KV Leyte-Luzon HVDC Power Transmission Project. direct the NPC to comply with RA No. 8974. In the said motion,
petitioners asseverated that pursuant to Sec. 4 of RA No. 8974, they are
On January 17, 1997, after the deposit of the initial assessed value of the entitled to 100% of the value of the subject property based on the current
subject property amounting to ₱2,468.09 with the Philippine National relevant zonal valuation made by the Bureau of Internal Revenue (BIR),
Bank, the RTC, upon an ex-parte motion of NPC, ordered the issuance of which at the time was pegged at ₱700.00 per square meter. Thus,
petitioners prayed that NPC be directed to pay ₱5,635,000.00 for the On January 14, 2003, petitioners filed a Motion for
subject property. Reconsideration17 which the CA denied in its Resolution18 dated May 15,
2003.
The Ruling of the RTC
Hence, this Petition based on the following grounds:
On July 10, 2001, the RTC issued an Order directing the NPC to comply
with RA No. 8974. The court held that RA No. 8974 is procedural in 1) The CA committed a reversible error when it declared that RA
nature, and, thus, may be given retroactive effect, viz.: No. 8974 cannot be applied retroactively because it is a
substantive law and not a remedial statute; and
WHEREFORE, premises considered, the plaintiff is ordered to pay the
defendants the amount equivalent to one hundred (100%) percent of the 2) Assuming for the sake of argument that RA No. 8974 is not
current Bureau of Internal Revenue's zonal valuation of their property retroactive, how should the petitioners be promptly paid just
consisting of eight thousand fifty (8,050) square meters affected by the compensation?
electrical project involved in this case within fifteen (15) days after receipt
of this Order. Petitioners contend that the Government's deliberate delay of payment of
just compensation is the evil sought to be remedied by RA No. 8974; that
Set the continuation of hearing for the determination of just compensation despite the issuance of Administrative Order (AO) No. 50 and NPC
to August 31, 2001 at 8:30 o'clock in the morning. Resolution No. 98-184, NPC never had the intention of making prompt
payment of just compensation; and that just compensation does not only
SO ORDERED. mean correct determination of the amount to be paid but also the prompt
payment thereof. Petitioners manifest that NPC, as observed by the RTC,
NPC filed a motion for reconsideration which was denied by the RTC in failed to pay the initial deposit of ₱32,930.00 as mandated by PD
its Order15 dated September 7, 2001. Aggrieved, NPC went to the CA via 42.19Thus, petitioners submit that they are entitled to the prompt payment
Petition for Certiorari16 under Rule 65 of the Rules of Civil Procedure. of just compensation and on account of NPC's delay in the payment
thereof, the imposition of legal interest is warranted.20
The CA's Ruling
On the other hand, NPC through the Office of the Solicitor General (OSG)
counters that RA No. 8974 is not a remedial statute that can be given
In its November 29, 2002 Decision, the CA declared that RA No. 8974
retroactive effect, and submits that Sec. 4 thereof is a substantive
cannot be applied retroactively since an initial deposit had already been
provision as it vests substantive rights; that the legislature did not intend
made and possession of the subject property had already been obtained
RA No. 8974 to have retroactive application; that the silence of the
by NPC. Moreover, the CA held that the retroactive application of said
Implementing Rules of RA No. 8974 as to prospectivity does
law would impose a greater burden on the part of the State where none
not ipso facto render it retroactive; that the RTC no longer had jurisdiction
had existed before. It would inflict substantial injury to a substantive right.
to amend its final Order dated January 17, 1997 for initial deposit and
Finally, the CA opined that RA No. 8974 itself made no mention of
possession; and that the valuation fixed by the RTC is improper since the
retroactivity. The CA disposed, to wit:
case involves an easement, and thus, NPC should be required to pay
only an easement fee.21
WHEREFORE, the petition at bench is GRANTED, and the impugned
orders are SET ASIDE. The temporary restraining order earlier issued is
The Court's Ruling
hereby converted into a writ of preliminary injunction upon the same bond
posted by the petitioner. Without costs.
The petition is bereft of merit.
SO ORDERED.
Petitioners' first ground must fail.
In the case of Republic v. Gingoyon,22 this Court held that RA No. 8974 is implication24 because the retroactive application of a law usually divests
a substantive law, to wit: rights that have already become vested.25 This is based on the Latin
maxim: Lex prospicit non respicit (the law looks forward, not backward).
It likewise bears noting that the appropriate standard of just
compensation is a substantive matter. It is well within the province In the application of RA No. 8974, the Court finds no justification to depart
of the legislature to fix the standard, which it did through the from this rule. First, RA No. 8974 is a substantive law. Second, there is
enactment of Rep. Act No. 8974. Specifically, this prescribes the new nothing in RA No. 8974 which expressly provides that it should have
standards in determining the amount of just compensation in retroactive effect. Third, neither is retroactivity necessarily implied from
expropriation cases relating to national government infrastructure RA No. 8974 or in any of its provisions. Unfortunately for the petitioners,
projects, as well as the payment of the provisional value as a prerequisite the silence of RA No. 8974 and its Implementing Rules on the matter
to the issuance of a writ of possession. cannot give rise to the inference that it can be applied retroactively. In the
two (2) cases26 wherein this Court applied the provisions of RA No. 8974,
This ruling was reiterated in this Court's Resolution23 of February 1, 2006, the complaints were filed at the time the law was already in full force and
which further states that: effect. Thus, these cases cannot serve as binding precedent to the case
at bench.
[I]f the rule takes away a vested right, it is not procedural, and so the
converse certainly holds that if the rule or provision creates a right, it As to petitioners' second ground, the parties may be guided by the
should be properly appreciated as substantive in nature. Indubitably, a following principles.
matter is substantive when it involves the creation of rights to be enjoyed
by the owner of property to be expropriated. The right of the owner to Expropriation of lands consists of two stages:
receive just compensation prior to acquisition of possession by the State
of the property is a proprietary right, appropriately classified as a The first is concerned with the determination of the authority of the
substantive matter and, thus, within the sole province of the legislature to plaintiff to exercise the power of eminent domain and the propriety of its
legislate on.
1avvphil

exercise in the context of the facts involved in the suit. It ends with an
order, if not of dismissal of the action, "of condemnation declaring that the
It is possible for a substantive matter to be nonetheless embodied in a plaintiff has a lawful right to take the property sought to be condemned,
rule of procedure, and to a certain extent, Rule 67 does contain matters for the public use or purpose described in the complaint, upon the
of substance. Yet the absorption of the substantive point into a payment of just compensation to be determined as of the date of the filing
procedural rule does not prevent the substantive right from being of the complaint x x x.
superseded or amended by statute, for the creation of property rights is a
matter for the legislature to enact on, and not for the courts to decide The second phase of the eminent domain action is concerned with the
upon. Indeed, if the position of the Government is sustained, it could very determination by the court of "the just compensation for the property
well lead to the absurd situation wherein the judicial branch of sought to be taken." This is done by the court with the assistance of not
government may shield laws with the veneer of irrepealability simply by more than three (3) commissioners x x x.27
absorbing the provisions of law into the rules of procedure. When the
1987 Constitution restored to the judicial branch of government the sole It is only upon the completion of these two stages that expropriation is
prerogative to promulgate rules concerning pleading, practice and said to have been completed. The process is not complete until payment
procedure, it should be understood that such rules necessarily pertain to of just compensation.28 Accordingly, the issuance of the writ of
points of procedure, and not points of substantive law. possession in this case does not write finis to the expropriation
proceedings. To effectuate the transfer of ownership, it is necessary for
It is a well-entrenched principle that statutes, including administrative the NPC to pay the property owners the final just compensation.29
rules and regulations, operate prospectively unless the legislative intent
to the contrary is manifest by express terms or by necessary
We observe that petitioners are not questioning the authority of the NPC amount in their prayer before this Court, the same shall simply be
to exercise the power of eminent domain nor the propriety of its exercise. considered by the RTC and included in the determination of the final just
While the constitutional restraint of public use has been overcome, the compensation.
imperative just compensation is still wanting. Thus, petitioners now
appeal for the prompt payment of just compensation. Indeed, just WHEREFORE, the instant petition is hereby DENIED. The Regional Trial
compensation is not only the correct determination of the amount to be Court of Sorsogon, Sorsogon, guided by the foregoing principles, is
paid to the property owner but also the payment of the property within a hereby directed to proceed with the hearing of the expropriation case,
reasonable time. Without prompt payment, compensation cannot be docketed as Civil Case No. 96-6295, and to resolve the issue of just
considered "just."30 compensation with utmost dispatch. No costs.

This Court understands the plight of petitioners. It has been ten (10) SO ORDERED.
years since they were divested of possession of their property, but they
still have to be paid just compensation. It may be noted that the
expropriation case still pends at the RTC, and it is in that case where a
determination of the amount of just compensation shall be made.
Inasmuch as this determination necessarily involves factual matters, and
considering that this Court is not a trier of facts, at this point, we can only
direct the RTC to try the case expeditiously, so that the amount of just
compensation for the subject property can be fixed and promptly paid, as
justice and equity dictate.

For this purpose, the RTC must bear in mind that it is the value of the
land at the time of the taking or at the time of the filing of the complaint,
whichever came first, not the value of the land at the time of the rendition
of judgment which should be considered.31 In this case, where the
institution of

an expropriation action preceded the taking of the subject property, just


compensation is based on the value of the land at the time of the
filing of the complaint. This is provided by the Rules of Court, the
assumption of possession by the expropriator ordinarily being conditioned
on its deposit with the National or Provincial Treasurer of the amount
equivalent to the value of the property as provisionally ascertained by the
court having jurisdiction of the proceedings.32

Finally, this Court takes cognizance of petitioners' manifestation that the


NPC, as found by the RTC, failed to pay the initial deposit of ₱32,930.00
as required in PD 42.33 The RTC had already fixed this amount on the
basis of its initial factual findings. The assailed CA Decision adopted the
RTC's factual findings. NPC's Comment filed with this Court and even its
petition for certiorari before the CA did not address, much less contest,
this fact. Because this factual finding was not disputed by the NPC in its
pleadings before the CA and before this Court, it is, therefore, deemed
admitted.34 However, inasmuch as petitioners made no mention of this
67.5 Republic of the Philippines Phil- 243189 425 P45,900.00 425 45,900.00 P1,062,500.00
SUPREME COURT Ville
Manila Sy Chi 29737 8,425 P658,690.00 2,924 P228,606.47 P7,310,000.00
Siong
FIRST DIVISION
On January 3, 2001, petitioner filed a complaint for expropriation before
G.R. No. 172243 June 26, 2007 the Regional Trial Court of Caloocan City for the acquisition of the
aforedescribed parcels of land. The case was raffled to Branch 131 of
REPUBLIC OF THE PHILIPPINES, represented by the TOLL that court.
REGULATORY BOARD, petitioner,
vs. After filing an Amended Complaint to reflect the proper schedule of
PHIL-VILLE DEVELOPMENT AND HOUSING CORPORATION and SY valuation of the properties sought to be expropriated, petitioner deposited
CHI SIONG AND CO., INC., respondents. with the Land Bank of the Philippines the amount of Two Million Three
Hundred Eleven Thousand Two Hundred Pesos (₱2,311,200.00),
DECISION representing the total zonal value of the properties under expropriation.
Thereafter, it filed with the court a Motion for Issuance of Writ of
GARCIA, J.: Possession.

Simply put, the lone legal issue involved in this petition for review is Both respondents separately moved to dismiss the complaint on the main
whether, under the facts obtaining in this case, a final determination of ground that the trial court lacked jurisdiction over the res. However, in its
just compensation in an expropriation proceedings must first be made Order of April 3, 2002, the trial court denied both motions and asserted
before an order of expropriation may be issued by the court. In its jurisdiction over the case. In time, respondents separately moved for
Decision1 of January 27, 2006 in CA-G.R. SP No. 89878, as reiterated in reconsideration but their motions were denied by the court in its
its Resolution2 of April 10, 2006, the Court of Appeals (CA) answered the subsequent Order of June 18, 2002. In the same Order, the court
issue in the affirmative. Disagreeing, petitioner Republic, as represented directed the issuance of a writ of possession in favor of petitioner and
by the Toll Regulatory Board, has come to this Court via this recourse to required the respondents to file their respective answers to the complaint.
seek the annulment and setting aside of the CA decision and resolution.
Of the two respondents impleaded as defendants in the complaint, only
But first the facts: Sy Chi Siong filed its Answer, thereunder reiterating the grounds pleaded
in its earlier motion to dismiss. In the alternative, it prayed for just
In an effort to ease traffic congestion on the North Luzon Expressway, compensation.
petitioner Republic, through the Toll Regulatory Board, sought to widen
the Balintawak Toll Plaza which would necessarily affect two (2) parcels As regards respondent Phil-Ville, petitioner alleged that this respondent
of land registered under the names of herein respondents Phil-Ville "has yet to file its responsive pleading to the complaint for expropriation."
Development and Housing Corporation (Phil-Ville, for brevity) and Sy Chi
Siong and Co., Inc. (Sy Chi Siong, for short). The parcels of land are Thereafter, petitioner filed a Motion for Issuance of Order of Expropriation
more particularly described as follows: and Appointment of Commissioners on the rationale that the respondents
had never challenged its right to expropriate their properties subject of
Owner TCT No./ Total Assessed Affected Assessed Zonal Value ofthe suit.
Area Value of Area Value of the Affected
Lot No. Entire Area Affected Area Area In an Order dated January 27, 2005, the trial court, even as it found the
(sq. aforementioned motion meritorious, deferred action on the petitioner’s
m.) prayer for an order of expropriation and instead set the same motion for
hearing on March 7, 2005 "so that the parties may nominate the use or purpose described in the complaint, upon the payment of just
commissioners who will ascertain and report to the court the just compensation. Thus, just compensation of the subject properties must
compensation for the aforementioned properties." Partly reads the Order: first be determined and paid before the Court can issue an order of
expropriation.
The motion is impressed with merit.
Premises considered, the 'Motion for Partial Reconsideration' is hereby
It is worthy to mention that: "The right of eminent domain is usually DENIED for lack of merit. (Italics supplied).
understood to be an ultimate right of the sovereign power to appropriate
any property within its territorial sovereignty for a public purpose" Dissatisfied, petitioner then went to the CA on certiorari, thereat docketed
[Republic vs. Court of Appeals, 383 SCRA 611, 2002]. as CA-G.R. SP No. 89878, imputing grave abuse of discretion on the part
of the trial court in insisting on the payment of just compensation before
An examination of the amended Complaint clearly show the overriding an order of expropriation may be issued.
necessity of expropriating the subject properties in order to give way to
the construction, rehabilitation and expansion of the North Luzon As stated at the threshold hereof, the appellate court, in its herein
Expressway, which is undoubtedly for public purpose and benefit. assailed Decision dated January 27, 2006, upheld the trial court. Partly
says the CA in its challenged decision:
Premises considered, the "Motion for issuance of Order of Expropriation"
is hereby deferred pending final determination of just compensation. Jurisprudential law has already settled that condemnation suits involve
two stages: the order authorizing expropriation, and the judgment on just
Meanwhile, let this case be set for hearing on March 7, 2005 at 8:30 in compensation. An order of expropriation is a court's resolution upholding
the morning so that the parties may nominate the commissioners who will the State's lawful right to take property sought to be expropriated and
ascertain and report to the court the just compensation for the thus forecloses any objection to the petitioner's authority to expropriate
aforementioned properties. [Emphasis supplied] for the public purpose stated in the complaint. This is implied in Rule 67,
Section 4. The order can be issued unless there are objections and
On February 22, 2005, petitioner filed a Motion for Partial defenses against the condemnation proceedings that would require the
Reconsideration of the above Order, arguing that since the case had presentation of evidence, and only after an adjudication of these
been set for hearing on March 7, 2005 for the nomination of the objections and defenses can a court proceed with the second stage of
commissioners and necessarily for the conduct of hearing for the the expropriation proceedings.
determination of just compensation, "it is proper that an order of
expropriation be forthwith issued before such determination of just However, under the circumstances at bar, there is already no more issue
compensation proceeds," citing, as basis therefor, Section 4, Rule 67 of as to the petitioner's authority to expropriate and the propriety of its
the 1997 Rules of Civil Procedure, and adding that where a defendant in exercise, which the lot owners themselves had acknowledged and
an expropriation case raises only the issue of just compensation, the admitted, and that the State has already been given the right to enter
court "should forthwith enter an order of expropriation." upon and to use the lots. In fact, the project has already been completed.
We thus find no grave abuse of discretion on the court's deferment of the
In an Order dated March 7, 2005, the trial court denied petitioner's motion issuance of the Order of expropriation pending the determination of just
for partial reconsideration, to wit: compensation, for this is not a major procedural flaw fatal to the action of
the petitioner.
The Court is of the opinion that the contentions of the counsel for the
petitioner [are] exactly the opposite of what the rules provide. The The only substantial issue now is the amount of compensation. The
provision of the rules relied upon, Section 4 Rule 67 is quite clear that this court a quo merely aims to secure its prompt adjudication and payment to
Court may issue an order of expropriation declaring that the plaintiff has a the owners, and the order would only be a formality. Hence, the second
lawful right to take the property sought to be expropriated, for the public stage of expropriation may proceed, the issuance of an order in this case
is only a permissive one and discretionary on the part of the trial court. A A final order sustaining the right to expropriate the property may be
failure to issue an expropriation order is no bar at all to the State to wield appealed by any party aggrieved thereby. Such appeal, however, shall
its power of eminent domain. In the case at bar, what will actually not prevent the court from determining the just compensation to be paid.
complete the vesting of title in favor of the State is the actual payment of
just compensation to the owners of the condemned properties. After the rendition of such an order, the plaintiff shall not be permitted to
dismiss or discontinue the proceeding except on such terms as the court
WHEREFORE, in view of the foregoing, the instant petition is hereby deems just and equitable. [Emphasis supplied]
DENIED. No pronouncement as to costs. (Emphasis supplied).
As is evident from the foregoing, there are two (2) stages in every action
SO ORDERED. for expropriation, namely:

With its motion for reconsideration having been denied by the CA in its 1. Determination of the authority of the plaintiff to exercise the power of
equally assailed resolution of April 10, 2006, petitioner is now with eminent domain and the propriety of its exercise in the context of the
us via the present recourse on the following submissions: facts involved in the suit. This ends with an order, if not of dismissal of the
action, of condemnation [or order of expropriation] declaring that the
I plaintiff has a lawful right to take the property sought to be condemned,
for the public use or purpose described in the complaint, upon the
AN ORDER OF EXPROPRIATION MERELY REQUIRES A payment of just compensation to be determined as of the date of the filing
DETERMINATION OF THE AUTHORITY TO EXERCISE THE POWER of the complaint; and
OF EMINENT DOMAIN; ITS ISSUANCE DOES NOT HINGE ON THE
PAYMENT OF JUST COMPENSATION; AND 2. Determination by the court of the just compensation for the property
sought to be taken.3
II
Petitioner Republic is correct in saying that an order of expropriation
PAYMENT OF JUST COMPENSATION IS NOT A CONDITION SINE denotes the end of the first stage of expropriation. Its end then paves the
QUA NON FOR THE ISSUANCE OF AN ORDER OF EXPROPRIATION. way for the second stage – the determination of just compensation, and,
ultimately, payment. An order of expropriation puts an end to any
ambiguity regarding the right of the petitioner to condemn the
WE GRANT the petition.
respondents’ properties. Because an order of expropriation merely
determines the authority to exercise the power of eminent domain and
Section 4, Rule 67 of the Rules of Court provides: the propriety of such exercise, its issuance does not hinge on the
payment of just compensation. After all, there would be no point in
Section 4. Order of expropriation. - If the objections to and the defenses determining just compensation if, in the first place, the plaintiff’s right to
against the right of the plaintiff to expropriate the property are overruled, expropriate the property was not first clearly established.
or when no party appears to defend as required by this Rule, the court
may issue an order of expropriation declaring that the plaintiff has a During the first stage, if the defendant had denied or objected to the
lawful right to take the property sought to be expropriated, for the public plaintiff's right to expropriate, a hearing would have been held to decide
use or purpose described in the complaint, upon the payment of just upon whether the land was private, and whether the purpose was, in fact,
compensation to be determined as of the date of the taking of the public.4However, once the objections and defenses against the right of
property or the filing of the complaint, whichever came first. the plaintiff to expropriate are overruled, an order of expropriation may
issue. With all the more reason must this be so when, as in this case,
there is no contest or objection by either of the herein respondents as to
the petitioner’s right to expropriate.
Neither respondent raised an issue as to petitioner's right to expropriate
its parcels of land, or the public purpose of the expropriation. For sure,
respondent Phil-Ville even allowed petitioner unimpeded entry and
unlimited access to the portion of its property under expropriation for the
eventual construction, completion, operation and maintenance of the
North Luzon Expressway Project.

After the trial court determined the right of petitioner to condemn the
subject properties for the expansion and rehabilitation of the North Luzon
Expressway, the first stage of the expropriation proceedings should have
been properly terminated with the issuance of an order of expropriation
declaring that petitioner has the right to take the properties.

To stress, payment of just compensation is not a condition sine qua


non to the issuance of an order of expropriation. In expropriation
proceedings, it is the transfer of title to the land expropriated that must
wait until the indemnity is actually paid.5 This is made all the more clear
when note is taken of the second paragraph of Section 4, Rule 67, supra,
which states that the defendant may appeal from the order of
expropriation by filing a record on appeal, which appeal does not prevent
the court from determining the just compensation to be paid.

Further, a perusal of Section 5, Rule 67 bolsters this point:

Section 5. Ascertainment of Compensation. - Upon the rendition of the


order of expropriation, the court shall appoint not more than three (3)
competent and disinterested persons as commissioners to ascertain and
report to the court the just compensation for the property sought to be
taken. x x x

Clearly, it is after the rendition of the order of expropriation that the court
shall appoint commissioners to ascertain the just compensation for the
property sought to be taken.

WHEREFORE, the petition is GRANTED and the assailed decision and


resolution of the Court of Appeals are ANNULLED and SET
ASIDE. Accordingly, the trial court is directed to issue an order of
expropriation in favor of petitioner Republic.

No costs.

SO ORDERED.
67.6 Republic of the Philippines Bernasconi, Martin C. Bernasconi, Jaime C. Bernasconi and Christina
SUPREME COURT Marie C. Bernasconi (Bernasconis).
Manila
The complaint alleged, inter alia, that:
THIRD DIVISION
5. Defendants are the declared owners of parcels of land situated
G.R. No. 176487 August 25, 2009 at Barangay Balaytigue, Nasugbu, Batangas as shown in the Tax
Declarations attached as Annexes "A", "B", "C", "D", "E", "F", "G",
REPUBLIC OF THE PHILIPPINES, REPRESENTED BY THE "H", "I", "J", "K", "L", "M", and "N", and certificates of title attached
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS, Petitioner, as annexes "O", "P", "Q", "R", "S", "T", "U", "V", "W", "X", "Y", "Z"
vs. and "AA" and more particularly described below together with the
FAR EAST ENTERPRISES, INC., ARSOL MANAGEMENT affected areas sought to be expropriated and the corresponding
CORPORATION,* MARIA CHRISTINA C. BERNASCONI, JORGE C. zonal values, to wit:
BERNASCONI, RENE C. BERNASCONI, REGINA B. TUASON,
CHRISTIAN C. BERNASCONI, MARTIN C. BERNASCONI, JAIME C. xxxx
BERNASCONI and CHRISTINA MARIE C.
BERNASCONI,Respondents. 6. To enable the plaintiff to construct the Ternate-Nasugbu Tali
Batangas Road, a public purpose authorized by law to be
DECISION undertaken by plaintiff, it is both necessary and urgent for plaintiff
to acquire portions of the above parcels of land consisting of a
CHICO-NAZARIO, J.: total area of 29, 786 sq. m., more or less, shown in the attached
sketch plan marked as Annex "CC" and made and integral part
Before Us is a Petition for Review on Certiorari under Rule 45 of the 1997 hereof.
Rules of Civil Procedure which seeks to reverse and set aside the
Decision1 of the Court of Appeals dated 9 November 2006 in CA-G.R. SP 7. The portion of above-described parcels of land sought to be
No. 72425 which dismissed petitioner Republic of the Philippines’ Petition expropriated have not been applied to nor expropriated for any
for Certiorari, and its Resolution2 dated 5 February 2007 denying public use and are selected by plaintiff as the site of the right-of-
petitioner’s motion for reconsideration. The Court of Appeals held that the way in connection with the construction of the Ternate-Nasugbu
Regional Trial Court of Nasugbu, Batangas, Branch 14, in Civil Case No. Tali Batangas in a manner compatible with the greatest public
674, did not act with grave abuse of discretion amounting to lack or good and the least public injury.
excess of jurisdiction in issuing the Resolution dated 17 June 2002
ordering petitioner to make an additional payment of ₱425.00 per square 8. Plaintiff has negotiated with defendants for the acquisition of
meter for the subject properties of respondents Far East and the portions of the properties for the public purpose as above-stated
Bernasconis before the issuance of an Order to take possession of the at a price prescribed by law, but failed to reach an agreement
subject properties, and a writ of possession. with them notwithstanding the negotiations.

On 23 November 2001, the Republic of the Philippines, represented by 9. Under Section 7 of the Executive Order No. 1035 dated June
the Secretary of the Department of Public Works and Highways (DPWH), 25, 1985, plaintiff represented by the DPWH is authorized to
filed a Complaint3 for Eminent Domain before the Regional Trial Court of institute expropriation proceedings through the Office of the
Nasugbu, Batangas against Far East Enterprises, Inc. (Far East), Arsol Solicitor General.
Management Corporation (Arsol), Maria Christina C. Bernasconi, Jorge
C. Bernasconi, Rene C. Bernasconi, Regina B. Tuason, Christian C. 10. Pursuant to Section 4 of Republic Act No. 89744 in relation to
Section 12 of the Implementing Rules and Regulations thereof,
plaintiff shall have the right to take or enter upon the possession on the merits. It likewise asked that petitioner, after trial, be ordered to
of the real properties involves upon the issue of this Honorable pay just compensation plus interest and penalties due for a property (Lot
Court of a Writ of Possession in favor of the plaintiff. 272) located along the Nasugbu-Ternate Road in Natipunan, Nasugbu,
Batangas, which was taken from it by the petitioner and used in a
xxxx previous road project without payment of just compensation.

11. Plaintiff is willing to deposit the total amount of ₱2.233M Respondent Far East filed its Answer8 dated 11 January 2002 which
representing the zonal valuation of the affected portions of the raised the following affirmative special defenses:
subject parcels of land as stated in paragraphs 5 and 6 hereof
and which for purposes of the issuance of the corresponding writ 10.2 That answering defendant manifests that on or about March
if possession, is required to be deposited by plaintiff with the 2001, during the meeting held at its office, plaintiff made an offer
authorized government depository, subject to the orders and final to purchase the properties, of the answering defendant, subject
disposition of this Honorable Court.5 matter of this case, at ₱200.00 per square meter. x x x.

The properties subjects of this case are all located in Barangay 10.2.1 That during the said meeting, answering defendant
Balaytigue, Nasugbu, Batangas. The particulars of the parcels of land are bargained for a higher price but Atty. Lamberto Aguilar, Legal
as follows: Office of Department of Public Works and Highway (DPWH, for
brevity), suggested that answering defendant accept the said
Owner OCT/TCT No. Lot/Block No. Tax Declaration No. Area Affected in amount of compensation at ₱75.00 per square meter because he
Square Meters
claims that the actual use of the real estate properties, although
Far East T-60966 Block 76 014-01029 1,704classified as residential by the Municipal Assessor of Nasugbu, is
Far East T-15189 Lot 339 014-01102 2,988agricultural;
Far East T-60540 Lot 536 014-01106 2,346
10.2.2 That in compliance with the suggestion of plaintiff to put
Far East T-57762 Lot 535 014-01105 3,051
into writing our counter-offer, answering defendant wrote the
Far East TP-1835 Lot 51 014-01313 former informing it of its desired amount and requesting for a
2,317
copy of the revised parcellary survey plan showing the area to be
Bernasconis T-54825 Lot 549 014-01119 2,053
affected after reduction in width of the right of way from 30 meters
Bernasconis T-54825 Lot 550 014-01120 190to 20 meters intended by the DPWH. 1avv phi 1

Arsol T-50152 Lot 534 014-00182 1,432


10.2.3 That after learning of its rights as landowner under
Arsol T-50168 Lot 254 014-0098 1,356
Administrative Order No. 50 and Republic Act (RA, for brevity)
Arsol T-50158 Lot 53 014-0097 No. 8974, answering defendant in a letter dated July 16, 2001,
2,960
retracted the previous amount offered to plaintiff in its letter dated
Arsol T-51059 Lot 190 014-0088 2,398
April 6, 2001 and, instead offered the said properties on a
Arsol T-50160 Lot 191 014-0087 negotiated sale at the amount of at least ₱600.00 per square
4,484
Arsol T-50170 Lot 256 014-00175 457meter.
Arsol T-51064 Lot 250 014-00109 1,898
x x x x.

Arsol filed its Answer with Counterclaim7 dated 7 January 2002. It prayed 10.2.4 That Plaintiff never replied to answering defendant’s letter
that the prayer of petitioner (plaintiff therein) for a writ of possession be under date of April 6, 2001. However, instead of commenting to
denied unless full payment of just compensation would be made after trial the price we offered by way of negotiated sale on the July 16,
2001 letter, and acting in bad faith as well by not observing due as those of answering defendant subject of the complaint, as
process as evidenced by failure of the DPWH to provide the determined in Annex "BB" in the complaint;
requested revised parcellary plan necessary for the defendant to
make an informed final decision, plaintiff chose instead to xxxx
endorse its complaint to the OSG for filing in court and, true to the
statement made by Atty. Aguilar, fixed the amount of 10.6 That similarly situated developed lots in the area are sold at
compensation at the amount of ₱75.00 per square meter. x x x. the range of ₱4,000.00 to 9,000.00 per square meter more or
less. x x x.
10.3 That plaintiff misleads the Honorable Court in stating that the
zonal valuation of the subject properties is ₱75.00 per square 10.7 All in all answering defendant is not objecting to the
meter as the said amount corresponds only to agricultural lands, expropriation of its properties but it must be paid justly in respect
not to residential lands owned by answering defendant and to not only the final compensation but also in respect to the initial
subject of this complaint, as determined in the schedule of BIR compensation to be deposited in full with the court, in conformity
zonal valuation attached as Annex "BB" in its complaint; with R.A. No. 8974 & A.O. No. 50 x x x.9

xxxx Respondent Far East prayed that, after due notice and hearing, the
complaint be given due course by ordering petitioner to comply with the
10.4 That the subject properties except for one (1) property, are mandate of Section 4 (a) of Republic Act No. 8974 by depositing in its
parts and parcels of Talibeach Subdivision, a residential name the initial amount of ₱7,433,600.00 or ₱600.00 per square meter
subdivision, in line with the approved subdivision plans and/or by for the total area of 12,406 sq.m. of its properties to be used in the
the said subdivision’s Deed of Restriction, xerox copies of which construction of the Ternate-Nasugbu Tali Batangas Road. It also asked
are attached as annexes "4" to "4-1"; that said amount be released to it and that the just compensation for its
lands be fixed.
10.4.1 That, in addition, the properties are located in the same
general area of other residential subdivisions such as Peninsula In their Joint Answer10 dated 11 January 2002, the Bernasconis admitted
de Punta Fuego, and Maya-Maya Subdivisions as well as they were the lawful and registered owners of parcels of land – Lots Nos.
approximately 3 kilometers from two other residential subdivisions 549 and 550 – covered by Transfer Certificates of Title (TCTs) No. T-
currently being developed as sold, specifically, Terrazas de Punta 54825, containing a total area of 2,243 sq.m., being expropriated by
Fuego and Kawayan Cove Subdivision; petitioner. They denied that petitioner made an offer to purchase the
properties, subject matter of the case. They further adopted all the claims
10.4.2 That Per Proclamation 1801 and Zoning Ordinance No. 03 and defenses that were interposed by Far East and were applicable to
of the Municipality of Nasugbu under date of April 1982, as their properties. Thus, they prayed that the complaint be given due
approved by the Human Settlements Regulatory Commission course and petitioner be ordered to comply with Section 4(a) of Republic
under Resolution No. 123 under date of May 4, 1983, the area is Act No. 8974 by depositing in their names the initial amount of ₱
declared as a Residential, Tourism and tourism potential area 1,345,800.00 or ₱600.00 per square meter for the 2,243 sq.m. of their
and therefore, may not even moreso be considered, classified as property being expropriated. They asked that said amount be released to
agricultural as self-servingly claimed by the DPWH Legal Officer, them, and that the just compensation for their properties be fixed.
Atty. Aguilar. x x x.
Petitioner filed separate replies to the Answers of Arsol and Far East/the
10.5 That as previously stated, the amount of ₱75.00 per square Bernasconis.11 Far East and the Bernasconis submitted their respective
meter corresponds to agricultural lands located at Brgy. rejoinders to the reply filed by petitioner.12
Balaytigue, Nasugbu, Batangas and not to residential lands such
On 7 February 2002, respondent Arsol filed a Motion to Release Deposit, submitted stated, however, that the properties sought to be expropriated
praying that the amount that may properly accrue for its lands sought to were classified as residential with a zonal valuation of ₱600.00 per
be expropriated be released as partial payment, to be taken from the square meter. They prayed that the issuance of the writ of possession be
funds deposited by petitioner for the benefit of all the defendants.13 deferred until petitioner had deposited with the trial court the correct
amounts of ₱1,345,800.00 (for the Bernasconis) and ₱7,443,600.00 (for
In its Order dated 8 February 2002, the trial court ordered petitioner to Far East), and that the previous amounts (₱168,225.00 for the
comply and manifest its compliance with the guidelines of Section 12 of Bernasconis and ₱930,450.00 for Far East) deposited be withdrawn by
the Implementing Rules and Regulations of Republic Act No. 8974, within them under protest without prejudice to the ruling of the trial court on the
ten days from receipt thereof, before it would issue an order for petitioner correct amount of zonal valuation of residential lands in Balaytigue,
to take possession of the affected properties, so it may commence the Nasugbu, Batangas.16
implementation of the project mentioned in the complaint.14
In an Order dated 2 April 2002, the trial court ordered petitioner to correct
On 15 March 2002, petitioner filed its Compliance and Motion for its zonal valuation with respect to Far East and the Bernasconis and to
Issuance of Order and Writ of Possession.15 It stated that DPWH Region make the corresponding deposit therefor. It added that the motion for the
IV certified that the amount of two million two hundred twenty-two issuance of an order and a writ of possession filed by petitioner shall be
thousand five hundred fifty pesos (₱2,222,550.00) had been allotted and acted upon after the correct deposit was made. It found that the amounts
made available to cover payment of properties sought to be expropriated deposited as regards Far East and the Bernasconis were not sufficient
as follows: because these were based on a zonal valuation of ₱75.00 per square
meter. It said that the deposit should be based on ₱500.00 per square
meter, because the subject lands were residential lands. As to Arsol, the
1. Arsol Management Corporation ₱1,123,875.00 trial court found the deposit of petitioner at ₱75.00 per square meter was
14,985 sq.m. @ - ₱75.00/sq.m. correct and directed Arsol to claim the check for ₱1,123,875.00 from the
2. Maria Christina Bernasconi, et al. - ₱ 168,225.00 Clerk of Court, under a proper receipt.17 On the same day, Arsol received
2,243 sq.m. @ - ₱75.00/sq.m. the check in the amount of ₱1,123,875.00 representing the initial
payment of just compensation for its lands which were subject of the
3. Far East Enterprises - ₱ 930,450.00 expropriation proceedings.18
12,406 sq.m. @ ₱75.00/sq.m.
Far East and the Bernasconis filed a Joint Motion to Release
₱ 2,222,550.00 Deposits.19 The trial court granted the same per its Order dated 15 April
2002 ordering the release to Far East and the Bernasconis the amounts
of ₱930,450.00 and ₱168,225.00, respectively, without prejudice to the
It informed the trial court that DPWH Regional Director Nestor V. Agustin final determination of just compensation for the affected properties.20 On
sent separate letters to the defendants tendering the price equivalent of 17 April 2002, Far East and the Bernasconis received the checks
100% of the zonal valuation declared by the Bureau of Internal Revenue corresponding to said amounts.21
(BIR) for their respective properties to be expropriated. Far East and the
Bernasconis disagreed with the price offered by petitioner. In view
Petitioner filed its Motion for Reconsideration dated 17 April 2002,
thereof, petitioner was constrained to deposit with the trial court the total
amount of ₱2,222,550.00 in three Land Bank checks in the names of the arguing that the trial court erred in ordering it to correct the zonal
valuation of Far East and the Bernasconis’ properties at ₱500.00 per
defendants, for its proper disposition.
square meter instead of ₱75.00 per square meter. It prayed that the trial
court reconsider its Order dated 2 April 2002 and a new one be issued
In their respective comments on petitioner’s compliance, both Far East declaring that the deposit made by it was sufficient compliance with
and the Bernasconis claimed that petitioner intentionally and wantonly Section 4 of Republic Act No. 8974 and Section 8 of its Implementing
disregarded and misled the trial court by stating that their properties were Rules and Regulations. It further asked that an order be issued for the
classified as agricultural to justify the deposit it made. The documents it conduct of an ocular inspection of the subject properties of Far East and
the Bernasconis to determine their actual classifications.22 Far East and classified as residential per plaintiff’s Annexes "A" to "G" of the
the Bernasconis filed their Joint Opposition to/Comment on the Motion for Complaint. The very tax declarations of the movants’ properties (Annexes
Reconsideration.23 Arsol likewise filed its Comment, arguing that "A" to "G", Complaint) show that subject properties are indeed residential
petitioner must deposit the additional amount to obtain the writ of and not agricultural.
possession.24
In this connection, tax declarations do not prove ownership of the
In a Resolution dated 26 April 2002, the trial court granted petitioner’s property. It is only an evidence of possession. It is the titles of the
motion for reconsideration. The trial court found the deposit (at ₱75.00 properties that show their ownership (Annexes "O" to "T" of the
per square meter) made by petitioner sufficient and substantial Complaint). The Court realizes its lack of discretion to substitute its
compliance with Section 4 of Republic Act No. 8974 and Section 8 of its judgment for the authority of the Municipality of Nasugbu, Batangas, on
Implementing Rules and Regulations, and that Far East and the land reclassification, on the mere premise that the properties of the
Bernasconis had already received the checks as deposits for their movants and of Arsol adjoin each other.
properties under expropriation. It ordered the petitioner to take
possession of the affected properties and to start the implementation of RA 8974 gives no discretion to the Court to determine the classification of
the road project. It likewise ordered the issuance of a writ of possession the expropriated properties.
commanding the proper officer to place petitioner in possession of the
affected portions of said properties.25 Plaintiff cannot question the very contents of its documents which are
parts and parcels of its complaint. It is a cardinal rule in adjective law that
Far East and the Bernasconis filed their Joint Motion for Reconsideration pleadings are binding on the pleader.
dated 2 May 2002 praying that the Order dated 26 April 2002 be
reconsidered, and that the court order petitioner to deposit the balance of In fine, the Court is fully convinced to give weight to the contents of
₱425.00 per square meter in order to comply with the required deposit of plaintiff’s Exhs. "A" to "G" and "BB", Complaint. Therefore, the deposit of
the zonal value of ₱500.00 per square meter, as correctly ordered by ₱75.00 per square meter made by plaintiff as regards movants’
respondent court in its Order dated 2 April 2002.26 properties is insufficient because the zonal valuation of the same is fixed
at ₱500.00 per square meter.
Petitioner filed its Opposition to Defendants’ Joint Motion for
Reconsideration,27 to which Far East and the Bernasconis filed a Reply WHEREFORE, foregoing premises considered, the order of April 26,
dated 14 June 2002.28 2002 is reconsidered and set aside. Plaintiff is ordered to make the
additional deposit of ₱425.00 per square meter for the properties of the
The trial court issued a Resolution29 dated 17 June 2002, the relevant movants before the order to possess and writ of possession issue.
portions of which read:
Respondents Far East and the Bernasconis filed a Joint Motion for
After a re-assessment of the respective arguments of both parties, the Compliance dated 21 June 2002 asking the trial court to order petitioner
Court finds merit in the joint motion for reconsideration. to comply with the Resolution dated 17 June 2002 by depositing the
additional amount of ₱425.00 per square meter.30
For one, the definition of agricultural land is clear and leaves nothing for
any other interpretation. The plaintiff has not shown any other definition of In its Manifestation and Urgent Motion for Issuance of Writ of Possession
agricultural land, different from the above definition. The fact, as claimed dated 10 July 2002, petitioner informed the trial court that it would elevate
by the plaintiff, that the lands of the movants are idle, raw and the Order requiring it to deposit the additional ₱425.00 per square meter
undeveloped, with no houses thereon, does not unmake the same as to a higher court. It also said that in the interest of expediting the
residential because they were already classified as such long before this implementation of the project the completion of which was of utmost
case was filed. The fact that the subject properties may be suitable for urgency, it had already made in protest a deposit of the additional amount
agricultural uses does not make it agricultural because they were of ₱425.00 per square meter as specified in the trial court’s Resolution
dated 17 June 2002. As proof thereof, it said it attached the Certificate as before the Court of Appeals.36 Far East and the Bernasconis filed a Joint
to Availability of Funds wherein the total amount of ₱6,225,825.00 Comment on/Opposition to the motion.37
(₱953,275.00 in favor of the Bernasconis and ₱5,272,550.00 in favor of
Far East) had been allotted for the purpose. Thus, it prayed that a writ of In its Resolution dated 28 November 2002, the trial court reconsidered its
possession be immediately issued.31 Resolution dated 20 August 2002 and granted petitioner’s motion for
reconsideration. It ordered that a writ of possession be issued and that
The trial court found that petitioner did not attach the Certificate as to petitioner be placed in possession of the properties subject of the
Availability of Funds in its Manifestation and Urgent Motion dated 10 July expropriation case.38 Far East and the Bernasconis filed a Joint Motion for
2002. Thus, in its Order dated 23 July 2002, the trial court ordered Reconsideration39 of said resolution, which the trial court denied in an
petitioner to submit said certification within ten days from receipt of its Order dated 12 September 2003.40
Order.32 In their Joint Comment on and Opposition to petitioner’s
manifestation and motion dated 26 July 2002, Far East and the Far East and the Bernasconis filed a Joint Petition for Certiorari before
Bernasconis prayed that the writ of possession be issued to petitioner the Court of Appeals praying that the Order of the trial court dated 12
only after payment of the balance of the zonal values of their properties September 2003 be set aside.41 The petition was docketed as CA-G.R.
had been made.33 SP No. 80278.

Petitioner filed its Compliance dated 12 August 2002 with the Order dated Far East and the Bernasconis then filed a Joint Motion for Clarification
23 July 2002 attaching therewith the Certificate as to Availability of Funds and Suspension of Proceedings dated 16 February 2004.42 In an Order
in the amount of ₱6,225,825.00. It also apologized for its failure to attach dated 11 August 2004, the trial court granted the motion and suspended
said certificate in its Manifestation and Urgent Motion dated 10 July 2002. the proceedings of the case pending resolution of CA-G.R. SP No. 72425
and CA-G.R. SP No. 80278 before the Court of Appeals.43
In an Order dated 20 August 2002, the trial court ordered petitioner to pay
the amounts of ₱953,775.00 and ₱5,272,550.00 to the Bernasconis and On 28 February 2005, the Court of Appeals, in CA-G.R. SP No. 80278,
Far East, respectively, or to deposit said amounts in court for payment to denied the petition for certiorari filed by Far East and the Bernasconis.
respondents within ten days from receipt, after which a writ of possession Their Joint Motion for Reconsideration44 was likewise denied in a
shall be issued.34 Resolution dated 31 August 2005.45 Far East and the Bernasconis
appealed to this Court via a Joint Petition for Certiorari.46 The case was
On 28 August 2002, petitioner filed a Petition for Certiorari with the Court docketed as G.R. No. 170178. This Court dismissed the petition for being
of Appeals seeking the reversal of the trial court’s Resolution dated 17 the wrong mode of appeal.47 Far East and the Bernasconis moved to
June 2002 requiring it to make the additional deposit of ₱425.00 per reconsider the dismissal, but we denied their motion with finality stating
square meter. It further asked the appellate court to require the trial court that even if the petition were to be treated as a petition for review on
to conduct an ocular inspection of the expropriated properties to certiorari under Rule 45, the same should nevertheless be denied for
determine their actual use and to allow it to present its evidence of the being filed out of time.48
classification of said lands.35The appeal was docketed as CA-G.R. SP
No. 72425. On 9 November 2006, the Court of Appeals in CA-G.R. SP No. 72425
rendered its decision dismissing, for lack of merit, the petition filed by
While CA-G.R. SP No. 72425 was pending before the Court of Appeals, petitioner DPWH.49 The appellate court found that the trial court did not
petitioner filed its Motion for Reconsideration of the Order of the trial court act with grave abuse of discretion amounting to lack or excess of
dated 20 August 2002, arguing that it sufficiently complied with the law jurisdiction in ordering petitioner to make the additional payment of
when it issued the certificate of availability of funds. It further argued that ₱425.00 per square meter for the subject properties of Far East and the
the trial court’s directive to pay the zonal valuation based on the Bernasconis before the issuance of the order to take possession, and the
residential classification of the properties would render moot the issue writ of possession. The pertinent portions of the decision read:
Petitioner submitted to respondent court the Land Bank checks payable have paid immediately to private respondents the amount equivalent to
to private respondents, as well as to Arsol, and a certification as to the sum of 100% of the value of the property based on the BIR zonal
availability of funds. However, private respondents Far East and the valuation of private respondents’ residential lots in Barangay Balaytigue,
Bernasconis disagreed with the amount of petitioner’s deposit and prayed Nasugbu, Batangas in the amount of Php500.00 per square meter, and
in their Joint Motion for Reconsideration of the Resolution dated 26 April not Php75.00 per square meter which is the BIR current zonal valuation
2002 that petitioner be ordered to deposit the balance of Php425.00 per for agricultural lots in said barangay. R.A. No. 8974 and its Implementing
square meter in order to comply with the zonal value of Php500.00 per Rules and Regulations are clear as to the amount of payment which
square meter, as contained in the Order dated 02 April 2002. They petitioner, through DPWH, the implementing agency, has to make, even
argued that their land is residential and that the zonal value of P500.00 as early as the filing of petitioner’s Complaint. No amount of verbiage on
per square meter should be paid to them, instead of the zonal value of petitioner’s part can alter the plain and unequivocal provisions of the law
P75.00 per square meter for agricultural lands. This Joint Motion of and the implementing rules. Thus, respondent court did not act with grave
private respondents was granted by respondent court in the Resolution abuse of discretion when it relied upon private respondents’ tax
dated 17 June 2002. The said Resolution is now being assailed by declarations (Complaint’s Annexes "A" to "G"), and the BIR zonal
petitioner. valuation of real properties in Nasugbu, Batangas (Complaint’s Annex
"BB"); found the amount of Php75.00 per square meter insufficient as
We sustain the ruling of respondent court in the assailed Resolution. regards private respondents’ subject residential properties, the zonal
However, to be more precise, petitioner should make the additional initial valuation of which is Php500.00 per square meter; and ordered petitioner
payment (not deposit) of Php425.00 per square meter for the properties to make the additional payment of Php425.00 per square meter before
of private respondents before the order to take possession and writ of the order to take possession and writ of possession can be issued in
possession can be issued. petitioner’s favor. As held in Republic v. Gingoyon [G.R. No. 166429, 19
December 2005, 478 SCRA 474, 520], R.A. No. 8974 provides, as the
Petitioner itself attached to its Complaint as Annex "BB" a certified relevant standard for initial compensation, the market value of the
photocopy of the BIR’s Schedule of Zonal Values of Real Properties in property as stated in the tax declaration or the current relevant zonal
the Municipality of Nasugbu, Batangas. The zonal valuation of properties valuation of the BIR, whichever is higher.
in Brgy. Balaytigue were classified as follows:
Rep. Act No. 8974 represents a significant change from previous
BRGY. BALAYTIGUE expropriation laws such as Rule 67, or even Section 19 of the Local
Government Code. In both cases, the private owner does not receive
compensation prior to the deprivation of property. On the other hand,
ALL LOTS50 RR 500.00 600.00 Rep. Act No. 8974 mandates immediate payment of the initial just
A 75.00 80.00 compensation prior to the issuance of the writ of possession in favor of
the Government. Rep. Act No. 8974 is plainly clear in imposing the
CR 1,500.00 1,700.00
requirement of immediate prepayment, and no amount of statutory
GP 200.00 deconstruction can evade such requisite. It enshrines a new approach
towards eminent domain that reconciles the inherent unease attending
Further, petitioner also appended to its Complaint as Annexes "A" to "G" expropriation proceedings with a position of fundamental equity. While
the Tax Declarations of private respondent Far East and Maria Christina expropriation proceedings have always demanded just compensation in
C. Bernasconi showing that the properties sought to be expropriated are exchange for private property, the previous deposit requirement impeded
classified as "Residential." Petitioner’s very own attachments to its immediate compensation to the private owner, especially in cases
Complaint show that private respondents’ properties are residential and wherein the determinations of the final amount of compensation would
not agricultural. prove highly disputed. Under the new modality prescribed by Rep. Act
No. 8974, the private owner sees immediate monetary recompense with
the same degree of speed as the taking of his/her property.
Thus, based on Section 4 of R.A. No. 8974 and Section 8 of the
Implementing Rules and Regulations of R.A. No. 8974, petitioner should
While eminent domain lies as one of the inherent powers of the State, I
there is no requirement that it undertake a prolonged procedure, or that
the payment of the private owner be protracted as far as practicable. In IN RULING THAT PETITIONER SHOULD IMMEDIATELY PAY THE BIR
fact, the expedited procedure of payment, as highlighted under Rep. Act ZONAL VALUATION OF THE PROPERTY BEFORE TAKING
No. 8974, is inherently more fair, especially to the layperson who would POSSESSION, THE COURT OF APPEALS FAILED TO RESOLVE
be hard-pressed to fully comprehend the social value of expropriation in THE LIS MOTA OF THE CASE, THAT IS, WHICH FACTORS SHOULD
the first place. Immediate payment placates to some degree whatever ill- CONTROL IN DETERMINING THE CLASSIFICATION OF THE
will that arises from expropriation, as well as satisfies the demand of PROPERTY FOR PURPOSES OF PAYMENT OF THE BIR ZONAL
basic fairness. VALUATION; COROLLARY THERETO, THE HONORABLE COURT’S
RELIANCE IN REPUBLIC VS. GINGOYON ("GINGOYON"), IS NOT
It is therefore erroneous for petitioner to contend that respondent court CONTROLLING IN THIS CASE, BECAUSE THE CLASSIFICATION OF
abdicated its authority in determining just compensation. The THE PROPERTY SOUGHT TO BE EXPROPRIATED IS NOT IN AN
compensations to private respondents based on the BIR zonal valuation ISSUE IN GINGOYON, AS IT IS IN THIS PETITION.
of the properties sought to be expropriated at Php500.00 per square
meter is merely the immediate payment of the initial just compensation II
prior to the issuance of the writ of possession in order to effectuate the
transfer of possession in favor of petitioner. THE COURT A QUO GRAVELY ERRED IN REFUSING TO APPLY THE
STANDARDS SET IN R.A. NO. 8974 IN DETERMINING THE
The issuance of the writ of possession does not write finis to the CLASSIFICATION OF THE PROPERTIES SUBJECT OF
expropriation proceedings. Expropriation is not completed until payment EXPROPRIATION.
to the property owner of just compensation. To effectuate transfer of
ownership, it is necessary of the Government to pay the property owner A. TAX DECLARATIONS AND THE MUNICIPAL
the final just compensation. ZONING ORDINANCE ARE NOT CONTROLLING BUT
ARE MERE FACTORS AMONG SEVERAL OTHER
Indeed, the determination of just compensation in expropriate FACTORS IN DETERMINING THE CLASSIFICATION
proceedings is a judicial function. Section 5 of R.A. No. 8974 enumerates OF THE EXPROPRIATED PROPERTY.
certain relevant standards which respondent court may consider, in order
to facilitate the determination of just compensation. B. THE CLASSIFICATION OF THE SURROUNDING
PROPERTIES AND THE ACTUAL USE OF THE
xxxx PROPERTY SOUGHT TO BE EXPROPRIATED AT THE
TIME OF THE TAKING, PARTICULARLY IN THIS CASE
Thus, it is at this stage of the expropriation proceedings where the judicial WHERE THE LAND IS RAW, UNCULTIVATED,
function of determining just compensation is to be exercised by AGRICULTURAL PROPERTY, SHOULD BE
respondent court. It is also at this point when petitioner’s evidence CONSIDERED IN DETERMINING THE
regarding the use of the subject properties, value declared by the owners, CLASSIFICATION OF THE PROPERTY FOR
current selling price, ocular findings, etc. will into play.51 PURPOSES OF PAYMENT OF THE BIR ZONAL
VALUATION;
Petitioner filed its Motion for Reconsideration dated 4 December
2006.52 On 5 February 2007, the Court of Appeals denied the same.53 C. ACCORDINGLY, IN CASE OF DOUBT AS TO THE
CLASSIFICATION OF THE PROPERTY, THE COURT
Hence, this petition for review. SHOULD MAKE A JUDICIAL DETERMINATION OF THE
CLASSIFICATION OF THE PROPERTY FOR
Petitioner raises the following grounds in support of the petition:
PURPOSES OF PAYMENT OF THE BIR ZONAL period of sixty (60) days from the date of filing of the expropriation
VALUATION; case, to come up with a zonal valuation for said area; and

III (c) In case the completion of a government infrastructure project


is of utmost urgency and importance, and there is no existing
COROLLARY THERETO, AND IN ACCORDANCE WITH THE RULE ON valuation of the area concerned, the implementing agency shall
MULTIPLE ADMISSIBILITY OF EVIDENCE, THE FACT THAT immediately pay the owner of the property its proffered value
PETITIONER INTRODUCED TAX DECLARATIONS OF THE taking into consideration the standards prescribed in Section 5
EXPROPRIATED PROPERTIES SOLELY AS PROOF OF OWNERSHIP hereof.
OF THE EXPROPRIATED PROPERTY DOES NOT PRECLUDE
PETITIONER FROM QUESTIONING RESPONDENTS’ UNILATERAL Upon compliance with the guidelines abovementioned, the court shall
STATEMENT IN THEIR TAX DECLARATIONS THAT THE immediately issue to the implementing agency an order to take
PROPERTIES ARE RESIDENTIAL. possession of the property and start the implementation of the project.

In paying a property owner 100% of the value of a property based on the Before the court can issue a Writ of Possession, the implementing
current relevant zonal valuation of the BIR for the purpose of an issuance agency shall present to the court a certificate of availability of funds from
of a writ of possession, under which classification of the expropriated the proper official concerned.
property should petitioner, as the implementing agency, be required to
make such payment? This, according to petitioner, is the issue in this In the event that the owner of the property contests the implementing
petition. agency's proffered value, the court shall determine the just compensation
to be paid the owner within sixty (60) days from the date of filing of the
Section 4 of Republic Act No. 8974 (An Act to Facilitate the Acquisition of expropriation case. When the decision of the court becomes final and
Right-of-Way, Site or Location for National Government Infrastructure executory, the implementing agency shall pay the owner the difference
Projects and for Other Purposes) provides the guidelines for between the amount already paid and the just compensation as
expropriation proceedings. Said section reads: determined by the court. (Underscoring supplied)

SECTION 4. Guidelines for Expropriation Proceedings. — Whenever it is Under said law, the requirements for authorizing immediate entry in
necessary to acquire real property for the right-of-way, site or location for expropriation proceedings involving real property are: (1) the filing of a
any national government infrastructure project through expropriation, the complaint for expropriation sufficient in form and substance; (2) due
appropriate implementing agency shall initiate the expropriation notice to the defendant; (3) payment of an amount equivalent to 100% of
proceedings before the proper court under the following guidelines: the value of the property based on the current relevant zonal valuation of
the BIR including payment of the value of the improvements and/or
(a) Upon the filing of the complaint, and after due notice to the structures if any, or if no such valuation is available and in cases of
defendant, the implementing agency shall immediately pay the utmost urgency, the payment of the proffered value of the property to be
owner of the property the amount equivalent to the sum of one seized; and (4) presentation to the court of a certificate of availability of
hundred percent (100%) of the value of the property based on the funds from the proper officials.54
current relevant zonal valuation of the Bureau of Internal
Revenue (BIR); and (2) the value of the improvements and/or Upon compliance with the requirements, a complainant in an
structures as determined under Section 7 hereof; expropriation case is entitled to a writ of possession as a matter of right,
and it becomes the ministerial duty of the trial court to forthwith issue the
(b) In provinces, cities, municipalities and other areas where there writ of possession. No hearing is required, and the court exercises neither
is no zonal valuation, the BIR is hereby mandated within the its discretion nor its judgment in determining the amount of the
provisional value of the properties to be expropriated, as the legislature We agree with petitioner that the courts have judicial discretion to
has fixed the amount under Section 4 of Republic Act No. 8974.55 determine the classification of lands, because such classification is one of
the relevant standards for the assessment of the value of lands, subject
In the instant case, petitioner does not dispute that the provisional value of expropriation proceedings. It is one factor that the courts consider in
to be paid before a writ of possession can be issued is 100% of the value determining just compensation. The determination of just compensation
of the property based on the current relevant zonal valuation by the BIR. is a function addressed by the courts of justice and may not be usurped
What it questions is the classification of the properties sought to be by any other branch or official of the government.56 However, we would
expropriated, which will then be used in determining the 100% value of like to make it clear that Section 5 of Republic Act No. 8974 lists the
the property based on the current relevant zonal valuation of the BIR. relevant standards that are to be considered in determining just
compensation for and not classification of lands, as petitioner would like
Petitioner contends that the subject properties are agricultural for the us to believe.
following reasons: (1) the BIR Zonal Valuation classifies properties in
Barangay Balaytigue, Nasugbu, Batangas as Residential, Agricultural, Section 5 of Republic Act No. 8974 enumerates the standards that assist
Commercial and Industrial; (2) the properties involved are actually used in the determination of just compensation:
for agricultural purposes (raw, undeveloped with no houses); and (3) all
the adjoining properties are classified as agricultural. On the other hand, SEC. 5. Standards for the Assessment of the Value of the Land Subject
respondents Far East and the Bernasconis assert that their properties are of Expropriation Proceedings or Negotiated Sale. – In order to facilitate
residential pursuant to Municipal Ordinance No. 3 enacted by the the determination of just compensation, the court may consider, among
Sangguniang Bayan of Nasugbu, Batangas on 3 May 1982, and that said other well-established factors, the following relevant standards:
reclassification was reflected in their corresponding tax declarations for
the properties. (a) The classification and use for which the property is suited;

Petitioner argues that in cases where there is a dispute on the (b) The developmental costs for improving the land;
classification of the property, the trial court is under obligation to judicially
determine the classification of the property prior to requiring the payment (c) The value declared by the owners;
of the amount based on the BIR zonal value. It should be allowed to
present evidence of the proper classification of the properties. Petitioner
(d) The current selling price of similar lands in the vicinity;
adds that nothing in Republic Act No. 8974 compels it or the Court to
classify the property based on tax declarations, for the latter has judicial
discretion to ascertain the classification and nature of the property based (e) The reasonable disturbance compensation for the removal
on the standards set under Section 5 of Republic Act No. 8974. Petitioner and/or demolition of certain improvements on the land and for the
states that the expropriation court is not bound by a property owner’s value of improvements thereon;
statement in the tax declaration that his property is residential or by a
municipal zoning ordinance that classifies the property as such, when (f) The size, shape or location, tax declaration and zonal valuation
there exists controverting evidence to the contrary. Thus, petitioner faults of the land;
both the trial court and the appellate court for ruling that the lands
involved are residential, notwithstanding petitioner’s claim that the there (g) The price of the land as manifested in the ocular findings, oral
is evidence to show that the same are agricultural. as well as documentary evidence presented; and

It is clear from the foregoing that petitioner is questioning the (h) Such facts and events as to enable the affected property
classification of the lands involved. owners to have sufficient funds to acquire similarly-situated lands
of approximate areas as those required from them by the
government, and thereby rehabilitate themselves as early as
possible.
The more important query to be resolved is: Are the courts, in the first reclassification shall be limited to the following percentage of the total
instance, the proper venue in which to resolve any dispute involving the agricultural land area at the time of the passage of the ordinance:
classification of lands?
(1) For highly urbanized and independent component cities,
We do not think so. FIFTEEN PERCENT (15%);

By questioning the classification of the lands involved, petitioner is, in (2) For component cities and first to third class municipalities, ten
effect, questioning the propriety, wisdom and legality of the act of the percent (10%); and
Municipal Council of Nasugbu, Batangas of reclassifying the subject
lands as Residential. Per certification of the Office of the Municipal (3) For fourth to sixth class municipalities, five percent
Planning and Development Coordinator/Zoning Administrator of the (5%); Provided further, That agricultural lands distributed to
Municipality of Nasugbu, Batangas, the lands of Far East and the agrarian reform beneficiaries pursuant to Republic Act No. 6657,
Bernasconis sought to be expropriated were classified as Residential, otherwise known as "The Comprehensive Agrarian Reform Law,"
pursuant to Municipal Zoning Ordinance No. 3 dated 3 May 1982, as shall not be affected by the said reclassification and the
approved under Resolution No. 123, series of 1983 dated 4 May 1983 by conversion of such lands into other purposes shall be governed
the Human Settlement Regulatory Commission (now HLURB57). by Section 65 of said Act.

This Court recognizes the power of a local government to reclassify and xxxx
convert lands through local ordinance, especially if said ordinance is
approved by the HLURB.58 In Pasong Bayabas Farmers Association, Inc. (c) The local government units shall in conformity with existing
v. Court Appeals,59 we acknowledged the power of local government units laws, continue to prepare their respective comprehensive land
to adopt zoning ordinances. Discretion is vested in the appropriate use plans enacted though zoning ordinances which shall be the
government agencies to determine the suitability of a land for residential, primary and dominant bases for the future use of land
commercial, industrial or other purposes.60 It is also a settled rule that an resources: Provided, That the requirements for food production,
ordinance enjoys the presumption of validity.61 Having the power to human settlements, and industrial expansion shall be taken into
classify lands, the local government unit may consider factors that are consideration in the preparation of such plans.
just, reasonable and legal, for it is within the local government unit’s
power to determine these. However, if they abuse their authority in the
xxxx
performance of this duty, the courts, if prompted, can step in.
(e) Nothing in this section shall be construed as repealing,
Section 20 of Republic Act No. 7160, otherwise known as the Local
amending or modifying in any manner the provisions of R.A. No.
Government Code of 1991, empowers the local government units to
6657.
reclassify agricultural lands:
In the case before us, the lands in question had long been (almost 20
Sec. 20. Reclassification of Lands. - (a) A city or municipality may,
years) reclassified as residential before the instant case was filed. All
through an ordinance passed by the Sanggunian after conducting public
those years, no one questioned the ordinance reclassifying the lands. If
hearings for the purpose, authorize the reclassification of agricultural
petitioner would like to have the reclassification of the lands involved
lands and provide for the manner of their utilization or disposition in the
changed to agricultural, the just and reasonable way of doing it is to go to
following cases: (1) when the land ceases to be economically feasible
the municipal council -- not the courts – that enacted the ordinance and to
and sound for agricultural purposes as determined by the Department of
ask that the lands be reclassified again as agricultural. Technical matters
Agriculture or (2) where the land shall have substantially greater
such as zoning classifications and building certifications should be
economic value for residential, commercial, or industrial purposes, as
primarily resolved first by the administrative agency whose expertise
determined by the Sanggunian concerned: Provided, That such
relates therein.62 The jurisprudential trend is for courts to refrain from
resolving a controversy involving matters that demand the special the two as regards classification. Even if there is any inconsistency, what
competence of administrative agencies, "even if the question[s] involved prevails is the determination for zoning purposes.67
[are] also judicial in character."63 In this manner, we give the respect due
to these agencies (the municipal council and the Human Settlement There is no question that a local government unit can determine the
Regulatory Commission [now HLURB]), which unquestionably have suitability of a land for residential, commercial, industrial of for other
primary jurisdiction to rule on matters of classification of lands. purposes. It can do this through an ordinance passed by the Sanggunian
for the purpose.68Moreover, under Section 447 of Republic Act No. 7160,
In Solmayor v. Arroyo,64 we declared: the Sangguniang Bayan or the Municipal Council, as the legislative body
of the municipality, has the power to enact ordinances for the general
Well settled is the principle that by reason of the special knowledge and welfare of the municipality and its inhabitants. Among the functions of the
expertise of administrative agencies over matters falling under their Sangguniang Bayan enumerated under Section 447 of Republic Act No.
jurisdiction, they are in a better position to pass judgment thereon; thus 7160 are:
their findings of fact in that regard are generally accorded great respect, if
not finality, by the courts. Accordingly, since specialized government (2) Generate and maximize the use of resources and revenues for the
agencies tasked to determine the classification of parcels of land, such as development plans, program objectives and priorities of the municipality
the Bureau of Soils and the HLURB, among other agencies, have already as provided for under Section 18 of this Code with particular attention to
certified that the subject land is residential/commercial, the Court must agro-industrial development and countryside growth and progress, and
accord such conclusions great respect, if not finality, in the absence of relative thereto, shall:
evidence to the contrary.65
xxxx
Under Section 3(m), Rule 131 of the Rules of Court, there is a
presumption that official duty has been regularly performed. Thus, in the (vii) Adopt a comprehensive land use plan for the municipality: Provided,
absence of evidence to the contrary, there is a presumption that public That the formulation, adoption, or modification of said plan shall be in
officers performed their official duties regularly and legally and in coordination with the approved provincial comprehensive land use plan;
compliance with applicable laws, in good faith, and in the exercise of
sound judgment.66 This presumption applies to this case. (vii) Reclassify land within the jurisdiction of the municipality subject to
the pertinent provision of this Code; x x x.
If after going to the local government unit or government agencies that
made the classification of the lands and the implementing agency fails to Under the facts obtaining, this Court agrees with both lower courts that
obtain the redress they seek (proper classification), despite evidence the classification of the lands concerned is residential. No other
clearly showing erroneous classification, it is only then that it can go to certification from the municipal council has been presented to show that a
the court to ask for intervention. new zoning ordinance has been passed by it changing the present
classification of the lands, subject of the expropriation case. Even if we
In the case at bar, the trial court and the Court of Appeals based their consider the allegations of petitioner that said lands are actually used for
classification of the lands concerned, not only on the tax declarations, but agriculture, and that the lands adjoining the same are all classified as
more importantly on the certification issued by the Office of the Municipal agricultural, the same will not necessarily change said classification to
Planning and Development Coordinator/Zoning Administrator of the agricultural.
1avv phi 1

Municipality of Nasugbu, Batangas that said lands had been (re)classified


as residential pursuant to Municipal Zoning Ordinance No. 3 dated 3 May Even assuming that the lands are still used for agricultural purposes, this
1982 as approved under Resolution No. 123, series of 1983 dated 4 May will not cause the reversion of the classification of the lands to
1983 by the Human Settlement Regulatory Commission (now HLURB). agricultural. In Pasong Bayabas Farmers Association, Inc. v. Court
The tax declarations adduced and the certification show that the lands Appeals,[69] we ruled that the failure of the landowner to complete the
concerned are classified as residential. There is no discrepancy between housing project did not have the effect of reverting the property to its
former classification. In De Guzman v. Court of Appeals,70 we held that Inasmuch as what is involved in this case is the payment of the amount
the continuous tillage of the land and the non-commencement of the equivalent to 100% of the value of the property based on the current
construction of the market complex did not strip the land of its relevant zonal valuation of the BIR, we must distinguish the same from
classification as commercial. Furthermore, even assuming that all the just compensation. In Capitol Steel Corporation v. Phividec Industrial
adjoining lands are still classified as agricultural, this does not mean that Authority,73 we ruled:
lands involved cannot be classified differently, as in this case. In the
certification issued by the Office of the Municipal Planning and To clarify, the payment of the provisional value as a prerequisite to the
Development Coordinator/Zoning Administrator of the Municipality of issuance of a writ of possession differs from the payment of just
Nasugbu, Batangas, the parcels of land reclassified, including those of compensation for the expropriated property. While the provisional value is
Far East and the Bernasconis which petitioner seeks to expropriate, were based on the current relevant zonal valuation, just compensation is based
individually listed. on the prevailing fair market value of the property. As the appellate court
explained:
We note that petitioner, in its Complaint, classified the lands of Far East
and the Bernasconis as Residential/Agricultural, while the properties of The first refers to the preliminary or provisional determination of the value
Arsol were classified as Agricultural.71 Petitioner uniformly pegged the of the property. It serves a double-purpose of pre-payment if the property
zonal valuation of all the lands sought to be expropriated at ₱75.00 per is fully expropriated, and of an indemnity for damages if the proceedings
square meter. The classification it made for the lands of Far East and the are dismissed. It is not a final determination of just compensation and
Bernasconis was residential/agricultural, but the zonal valuation was for may not necessarily be equivalent to the prevailing fair market value of
agricultural lands. From the tax declarations72 it attached to the complaint, the property. Of course, it may be a factor to be considered in the
it is clear that the lands of Far East and the Bernasconis were classified determination of just compensation.
as Residential. Why not use then the zonal valuation for residential,
which was ₱500.00 per square meter? As to the lands of Arsol, they were Just compensation, on the other hand, is the final determination of the fair
classified as agricultural in the tax declarations, so petitioners used the market value of the property. It has been described as "the just and
zonal valuation for agricultural lands, which was ₱75.00 per square complete equivalent of the loss which the owner of the thing expropriated
meter. From the foregoing, it can be gathered that from the very inception has to suffer by reason of the expropriation." Market values, has also
of this case, petitioner, though knowing that the lands of Far East and the been described in a variety of ways as the "price fixed by the buyer and
Bernasconis were classified as residential, still used the zonal valuation seller in the open market in the usual and ordinary course of legal trade
for agricultural lands (₱75.00 per square meter). Petitioner knew that the and competition; the price and value of the article established as shown
lands of Far East and the Bernasconis were classified as residential, and by sale, public or private, in the ordinary way of business; the fair value of
this was why it indicated in its complaint the classification the property between one who desires to purchase and one who desires
"Residential/Agricultural." It cannot simply do away with the classification to sell; the current price; the general or ordinary price for which property
made in the tax declaration. It also used the said classification may be sold in that locality.
("Residential/Agricultural") to justify the zonal value it indicated in the
complaint. Thus, petitioner classified the lands of Far East and the
As the preliminary or provisional determination of the value of the
Bernasconis in its own way, contrary to the documents it had. What
property equivalent to 100% of the value of the property based on the
further militates against petitioner’s claim that the lands of Far East and
current relevant zonal valuation of the BIR, said amount serves a double
the Bernasconis are agricultural is the certification of the Office of the
purpose of pre-payment if the property is fully expropriated, and of
Municipal Planning and Development Coordinator/Zoning Administrator
indemnity for damages if the proceedings are dismissed. Said provisional
of the Municipality of Nasugbu, Batangas that the said lands have been
value must be paid to the owner of the land before a writ of possession
classified as residential by Municipal Zoning Ordinance No. 3 dated 3
may be issued. The issuance of a certificate of availability of funds will
May 1982 as approved under Resolution No. 123, series of 1983 dated 4
not suffice for the purpose of issuance of a writ of possession.
May 1983 by the Human Settlement Regulatory Commission (now
HLURB).
After payment of the provisional amount, the court may now proceed to
determine the amount of just compensation. Petitioner can now present
its evidence relative to the properties’ fair market value as provided in
Section 5 of Republic Act No. 8974.74

WHEREFORE, premises considered, the decision of the Court of


Appeals dated 9 November 2006 in CA-G.R. SP No. 72425 is hereby
AFFIRMED. No costs.

SO ORDERED.
67.7 Republic of the Philippines Title (TCT) No. T-44894 (the Subject Property) to be used as a school
SUPREME COURT site for Lapaz High School.5 Petitioner alleged that the Subject Property
Manila was declared for tax purposes in Tax Declaration No. 40080 to have a
value of ₱60.00 per square meter, or a total value of ₱43,560.00. The
SECOND DIVISION case was docketed as Civil Case No. 14052 and raffled to then Court of
First Instance of Iloilo, Branch 7.
G.R. No. 168967 February 12, 2010
On December 9, 1981, Javellana filed his Answer6 where he admitted
CITY OF ILOILO represented by HON. JERRY P. TREÑAS, City ownership of the Subject Property but denied the petitioner’s avowed
Mayor, Petitioner, public purpose of the sought-for expropriation, since the City of Iloilo
vs. already had an existing school site for Lapaz High School. Javellana also
HON. LOLITA CONTRERAS-BESANA, Presiding Judge, Regional claimed that the true fair market value of his property was no less than
Trial Court, Branch 32, and ELPIDIO JAVELLANA, Respondents. ₱220.00 per square meter. 7

DECISION On May 11, 1982, petitioner filed a Motion for Issuance of Writ of
Possession, alleging that it had deposited the amount of ₱40,000.00 with
the Philippine National Bank-Iloilo Branch. Petitioner claimed that it was
DEL CASTILLO, J.:
entitled to the immediate possession of the Subject Property, citing
Section 1 of Presidential Decree No. 1533,8 after it had deposited an
It is arbitrary and capricious for the government to initiate expropriation amount equivalent to 10% of the amount of compensation. Petitioner
proceedings, seize a person’s property, allow the order of expropriation to attached to its motion a Certification issued by Estefanio C. Libutan, then
become final, but then fail to justly compensate the owner for over 25 Officer-in-Charge of the Iloilo City Treasurer’s Office, stating that said
years. This is government at its most high-handed and irresponsible, and deposit was made.9
should be condemned in the strongest possible terms. For its failure to
properly compensate the landowner, the City of Iloilo is liable for
Javellana filed an Opposition to the Motion for the Issuance of Writ of
damages.
Possession10 citing the same grounds he raised in his Answer – that the
city already had a vast tract of land where its existing school site was
This Petition for Certiorari under Rule 65 of the Rules of Court with a located, and the deposit of a mere 10% of the Subject Property’s tax
prayer for the issuance of a temporary restraining order seeks to overturn valuation was grossly inadequate.
the three Orders issued by Regional Trial Court (RTC) of Iloilo City,
Branch 32 on the following dates: December 12, 2003 (the First Assailed
On May 17, 1983, the trial court issued an Order11 which granted
Order),1 June 15, 2004 (the Second Assailed Order),2and March 9, 2005
petitioner’s Motion for Issuance of Writ of Possession and authorized the
(the Third Assailed Order) (the three aforementioned Orders are
petitioner to take immediate possession of the Subject Property. The
collectively referred to as the Assailed Orders).3
court ruled:
Factual Antecedents
Premises considered, the Motion for the Issuance of a Writ of Possession
dated May 10, 1982, filed by plaintiff is hereby granted. Plaintiff is hereby
The essential facts are not in dispute. allowed to take immediate possession, control and disposition of the
properties known as Lot Nos. 3497-CC and 3497-DD x x x.12
On September 18, 1981, petitioner filed a Complaint4 for eminent domain
against private respondent Elpidio T. Javellana (Javellana) and Southern Thereafter, a Writ of Possession13 was issued in petitioner’s favor, and
Negros Development Bank, the latter as mortgagee. The complaint petitioner was able to take physical possession of the properties
sought to expropriate two parcels of land known as Lot Nos. 3497-CC sometime in the middle of 1985. At no time has Javellana ever denied
and 3497-DD registered in Javellana’s name under Transfer Certificate of
that the Subject Property was actually used as the site of Lapaz National On November 20, 2003, private respondent filed a Motion/Manifestation
High School. Aside from the filing by the private respondent of dated November 19, 2003 claiming that before a commission is created,
his Amended Answer on April 21, 1984,14 the expropriation proceedings the trial court should first order the condemnation of the property, in
remained dormant. accordance with the Rules of Court. Javellana likewise insisted that the
fair market value of the Subject Property should be reckoned from the
Sixteen years later, on April 17, 2000, Javellana filed an Ex Parte date when the court orders the condemnation of the property, and not the
Motion/Manifestation, where he alleged that when he finally sought to date of actual taking, since petitioner’s possession of the property was
withdraw the ₱40,000.00 allegedly deposited by the petitioner, he questionable.21 Before petitioner could file its Comment, the RTC issued
discovered that no such deposit was ever made. In support of this an Order dated November 21, 2003 denying the Motion.22
contention, private respondent presented a Certification from the
Philippine National Bank stating that no deposit was ever made for the Undeterred, Javellana filed on November 25, 2003, an Omnibus Motion
expropriation of the Subject Property.15Private respondent thus to Declare Null and Void the Order of May 17, 1983 and to Require
demanded his just compensation as well as interest. Attempts at an Plaintiff to Deposit 10% or ₱254,000.00. Javellana claimed that the
amicable resolution and a negotiated sale were unsuccessful. It bears amount is equivalent to the 10% of the fair market value of the Subject
emphasis that petitioner could not present any evidence – whether Property, as determined by the Iloilo City Appraisal Committee in 2001, at
documentary or testimonial – to prove that any payment was actually the time when the parties were trying to negotiate a settlement.23
made to private respondent.
First Assailed Order
Thereafter, on April 2, 2003, private respondent filed a
Complaint16 against petitioner for Recovery of Possession, Fixing and On December 12, 2003, the RTC issued the First Assailed Order, which
Recovery of Rental and Damages. The case was docketed as Civil Case nullified the Order dated May 17, 1983 (concerning the issuance of a writ
No. 03-27571, and raffled to Branch 28 of the Iloilo City Regional Trial of possession over the Subject Property). The trial court ruled:
Court. Private respondent alleged that since he had not been
compensated for the Subject Property, petitioner’s possession was x x x the Order dated May 17, 1983 is hereby declared null and void and
illegal, and he was entitled to recovery of possession of his lots. He the plaintiff [is] hereby ordered to immediately deposit with the PNB the
prayed that petitioner be ordered to vacate the Subject Property and pay 10% of the just compensation after the Commission shall have rendered
rentals amounting to ₱15,000.00 per month together with moral, its report and have determined the value of the property not at the time it
exemplary, and actual damages, as well as attorney’s fees. 1avvphi1

was condemned but at the time the complaint was filed in


court.24 (Emphasis ours)
On May 15, 2003, petitioner filed its Answer,17 arguing that Javellana
could no longer bring an action for recovery since the Subject Property Second Assailed Order
was already taken for public use. Rather, private respondent could only
demand for the payment of just compensation. Petitioner also maintained
Neither party sought reconsideration of this Order.25 Nonetheless, about
that the legality or illegality of petitioner’s possession of the property
six months later, the RTC issued the Second Assailed Order, which it
should be determined in the eminent domain case and not in a separate
denominated as an "Amended Order". The Second Assailed Order was
action for recovery of possession.
identical to the first, except that the reckoning point for just compensation
was now the "time this order was issued," which is June 15, 2004.
Both parties jointly moved to consolidate the expropriation case (Civil
Case No. 14052) and the case for recovery of possession (Civil Case No.
x x x the Order dated May 17, 1983 is hereby declared null and void and
03-27571),18 which motion was granted by the trial court in an Order
the plaintiff [is] hereby ordered to immediately deposit with the PNB the
dated August 26, 2003.19 On November 14, 2003, a commission was
10% of the just compensation after the Commission shall have rendered
created to determine the just compensation due to Javellana.20
its report and have determined the value of the property not at the time it
was condemned but at the time this order was issued. (Underscoring in Value per Fair Market
original text) Reckoning Point B
square meter Value

This time, petitioner filed a Motion for Reconsideration claiming that there 1981 - at the
based on three or
was no legal basis for the issuance of the Second Assailed time the
₱110.00/sqm ₱79,860.00 of similar types o
Order.26 Javellana opposed, arguing that since the May 17, 1983 Order complaint was
the s
and the Second Assailed Order were interlocutory in character, they were filed
always subject to modification and revision by the court anytime.27 Appraisal by
1981 – at the
Development Ba
time the
Third Assailed Order ₱686.81/sqm ₱498,625.22 value, zonal valu
complaint was
other banks, re
filed
After the parties were able to fully ventilate their respective neighb
positions,28 the public respondent issued the Third Assailed Order,
Appraisal by t
denying the Motion for Reconsideration, and ruling as follows: 2002 ₱3,500.00/sqm ₱2,541,000.00
Committee, Office
The Order dated June 15, 2004 among other things stated that parties Private Appraisal
2004 ₱4,200.00/sqm ₱hP3,049,200.00
and counsels must be bound by the Commissioner’s Report regarding Cal Catolico d
the value of the property not at the time it was condemned but at the time
this order was issued. Hence, the present petition.

This is true inasmuch as there was no deposit at the PNB and their taking Petitioner’s Arguments
was illegal.
Petitioner is before us claiming that (1) the trial court gravely abused its
The plaintiff thru [sic] Atty. Laurea alleged that this Court had a change of discretion amounting to lack or excess of jurisdiction in overturning the
heart and issued an Amended Order with the same wordings as the order Order dated May 17, 1983, which was already a final order; and (2) just
of December 12, 2003 but this time stated not at the time it was compensation for the expropriation should be based on the Subject
condemned but at the time the order was issued. Naturally, this Court in Property’s fair market value either at the time of taking or filing of the
the interest of justice, can amend its order because there was no deposit complaint.
by plaintiff.
Private Respondent’s Arguments
The jurisprudence cited by plaintiff that the just compensation must be
determined as of the date of the filing of the complaint is true if there was
Private respondent filed his Comment on October 3, 2005,31 arguing that
a deposit. Because there was none the filing was not in accordance with
(1) there was no error of jurisdiction correctible by certiorari; and (2) that
law, hence, must be at the time the order was issued.
the Assailed Orders were interlocutory orders that were subject to
amendment and nullification at the discretion of the court.
The allegation of defendant thru [sic] counsel that the orders attacked by
plaintiff thru [sic] counsel saying it has become final and executory are
Issues
interlocutory orders subject to the control of the Judge until final judgment
is correct. Furthermore, it is in the interes[t] of justice to correct errors.29
There are only two questions we need answer, and they are not at all
novel. First, does an order of expropriation become final? Second, what
In the meantime, on April 15, 2004, the Commission submitted its Report,
is the correct reckoning point for the determination of just compensation?
providing the following estimates of value, but without making a proper
recommendation:30
Our Ruling is to be determined "as of the date of the filing of the complaint." Here,
there is no reason to depart from the general rule that the point of
Expropriation proceedings have two stages. The first phase ends with an reference for assessing the value of the Subject Property is the time of
order of dismissal, or a determination that the property is to be acquired the filing of the complaint for expropriation.40
for a public purpose.32 Either order will be a final order that may be
appealed by the aggrieved party.33 The second phase consists of the Private respondent claims that the reckoning date should be in 2004
determination of just compensation. 34 It ends with an order fixing the because of the "clear injustice to the private respondent who all these
amount to be paid to the landowner. Both orders, being final, are years has been deprived of the beneficial use of his properties."
appealable.35
We commiserate with the private respondent. The school was
An order of condemnation or dismissal is final, resolving the question of constructed and has been in operation since 1985. Petitioner and the
whether or not the plaintiff has properly and legally exercised its power of residents of Iloilo City have long reaped the benefits of the property.
eminent domain.36 Once the first order becomes final and no appeal However, non-payment of just compensation does not entitle the private
thereto is taken, the authority to expropriate and its public use can no landowners to recover possession of their expropriated lot.41
longer be questioned.37 1avv phi 1

Concededly, Javellana also slept on his rights for over 18 years and did
Javellana did not bother to file an appeal from the May 17, 1983 Order not bother to check with the PNB if a deposit was actually made by the
which granted petitioner’s Motion for Issuance of Writ of Possession and petitioner. Evidently, from his inaction in failing to withdraw or even verify
which authorized petitioner to take immediate possession of the Subject the amounts purportedly deposited, private respondent not only accepted
Property. Thus, it has become final, and the petitioner’s right to the valuation made by the petitioner, but also was not interested enough
expropriate the property for a public use is no longer subject to review. to pursue the expropriation case until the end. As such, private
On the first question, therefore, we rule that the trial court gravely erred in respondent may not recover possession of the Subject Property, but is
nullifying the May 17, 1983 Order. entitled to just compensation.42 It is high time that private respondent be
paid what was due him after almost 30 years.
We now turn to the reckoning date for the determination of just
compensation. Petitioner claims that the computation should be made as We stress, however, that the City of Iloilo should be held liable for
of September 18, 1981, the date when the expropriation complaint was damages for taking private respondent’s property without payment of just
filed. We agree. compensation. In Manila International Airport Authority v. Rodriguez,43 the
Court held that a government agency’s prolonged occupation of private
In a long line of cases, we have constantly affirmed that: property without the benefit of expropriation proceedings undoubtedly
entitled the landowner to damages:
x x x just compensation is to be ascertained as of the time of the taking,
which usually coincides with the commencement of the expropriation Such pecuniary loss entitles him to adequate compensation in the
proceedings. Where the institution of the action precedes entry into the form of actual or compensatory damages, which in this case should
property, the just compensation is to be ascertained as of the time of the be the legal interest (6%) on the value of the land at the time of
filing of the complaint.38 taking, from said point up to full payment by the MIAA. This is based
on the principle that interest "runs as a matter of law and follows from the
When the taking of the property sought to be expropriated coincides with right of the landowner to be placed in as good position as money can
the commencement of the expropriation proceedings, or takes place accomplish, as of the date of the taking x x x.
subsequent to the filing of the complaint for eminent domain, the just
compensation should be determined as of the date of the filing of the xxxx
complaint.39 Even under Sec. 4, Rule 67 of the 1964 Rules of Procedure,
under which the complaint for expropriation was filed, just compensation
For more than twenty (20) years, the MIAA occupied the subject lot
without the benefit of expropriation proceedings and without the MIAA
exerting efforts to ascertain ownership of the lot and negotiating with any
of the owners of the property. To our mind, these are wanton and
irresponsible acts which should be suppressed and corrected.
Hence, the award of exemplary damages and attorneys fees is in
order. x x x.44 (Emphasis supplied)

WHEREFORE, the petition is GRANTED. The Orders of the Regional


Trial Court of Iloilo City, Branch 32 in Civil Case No. 14052 and Civil
Case No. 03-27571 dated December 12, 2003, June 15, 2004, and
March 9, 2005 are hereby ANNULLED and SET ASIDE.

The Regional Trial Court of Iloilo City, Branch 32 is DIRECTED to


immediately determine the just compensation due to private respondent
Elpidio T. Javellana based on the fair market value of the Subject
Property at the time Civil Case No. 14052 was filed, or on September 18,
1981 with interest at the legal rate of six percent (6%) per annum from
the time of filing until full payment is made.

The City of Iloilo is ORDERED to pay private respondent the amount of


₱200,000.00 as exemplary damages.

SO ORDERED.
Republic of the Philippines while HPI’s property was valued at ₱164,478,178.14. HPI and AFC
SUPREME COURT rejected these valuations for being very low.
Manila
In its follow through action, the DAR requested the Land Bank of the
EN BANC Philippines (LBP) to deposit ₱26,409,549.86 in AFC’s bank account and
₱45,481,706.76 in HPI’s bank account, which amounts the petitioners
G.R. No. 164195 October 12, 2010 then withdrew. The titles over AFC and HPI’s properties were thereafter
cancelled, and new ones were issued on December 9, 1996 in the name
APO FRUITS CORPORATION and HIJO PLANTATION, of the Republic of the Philippines.
INC., Petitioners,
vs. On February 14, 1997, AFC and HPI filed separate petitions for
LAND BANK OF THE PHILIPPINES, Respondent. determination of just compensation with the DAR Adjudication Board
(DARAB). When the DARAB failed to act on these petitions for more than
RESOLUTION three years, AFC and HPI filed separate complaints for determination and
payment of just compensation with the Regional Trial Court (RTC) of
Tagum City, acting as a Special Agrarian Court. These complaints were
BRION, J.:
subsequently consolidated.
We resolve the petitioners’ motion for reconsideration addressing our
On September 25, 2001, the RTC resolved the consolidated cases, fixing
Resolution of December 4, 2009 whose dispositive portion directs:
the just compensation for the petitioners’ 1,338.6027 hectares of land1 at
₱1,383,179,000.00, with interest on this amount at the prevailing market
WHEREFORE, the Court denies the petitioners’ second motion for interest rates, computed from the taking of the properties on December 9,
reconsideration (with respect to the denial of the award of legal interest 1996 until fully paid, minus the amounts the petitioners already received
and attorney’s fees), and reiterates the decision dated February 6, 2007 under the initial valuation. The RTC also awarded attorney’s fees.
and the resolution dated December 19, 2007 of the Third Division.
LBP moved for the reconsideration of the decision. The RTC, in its order
For a fuller and clearer presentation and appreciation of this Resolution, of December 5, 2001, modified its ruling and fixed the interest at the rate
we hark back to the roots of this case. of 12% per annum from the time the complaint was filed until finality of
the decision. The Third Division of this Court, in its Decision of February
Factual Antecedents 6, 2007, affirmed this RTC decision.

Apo Fruits Corporation (AFC) and Hijo Plantation, Inc. (HPI), together On motion for reconsideration, the Third Division issued its Resolution of
also referred to as petitioners, were registered owners of vast tracks of December 19, 2007, modifying its February 6, 2007 Decision by deleting
land; AFC owned 640.3483 hectares, while HPI owned 805.5308 the 12% interest due on the balance of the awarded just compensation.
hectares. On October 12, 1995, they voluntarily offered to sell these The Third Division justified the deletion by the finding that the LBP did not
landholdings to the government via Voluntary Offer to Sell applications delay the payment of just compensation as it had deposited the pertinent
filed with the Department of Agrarian Reform (DAR). amounts due to AFC and HPI within fourteen months after they filed their
complaints for just compensation with the RTC. The Court also
On October 16, 1996, AFC and HPI received separate notices of land considered that AFC had already collected approximately ₱149.6 million,
acquisition and valuation of their properties from the DAR’s Provincial while HPI had already collected approximately ₱262 million from the LBP.
Agrarian Reform Officer (PARO). At the assessed valuation of The Third Division also deleted the award of attorney’s fees.
₱165,484.47 per hectare, AFC’s land was valued at ₱86,900,925.88,
All parties moved for the reconsideration of the modified ruling. The Court Justice Minita V. Chico-Nazario,2 the ponente of the original December
uniformly denied all the motions in its April 30, 2008 Resolution. Entry of 19, 2007 Resolution (deleting the 12% interest), dissented from the Court
Judgment followed on May 16, 2008. En Banc’s December 4, 2009 Resolution.

Notwithstanding the Entry of Judgment, AFC and HPI filed the following On the issue of immutability of judgment, Justice Chico-Nazario pointed
motions on May 28, 2008: (1) Motion for Leave to File and Admit Second out that under extraordinary circumstances, this Court has recalled
Motion for Reconsideration; (2) Second Motion for Reconsideration, with entries of judgment on the ground of substantial justice. Given the special
respect to the denial of the award of legal interest and attorney’s fees; circumstances involved in the present case, the Court En Banc should
and (3) Motion to Refer the Second Motion for Reconsideration to the have taken a second hard look at the petitioners’ positions in their second
Honorable Court En Banc. motion for reconsideration, and acted to correct the clearly erroneous
December 19, 2007 Resolution.
The Third Division found the motion to admit the Second Motion for
Reconsideration and the motion to refer this second motion to the Court Specifically, Justice Chico-Nazario emphasized the obligation of the
En Banc meritorious, and accordingly referred the case to the Court En State, in the exercise of its inherent power of eminent domain, to pay just
Banc. On September 8, 2009, the Court En Banc accepted the referral. compensation to the owner of the expropriated property. To be just, the
compensation must not only be the correct amount to be paid; it must
The Court En Banc Resolution also be paid within a reasonable time from the time the land is taken from
the owner. If not, the State must pay the landowner interest, by way of
On December 4, 2009, the Court En Banc, by a majority vote, denied the damages, from the time the property was taken until just compensation is
petitioners’ second motion for reconsideration based on two fully paid. This interest, deemed a part of just compensation due, has
considerations. been established by prevailing jurisprudence to be 12% per annum.

First, the grant of the second motion for reconsideration runs counter to On these premises, Justice Nazario pointed out that the government
the immutability of final decisions. Moreover, the Court saw no reason to deprived the petitioners of their property on December 9, 1996, and paid
recognize the case as an exception to the immutability principle as the the balance of the just compensation due them only on May 9, 2008. The
petitioners’ private claim for the payment of interest does not qualify as delay of almost twelve years earned the petitioners interest in the total
either a substantial or transcendental matter or an issue of paramount amount of ₱1,331,124,223.05.
public interest.
Despite this finding, Justice Chico-Nazario did not see it fit to declare the
Second, on the merits, the petitioners are not entitled to recover interest computed interest to be totally due; she found it unconscionable to apply
on the just compensation and attorney’s fees because they caused the the full force of the law on the LBP because of the magnitude of the
delay in the payment of the just compensation due them; they amount due. She thus reduced the awarded interest to ₱400,000,000.00,
erroneously filed their complaints with the DARAB when they should have or approximately 30% of the computed interest.
directly filed these with the RTC acting as an agrarian court. Furthermore,
the Court found it significant that the LBP deposited the pertinent The Present Motion for Reconsideration
amounts in the petitioners’ favor within fourteen months after the petitions
were filed with the RTC. Under these circumstances, the Court found no In their motion to reconsider the Court En Banc’s December 4, 2009
unreasonable delay on the part of LBP to warrant the award of 12% Resolution (the present Motion for Reconsideration), the petitioners
interest. principally argue that: (a) the principle of immutability of judgment does
not apply since the Entry of Judgment was issued even before the lapse
The Chico-Nazario Dissent of fifteen days from the parties’ receipt of the April 30, 2008 Resolution
and the petitioners timely filed their second motion for reconsideration
within fifteen days from their receipt of this resolution; (b) the April 30,
2008 Resolution cannot be considered immutable considering the special At the heart of the present controversy is the Third Division’s December
and compelling circumstances attendant to the present case which fall 19, 2007 Resolution which held that the petitioners are not entitled to
within the exceptions to the principle of immutability of judgments; (c) the 12% interest on the balance of the just compensation belatedly paid by
legal interest due is at 12% per annum, reckoned from the time of the the LBP. In the presently assailed December 4, 2009 Resolution, we
taking of the subject properties and this rate is not subject to reduction. affirmed the December 19, 2007 Resolution’s findings that: (a) the LBP
The power of the courts to equitably reduce interest rates applies solely deposited "pertinent amounts" in favor of the petitioners within fourteen
to liquidated damages under a contract and not to interest set by the months after they filed their complaint for determination of just
Honorable Court itself as due and owing in just compensation cases; and compensation; and (b) the LBP had already paid the petitioners
(d) the Honorable Court’s fears that the interest payments due to the ₱411,769,168.32. We concluded then that these circumstances refuted
petitioners will produce more harm than good to the system of agrarian the petitioners’ assertion of unreasonable delay on the part of the LBP.
reform are misplaced and are based merely on conjectures.
A re-evaluation of the circumstances of this case and the parties’
The Comment of the Land Bank of the Philippines arguments, viewed in light of the just compensation requirement in the
exercise of the State’s inherent power of eminent domain, compels us to
The LBP commented on the petitioners’ motion for reconsideration on re-examine our findings and conclusions.
April 28, 2010. It maintained that: (a) the doctrine of immutability of the
decisions of the Supreme Court clearly applies to the present case; (b) Eminent domain is the power of the State to take private property for
the LBP is not guilty of undue delay in the payment of just compensation public use.3 It is an inherent power of State as it is a power necessary for
as the petitioners were promptly paid once the Court had determined the the State’s existence; it is a power the State cannot do without.4 As an
final value of the properties expropriated; (c) the Supreme Court rulings inherent power, it does not need at all to be embodied in the Constitution;
invoked by the petitioners are inapplicable to the present case; (d) since if it is mentioned at all, it is solely for purposes of limiting what is
the obligation to pay just compensation is not a forbearance of money, otherwise an unlimited power. The limitation is found in the Bill of
interest should commence only after the amount due becomes Rights5 – that part of the Constitution whose provisions all aim at the
ascertainable or liquidated, and the 12% interest per annum applies only protection of individuals against the excessive exercise of governmental
to the liquidated amount, from the date of finality of judgment; (e) the powers.
imposition of 12% interest on the balance of P971,409,831.68 is
unwarranted because there was no unjustified refusal by LBP to pay just Section 9, Article III of the 1987 Constitution (which reads "No private
compensation, and no contractual breach is involved; (f) the deletion of property shall be taken for public use without just compensation.")
the attorney’s fees equivalent to 10% of the amount finally awarded as provides two essential limitations to the power of eminent domain,
just compensation is proper; (g) this case does not involve a violation of namely, that (1) the purpose of taking must be for public use and (2) just
substantial justice to justify the alteration of the immutable resolution compensation must be given to the owner of the private property.
dated December 19, 2007 that deleted the award of interest and
attorney’s fees. It is not accidental that Section 9 specifies that compensation should be
"just" as the safeguard is there to ensure a balance – property is not to be
The Court’s Ruling taken for public use at the expense of private interests; the public,
through the State, must balance the injury that the taking of property
We find the petitioners’ arguments meritorious and accordingly GRANT causes through compensation for what is taken, value for value.
the present motion for reconsideration.
Nor is it accidental that the Bill of Rights is interpreted liberally in favor of
Just compensation – a Basic Limitation on the State’s the individual and strictly against the government. The protection of the
individual is the reason for the Bill of Rights’ being; to keep the exercise
Power of Eminent Domain of the powers of government within reasonable bounds is what it seeks.6
The concept of "just compensation" is not new to Philippine constitutional actual value of the expropriated properties. We point this aspect out to
law,7 but is not original to the Philippines; it is a transplant from the show that the initial payments made by the LBP when the petitioners’
American Constitution.8 It found fertile application in this country landholdings were taken, although promptly withdrawn by the petitioners,
particularly in the area of agrarian reform where the taking of private could not by any means be considered a fair exchange of values at the
property for distribution to landless farmers has been equated to the time of taking; in fact, the LBP’s actual deposit could not be said to be
"public use" that the Constitution requires. In Land Bank of the substantial even from the original LBP valuation of ₱251,379,103.90.
Philippines v. Orilla,9 a valuation case under our agrarian reform law, this
Court had occasion to state: Thus, the deposits might have been sufficient for purposes of the
immediate taking of the landholdings but cannot be claimed as amounts
Constitutionally, "just compensation" is the sum equivalent to the market that would excuse the LBP from the payment of interest on the unpaid
value of the property, broadly described as the price fixed by the seller in balance of the compensation due. As discussed at length below, they
open market in the usual and ordinary course of legal action and were not enough to compensate the petitioners for the potential income
competition, or the fair value of the property as between the one who the landholdings could have earned for them if no immediate taking had
receives and the one who desires to sell, it being fixed at the time of the taken place. Under the circumstances, the State acted oppressively and
actual taking by the government. Just compensation is defined as the full was far from "just" in their position to deny the petitioners of the potential
and fair equivalent of the property taken from its owner by the income that the immediate taking of their properties entailed.
expropriator. It has been repeatedly stressed by this Court that the true
measure is not the taker's gain but the owner's loss. The word "just" is Just Compensation from the Prism of the Element of Taking.
used to modify the meaning of the word "compensation" to convey the
idea that the equivalent to be given for the property to be taken shall be Apart from the requirement that compensation for expropriated land must
real, substantial, full and ample.10 [Emphasis supplied.] be fair and reasonable, compensation, to be "just," must also be made
without delay.12 Without prompt payment, compensation cannot be
In the present case, while the DAR initially valued the petitioners’ considered "just" if the property is immediately taken as the property
landholdings at a total of ₱251,379,104.02,11 the RTC, acting as a special owner suffers the immediate deprivation of both his land and its fruits or
agrarian court, determined the actual value of the petitioners’ income.
landholdings to be ₱1,383,179,000.00. This valuation, a finding of fact,
has subsequently been affirmed by this Court, and is now beyond This is the principle at the core of the present case where the petitioners
question. In eminent domain terms, this amount is the "real, substantial, were made to wait for more than a decade after the taking of their
full and ample" compensation the government must pay to be "just" to the property before they actually received the full amount of the principal of
landowners. the just compensation due them.13 What they have not received to date is
the income of their landholdings corresponding to what they would have
Significantly, this final judicial valuation is far removed from the initial received had no uncompensated taking of these lands been immediately
valuation made by the DAR; their values differ by ₱1,131,799,897.00 – in made. This income, in terms of the interest on the unpaid principal, is the
itself a very substantial sum that is roughly four times the original DAR subject of the current litigation.
valuation. We mention these valuations as they indicate to us how
undervalued the petitioners’ lands had been at the start, particularly at the We recognized in Republic v. Court of Appeals14 the need for prompt
time the petitioners’ landholdings were "taken". This reason apparently payment and the necessity of the payment of interest to compensate for
compelled the petitioners to relentlessly pursue their valuation claims all any delay in the payment of compensation for property already taken. We
they way up to the level of this Court. ruled in this case that:

While the LBP deposited the total amount of ₱71,891,256.62 into the The constitutional limitation of "just compensation" is considered to be the
petitioners’ accounts (₱26,409,549.86 for AFC and ₱45,481,706.76 for sum equivalent to the market value of the property, broadly described to
HPI) at the time the landholdings were taken, these amounts were mere be the price fixed by the seller in open market in the usual and ordinary
partial payments that only amounted to 5% of the ₱1,383,179,000.00
course of legal action and competition or the fair value of the property as These were the established rulings that stood before this Court issued
between one who receives, and one who desires to sell, i[f] fixed at the the currently assailed Resolution of December 4, 2009. These would be
time of the actual taking by the government. Thus, if property is taken for the rulings this Court shall reverse and de-establish if we maintain and
public use before compensation is deposited with the court having affirm our ruling deleting the 12% interest on the unpaid balance of
jurisdiction over the case, the final compensation must include interest[s] compensation due for properties already taken.
on its just value to be computed from the time the property is taken to the
time when compensation is actually paid or deposited with the court. In Under the circumstances of the present case, we see no compelling
fine, between the taking of the property and the actual payment, legal reason to depart from the rule that Republic firmly established. Let it be
interest[s] accrue in order to place the owner in a position as good as (but remembered that shorn of its eminent domain and social justice aspects,
not better than) the position he was in before the taking what the agrarian land reform program involves is the purchase by the
occurred.15 [Emphasis supplied.] government, through the LBP, of agricultural lands for sale and
distribution to farmers. As a purchase, it involves an exchange of values
Aside from this ruling, Republic notably overturned the Court’s previous – the landholdings in exchange for the LBP’s payment. In determining the
ruling in National Power Corporation v. Angas16 which held that just just compensation for this exchange, however, the measure to be borne
compensation due for expropriated properties is not a loan or in mind is not the taker's gain but the owner's loss25 since what is involved
forbearance of money but indemnity for damages for the delay in is the takeover of private property under the State’s coercive power. As
payment; since the interest involved is in the nature of damages rather mentioned above, in the value-for-value exchange in an eminent domain
than earnings from loans, then Art. 2209 of the Civil Code, which fixes situation, the State must ensure that the individual whose property is
legal interest at 6%, shall apply. taken is not shortchanged and must hence carry the burden of showing
that the "just compensation" requirement of the Bill of Rights is satisfied.
In Republic, the Court recognized that the just compensation due to the
landowners for their expropriated property amounted to an effective The owner’s loss, of course, is not only his property but also its income-
forbearance on the part of the State. Applying the Eastern Shipping Lines generating potential. Thus, when property is taken, full compensation of
ruling,17 the Court fixed the applicable interest rate at 12% per annum, its value must immediately be paid to achieve a fair exchange for the
computed from the time the property was taken until the full amount of property and the potential income lost. The just compensation is made
just compensation was paid, in order to eliminate the issue of the available to the property owner so that he may derive income from this
constant fluctuation and inflation of the value of the currency over time. In compensation, in the same manner that he would have derived income
the Court’s own words: from his expropriated property. If full compensation is not paid for
property taken, then the State must make up for the shortfall in the
The Bulacan trial court, in its 1979 decision, was correct in imposing earning potential immediately lost due to the taking, and the absence of
interest[s] on the zonal value of the property to be computed from the replacement property from which income can be derived; interest on the
time petitioner instituted condemnation proceedings and "took" the unpaid compensation becomes due as compliance with the constitutional
property in September 1969. This allowance of interest on the amount mandate on eminent domain and as a basic measure of fairness.
found to be the value of the property as of the time of the taking
computed, being an effective forbearance, at 12% per annum should help In the context of this case, when the LBP took the petitioners’
eliminate the issue of the constant fluctuation and inflation of the value of landholdings without the corresponding full payment, it became liable to
the currency over time.18 [Emphasis supplied.] 1avvphi1 the petitioners for the income the landholdings would have earned had
they not immediately been taken from the petitioners. What is interesting
We subsequently upheld Republic’s 12% per annum interest rate on the in this interplay, under the developments of this case, is that the LBP, by
unpaid expropriation compensation in the following cases: Reyes v. taking landholdings without full payment while holding on at the same
National Housing Authority,19 Land Bank of the Philippines v. time to the interest that it should have paid, effectively used or retained
Wycoco,20 Republic v. Court of Appeals,21 Land Bank of the Philippines v. funds that should go to the landowners and thereby took advantage of
Imperial,22 Philippine Ports Authority v. Rosales-Bondoc,23 and Curata v. these funds for its own account.
Philippine Ports Authority.24
From this point of view, the December 19, 2007 Resolution deleting the In any language and by any measure, a lengthy delay in payment
award of 12% interest is not only patently and legally wrong, but is also occurred.
morally unconscionable for being grossly unfair and unjust. If the interest
on the just compensation due – in reality the equivalent of the fruits or An important starting point in considering attribution for the delay is that
income of the landholdings would have yielded had these lands not been the petitioners voluntarily offered to sell their landholdings to the
taken – would be denied, the result is effectively a confiscatory action by government’s land reform program; they themselves submitted their
this Court in favor of the LBP. We would be allowing the LBP, for twelve Voluntary Offer to Sell applications to the DAR, and they fully cooperated
long years, to have free use of the interest that should have gone to the with the government’s program. The present case therefore is not one
landowners. Otherwise stated, if we continue to deny the petitioners’ where substantial conflict arose on the issue of whether expropriation is
present motion for reconsideration, we would – illogically and without proper; the petitioners voluntarily submitted to expropriation and
much thought to the fairness that the situation demands – uphold the surrendered their landholdings, although they contested the valuation that
interests of the LBP, not only at the expense of the landowners but also the government made.
that of substantial justice as well.
Presumably, had the landholdings been properly valued, the petitioners
Lest this Court be a party to this monumental unfairness in a social would have accepted the payment of just compensation and there would
program aimed at fostering balance in our society, we now have to ring have been no need for them to go to the extent of filing a valuation case.
the bell that we have muted in the past, and formally declare that the But, as borne by the records, the petitioners’ lands were grossly
LBP’s position is legally and morally wrong. To do less than this is to undervalued by the DAR, leaving the petitioners with no choice but to file
leave the demands of the constitutional just compensation standard (in actions to secure what is justly due them.
terms of law) and of our own conscience (in terms of morality) wanting
and unsatisfied. The DAR’s initial gross undervaluation started the cycle of court actions
that followed, where the LBP eventually claimed that it could not be
The Delay in Payment Issue faulted for seeking judicial recourse to defend the government’s and its
own interests in light of the petitioners’ valuation claims. This LBP claim,
Separately from the demandability of interest because of the failure to of course, conveniently forgets that at the root of all these valuation
fully pay for property already taken, a recurring issue in the case is the claims and counterclaims was the initial gross undervaluation by DAR
attribution of the delay. that the LBP stoutly defended. At the end, this undervaluation was proven
incorrect by no less than this Court; the petitioners were proven correct in
That delay in payment occurred is not and cannot at all be disputed. their claim, and the correct valuation – more than five-fold the initial DAR
While the LBP claimed that it made initial payments of ₱411,769,168.32 valuation – was decreed and became final.
(out of the principal sum due of P1,383,179,000.00), the undisputed fact
is that the petitioners were deprived of their lands on December 9, 1996 All these developments cannot now be disregarded and reduced to
(when titles to their landholdings were cancelled and transferred to the insignificance. In blunter terms, the government and the LBP cannot now
Republic of the Philippines), and received full payment of the principal be heard to claim that they were simply protecting their interests when
amount due them only on May 9, 2008. they stubbornly defended their undervalued positions before the courts.
The more apt and accurate statement is that they adopted a grossly
In the interim, they received no income from their landholdings because unreasonable position and the adverse developments that followed,
these landholdings had been taken. Nor did they receive adequate particularly the concomitant delay, should be directly chargeable to them.
income from what should replace the income potential of their
landholdings because the LBP refused to pay interest while withholding To be sure, the petitioners were not completely correct in the legal steps
the full amount of the principal of the just compensation due by claiming a they took in their valuation claims. They initially filed their valuation claim
grossly low valuation. This sad state continued for more than a decade. before the DARAB instead of immediately seeking judicial intervention.
The DARAB, however, contributed its share to the petitioners’ error when
it failed or refused to act on the valuation petitions for more than three (3) failed to act at all on the petitioners’ complaints for determination of just
years. Thus, on top of the DAR undervaluation was the DARAB inaction compensation.
after the petitioners’ landholdings had been taken. This Court’s Decision
of February 6, 2007 duly noted this and observed: In sum, in a balancing of the attendant delay-related circumstances of
this case, delay should be laid at the doorsteps of the government, not at
It is not controverted that this case started way back on 12 October 1995, the petitioners’. We conclude, too, that the government should not be
when AFC and HPI voluntarily offered to sell the properties to the DAR. In allowed to exculpate itself from this delay and should suffer all the
view of the failure of the parties to agree on the valuation of the consequences the delay caused.
properties, the Complaint for Determination of Just Compensation was
filed before the DARAB on 14 February 1997. Despite the lapse of more The LBP’s arguments on the applicability of cases imposing 12% interest
than three years from the filing of the complaint, the DARAB failed to
render a decision on the valuation of the land. Meantime, the titles over The LBP claims in its Comment that our rulings in Republic v. Court of
the properties of AFC and HPI had already been cancelled and in their Appeals,26 Reyes v. National Housing Authority,27 and Land Bank of the
place a new certificate of title was issued in the name of the Republic of Philippines v. Imperial,28 cannot be applied to the present case.
the Philippines, even as far back as 9 December 1996. A period of almost
10 years has lapsed. For this reason, there is no dispute that this case
According to the LBP, Republic is inapplicable because, first, the
has truly languished for a long period of time, the delay being mainly
landowners in Republic remained unpaid, notwithstanding the fact that
attributable to both official inaction and indecision, particularly on the
the award for just compensation had already been fixed by final
determination of the amount of just compensation, to the detriment of
judgment; in the present case, the Court already acknowledged that
AFC and HPI, which to date, have yet to be fully compensated for the
"pertinent amounts" were deposited in favor of the landowners within 14
properties which are already in the hands of farmer-beneficiaries, who,
months from the filing of their complaint. Second, while Republic involved
due to the lapse of time, may have already converted or sold the land
an ordinary expropriation case, the present case involves expropriation
awarded to them.
for agrarian reform. Finally, the just compensation in Republic remained
unpaid notwithstanding the finality of judgment, while the just
Verily, these two cases could have been disposed with dispatch were it compensation in the present case was immediately paid in full after LBP
not for LBP’s counsel causing unnecessary delay. At the inception of this received a copy of the Court’s resolution
case, DARAB, an agency of the DAR which was commissioned by law to
determine just compensation, sat on the cases for three years, which was
We find no merit in these assertions.
the reason that AFC and HPI filed the cases before the RTC. We
underscore the pronouncement of the RTC that "the delay by DARAB in
the determination of just compensation could only mean the reluctance of As we discussed above, the "pertinent amounts" allegedly deposited by
the Department of Agrarian Reform and the Land Bank of the Philippines LBP were mere partial payments that amounted to a measly 5% of the
to pay the claim of just compensation by corporate landowners." actual value of the properties expropriated. They could be the basis for
the immediate taking of the expropriated property but by no stretch of the
imagination can these nominal amounts be considered "pertinent"
To allow the taking of landowners’ properties, and to leave them empty-
enough to satisfy the full requirement of just compensation – i.e., the full
handed while government withholds compensation is undoubtedly
and fair equivalent of the expropriated property, taking into account its
oppressive. [Emphasis supplied.]
income potential and the foregone income lost because of the immediate
taking.
These statements cannot but be true today as they were when we
originally decided the case and awarded 12% interest on the balance of
We likewise find no basis to support the LBP’s theory that Republic and
the just compensation due. While the petitioners were undisputedly
the present case have to be treated differently because the first involves
mistaken in initially seeking recourse through the DAR, this agency itself
a "regular" expropriation case, while the present case involves
– hence, the government – committed a graver transgression when it
expropriation pursuant to the country’s agrarian reform program. In both
cases, the power of eminent domain was used and private property was property is taken to the time when compensation is actually paid or
taken for public use. Why one should be different from the other, so that deposited with the court. In fine, between the taking of the property and
the just compensation ruling in one should not apply to the other, truly the actual payment, legal interest[s] accrue in order to place the owner in
escapes us. If there is to be a difference, the treatment of agrarian reform a position as good as (but not better than) the position he was in before
expropriations should be stricter and on a higher plane because of the the taking occurred."29 This is the same legal principle applicable to the
government’s societal concerns and objectives. To be sure, the present case, as discussed above.
government cannot attempt to remedy the ills of one sector of society by
sacrificing the interests of others within the same society. While the LBP immediately paid the remaining balance on the just
compensation due to the petitioners after this Court had fixed the value of
Finally, we note that the finality of the decision (that fixed the value of just the expropriated properties, it overlooks one essential fact – from the time
compensation) in Republic was not a material consideration for the Court that the State took the petitioners’ properties until the time that the
in awarding the landowners 12% interest. The Court, in Republic, simply petitioners were fully paid, almost 12 long years passed. This is the
affirmed the RTC ruling imposing legal interest on the amount of just rationale for imposing the 12% interest – in order to compensate the
compensation due. In the process, the Court determined that the legal petitioners for the income they would have made had they been properly
interest should be 12% after recognizing that the just compensation due compensated for their properties at the time of the taking.
was effectively a forbearance on the part of the government. Had the
finality of the judgment been the critical factor, then the 12% interest Finally, the LBP insists that the petitioners quoted our ruling in Land Bank
should have been imposed from the time the RTC decision fixing just of the Philippines v. Imperial out of context. According to the LBP, the
compensation became final. Instead, the 12% interest was imposed from Court imposed legal interest of 12% per annum only after December 31,
the time that the Republic commenced condemnation proceedings and 2006, the date when the decision on just compensation became final.
"took" the property.
The LBP is again mistaken. The Imperial case involved land that was
The LBP additionally asserts that the petitioners erroneously relied on the expropriated pursuant to Presidential Decree No. 27,30 and fell under the
ruling in Reyes v. National Housing Authority. The LBP claims that we coverage of DAR Administrative Order (AO) No. 13.31 This AO provided
cannot apply Reyes because it involved just compensation that remained for the payment of a 6% annual interest if there is any delay in payment
unpaid despite the finality of the expropriation decision. LBP’s point of of just compensation. However, Imperial was decided in 2007 and AO
distinction is that just compensation was immediately paid in the present No. 13 was only effective up to December 2006. Thus, the Court, relying
case upon the Court’s determination of the actual value of the on our ruling in the Republic case, applied the prevailing 12% interest
expropriated properties. LBP claims, too, that in Reyes, the Court ruling to the period when the just compensation remained unpaid after
established that the refusal of the NHA to pay just compensation was December 2006. It is for this reason that December 31, 2006 was
unfounded and unjustified, whereas the LBP in the present case clearly important, not because it was the date of finality of the decision on just
demonstrated its willingness to pay just compensation. Lastly, in Reyes, compensation.
the records showed that there was an outstanding balance that ought to
be paid, while the element of an outstanding balance is absent in the The 12% Interest Rate and the Chico-Nazario Dissent
present case.
To fully reflect the concerns raised in this Court’s deliberations on the
Contrary to the LBP’s opinion, the imposition of the 12% interest in Reyes present case, we feel it appropriate to discuss the Justice Minita Chico-
did not depend on either the finality of the decision of the expropriation Nazario’s dissent from the Court’s December 4, 2009 Resolution.
court, or on the finding that the NHA’s refusal to pay just compensation
was unfounded and unjustified. Quite clearly, the Court imposed 12%
While Justice Chico-Nazario admitted that the petitioners were entitled to
interest based on the ruling in Republic v. Court of Appeals that "x x x if
the 12% interest, she saw it appropriate to equitably reduce the interest
property is taken for public use before compensation is deposited with the
charges from ₱1,331,124,223.05 to ₱400,000,000.00. In support of this
court having jurisdiction over the case, the final compensation must
include interest[s] on its just value to be computed from the time the
proposal, she enumerated various cases where the Court, pursuant to If the full payment of the principal sum of the just compensation is legally
Article 1229 of the Civil Code,32 equitably reduced interest charges. significant at all under the circumstances of this case, the significance is
only in putting a stop to the running of the interest due because the
We differ with our esteemed colleague’s views on the application of principal of the just compensation due has been paid. To close our eyes
equity. to these realities is to condone what is effectively a confiscatory action in
favor of the LBP.
While we have equitably reduced the amount of interest awarded in
numerous cases in the past, those cases involved interest that was That the legal interest due is now almost equivalent to the principal to be
essentially consensual in nature, i.e., interest stipulated in signed paid is not per se an inequitable or unconscionable situation, considering
agreements between the contracting parties. In contrast, the interest the length of time the interest has remained unpaid – almost twelve long
involved in the present case "runs as a matter of law and follows as a years. From the perspective of interest income, twelve years would have
matter of course from the right of the landowner to be placed in as good a been sufficient for the petitioners to double the principal, even if invested
position as money can accomplish, as of the date of taking."33 conservatively, had they been promptly paid the principal of the just
compensation due them. Moreover, the interest, however enormous it
Furthermore, the allegedly considerable payments made by the LBP to may be, cannot be inequitable and unconscionable because it resulted
the petitioners cannot be a proper premise in denying the landowners the directly from the application of law and jurisprudence – standards that
interest due them under the law and established jurisprudence. If the just have taken into account fairness and equity in setting the interest rates
compensation for the landholdings is considerable, this compensation is due for the use or forebearance of money.
not undue because the landholdings the owners gave up in exchange are
also similarly considerable – AFC gave up an aggregate landholding of If the LBP sees the total interest due to be immense, it only has itself to
640.3483 hectares, while HPI’s gave up 805.5308 hectares. When the blame, as this interest piled up because it unreasonably acted in its
petitioners surrendered these sizeable landholdings to the government, valuation of the landholdings and consequently failed to promptly pay the
the incomes they gave up were likewise sizeable and cannot in any way petitioners. To be sure, the consequences of this failure – i.e., the
be considered miniscule. The incomes due from these properties, enormity of the total interest due and the alleged financial hemorrhage
expressed as interest, are what the government should return to the the LBP may suffer – should not be the very reason that would excuse it
petitioners after the government took over their lands without full payment from full compliance. To so rule is to use extremely flawed logic. To so
of just compensation. In other words, the value of the landholdings rule is to disregard the question of how the LBP, a government financial
themselves should be equivalent to the principal sum of the just institution that now professes difficulty in paying interest at 12% per
compensation due; interest is due and should be paid to compensate for annum, managed the funds that it failed to pay the petitioners for twelve
the unpaid balance of this principal sum after taking has been completed. long years.
This is the compensation arrangement that should prevail if such
compensation is to satisfy the constitutional standard of being "just." It would be utterly fallacious, too, to argue that this Court should tread
lightly in imposing liabilities on the LBP because this bank represents the
Neither can LBP’s payment of the full compensation due before the government and, ultimately, the public interest. Suffice it to say that public
finality of the judgment of this Court justify the reduction of the interest interest refers to what will benefit the public, not necessarily the
due them. To rule otherwise would be to forget that the petitioners had to government and its agencies whose task is to contribute to the benefit of
wait twelve years from the time they gave up their lands before the the public. Greater public benefit will result if government agencies like
government fully paid the principal of the just compensation due them. the LBP are conscientious in undertaking its tasks in order to avoid the
These were twelve years when they had no income from their situation facing it in this case. Greater public interest would be served if it
landholdings because these landholdings have immediately been taken; can contribute to the credibility of the government’s land reform program
no income, or inadequate income, accrued to them from the proceeds of through the conscientious handling of its part of this program.
compensation payment due them because full payment has been
withheld by government. As our last point, equity and equitable principles only come into full play
when a gap exists in the law and jurisprudence.34 As we have shown
above, established rulings of this Court are in place for full application to reversing judgments and recalling their entries in the interest of
the present case. There is thus no occasion for the equitable substantial justice and where special and compelling reasons called for
consideration that Justice Chico-Nazario suggested. such actions.

The Amount Due the Petitioners as Just Compensation Notably, in San Miguel Corporation v. National Labor Relations
Commission,37 Galman v. Sandiganbayan,38Philippine Consumers
As borne by the records, the 12% interest claimed is only on the Foundation v. National Telecommunications Commission,39 and Republic
difference between the price of the expropriated lands (determined with v. de los Angeles,40 we reversed our judgment on the second motion for
finality to be ₱1,383,179,000.00) and the amount of ₱411,769,168.32 reconsideration, while in Vir-Jen Shipping and Marine Services v.
already paid to the petitioners. The difference between these figures National Labor Relations Commission,41 we did so on a third motion for
amounts to the remaining balance of ₱971,409,831.68 that was only paid reconsideration. In Cathay Pacific v. Romillo42 and Cosio v. de
on May 9, 2008. Rama,43 we modified or amended our ruling on the second motion for
reconsideration. More recently, in the cases of Munoz v. Court of
As above discussed, this amount should bear interest at the rate of 12% Appeals,44 Tan Tiac Chiong v. Hon. Cosico,45Manotok IV v. Barque,46 and
per annum from the time the petitioners’ properties were taken on Barnes v. Padilla,47 we recalled entries of judgment after finding that
December 9, 1996 up to the time of payment. At this rate, the LBP now doing so was in the interest of substantial justice. In Barnes, we said:
owes the petitioners the total amount of One Billion Three Hundred
Thirty-One Million One Hundred Twenty-Four Thousand Two Hundred x x x Phrased elsewise, a final and executory judgment can no longer be
Twenty-Three and 05/100 Pesos (₱1,331,124,223.05), computed as attacked by any of the parties or be modified, directly or indirectly, even
follows: by the highest court of the land.

Just Compensation ₱971,409,831.68 However, this Court has relaxed this rule in order to serve substantial
justice considering (a) matters of life, liberty, honor or property, (b) the
Legal Interest from 12/09/1996 existence of special or compelling circumstances, (c) the merits of the
case, (d) a cause not entirely attributable to the fault or negligence of the
party favored by the suspension of the rules, (e) a lack of any showing
To 05/09/2008 @ 12%/annum
that the review sought is merely frivolous and dilatory, and (f) the other
party will not be unjustly prejudiced thereby.
12/09/1996 to 12/31/1996 23 days 7,345,455.17
Invariably, rules of procedure should be viewed as mere tools designed
01/01/1997 to 12/31/2007 11 years 1,282,260,977.82 to facilitate the attainment of justice. Their strict and rigid application,
which would result in technicalities that tend to frustrate rather than
01/01/2008 to 05/09/2008 130 days 41,517,790.07 promote substantial justice, must always be eschewed. Even the Rules of
Court reflects this principle. The power to suspend or even disregard
₱1,331,124,223.0535 rules can be so pervasive and compelling as to alter even that which this
Court itself had already declared to be final.48 [Emphasis supplied.]
The Immutability of Judgment Issue
That the issues posed by this case are of transcendental importance is
As a rule, a final judgment may no longer be altered, amended or not hard to discern from these discussions. A constitutional limitation,
modified, even if the alteration, amendment or modification is meant to guaranteed under no less than the all-important Bill of Rights, is at stake
correct what is perceived to be an erroneous conclusion of fact or law in this case: how can compensation in an eminent domain be "just" when
and regardless of what court, be it the highest Court of the land, rendered the payment for the compensation for property already taken has been
it.36 In the past, however, we have recognized exceptions to this rule by unreasonably delayed? To claim, as the assailed Resolution does, that
only private interest is involved in this case is to forget that an The emerging trend in the rulings of this Court is to afford every party
expropriation involves the government as a necessary actor. It forgets, litigant the amplest opportunity for the proper and just determination of
too, that under eminent domain, the constitutional limits or standards his cause, free from the constraints of technicalities. Time and again, this
apply to government who carries the burden of showing that these Court has consistently held that rules must not be applied rigidly so as
standards have been met. Thus, to simply dismiss this case as a private not to override substantial justice.52 [Emphasis supplied.]
interest matter is an extremely shortsighted view that this Court should
not leave uncorrected. Similarly, in de Guzman v. Sandiganbayan,53 we had occasion to state:

As duly noted in the above discussions, this issue is not one of first The Rules of Court was conceived and promulgated to set forth
impression in our jurisdiction; the consequences of delay in the payment guidelines in the dispensation of justice but not to bind and chain the
of just compensation have been settled by this Court in past rulings. Our hand that dispenses it, for otherwise, courts will be mere slaves to or
settled jurisprudence on the issue alone accords this case primary robots of technical rules, shorn of judicial discretion. That is precisely why
importance as a contrary ruling would unsettle, on the flimsiest of courts in rendering justice have always been, as they ought to be,
grounds, all the rulings we have established in the past. conscientiously guided by the norm that when on the balance,
technicalities take a backseat against substantive rights, and not the
More than the stability of our jurisprudence, the matter before us is of other way around. Truly then, technicalities, in the appropriate language
transcendental importance to the nation because of the subject matter of Justice Makalintal, "should give way to the realities of the
involved – agrarian reform, a societal objective that the government has situation.54 [Emphasis supplied.]
unceasingly sought to achieve in the past half century. This reform
program and its objectives would suffer a major setback if the We made the same recognition in Barnes,55 on the underlying premise
government falters or is seen to be faltering, wittingly or unwittingly, that a court’s primordial and most important duty is to render justice; in
through lack of good faith in implementing the needed reforms. Truly, discharging the duty to render substantial justice, it is permitted to re-
agrarian reform is so important to the national agenda that the Solicitor examine even a final and executory judgment.
General, no less, pointedly linked agricultural lands, its ownership and
abuse, to the idea of revolution.49 This linkage, to our mind, remains valid Based on all these considerations, particularly the patently illegal and
even if the landowner, not the landless farmer, is at the receiving end of erroneous conclusion that the petitioners are not entitled to 12% interest,
the distortion of the agrarian reform program. we find that we are duty-bound to re-examine and overturn the assailed
Resolution. We shall completely and inexcusably be remiss in our duty as
As we have ruled often enough, rules of procedure should not be applied defenders of justice if, given the chance to make the rectification, we shall
in a very rigid, technical sense; rules of procedure are used only to help let the opportunity pass.
secure, not override, substantial justice.50 As we explained in Ginete v.
Court of Appeals:51 Attorney’s Fees

Let it be emphasized that the rules of procedure should be viewed as We are fully aware that the RTC has awarded the petitioners attorney’s
mere tools designed to facilitate the attainment of justice. Their strict and fees when it fixed the just compensation due and decreed that interest of
rigid application, which would result in technicalities that tend to frustrate 12% should be paid on the balance outstanding after the taking of the
rather than promote substantial justice, must always be eschewed. Even petitioners’ landholdings took place. The petitioners, however, have not
the Rules of Court reflect this principle. The power to suspend or even raised the award of attorney’s fees as an issue in the present motion for
disregard rules can be so pervasive and compelling as to alter even that reconsideration. For this reason, we shall not touch on this issue at all in
which this Court itself has already declared to be final, as we are now this Resolution.
constrained to do in the instant case.
WHEREFORE, premises considered, we GRANT the petitioners’ motion
xxxx for reconsideration. The Court En Banc’s Resolution dated December 4,
2009, as well as the Third Division’s Resolutions dated April 30, 2008 and
December 19, 2007, are hereby REVERSED and SET ASIDE.

The respondent Land Bank of the Philippines is hereby ORDERED to pay


petitioners Apo Fruits Corporation and Hijo Plantation, Inc. interest at the
rate of 12% per annum on the unpaid balance of the just compensation,
computed from the date the Government took the properties on
December 9, 1996, until the respondent Land Bank of the Philippines
paid on May 9, 2008 the balance on the principal amount.

Unless the parties agree to a shorter payment period, payment shall be in


monthly installments at the rate of ₱60,000,000.00 per month until the
whole amount owing, including interest on the outstanding balance, is
fully paid.

Costs against the respondent Land Bank of the Philippines.

SO ORDERED.
Republic of the Philippines On May 26, 1995, NAPOCOR filed a complaint for expropriation in the
SUPREME COURT Regional Trial Court in Batangas City (RTC),4seeking the acquisition of an
Manila easement of right of way over a portion of the property involving an area
of only 6,326 square meters, more or less,5 alleging that it had negotiated
FIRST DIVISION with the respondents for the acquisition of the easement but they had
failed to reach any agreement; and that, nonetheless, it was willing to
G.R. No. 165354 January 12, 2015 deposit the amount of ₱9,790.00 representing the assessed value of the
portion sought to be expropriated.6 It prayed for the issuance of a writ of
possession upon deposit to enable it to enter and take possession and
REPUBLIC OF THE PHILIPPINES, represented by the NATIONAL
control of the affected portion of the property; to demolish all
POWER CORPORATION, Petitioner,
improvements existing thereon; and to commence construction of the
vs.
transmission line project. It likewise prayed for the appointment of three
HEIRS OF SATURNINO Q. BORBON, AND COURT OF
commissioners to determine the just compensation to be paid.7
APPEALS, Respondents.
In their answer with motion to dismiss,8 the respondents staunchly
DECISION
maintained that NAPOCOR had not negotiated with them before entering
the property and that the entry was done without their consent in the
BERSAMIN, J.: process, destroying some fruit trees without payment, and installing five
transmission line posts and five woodpoles for its project;9 that the area
The expropriator who has taken possession of the property subject of being expropriated only covered the portion directly affected by the
expropriation is obliged to pay reasonable compensation to the transmission lines; that the remaining portion of the property was also
landowner for the period of such possession although the proceedings affected because the transmission line passed through the center of the
had been discontinued on the ground that the public purpose for the land, thereby dividing the land into three lots; that the presence of the
expropriation had meanwhile ceased. high tension transmission line had rendered the entire property inutile for
any future use and capabilities;10 that, nonetheless, they tendered no
Antecedents objection to NAPOCOR’s entry provided it would pay just compensation
not only for the portion sought to be expropriated but for the entire
The National Power Corporation (NAPOCOR) is a government-owned property whose potential was greatly diminished, if not totally lost, due to
and -controlled corporation vested with authority under Republic Act No. the project;11 and that their property was classified as industrial land.
6395, as amended, to undertake the development of hydro-electric Thus, they sought the dismissal of the complaint, the payment of just
generation of power, production of electricity from any and all sources, compensation of ₱1,000.00/square meter, and attorney’s fees;12 and to be
construction, operation and maintenance of power plants, auxiliary plants, allowed to nominate their representative to the panel of commissioners to
dams, reservoirs, pipes, main transmission lines, power stations and be appointed by the trial court.13
substations, and other works for the purpose of developing hydraulic
power from any river, lake, creek, spring and waterfalls in the Philippines In the pre-trial conference conducted on December 20, 1995, the parties
and to supply such power to the inhabitants thereof.1 stipulated on: (1) the location of the property; (2) the number of the heirs
of the late Saturnino Q. Borbon; (3) the names of the persons upon whom
In February 1993, NAPOCOR entered a property located in Barangay title to the property was issued; and (4) the ownership and possession of
San Isidro, Batangas City in order to construct and maintain transmission the property.14 In its order of that date, the RTC directed the parties to
lines for the 230 KV Mahabang Parang-Pinamucan Power Transmission submit the names of their nominees to sit in the panel of commissioners
Project.2 Respondents heirs of Saturnino Q. Borbon owned the property, within 10 days from the date of the pre-trial.15
with a total area of 14,257 square meters, which was registered under
Transfer Certificate of Title No. T-9696 of the Registry of Deeds of The RTC constituted the panel of three commissioners. Two
Batangas.3 commissioners submitted a joint report on April 8, 1999,16 in which they
found that the property was classified as industrial land located within the Accordingly, the RTC ordered NAPOCOR to pay the respondents: (1) just
Industrial 2 Zone;17that although the property used to be classified as compensation for the whole area of 14,257 square meters at the rate of
agricultural (i.e., horticultural and pasture land), it was reclassified to ₱550.00/square meter; (2) legal rate of interest from May 5, 1995 until full
industrial land for appraisal or taxation purposes on June 30, 1994; and payment; and (3) the costs of suit.27
that the reclassification was made on the basis of a certification issued by
the Zoning Administrator pursuant to Section 3.10 (d) of the Amended NAPOCOR appealed (CA-G.R. No. 72069).
Zoning Ordinance (1989) of the City of Batangas.18 The two
commissioners appraised the value at ₱550.00/square meter.19However, On April 29, 2004,28 the CA promulgated its decision, viz:
the third commissioner filed a separate report dated March 16,
1999,20 whereby he recommended the payment of "an easement fee of at
WHEREFORE, premises considered, the Decision dated November 27,
least ten percent (10%) of the assessed value indicated in the tax
2000 of Branch I of the Regional Trial Court of Batangas City, is hereby
declaration21plus cost of damages in the course of the construction,
AFFIRMED with the MODIFICATION that plaintiff-appellant shall pay only
improvements affected and tower occupancy fee."22
for the occupied 6,326 square meters of the subject real property at the
rate of ₱550.00 per square meter and to pay legal interest therefrom until
The parties then submitted their respective objections to the reports. On fully paid.
their part, the respondents maintained that NAPOCOR should
compensate them for the entire property at the rate of ₱550.00/square
SO ORDERED.29
meter because the property was already classified as industrial land at
the time NAPOCOR entered it.23 In contrast, NAPOCOR objected to the
joint report, insisting that the property was classified as agricultural land Hence, this appeal by NAPOCOR.
at the time of its taking in March 1993; and clarifying that it was only
seeking an easement of right of way over a portion of the property, not Issue
the entire area thereof, so that it should pay only 10% of the assessed
value of the portion thus occupied.24 On December 3, 2012, during the pendency of the appeal, NAPOCOR
filed a Motion to Defer Proceedings stating that negotiations between the
In the judgment dated November 27, 2000,25 the RTC adopted the parties were going on with a view to the amicable settlement of the
recommendation contained in the joint report, and ruled thusly: case.30

The price to be paid for an expropriated land is its value at the time of On January 3, 2014, NAPOCOR filed a Manifestation and Motion to
taking, which is the date when the plaintiff actually entered the property or Discontinue Expropriation Proceedings,31informing that the parties failed
the date of the filing of the complaint for expropriation. In this case, there to reach an amicable agreement; that the property sought to be
is no evidence as to when the plaintiff actually entered the property in expropriated was no longer necessary for public purpose because of the
question, so the reference point should be the date of filing of the intervening retirement of the transmission lines installed on the
complaint, which is May 5, 1995. respondents’ property;32 that because the public purpose for which such
property would be used thereby ceased to exist, the proceedings for
On this date, the property in question was already classified as industrial. expropriation should no longer continue, and the State was now duty-
So, the Joint Report (Exhibit "1") is credible on this point. The two bound to return the property to its owners; and that the dismissal or
Commissioners who submitted the Joint Report are government officials discontinuance of the expropriation proceedings was in accordance with
who were not shown to be biased. So, that their report should be given Section 4, Rule 67 of the Rules of Court. Hence, NAPOCOR prayed that
more weight than the minority report submitted by a private lawyer the proceedings be discontinued "under such terms as the court deems
representing the plaintiff. In view of these, the Court adopts the Joint just and equitable,"33 and that the compensation to be awarded the
Report and rejects the minority report. The former fixed the just respondents be reduced by the equivalent of the benefit they received
compensation at ₱550.00 per square meter for the whole lot of 14,257 from the land during the time of its occupation, for which purpose the
square meters.26
case could be remanded to the trial court for the determination of Department of Transportation and Communications,41 Justice Corona, in
reasonable compensation to be paid to them.34 his dissenting opinion said that:

In light of its Manifestation and Motion to Discontinue Expropriation To be valid, the taking must be for public use. The meaning of the term
Proceedings, NAPOCOR contends that the expropriation has become "public use" has evolved over time in response to changing public needs
without basis for lack of public purpose as a result of the retirement of the and exigencies. Public use which was traditionally understood as strictly
transmission lines; that if expropriation still proceeds, the Government will limited to actual "use by the public" has already been abandoned. "Public
be unduly burdened by payment of just compensation for property it no use" has now been held to be synonymous with "public interest," "public
longer requires; and that there is legal basis in dismissing the benefit," and "public convenience."
proceedings, citing Metropolitan Water District v. De los Angeles35 where
the Court granted petitioner’s prayer for the quashal of expropriation It is essential that the element of public use of the property be maintained
proceedings and the eventual dismissal of the proceedings on the ground throughout the proceedings for expropriation. The effects of abandoning
that the land sought to be expropriated was no longer "indispensably the public purpose were explained in Mactan-Cebu International Airport
necessary" in the maintenance and operation of petitioner's waterworks Authority v. Lozada, Sr.,42 to wit:
system.
More particularly, with respect to the element of public use, the
The issue to be considered and resolved is whether or not the expropriator should commit to use the property pursuant to the purpose
expropriation proceedings should be discontinued or dismissed pending stated in the petition for expropriation filed, failing which, it should file
appeal. another petition for the new purpose. If not, it is then incumbent upon the
expropriator to return the said property to its private owner, if the latter
Ruling of the Court desires to reacquire the same. Otherwise, the judgment of expropriation
suffers an intrinsic flaw, as it would lack one indispensable element for
The dismissal of the proceedings for expropriation at the instance of the proper exercise of the power of eminent domain, namely, the
NAPOCOR is proper, but, conformably with Section 4,36 Rule 67 of the particular public purpose for which the property will be devoted.
Rules of Court, the dismissal or discontinuance of the proceedings must Accordingly, the private property owner would be denied due process of
be upon such terms as the court deems just and equitable. law, and the judgment would violate the property owner's right to justice,
fairness and equity.43
Before anything more, we remind the parties about the nature of the
power of eminent domain. The right of eminent domain is "the ultimate A review reveals that Metropolitan Water District v. De los Angeles44 is an
right of the sovereign power to appropriate, not only the public but the appropriate precedent herein. There, the Metropolitan Water District
private property of all citizens within the territorial sovereignty, to public passed a board resolution requesting the Attorney-General to file a
purpose."37 But the exercise of such right is not unlimited, for two petition in the Court of First Instance of the Province of Rizal praying that
mandatory requirements should underlie the Government’s exercise of it be permitted to discontinue the condemnation proceedings it had
the power of eminent domain, namely: (1) that it is for a particular public initiated for the expropriation of a parcel of land in Montalban, Rizal to be
purpose; and (2) that just compensation be paid to the property used in the construction of the Angat Waterworks System. It claimed that
owner.38 These requirements partake the nature of implied conditions that the land was no longer indispensably necessary in the maintenance and
should be complied with to enable the condemnor to keep the property operation of its waterworks system, and that the expropriation complaint
expropriated.39 should then be dismissed. The Court, expounding on the power of the
State to exercise the right of eminent domain, then pronounced:
Public use, in common acceptation, means "use by the public." However,
the concept has expanded to include utility, advantage or productivity for There is no question raised concerning the right of the plaintiff here to
the benefit of the public.40 In Asia's Emerging Dragon Corporation v. acquire the land under the power of eminent domain. That power was
1âwphi1

expressly granted it by its charter. The power of eminent domain is a right


reserved to the people or Government to take property for public use. It is It is notable that the dismissal of the expropriation proceedings in
the right of the state, through its regular organization, to reassert either Metropolitan Water District v. De los Angeles was made subject to
temporarily or permanently its dominion over any portion of the soil of the several conditions in order to address the dispossession of the
state on account of public necessity and for the public good. The right of defendants of their land, and the inconvenience, annoyance and
eminent domain is the right which the Government or the people retains damages suffered by the defendants on account of the proceedings.
over the estates of individuals to resume them for public use. It is the Accordingly, the Court remanded the case to the trial court for the
right of the people, or the sovereign, to dispose, in case of public issuance of a writ of possession ordering Metropolitan Water District to
necessity and for the public safety, of all the wealth contained in the immediately return possession of the land to the defendants, and for the
state.45 determination of damages in favor of the defendants, the claims for which
must be presented within 30 days from the return of the record to the
Indeed, public use is the fundamental basis for the action for court of origin and notice thereof.47
expropriation; hence, NAPOCOR’s motion to discontinue the proceedings
is warranted and should be granted. The Court has observed in Here, NAPOCOR seeks to discontinue the expropriation proceedings on
Metropolitan Water District v. De los Angeles: the ground that the transmission lines constructed on the respondents’
property had already been retired. Considering that the Court has
It is not denied that the purpose of the plaintiff was to acquire the land in consistently upheld the primordial importance of public use in
question for public use. The fundamental basis then of all actions brought expropriation proceedings, NAPOCOR’s reliance on Metropolitan Water
for the expropriation of lands, under the power of eminent domain, is District v. De los Angeles was apt and correct. Verily, the retirement of
public use. That being true, the very moment that it appears at any stage the transmission lines necessarily stripped the expropriation proceedings
of the proceedings that the expropriation is not for a public use, the action of the element of public use. To continue with the expropriation
must necessarily fail and should be dismissed, for the reason that the proceedings despite the definite cessation of the public purpose of the
action cannot be maintained at all except when the expropriation is for project would result in the rendition of an invalid judgment in favor of the
some public use. That must be true even during the pendency of the expropriator due to the absence of the essential element of public use.
appeal or at any other stage of the proceedings. If, for example, during
the trial in the lower court, it should be made to appear to the satisfaction Unlike in Metropolitan Water District v. De los Angeles where the request
of the court that the expropriation is not for some public use, it would be to discontinue the expropriation proceedings was made upon the
the duty and the obligation of the trial court to dismiss the action. And authority appearing in the board resolution issued on July 14,
even during the pendency of the appeal, if it should be made to appear to 1930,48 counsel for NAPOCOR has not presented herein any document to
the satisfaction of the appellate court that the expropriation is not for show that NAPOCOR had decided, as a corporate body, to discontinue
public use, then it would become the duty and the obligation of the the expropriation proceedings. Nonetheless, the Court points to the
appellate court to dismiss it. Memorandum dated December 13, 201249 and the Certificate of
Inspection/Accomplishment dated February 5, 200550 attached to
In the present case the petitioner admits that the expropriation of the land NAPOCOR’s motion attesting to the retirement of the transmission lines.
in question is no longer necessary for public use. Had that admission Also, Metropolitan Water District v. De los Angeles emphasized that it
been made in the trial court the case should have been dismissed there. became the duty and the obligation of the court, regardless of the stage
It now appearing positively, by resolution of the plaintiff, that the of the proceedings, to dismiss the action "if it should be made to appear
expropriation is not necessary for public use, the action should be to the satisfaction of the court that the expropriation is not for some public
dismissed even without a motion on the part of the plaintiff. The moment use."51 Despite the lack of the board resolution, therefore, the Court now
it appears in whatever stage of the proceedings that the expropriation is considers the documents attached to NAPOCOR’s Manifestation and
not for a public use the complaint should be dismissed and all the parties Motion to Discontinue Expropriation Proceedings to be sufficient to
thereto should be relieved from further annoyance or establish that the expropriation sought is no longer for some public
litigation.46 (underscoring and emphasis supplied) purpose.
Accordingly, the Court grants the motion to discontinue the proceedings taken by the expropriator more than 40 years prior to suit. In these
subject to the conditions to be shortly mentioned hereunder, and requires instances, this Court has ruled that the just compensation shall be
the return of the property to the respondents. Having said that, we must determined as of the time of taking, not as of the time of filing of the
point out that NAPOCOR entered the property without the owners’ action of eminent domain.
consent and without paying just compensation to the respondents.
Neither did it deposit any amount as required by law prior to its entry. The In the context of the State's inherent power of eminent domain, there is a
Constitution is explicit in obliging the Government and its entities to pay "taking" when the owner is actually deprived or dispossessed of his
just compensation before depriving any person of his or her property for property; when there is a practical destruction or a material impairment of
public use.52 Considering that in the process of installing transmission the value of his property or when he is deprived of the ordinary use
lines, NAPOCOR destroyed some fruit trees and plants without payment, thereof. There is a "taking" in this sense when the expropriator enters
and the installation of the transmission lines went through the middle of private property not only for a momentary period but for a more
the land as to divide the property into three lots, thereby effectively permanent duration, for the purpose of devoting the property to a public
rendering the entire property inutile for any future use, it would be unfair use in such a manner as to oust the owner and deprive him of all
for NAPOCOR not to be made liable to the respondents for the beneficial enjoyment thereof. For ownership, after all, "is nothing without
disturbance of their property rights from the time of entry until the time of the inherent rights of possession, control and enjoyment. Where the
restoration of the possession of the property. There should be no owner is deprived of the ordinary and beneficial use of his property or of
question about the taking. In several rulings, notably National Power its value by its being diverted to public use, there is taking within the
Corporation v. Zabala,53 Republic v. Libunao,54 National Power Constitutional sense." x x x.58
Corporation v. Tuazon,55 and National Power Corporation v.
Saludares,56 this Court has already declared that "since the high-tension In view of the discontinuance of the proceedings and the eventual return
electric current passing through the transmission lines will perpetually of the property to the respondents, there is no need to pay "just
deprive the property owners of the normal use of their land, it is only just compensation" to them because their property would not be taken by
and proper to require Napocor to recompense them for the full market NAPOCOR. Instead of full market value of the property, therefore,
value of their property." NAPOCOR should compensate the respondents for the disturbance of
their property rights from the time of entry in March 1993 until the time of
There is a sufficient showing that NAPOCOR entered into and took restoration of the possession by paying to them actual or other
possession of the respondents’ property as early as in March 1993 compensatory damages. This conforms with the following
without the benefit of first filing a petition for eminent domain. For all pronouncement in Mactan-Cebu International Airport Authority v. Lozada,
intents and purposes, therefore, March 1993 is the reckoning point of Sr.:59
NAPOCOR’s taking of the property, instead of May 5, 1995, the time
NAPOCOR filed the petition for expropriation. The reckoning conforms to In light of these premises, we now expressly hold that the taking of
the pronouncement in Ansaldo v. Tantuico, Jr.,57 to wit: private property, consequent to the Government’s exercise of its power of
eminent domain, is always subject to the condition that the property be
Normally, of course, where the institution of an expropriation action devoted to the specific public purpose for which it was taken. Corollarily,
precedes the taking of the property subject thereof, the just compensation if this particular purpose or intent is not initiated or not at all pursued, and
is fixed as of the time of the filing of the complaint. This is so provided by is peremptorily abandoned, then the former owners, if they so desire,
the Rules of Court, the assumption of possession by the expropriator may seek the reversion of the property, subject to the return of the
ordinarily being conditioned on its deposits with the National or Provincial amount of just compensation received. In such a case, the exercise of the
Treasurer of the value of the property as provisionally ascertained by the power of eminent domain has become improper for lack of the required
court having jurisdiction of the proceedings. factual justification.60

There are instances, however, where the expropriating agency takes over This should mean that the compensation must be based on what they
the property prior to the expropriation suit, as in this case although, to actually lost as a result and by reason of their dispossession of the
repeat, the case at bar is quite extraordinary in that possession was property and of its use, including the value of the fruit trees, plants and
crops destroyed by NAPOCOR’s construction of the transmission lines.
Considering that the dismissal of the expropriation proceedings is a
development occurring during the appeal, the Court now treats the
dismissal of the expropriation proceedings as producing the effect of
converting the case into an action for damages. For that purpose, the
Court remands the case to the court of origin for further proceedings, with
instruction to the court of origin to enable the parties to fully litigate the
action for damages by giving them the opportunity to re-define the factual
and legal issues by the submission of the proper pleadings on the extent
of the taking, the value of the compensation to be paid to the respondents
by NAPOCOR, and other relevant matters as they deem fit. Trial shall be
limited to matters the evidence upon which had not been heretofore
heard or adduced. The assessment and payment of the correct amount
of filing fees due from the respondents shall be made in the judgment,
and such amount shall constitute a first lien on the recovery. Subject to
these conditions, the court of origin shall treat the case as if originally
filed as an action for damages.

WHEREFORE, the Court DISMISSES the expropriation proceedings due


to the intervening cessation of the need for public use; REMANDS the
records to the Regional Trial Court, Branch 1, in Batangas City as the
court of origin for further proceedings to be conducted in accordance with
the foregoing instructions; and ORDERS said trial court to try and decide
the issues with dispatch.

SO ORDERED.
SECOND DIVISION On 25 February 2010, respondents filed a Verified Answer,6 claiming that
the then current market value of the property was ₱10,000 per square
August 17, 2016 meter on the inner portion and ₱12,000 per square meter near the
highway. Respondents prayed, among others, for a just compensation in
G.R. No. 210218 the amount of ₱1,250,700, representing the Bureau of Internal Revenue
(BIR) zonal valuation for the "actual area to be occupied" by NAPOCOR
which is 2,274 square meters, instead of 822 square meters only. In
NATIONAL POWER CORPORATION, Petitioner
addition, respondents sought payment for NAPOCOR’s alleged
vs.
unauthorized entry and use of the property from 1940 to date.
HEIRS OF ANTONINA RABIE, represented by ABRAHAM R. DELA
CRUZ, Respondents
On 5 July 2010, NAPOCOR deposited with the Land Bank of the
Philippines (Land Bank) the amount of ₱411,000 representing the BIR
DECISION
zonal valuation of the affected portion of the subject property, which was
₱500 per square meter.
CARPIO, J.:
Respondents filed a Motion to Withdraw Deposit dated 15 November
The Case 2010,7 which the trial court granted in an Order dated 17 November
2010.8
This petition for review on certiorari1 assails the 28 November 2013
Decision2 of the Court of Appeals in CA-G.R. SP No. 131335, dismissing NAPOCOR filed a Motion to Issue Order of Expropriation dated 18 March
the petition for certiorari filed by petitioner National Power Corporation 2011.9 NAPOCOR also filed a Motion for Annotation/Registration of
(NAPOCOR). Partial Payment dated 7 June 2011.10

The Facts In an Order dated 5 October 2011,11 the trial court granted the motions
and constituted the Board of Commissioners to assist the trial court in the
NAPOCOR is a government-owned and controlled corporation created determination of just compensation for the affected portion of the subject
pursuant to Republic Act No. 6395,3 as amended. Under the property.
EPIRA, 4 NAPOCOR was tasked to perform the missionary electrification
function and to provide power generation and its associated power On 8 February 2012, the Board of Commissioners submitted its Report.
delivery systems in areas that are not connected to the transmission On 17 May 2012, NAPOCOR filed its Comment/Opposition to the
system. Commissioners’ Report objecting to the recommendation that the
affected portion of the subject property consists of 2,274 square meters
On 1 December 2009, NAPOCOR filed a complaint for and that the value per square meter is ₱11,000. NAPOCOR also
expropriation5 against respondents Heirs of Antonina Rabie (respondents) questioned the Commissioners’ recommendation on the payment of
for the acquisition of the 822-square meter portion of Lot No. 1439, a rentals and the fact that NAPOCOR was not given the opportunity to be
residential lot located in Barangay Lewin, Lumban, Laguna consisting of heard and to argue as to the amount of just compensation.
12,657 square meters and covered by Original Certificate of Title No. P-
9196, to be used as access road for the Caliraya Hydro Electric Power On 29 January 2013, the trial court issued an Order, the dispositive
Plant of the Caliraya Botocan-Kalayaan Build Rehabilitate and Operate portion of which reads:
Transfer Project of the NAPOCOR. The case was raffled to Regional Trial
Court, Branch 91, Sta. Cruz, Laguna (trial court) and docketed as Civil
WHEREFORE, the Eight Hundred Twenty Two (822) square meters of
Case No. SC-4842.
the land owned by the defendants is hereby expropriated in favor of the
National Power Corporation effective December 2009 upon payment of
the fair market value of the property at Eleven Thousand (₱11,000.00) ₱12,000 yearly rentals plus 12% interest from 1940 up to the present until
Pesos per square meter or a total of Nine Million Forty-Two Thousand fully paid within ten days from receipt thereof.
(₱9,042,000.00) Pesos. Defendants’ claim that said property was
occupied by plaintiff since 1940 is unrebutted, hence, reasonable rentals On 30 July 2013, NAPOCOR received a letter from the LBPNAPOCOR
of Twelve Thousand Pesos (₱12,000.00) yearly is hereby awarded to Extension Office informing NAPOCOR of its receipt of a Notice of
defendants from the year 1940 to the present at a twelve percent (12%) Garnishment in the amount of ₱14,873,999.28 issued by Sheriff Claveria.
annual interest rate, until fully paid.
Aggrieved, NAPOCOR filed with the Court of Appeals a petition
SO ORDERED.12 for certiorari under Rule 65, with prayer for the issuance of a temporary
restraining order and/or writ of preliminary injunction.
On 8 March 2013, NAPOCOR filed a Motion for Reconsideration of the
Order. However, the trial court denied the motion in an Order dated 30 On 28 November 2013, the Court of Appeals rendered a Decision
April 201313 which was received by NAPOCOR on 23 May 2013 and by dismissing the petition.
respondents on 15 May 2013.
Hence, this petition filed on 23 January 2014.
On 22 May 2013, respondents filed a Motion for Execution Pending
Appeal.14 NAPOCOR filed its Comment/Opposition thereto on 4 June On 22 October 2014, respondents filed an Omnibus Motion (to Dismiss
2013. and to Cite Petitioner in Contempt), contending that NAPOCOR is guilty
of forum-shopping considering that there is another petition21 filed by
On 6 June 2013, NAPOCOR filed its Notice of Appeal and Record on NAPOCOR before this Court (docketed as G.R. No. 214070).
Appeal.15 Respondents alleged that G.R. No. 214070 involves the same parties
and the same facts and seeks the same relief of preventing the
In an Order dated 18 June 2013,16 the trial court gave due course to implementation of the trial court’s Order dated 11 July 2013 granting
NAPOCOR’s Notice of Appeal and directed the transmittal of the records execution pending appeal and the Order dated 29 January 2013 ordering
of the case to the Court of Appeals. NAPOCOR to pay just compensation to respondents.

The trial court set for hearing respondents’ Motion for Execution Pending In its 19 November 2014 Resolution, the Court noted the motion.
Appeal on 10 July 2013.
In its 29 September 2014 Resolution, the Court dismissed the petition in
On 11 July 2013, the trial court issued an Order granting respondents’ G.R. No. 214070 for NAPOCOR’s failure to sufficiently show that the
Motion for Execution Pending Appeal.17 The trial court held: assailed resolutions of the Court of Appeals, dated 15 April 2014 and 8
August 2014, are tainted with grave abuse of discretion. The 15 April
In determining the propriety of execution of its Order dated January 29, 2014 Resolution of the Court of Appeals assailed in G.R. No. 214070
2013, pending appeal, showing good reasons as stated in the motion and ordered NAPOCOR to submit an affidavit containing a list of its assets
while the Court has its jurisdiction over the case and still in possession of and ordered Land Bank to submit a bank certification containing a list of
original record thereof or the record on appeal, the Court NAPOCOR’s bank deposits with Land Bank.

grants the "Motion for Execution Pending Appeal."18 The Court of Appeals’ Ruling

On 12 July 2013, the trial court’s Officer-in-Charge issued a Writ of The Court of Appeals held that the trial court still had jurisdiction when
Execution.19 Sheriff Raymundo P. Claveria issued a Notice20 addressed to respondents filed their motion for execution pending appeal on 22 May
the President of NAPOCOR demanding payment of ₱9,042,000 and 2013, or seven days after their receipt of the trial court’s order denying
their Motion for Partial Reconsideration. Hence, respondents’ motion for Execution pending appeal, also called discretionary execution under
execution pending appeal was timely filed. Section 2(a), Rule 39 of the Rules of Court, is allowed upon good
reasons to be stated in a special order after due hearing. Section 2(a),
The Court of Appeals ruled that there exists good reasons for the trial Rule 39 provides:
court’s order granting execution pending appeal. The Court of Appeals
agreed with respondents’ invocation of Borja v. Court of Appeals, 22 where SEC. 2. Discretionary execution. –
petitioner’s advanced age, together with the posting of a supersedeas
bond, justified the execution pending appeal. (a) Execution of a judgment or a final order pending appeal. – On motion
of the prevailing party with notice to the adverse party filed in the trial
The Court of Appeals rejected NAPOCOR’s argument that the alleged court while it has jurisdiction over the case and is in possession of either
physical and financial conditions of respondents do not outweigh the the original record or the record on appeal, as the case may be, at the
damages that it would suffer in the event that the Order subject of the writ time of the filing of such motion, said court may, in its discretion, order
of execution is later reversed, and that such conditions increase the risk execution of a judgment or final order even before the expiration of the
that respondents would not be able to reimburse the amounts fixed in the period to appeal.
Order. The CA held that "where the executed judgment is reversed, x x x
the trial court may, on motion, issue such orders of restitution or After the trial court has lost jurisdiction, the motion for execution pending
reparation of damages x x x."23 appeal may be filed in the appellate court.

The Court of Appeals also held that NAPOCOR’s funds may be Discretionary execution may only issue upon good reasons to be stated
garnished as "it would be absurd to rule that petitioner’s funds may not be in a special order after due hearing.
garnished x x x considering that the winning party would not enjoy the
fruits of his victory, x x x."24 The Court of Appeals cited Cosculluela v. In this case, the motion for execution pending appeal was filed by
Court of Appeals,25 where the Court held that "[i]t is arbitrary and respondents seven days after their receipt of the trial court’s order
capricious for a government agency to initiate expropriation proceedings denying the motions for reconsideration filed by both parties. Clearly,
x x x and then refuse to pay on the ground that there are no respondents filed the motion for execution pending appeal before the
appropriations for the property earlier taken x x x x."26 lapse of the period to file an appeal, which is fifteen days from notice of
the order denying the motion for reconsideration.27 Therefore, the trial
The Issues court still had jurisdiction when respondents filed their motion for
execution pending appeal.
The issues in this case are: (1) whether the trial court still had jurisdiction
when it ruled on the Motion for Execution Pending Appeal; (2) whether Further, prior to transmittal of the records of the case, the trial court does
there exists good reasons for the execution of the trial court’s decision not lose jurisdiction over the case and in fact, may issue an order for
pending appeal; and (3) whether the NAPOCOR’s funds may be execution pending appeal. Section 9, Rule 41 of the Rules of Court
garnished or be the subject of execution. provides:

The Court’s Ruling SEC. 9. Perfection of appeal; effect thereof. A party’s appeal by notice of
appeal is deemed perfected as to him upon the filing of the notice of
We grant the petition. appeal in due time.

Trial court had jurisdiction to resolve A party’s appeal by record on appeal is deemed perfected as to him with
respect to the subject matter thereof upon the approval of the record on
motion for discretionary execution appeal filed in due time.
In appeals by notice of appeal, the court loses jurisdiction over the case The Court rules that discretionary execution of judgments pending appeal
upon the perfection of the appeals filed in due time and the expiration of under Sec. 2(a) of Rule 39 does not apply to eminent domain
the time to appeal of the other parties. proceedings. 1awp++i1

In appeals by record on appeal, the court loses jurisdiction only over the As early as 1919 in Visayan Refining Co. v. Camus and Paredes, the
subject matter thereof upon the approval of the records on appeal filed in Court held:
due time and the expiration of the time to appeal of the other parties.
When the Government is plaintiff the judgment will naturally take the form
In either case, prior to the transmittal of the original record or the of an order merely requiring the payment of the award as a condition
record on appeal, the court may issue orders for the protection and precedent to the transfer of the title, as a personal judgment against the
preservation of the rights of the parties which do not involve any Government could not be realized upon execution.
matter litigated by the appeal, approve compromises, permit
appeals of indigent litigants, order execution pending appeal in In Commissioner of Public Highways v. San Diego, no less than the
accordance with Section 2 of Rule 39, and allow withdrawal of the eminent Chief Justice Claudio Teehankee explained the rationale behind
appeal. (Emphasis supplied) the doctrine that government funds and properties cannot be seized
under a writ of execution, thus:
In this case, the trial court issued its Order granting the motion for
execution pending appeal on 11 July 2013. That Order expressly stated The universal rule that where the State gives its consent to be sued by
that the trial court was still in possession of the original record of the case private parties either by general or special law, it may limit claimants
at the time. In fact, the records were transmitted to the Court of Appeals action only up to the completion of proceedings anterior to the stage of
on 19 July 2013.28 In other words, the trial court issued the Order granting execution and that the power of the Courts ends when the judgment is
the motion for execution pending appeal before the transmittal of the rendered, since government funds and properties may not be seized
records to the Court of Appeals. Hence, contrary to NAPOCOR’s under writs of execution or garnishment to satisfy such judgments, is
contention, the Court of Appeals correctly ruled that the trial court still had based on obvious considerations of public policy. Disbursements of
jurisdiction when the motion for execution pending appeal was filed and public funds must be covered by the corresponding appropriation as
when the trial court resolved such motion. required by law. The functions and public services rendered by the State
cannot be allowed to be paralyzed or disrupted by the diversion of public
Discretionary execution does not apply funds from their legitimate and specific objects, as appropriated by law.

to eminent domain proceedings PPA’s monies, facilities and assets are government properties. Ergo, they
are exempt from execution whether by virtue of a final judgment or
While the trial court still had jurisdiction when it issued the order granting pending appeal.
execution pending appeal, the Court holds that discretionary execution
does not apply to eminent domain proceedings. In Spouses Curata v. PPA is a government instrumentality charged with carrying out
Philippine Ports Authority, 29 where movants alleged advanced age as
ground for their motion for discretionary execution, the Court found the governmental functions through the management, supervision, control
trial court to have committed grave abuse of discretion in issuing the and
order granting execution pending appeal. The Court held that
discretionary execution is not applicable to expropriation proceedings, regulation of major ports of the country. It is an attached agency of the
thus:
Department of Transportation and Communication pursuant to PD 505.

xxxx
Therefore, an undeniable conclusion is that the funds of PPA partake of of the period to appeal. Good reasons consist of compelling
government funds, and such may not be garnished absent an allocation circumstances justifying immediate execution lest judgment becomes
by its Board or by statutory grant. If the PPA funds cannot be illusory, or the prevailing party after the lapse of time be unable to enjoy
garnished and its properties, being government properties, cannot it, considering the tactics of the adverse party who may have apparently
be levied via a writ of execution pursuant to a final judgment, then no cause but to delay. Such reasons must constitute superior
the trial court likewise cannot grant discretionary execution pending circumstances demanding urgency which will outweigh the injury or
appeal, as it would run afoul of the established jurisprudence that damages should the losing party secure a reversal of the judgment. Were
government properties are exempt from execution. What cannot be it otherwise, execution pending appeal may well become a tool of
done directly cannot be done indirectly. oppression and inequity instead of an instrument of solicitude and justice.

From the above discussion, we find that the RTC committed grave abuse The execution of judgment pending appeal is an exception to the
of discretion in its July 24, 2000 Order directing the execution of the First general rule and must, therefore, be strictly construed. So, too, it is
1âwphi1

Compensation Order (July 10, 2000 Order) pending appeal.30 (Emphasis not to be availed of and applied routinely, but only in extraordinary
supplied) circumstances.

The Court of Appeals’ reliance on the case of Borja v. Court of This rule is strictly construed against the movant, for courts look
Appeals31 is misplaced. Borja involved a complaint for sum of money with disfavor upon any attempt to execute a judgment which has not
totalling ₱78,325 representing unpaid commissions and damages. On the acquired a final character. In the same vein, the Court has held that
other hand, this case involves expropriation proceedings, where the trial such execution is "usually not favored because it affects the rights
court fixed the just compensation for the subject property at ₱9,042,000 of the parties which are yet to be ascertained on appeal."
and yearly rentals at ₱12,000 since 1940 plus 12% interest per annum for
a total award of ₱14,873,999.28. The difference in the nature of the The exercise of the power to grant or deny immediate or advance
actions and the amounts involved in Borja and in this case justifies the execution is addressed to the sound discretion of the trial court. However,
non-application of the rule on discretionary execution. the existence of good reasons is indispensable to the grant of execution
pending appeal. Absent any such good reason, the special order of
Non-existence of good reasons for the execution pending appeal execution must be struck down for having been issued with grave abuse
of discretion. (Emphasis supplied)
The trial court also committed grave abuse of discretion when it failed to
specify and discuss any good reason required for granting execution In this case, the trial court granted the motion for execution pending
pending appeal. appeal based on "good reasons as stated in the motion," without
identifying and discussing any of these alleged good reasons. A mere
In Villamor v. NAPOCOR, 32 the Court discussed the requisites for statement of"good reasons as stated in the motion" does not suffice to
execution pending appeal, thus: justify execution pending appeal. It is basic that the trial court should
make a finding on whether the allegations in the motion for execution
Execution pending appeal requires the observance of the following pending appeal constitute good reasons as required in Section 2 of Rule
requisites: (a) there must be a motion therefor by the prevailing party; (b) 39. The trial court should have expressed clearly and distinctly the facts
there must be a good reason for issuing the writ of execution; and (c) the and law on which the order granting the motion for execution pending
good reason must be stated in a special order. appeal was based, but it did not. Without such finding, the allegations in
the motion for execution pending appeal remain as allegations.
Consequently, the trial court committed grave abuse of discretion in
The prevailing doctrine as provided for in Section 2, paragraph 3 of Rule
granting discretionary execution without stating and explaining clearly the
39 of the Rules of Civil Procedure is that discretionary execution is
basis therefor.
permissible only when good reasons exist for immediately executing the
judgment before finality or pending appeal or even before the expiration
In view of the foregoing, the Court deems it unnecessary to discuss the
issue of garnishment ofNAPOCOR's funds.

WHEREFORE, the petition is GRANTED. The 28 November 2013


Decision of the Court of Appeals in CA-G.R. SP No. 131335 is SET
ASIDE.

SO ORDERED.
FIRST DIVISION summary administrative proceedings for the preliminary determination of
just compensation in 1992 and 1993. Said cases were docketed as
January 11, 2017 DARAB Case Nos. 068-B'92 for TCT No. 12610 and 103-BT'93 for TCT
No. T-8483 with the Department of Agrarian Reform Adjudication Board
G.R. No. 170506 (DARAB) in Region III.

LAND BANK OF THE PHILIPPINES, Petitioner, With the DARAB's affirmation of the acquisition cost fixed by petitioner for
vs. the subject properties, respondents instituted separate petitions for the
HEIRS OF LORENZO TAÑADA AND EXPEDITA EBARLE, determination and payment of just compensation, viz.: Civil Case No.
Respondents. 6328 for the 16.7692 hectares covered by TCT No. T-8483 and Civil
Case No. 6353 for the 13 hectares under TCT No. T-12610, both with the
RTC of Bataan, Branch I. Contending that the price fixed by petitioner
DECISION
was unconscionably low, respondents prayed that their properties be
revalued at ₱150,000.00 per hectare. Since they raised similar issues,
LEONARDO-DE CASTRO, J.: the two (2) cases were eventually consolidated.

Before the Court is a petition for review under Rule 45 of the 1997 Rules To establish their claim for just compensation, respondents presented
of Civil Procedure assailing the Decision 1dated April 8, 2005 as well as Jose Dela Cruz, a vault keeper from the Office of the Bataan Register of
the Resolution2 dated November 22, 2005 of the Court of Appeals in CA- Deeds, who testified that he is the custodian of documents and titles in
G.R. SP No. 79245, entitled "Land Bank of the Philippines v. Heirs of the said office. Said witness identified a Deed of Sale dated 05 April 1997
Lorenzo Tañada and Expedita Ebarle." The assailed April 8, 2005 executed by Horacio Limcangco who sold 6,158 square meters of land in
appellate court ruling was an affirmance of the Decision3 dated July 13, Abucay, Bataan for ₱20,000.00 or for ₱3.24 per square meter. He also
1999 of Branch 1 of the Regional Trial Court of Bataan in Civil Case Nos. identified a Deed of Absolute Sale dated 27 August 1996 executed by
6328 and 6333. On the other hand, the assailed November 22, 2005 Franklin and Benigno Morales whereby 53,102 square meters of land in
Resolution denied for lack of merit the motion for reconsideration filed by Abucay, Bataan was sold for ₱830,000.00 or for ₱15.91 per square
petitioner. meter.

In the aforementioned April 8, 2005 Decision of the Court of Appeals, the On the other hand, neither the Department of Agrarian Reform (DAR) nor
factual antecedents of this case were synthesized as follows: petitioner presented any witness to refute the evidence presented by
respondents. Instead, they offered documentary exhibits to show how, in
Respondents, the Heirs of Lorenzo Tañada and Expedita Ebarle, are the adherence to DAR Administrative Order No. 6, Series of 1992, they
owners of several parcels of land situated in Gabon, Abucay, Bataan, arrived at the valuation of the just compensation for the subject
covered by TCT Nos. T-8483 and T-12610, with respective land areas of parcels. 4 (Citations omitted.)
56.8564 and 16.9268 hectares. The record shows that sometime in 1988,
the aforesaid parcels of land were placed under the land reform program Upon termination of the proceedings, the trial court acting as a Special
of the government. It was determined that 16.7692 hectares from TCT Agrarian Court (SAC) rendered the assailed July 13, 1999 Decision which
No. T-8483 and 13 hectares from TCT No. T-12610 would be included in favored the respondents in this case and pegged the value of the lots in
the program. question at fifteen pesos per square meter or P-150,000.00 per hectare.
The dispositive portion of the trial court's judgment is reproduced here:
Pursuant to its mandate under Executive Order No. 405, petitioner Land
Bank of the Philippines (LBP) valued the properties to be taken at WHEREFORE, judgment is hereby rendered:
₱223,837.29 for 16.7692 hectares and ₱192,610.16 for 13 hectares or a
total of ₱416,447.43. Dissatisfied with this valuation for being
1. Declaring that the petitioners are entitled to just compensation; and
unreasonably and unconscionably low, respondents instituted the
2. That ₱150,000.00 per hectare is just compensation for the land of the Dissatisfied with the adverse judgment, petitioner elevated the case to
petitioners to be paid by the Land Bank of the Philippines for the areas the Court of Appeals. However, the appellate court merely denied
selected by the Department of Agrarian Reform namely: 16.7692 petitioner's appeal and affirmed the appealed decision of the trial court in
hectares under Transfer Certificate of Title No. T-8483 and 13 hectares the now assailed April 8, 2005 Decision, which dispositively states:
under Transfer Certificate of Title No. T-12610 both of the Office of the
Register of Deeds of Bataan. 5 WHEREFORE, the petition is DENIED for lack of merit and the appealed
Decision dated 13 July 1999 is AFFIRMED in toto.8
In arriving at the said ruling, the trial court reasoned, thus:
When the appellate court refused to reconsider the foregoing decision,
The issue to be resolved is whether or not the valuation made by the petitioner sought our review of the case and our ruling on the following
Land Bank of the Philippines and DARAB [is] just compensation for the issue:
said properties to be acquired by the Department of Agrarian Reform.
WHETHER OR NOT THE SPECIAL AGRARIAN COURT CAN
In the case of Association of Small Landowners in the Philippines, Inc. vs. DISREGARD THE VALUATION GUIDELINES OR FORMULA
Secretary of Agrarian Reform, 175 SCRA 343, the Supreme Court held PRESCRIBED UNDER DAR AO NO. 6, SERIES OF 1992, AND AS
that: HELD IN THE CASE OF SPS. BANAL, SUPRA, IN FIXING THE JUST
COMPENSATION OF THE SUBJECT PROPERTIES.9
Just compensation is defined as the full and fair equivalent of the
property taken from its owner by the expropriator. It has been repeatedly
1âw phi 1 Respondents, in turn, opposed the petition on the ground that petitioner's
stressed by this Court that the measure is not the taker's gain but the valuation based on the formula in DAR Administrative Order No. 06,
owner's loss. The word just is used to intensify the meaning of the word series of 1992, may not supplant the valuation of the SAC, which was
"compensation" to convey the idea that the equivalent to be rendered for affirmed by the Court of Appeals. 10 They further argued that the
the property to be taken shall be real, substantial, full, ample. Manila petitioner's valuation of the lots (at an average of a little over one peso
Railroad Co. vs. Velasquez, 32 Phil. 286; Manotok vs. National Housing per square meter) was grossly unjust and unsupported by proof.
Authority, 150 SCRA 89.
Essentially, the sole issue to be resolved by this Court is whether or not
Based on said definition of what is just compensation, this Court believes the trial court utilized the correct method in fixing the just compensation
that the price of ₱150,000.00 per hectare or ₱15.00 per square meter due to respondents' parcels of land which have been subjected to land
which the petitioners are asking is just and reasonable. This is the same reform proceedings under Republic Act No. 6657 or the Comprehensive
price for which the owner of adjoining land was sold in Abucay, Bataan in Agrarian Reform Law of 1988.
1996.
After carefully weighing the issues and arguments presented by the
This Court cannot close its eyes to the prevalent practice of tenants that parties in this case, we find the petition meritorious.
once they are awarded lots under the Comprehensive Agrarian Reform
Program, they immediately look for prospective buyers, selling the In Land Bank of the Philippines v. American Rubber Corporation, 11 we
property from ₱500,000.00 to ₱1,000,000.00 per hectare which they only elaborated on the concept of just compensation in this wise:
acquired at a very low price to the point of being confiscatory to the
prejudice of the real owners.6 This Court has defined "just compensation" for parcels of land taken
pursuant to the agrarian reform program as "the full and fair equivalent
A motion for reconsideration was subsequently filed by petitioner but this of the property taken from its owner by the expropriator." The measure of
was denied by the trial court in its Order dated August 7, 2003. 7 compensation is not the taker's gain but the owner's loss. Just
compensation means the equivalent for the value of the property at the
time of its taking. It means a fair and full equivalent value for the loss
sustained. All the facts as to the condition of the property and its of 1992, which was in effect at the time the lots of respondents were
surroundings, its improvements and capabilities should be considered. x subjected to coverage by the government's land reform program. The
x x. (Citations omitted.) said formula is reproduced as follows:

Since there is no dispute that the subject properties are qualified for II. THE FOLLOWING RULES AND REGULATIONS ARE HEREBY
coverage under the agrarian reform law, the just compensation for the PROMULGATED TO AMEND CERTAIN PROVISIONS OF
said properties must be governed by the valuation factors under Section ADMINISTRATIVE ORDER NO. 17, SERIES OF 1989, AS AMENDED
17 of Republic Act No. 6657 which provides: BY ADMINISTRATIVE ORDER NO. 3, SERIES OF 1991 WHICH
GOVERN THE VALUATION OF LANDS SUBJECT OF ACQUISITION
SEC. 17. Determination of Just Compensation. - In determining just WHETHER UNDER VOLUNTARY OFFER TO SELL (VOS) OR
compensation, the cost of acquisition of the land, the current value of like COMPULSORY ACQUISITION (CA)
properties, its nature, actual use and income, the sworn valuation by the
owner, the tax declarations, and the assessment made by government A. There shall be one basic formula for the valuation of land covered by
assessors shall be considered. The social and economic benefits VOS or CA regardless of the date of offer or coverage of the claim:
contributed by the farmers and the farmworkers and by the Government
to the property as well as the nonpayment of taxes or loans secured from LV = (CNI x 0.6) + (CS x 0.3) + (MV x 0.1)
any government financing institution on the said land shall be considered
as additional factors to determine its valuation. Where: LV = Land Value

Thus, we have held that when handling just compensation cases, the trial CNI =Capitalized Net Income
court acting as a SAC should be guided by the following factors: (1) the
acquisition cost of the land; (2) the current value of the properties; (3) its
CS = Comparable Sales
nature, actual use, and income; (4) the sworn valuation by the owner; (5)
the tax declarations; (6) the assessment made by government assessors;
(7) the social and economic benefits contributed by the farmers and the MV = Market Value per Tax Declaration
farmworkers, and by the government to the property; and (8) the
nonpayment of taxes or loans secured from any government financing The above formula shall be used if all the three factors are present,
institution on the said land, if any. 12 relevant, and applicable.

Pursuant to the rule-making power of the Department of Agrarian Reform Al. When the CS factor is not present and CNI and MV are applicable, the
(DAR) under Section 49 of Republic Act No. 6657, 13 the enumerated formula shall be:
factors were translated into a formula that was outlined in DAR
Administrative Order No. 17, series of 1989, as amended by DAR LV = (CNI x 0.9) + (MV x 0.1)
Administrative Order No. 03, series of 1991, and as further amended by
DAR Administrative Order No. 06, series of 1992, entitled "RULES AND A2. When the CNI factor is not present, and CS and MV are applicable,
REGULATIONS AMENDING THE VALUATION OF LANDS the formula shall be:
VOLUNTARILY OFFERED AND COMPULSORILY ACQUIRED AS
PROVIDED FOR UNDER ADIVHNISTRATIVE ORDER NO. 17, SERIES LV = (CS x 0.9) + (MV x 0.1)
OF 1989, AS AMENDED, ISSUED PURSUANT TO REPUBLIC ACT NO.
6657. 14 A3. When both the CS and CNI are not present and only MV is
applicable, the formula shall be:
In determining the just compensation to be paid to respondents, petitioner
utilized the formula indicated in DAR Administrative Order No. 06, series
LV = MV x 215
It is settled in jurisprudence that, in order to determine just compensation, as in this case, its validity was not put in issue. Unless an administrative
the trial court acting as a SAC must take into consideration the factors order is declared invalid, courts have no option but to apply the same.
prescribed by Section 17 of Republic Act No. 6657 and is obliged to apply
the formula crafted by the DAR. We discussed the long line of cases We reiterated the mandatory application of the formula in the applicable
calling for the mandatory application of the DAR formula in Land Bank of DAR administrative regulations in Land Bank of the Philippines v. Lim,
the Philippines v. Honeycomb Farms Corporation, 16 to wit: Land Bank of the Philippines v. Heirs of Eleuterio Cruz, and Land Bank of
the Philippines v. Barrido. x x x.
In Land Bank of the Philippines v. Sps. Banal, we recognized that the
DAR, as the administrative agency tasked with the implementation of the In Land Bank of the Philippines v. Gonzalez, 17 we reiterated this doctrine:
agrarian reform program, already came up with a formula to determine
just compensation which incorporated the factors enumerated in Section While the determination of just compensation is essentially a judicial
17 of RA 6657. We said: function vested in the R TC acting as a SAC, the judge cannot abuse his
discretion by not taking into full consideration the factors specifically
These factors [enumerated in Section 17] have been translated into a identified by law and implementing rules. SACs are not at liberty to
basic formula in DAR Administrative Order No. 6, Series of 1992, as disregard the formula laid down in DAR A.O. No. 5, series of 1998,
amended by DAR Administrative Order No. 11, Series of 1994, issued because unless an administrative order is declared invalid, courts have
pursuant to the DAR's rule-making power to carry out the object and no option but to apply it. Simply put, courts cannot ignore, without
purposes of R.A. 6657, as amended. violating the agrarian reform law, the formula provided by the DAR for the
determination of just compensation. (Citation omitted.)
In Landbank of the Philippines v. Celada, we emphasized the duty of the
RTC to apply the formula provided in the applicable DAR AO to To settle the lingering legal objections to the use of Section 17 of
determine just compensation, stating that: Republic Act No. 6657 and the implementing formulas of the DAR in the
valuation of properties covered by the government's agrarian reform
While [the RTC] is required to consider the acquisition cost of the land, program, the Court En Banc held in the recent case of Alfonso v. Land
the current value of like properties, its nature, actual use and income, the Bank of the Philippines18:
sworn valuation by the owner, the tax declaration and the assessments
made by the government assessors to determine just compensation, it is For clarity, we restate the body of rules as follows: The factors listed
equally true that these factors have been translated into a basic formula under Section 17 of RA 6657 and its resulting formulas provide a
by the DAR pursuant to its rule-making power under Section 49 of R.A. uniform framework or structure for the computation of just
No. 6657. As the government agency principally tasked to implement the compensation which ensures that the amounts to be paid to
agrarian reform program, it is the DAR's duty to issue rules and affected landowners are not arbitrary, absurd or even contradictory
regulations to carry out the object of the law. [The] DAR [Administrative to the objectives of agrarian reform. Until and unless declared
Order] precisely "filled in the details" of Section 17, R.A. No. 6657 by invalid in a proper case, the DAR formulas partake of the nature of
providing a basic formula by which the factors mentioned therein may be statutes, which under the 2009 amendment became law itself, and
taken into account. The [RTC] was at no liberty to disregard the formula thus have in their favor the presumption of legality, such that courts
which was devised to implement the said provision. shall consider, and not disregard, these formulas in the
determination of just compensation for properties covered by the
It is elementary that rules and regulations issued by administrative bodies CARP. When faced with situations which do not warrant the
to interpret the law which they are entrusted to enforce, have the force of formula's strict application, courts may, in the exercise of their
law, and are entitled to great respect. Administrative issuances partake of judicial discretion, relax the formula's application to fit the factual
the nature of a statute and have in their favor a presumption of legality. situations before them, subject only to the condition that they
As such, courts cannot ignore administrative issuances especially when, clearly explain in their Decision their reasons (as borne by the
evidence on record) for the deviation undertaken. It is thus entirely
allowable for a court to allow a landowner's claim for an amount valuation made by the trial court cannot be upheld and must be struck
higher than what would otherwise have been offered (based on an down as illegal.
application of the formula) for as long as there is evidence on
record sufficient to support the award. However, despite the necessity of setting aside the computation of just
compensation of the trial court, the Court cannot automatically adopt
In the case at bar, the trial court, in arriving at the amount of just petitioner's own calculation as prayed for in the instant petition. As we
compensation to be paid to respondents, solely based its conclusion on decreed in Heirs of Lorenzo and Carmen Vidad v. Land Bank of the
the alleged selling price or market value of the land adjoining Philippines,20the "LBP's valuation has to be substantiated during an
respondents' properties. appropriate hearing before it could be considered sufficient in accordance
with Section 17 of Republic Act No. 6657 and the DAR regulations."
Likewise, the Court of Appeals merely sustained the trial court's method
of valuation which was chiefly based on the market value of adjoining The veracity of the facts and figures which petitioner used in arriving at
properties. The appellate court held: the amount of just compensation under the circumstances involves the
resolution of questions of fact which is, as a rule, improper in a petition for
In the case at bench, it cannot be gainsaid that the valuation of review on certiorari. We have likewise consistently taken the position that
respondents' properties was based mainly on the market value of the Court is not a trier of facts. 21 Thus, a remand of this case for
properties within the surrounding area. To our mind, the trial court's fixing reception of further evidence is necessary in order for the trial court
of the just compensation for respondents' properties at ₱150,000.00 per acting as a SAC to determine just compensation in accordance with
hectare or at ₱l5.00 per square meter is a fair valuation considering their Section 17 of Republic Act No. 6657 and the applicable DAR regulations.
suitability for agriculture, accessibility to both provincial and municipal
roads and close proximity to the barangay road in the locality. Aside from WHEREFORE, premises considered, the petition is PARTIALLY
the income-yielding crops and fruit bearing trees to which the subject GRANTED. The Decision dated April 8, 2005 and the Resolution dated
realties are already planted, we find that the trial court also correctly took November 22, 2005 of the Court of Appeals in CA-G.R. SP No. 79245
appropriate note of the fact that properties within the area commanded are REVERSED and SET ASIDE. Civil Case Nos. 6328 and 6333
the price of ₱3.24 per square meter in 1977 and ₱l5.91 per square meter are REMANDED to the Regional Trial Court of Bataan, Branch 1 for the
in 1996. 19(Citations omitted.) determination of just compensation, based on Section 17 of Republic Act
No. 6657 and the applicable administrative orders of the Department of
Notably, in Alfonso, we recognized that comparable sales is one of the Agrarian Reform, and in consonance with prevailing jurisprudence.
factors that may be considered in determining the just compensation that
may be paid to the landowner. However, there must still be proof that SO ORDERED.
such comparable sales met the guidelines set forth in DAR AO No. 5
(1998), which included among others, that such sales should have been
executed within the period January 1, 1985 to June 15, 1988 and
registered within the period January 1, 1985 to September 13, 1988.

It is apparent from the foregoing that both the trial court and the Court of
Appeals did not observe the valuation factors under Section 17 of
Republic Act No. 6657 as translated into a basic formula in DAR
Administrative Order No. 06, series of 1992, without a well-reasoned
justification for the deviation as supported by the evidence on record.
This is in clear violation of the express mandate of both the law and
jurisprudence concerning the determination of just compensation of land
subjected to coverage by the agrarian reform law. For this reason, the
SECOND DIVISION refused to pay both the principal obligation and the interest due starting from
February 2011 to the present notwithstanding repeated demands;
G.R. No. 214803, April 23, 2018
5. That there are no other persons having or claiming interest in the
mortgaged property except Romel D. Matorres whom plaintiff recently
ALONA G. ROLDAN, Petitioner, v. SPOUSES CLARENCE I. BARRIOS AND discovered that the defendants mortgaged again to the said person the same
ANNA LEE T. BARRIOS, ROMMEL MATORRES, AND HON. JEMENA property subject of this suit for One Hundred Fifty Thousand Pesos,
ABELLAR ARBIS, IN HER CAPACITY AS PRESIDING JUDGE, BRANCH 6, (P150,000.00) on June 11, 2012 x x x The said Romel D. Matorres is however
REGIONAL TRIAL COURT, AKLAN, Respondents. a mortgagee in bad faith.

DECISION WHEREFORE, it is respectfully prayed that upon due notice and hearing,
judgment be rendered ordering defendants SPS. CLARENCE I. BARRIOS and
ANNA LEE T. BARRIOS:
PERALTA, J.:
1. To pay unto the court within the reglementary period of ninety days the sum
of P250,000.00 together with the stipulated interest at five percent (5%) per
Before us is a petition for certiorari assailing the Order1 dated July 22, 2014 month starting from February 2011 to the present, plus the additional sum of
issued by the Regional Trial Court (RTC), Branch 6, Kalibo, Aklan as well as the P25,000.00 the total amount due for attorney's fees; litigation expenses and
Order2 dated August 18, 2014 denying reconsideration thereof. costs; and that in default of such payment, the above-mentioned property be
ordered sold to pay off the mortgage debt and its accumulated interest;
The antecedent facts are as follows:
2. To teach the defendants a lesson for having mortgaged the property subject
On February 3, 2014, petitioner Alona G. Roldan filed an action3 for foreclosure of this suit without plaintiffs consent or knowledge, the defendants be ordered
of real estate mortgage against respondents spouses Clarence I. Barrios and to pay the plaintiff the sum of P50,000.00 as exemplary damages.
Anna Lee T. Barrios and respondent Romel D. Matorres, docketed as Civil Case
No. 9811. She alleged the following: 3. That plaintiff be granted such other relief in law and equity.4
Respondents spouses Barrios filed their Answer5 with Special and Affirmative
xxxx Defenses contending that the computation of their alleged loan obligation was
not accurate; that they had filed with the RTC a petition for rehabilitation of a
2. That on October 13, 2008, defendants borrowed from plaintiff the sum of financially distressed individuals under Special Proceeding No. 9845, thus there
Two Hundred Fifty Thousand Pesos (P250,000.00), Philippine Currency, is a need to suspend the foreclosure proceedings. On the other hand,
payable within the period of one (1) year from said date, with an interest respondent Matorres filed his Answer6 with Special and Affirmative Defenses
thereon at the rate of 5% per month; and to secure the prompt and full admitting that the subject land was mortgaged to him; that he had also filed a
payment of the principal and interest, defendants made and executed on judicial foreclosure case against respondents spouses Barrios pending with the
October 13, 2008 a Deed of Real Estate Mortgage in favor of plaintiff upon a RTC of Kalibo Aklan, Branch 6, docketed as Civil Case No. 9642; that petitioner
parcel of land and improvements thereon described as follows: had no cause of action against him as they did not have any transaction with
each other; and prayed for damages and attorney's fees, and cross-claim
A parcel of land (Lot 5891-A-4) situated in Baybay, Makato, Aklan, containing against respondent spouses for moral damages.
an area of four hundred seventy-eight (478) square meters, more or less x x x
declared in the name of Spouses Clarence Barrios and Anna Lee T. Barrios, On July 22, 2014, the RTC issued the assailed Order as follows:
assessed in the sum of P13,380.00, tax effectivity for the year 2008. Said land Civil Cases Nos. 9642 and 9811 are complaints for Foreclosure of Real Estate
is covered by OCT No. P-5561 pt. Mortgage that involved the same property, Lot 5891-A-4, situated in Baybay,
Makato, Aklan, owned by Spouses Clarence Barrios and Anna Lee Barrios.
xxx
It appearing from the complaint that the assessed value of the property
3. That the condition of said mortgage, as stated therein, is such, that if within mortgaged is only P13,380.00 and the instant cases being a real action, the
the period of one year from October 13, 2008, the defendants shall pay or assessed value of the property determines the jurisdiction.
cause to be paid to the plaintiff, her heirs and assigns, the said sum of
P250,000.00 together with the agreed interest, then the said mortgage shall be The assessed value of the property involved being below P20,000.00, it is the
discharged; otherwise, it shall remain in full force and effect, to be enforceable first level court that has jurisdiction over the cases.
in the manner provided by law.
Premises considered, for lack of jurisdiction, Civil Cases Nos. 9642 and 9811
4. That the time for payment of said loan is overdue and defendants failed and
are ordered DISMISSED without prejudice. prohibition, mandamus, quo warranto, habeas corpus and injunction, such
concurrence does not give the petitioner unrestricted freedom of choice of
SO ORDERED.7 court forum. This Court is a court of last resort, and must so remain if it is to
satisfactorily perform the functions assigned to it by the Constitution and
Petitioner and respondent Matorres filed their respective motions for
immemorial tradition.10However, the judicial hierarchy of courts is not an iron-
reconsideration.
clad rule. A strict application of the rule of hierarchy of courts is not necessary
when the cases brought before the appellate courts do not involve factual but
In an Order dated August 18, 2014, the RTC denied petitioner's motion as
legal questions.11 Since petitioner raises a pure question of law pertaining to
follows:
the court's jurisdiction on complaint for judicial foreclosure of sale, we would
xxxx
allow petitioner's direct resort to us.
Petitioner in her Motion argued that foreclosure of real estate mortgage is an
The RTC dismissed the foreclosure cases finding that being a real action and
action incapable of pecuniary estimation and jurisdiction lies with the Regional
the assessed value of the mortgaged property is only P13,380.00, it is the first
Trial Court.
level court which has jurisdiction over the case and not the RTC.
Petitioner's argument is devoid of merit.
Jurisdiction over the subject matter is the power to hear and determine cases
of the general class to which the proceedings in question belong. It is conferred
A petition for foreclosure of real estate mortgage is a real action and the
by law and an objection based on this ground cannot be waived by the
assessed value of the property determines jurisdiction while location of the
parties.12 To determine whether a court has jurisdiction over the subject matter
property determines the venue.
of a case, it is important to determine the nature of the cause of action and of
the relief sought.13
Premises considered, the Motion for Reconsideration is DENIED for lack of
merit.
Batas Pambansa Blg. (BP) 129 as amended by Republic Act No. (RA) 7691
pertinently provides for the jurisdiction of the RTC and the first level courts as
SO ORDERED.8
follows:
Respondent Matorres' motion for reconsideration was also denied in an Sec. 19. Jurisdiction in civil cases. - Regional Trial Courts shall exercise
Order9 dated September 1, 2014. exclusive original jurisdiction:

Petitioner filed the instant petition for certiorari alleging grave abuse of 1. In all civil actions in which the subject of the litigation is incapable of
discretion committed by the RTC when it ordered the dismissal of her pecuniary estimation;
foreclosure case without prejudice and denying her motion for reconsideration.
She argues that foreclosure of mortgage is an action incapable of pecuniary 2. In all civil actions which involve the title to, or possession of, real property,
estimation which is within the exclusive jurisdiction of the RTC. or any interest therein, where the assessed value of the property involved
exceeds Twenty thousand pesos (P20,000.00) or, for civil actions in Metro
In his Comment, respondent Matorres joins the position and arguments of Manila, where such value exceeds Fifty thousand pesos (P50,000.00) except
petitioner that the cause of action of the foreclosure cases is incapable of actions for forcible entry into and unlawful detainer of lands or buildings,
pecuniary estimation, hence, falling within the jurisdiction of the RTC. original jurisdiction over which is conferred upon the Metropolitan Trial Courts,
Municipal Trial Courts, and Municipal Circuit Trial Courts.
Respondents spouses Barrios filed their Explanation and Comment alleging that
and
petitioner violated the Tax Reform Act of 1997 for her failure to issue official
Sec. 33. Jurisdiction of Metropolitan Trial Courts, Municipal Trial Courts and
receipts on the payments made by them; that she failed to show any proof of
Municipal Circuit Trial Courts in civil cases. - Metropolitan Trial Courts,
authority from the Bangko Sentral ng Pilipinas relative to her money-lending
Municipal Trial Courts, and Municipal Circuit Trial Courts shall exercise:
activities.
xxxx
The issue for resolution is whether the RTC committed grave abuse of
3) Exclusive original jurisdiction in all civil actions which involve title to, or
discretion in dismissing the foreclosure cases filed with it on the ground of lack
possession of, real property, or any interest therein where the assessed value
of jurisdiction.
of the property or interest therein does not exceed Twenty thousand pesos
(P20,000.00) or, in civil actions in Metro Manila, where such assessed value
Preliminarily, we need to point out that generally a direct recourse to this Court
does not exceed Fifty thousand pesos (P50,000.00) exclusive of interest,
is highly improper, for it violates the established policy of strict observance of
damages of whatever kind, attorney's fees, litigation expenses and costs:
the judicial hierarchy of courts. Although this Court, the RTCs and the Court of
Appeals have concurrent jurisdiction to issue writs of certiorari,
Provided, That in cases of land not declared for taxation purposes, the value of actions as cases where the subject of the litigation may not be estimated in
such property shall be determined by the assessed value of the adjacent lots. terms of money, and are cognizable exclusively by courts of first instance (now
Regional Trial Courts).
From the foregoing, the RTC exercises exclusive original jurisdiction in civil
actions where the subject of the litigation is incapable of pecuniary estimation.
Examples of actions incapable of pecuniary estimation are those for specific
It also has jurisdiction in civil cases involving title to, or possession of, real
performance, support, or foreclosure of mortgage or annulment of judgment;
property or any interest in it where the assessed value of the property involved
also actions questioning the validity of a mortgage, annulling a deed of sale or
exceeds P20,000.00, and if it is below P20,000.00, it is the first level court
conveyance and to recover the price paid and for rescission, which is a
which has jurisdiction. An action "involving title to real property" means that
counterpart of specific performance.
the plaintiffs cause of action is based on a claim that he owns such property or
that he has the legal right to have exclusive control, possession, enjoyment, or
While actions under Sec. 33(3) of B.P. 129 are also incapable of pecuniary
disposition of the same.14
estimation, the law specifically mandates that they are cognizable by the MTC,
METC, or MCTC where the assessed value of the real property involved does
The allegations and reliefs sought in petitioner's action for foreclosure of
exceed P20,000.00 in Metro Manila, or P50,000.00, if located elsewhere. If the
mortgage showed that the loan obtained by respondents spouses Barrios from
value exceeds P20,000.00 or P50,000.00 as the case may be, it is the Regional
petitioner fell due and they failed to pay such loan which was secured by a
Trial Courts which have jurisdiction under Sec. 19(2). However, the subject
mortgage on the property of the respondents spouses; and prayed that in case
matter of the complaint in this case is annulment of a document denominated
of default of payment of such mortgage indebtedness to the court, the property
as "DECLARATION OF HEIRS AND DEED OF CONFIRMATION OF PREVIOUS
be ordered sold to answer for the obligation under the mortgage contract and
ORAL PARTITION."20
the accumulated interest. It is worthy to mention that the essence of a contract
of mortgage indebtedness is that a property has been identified or set apart Clearly, the last paragraph clarified that while civil actions which involve title
from the mass of the property of the debtor-mortgagor as security for the to, or possession of, real property, or any interest therein, are also incapable of
payment of money or the fulfillment of an obligation to answer the amount of pecuniary estimation as it is not for recovery of money, the court's jurisdiction
indebtedness, in case of default in payment.15Foreclosure is but a necessary will be determined by the assessed value of the property involved.
consequence of non-payment of the mortgage indebtedness.16 In a real estate
mortgage when the principal obligation is not paid when due, the mortgagee WHEREFORE, the petition for certiorari is DISMISSED as we find no grave
has the right to foreclose the mortgage and to have the property seized and abuse of discretion committed by the Regional Trial Court, Branch 6, Kalibo,
sold with the view of applying the proceeds to the payment of the Aklan in dismissing the complaint for lack of jurisdiction.
obligation.17 Therefore, the foreclosure suit is a real action so far as it is
against property, and seeks the judicial recognition of a property debt, and an SO ORDERED.
order for the sale of the res.18

As foreclosure of mortgage is a real action, it is the assessed value of the


property which determines the court's jurisdiction. Considering that the
assessed value of the mortgaged property is only P13,380.00, the RTC
correctly found that the action falls within the jurisdiction of the first level
court. er Section 33(3) of BP 129 as amended.

Petitioner cites Russell v. Vestil19 to show that action for foreclosure of


mortgage is an action incapable of pecuniary estimation and, therefore, within
the jurisdiction of the RTC. We are not persuaded. In the Russell case, we held:
In Singsong vs. Isabela Sawmill, we had the occasion to rule that:

[I]n determining whether an action is one the subject matter of which is not
capable of pecuniary estimation, this Court has adopted the criterion of first
ascertaining the nature of the principal action or remedy sought. If it is
primarily for the recovery of a sum of money, the claim is considered capable
of pecuniary estimation, and whether jurisdiction is in the municipal courts or
in the courts of first instance would depend on the amount of the claim.
However, where the basic issue is something other than the right to recover a
sum of money, where the money claim is purely incidental to, or a
consequence of, the principal relief sought, this Court has considered such
Republic of the Philippines of paying the repurchase price of the auctioned property. Within the year
SUPREME COURT of redemption, that is, on December 29, 1951, the assignee-spouses and
Manila the RFC executed a "Deed of Resale" whereby the mortgaged property
was resold and reconveyed in favor of the "redemptioners, their heirs,
EN BANC assignees and successors in interest". However, instead of paying the
whole redemption price, only P5,500 was paid on hand and the sum of
G.R. No. L-14303 March 24, 1960 P21,505.11, balance of the total indebtedness including 6% interest was
agreed to be paid in ten annual amortizations.
REHABILITATION FINANCE CORPORATION, plaintiff-appellant,
vs. On April 3, 1952, Alto, as junior encumbrancer, wrote the RFC inquiring
ALTO SURETY and INSURANCE COMPANY, INC., oppositor-appellee. as to the actual status of the property subject to redemption expiring on
April 17, 1952. In its reply dated April 9, 1952, RFC advised Alto that the
auctioned property had already been sold to the Trinidad spouses "under
Jesus A. Avanceña and Federico G. Cabling for appellant.
a deed of redemption on the installment plan".
Raul A. Aristorenas and Benjamin Relova for appellee.
This notwithstanding, the RFC, on October 2, 1952, executed an affidavit
BARRERA, J.:
consolidating ownership on the purchased property, stating therein that
the period of redemption had expired on April 18, 1952 without the debtor
This is an appeal from an order of the Court of First Instance of or any lien-holder thereon exercising said right of redemption or
Camarines Sur, sitting as a land registration court (in Special Proceeding repurchase. This affidavit, together with the deed of sale evidencing its
No. 781—G.L.R.O. Rec. No. 14837) denying appellant's petition under (RFC's) purchase of the property at public auction were registered on
Section 112 of Act No. 496 for cancellation of the annotation of appellee's December 16, 1953, by virtue of which, RFC was able to secure the
second mortgage on appellant's transfer certificate of title No. 1155 of the cancellation of Transfer Certificate of Title No. 12, in the name of the
Register of Deeds of Camarines Sur. owner-mortgagor Eustaquio Palma, and the issuance of a new title in its
name (T.C.T. No. 1155). The second mortgage in favor of Alto, however,
Eustaquio Palma registered owner of a parcel of land with its was carried and annotated at the back of the new title.
improvements, located in San Agustin, Iriga, Camarines Sur, covered by
Transfer Certificate of Title No. 12—Camarines Sur, executed a first It is this annotation on its certificate of title No. 1155 that the RFC sought
mortgage to secure a loan of P20,000.00, in favor of the Rehabilitation to have cancelled, alleging that with the consolidation and transfer to it as
Finance Corporation (RFC), and subsequently, with the consent of the the first mortgagee of the mortgagee's rights on the property, the junior
RFC, a second mortgage over the same property, in favor of Alto Surety encumbrancer's lien on the same property had ceased. Alto, the second
& Insurance Company, Inc. (Alto). Both mortgages were duly registered mortgagee, opposed the petition contending that with the execution of the
in the Office of the Register of Deeds of Camarines Sur and annotated on Deed of Resale between RFC and the spouses Anacleto Trinidad and
the corresponding certificate of title. Upon failure of the mortgagor to Rosa S. de Trinidad, assignees of the mortgagor, the mortgaged property
settle the P20,000.00 loan on its maturity, RFC foreclosed the mortgage had been completely released from the first mortgage and the second
extrajudicially under Act 3135 as authorized in the deed of mortgage and mortgage had been automatically transformed into a first lien on the
the property was sold in public auction under the direction of the property.
Provincial Sheriff of Camarines Sur on April 17, 1951 in favor of
mortgagee RFC as the highest bidder for the sum of P11,211.68.
From the order denying the petition for cancellation, RFC appealed to the
Court of Appeals. The case, however, was certified to this Court, the
Six months later, mortgagor Palma, by a deed of assignment dated questions raised therein being purely of law.
October 15, 1951, transferred and conveyed all his rights, title and
interest in and to the mortgaged property to the spouses Anacleto
Trinidad and Rosa S. de Trinidad, the assignees assuming the obligation
As stated by the lower court: "The only question at issue is whether the While as a general rule, the junior encumbrancer is not a necessary party
annotation of the second mortgage in favor of the oppositor on the back to a suit to foreclose by a senior mortgagee, it is always proper and
of Transfer Certificate of Title No. 1155 was made in accordance with prudent to join him as a defendant, both to give an opportunity to defend
law". The petition for cancellation was filed by the RFC and the original and to extinguish his right of redemption (Lee vs. Slemons, 150 So. 792,
registration case, under Section 112 of Act 496, on the alleged ground 112 Fla. 675; Woodward vs. Householder, 289 S.W. 571, 315 Mo. 1155).
that the lien in favor of Alto had already ceased. In opposing this petition,
Alto claimed that with the execution of the deed of resale between RFC When a senior mortgagee forecloses and becomes the purchaser at his
and the Spouses Anacleto and Rosa S. de Trinidad, (Exhibit J), there had own foreclosure sale, but the holder of a subsequent mortgage or other
been a valid exercise by the latter, as the mortgagor's successors-in- subordinate interest has not been joined or has been eliminated from the
interest, of the right of redemption, thus justifying the retention of the proceeding, equity will keep the senior mortgage alive against the
encumbrance in favor of the junior mortgagee in the certificate of title subsequent encumbrance and the senior mortgagee will be entitled to an
covering the property. action de novo to reforeclose the mortgage as to the omitted persons
(Van Meter vs. Field, 159 P. 2d 546, 195 Okl. 55; Rives vs. Stanford, 106
The court a quo acted correctly in denying, under the circumstances, the P. 2d 1101).
petition to cancel the annotation of the second mortgage at the back of
the title covering the property originally owned by Eustaquio Palma. It has In view of the foregoing, the decision appealed from denying the first
been consistently held by this Court, that the relief afforded by Section mortgagee's petition to cancel the annotation of the second mortgage at
112 of the Land Registration Act may only be allowed if "there is a the back of Transfer Certificate of Title No. 1155, is hereby affirmed,
unanimity among the parties, or there is no adverse claim or serious without prejudice to the proper adjudication, in an appropriate ordinary
objection on the part of any party in interest; otherwise, the case action, of the respective rights of the parties herein as a result of the
becomes controversial and should be threshed out in an ordinary execution of the Deed of Resale, Exhibit J. The petitioner-appellant shall
case.1 In another case, this Court2 has held that "Section 112 authorizes, pay the costs. It is so ordered.
in our opinion, only alterations which do not impair rights recorded in the
decree, or alterations which, if they do prejudice such rights, are Paras, C. J., Bengzon, Montemayor, Bautista Angelo, Labrador,
consented to by all parties concerned or alterations to correct obvious Concepcion, Reyes, J.B.L., Endencia, and Gutierrez David, JJ., concur.
mistakes". This doctrine is but sound and proper. The proceedings
provided in the Land Registration Act being summary in nature, they are
inadequate for the litigation of issues properly pertaining to ordinary civil
actions,3 thus, questions involving ownership of or title to a real
property,4 or relating to the validity or cancellation or discharge of a
mortgage should properly be ventilated in an ordinary proceeding."5

There is another reason why the petition must be denied.


Granting arguendo that the extrajudicial foreclosure proceeding instituted
by the RFC is proper and justified, since the junior encumbrancer was
admittedly not notified thereof, the foreclosure of the first mortgage
cannot be considered to have terminated or extinguished the rights of
said junior encumbrancer over the property.

An interest in the mortgaged property acquired subsequent to the (first)


mortgage may be divested or barred only by making the holder thereof a
party to the proceedings to foreclose (Kurz vs. Pappas, 146 So. 100, 107
Fla. 861; Mediterranean Corp. vs. Pappas, 146 So. 106, 107 Fla. 876).
(Emphasis supplied.)
Republic of the Philippines null and void, because the defendant's former counsel had no special
SUPREME COURT authority to settle the case in the manner stated in said judgment, and (2)
Manila that the sheriff's sale was not legally confirmed, because the defendant
was not given notice of the motion for confirmation or its hearing. On
EN BANC June 30, 1948, the court granted plaintiff's motion for the issuance of a
writ of possession. The defendant filed on July 7, 1948, a motion for
G.R. No. L-3619 October 29, 1951 reconsideration and under date of September 9, 1948, a motion invoking
moratorium under Republic Act No. 342 and praying that all proceedings
be suspended. In its order of October 12, 1948, the Court of First
BERNARDO TIGLAO, plaintiff-appellee,
Instance of Tarlac denied the motion for reconsideration. The defendant
vs.
appealed.
ENGRACIO BOTONES, defendant-appellant.
Appellant's first contention is that the trial court erred in sustaining the
Barrera, Calanog and Alafriz for appellant.
order confirming the sheriff's sale and in issuing the corresponding writ of
Enrico I. de la Cruz for appellee.
possession in favor of the appellee. Under section 3 of rule 70 of the
Rules of Court, the sale of mortgaged property "when confirmed by an
PARAS, C.J.:, order of the court . . . shall operate to divest the rights of all the parties to
the action and to vest their rights in the purchaser, subject to such rights
In civil case No. 5115 of the Court of First Instance of Tarlac in which of redemption as may be allowed by law." The effect of confirmation was
Bernardo Tiglao was the plaintiff and Engracio Botones the defendant, more elaborately explained in the case of Raymundo vs. Sunico, 25 Phil.,
judgment was rendered on March 24, 1943, the dispositive part of which 365, 368-369, as follows: "As the title to mortgaged real property does not
reads as follows: "El Juzgado, de acuerdo con dicho convenio, condena vest in the purchaser until after the confirmation of the sale, he has, prior
al demandado al pago de la catidad de P4,000 con los intereses de 12 to that time, no right to the possession of such property, and no legal
por ciento al año desde el 29 de Noviembre de 1937 hasta su pago cause of complaint against the defendants, who remain in possession,
completo y se le ordena que deposite esta cantidad en poder del exercising the rights of ownership. On the other hand, the mortgagors
Escribano dentro del plazo de 90 dias, de lo contrario se ordenara la have no means, until the confirmation of compelling the purchaser to
ejecucion de la sentencia vendiendo en publica subasta los bienes comply with the terms of the sale. Should the mortgagors attempt to
hipotecados, con las costas a cargo del demandado." compel a purchaser to pay in his money, an answer on the part of the
purchaser to the effect that the sale had not been confirmed would be
Upon motion of the plaintiff, the Court of First Instance of Tarlac on July sufficient. The confirmation operates to divest the title out of the former
20, 1943, ordered the issuance of a writ of execution. Accordingly, on owner and to vest it in the purchaser. It is at this time when the rights or
October 9, 1943, the provincial sheriff sold at public auction the title passes, and not before. Sales of mortgaged real estate should be
mortgaged properties to the plaintiff as the highest bidder. On March 7, more strictly scrutinized than ordinary sales under execution. In the
1944, the plaintiff filed an ex parte motion with the Court of First Instance former the title, as we have said, passes to the purchaser upon
of Tarlac, for the confirmation of the sale in his favor. On March 22, 1944, confirmation by the court, and the defendant or debtor has no right to
the court issued the following order: " As prayed for in the "Motion for redeem within the statutory period granted in cases ordinary execution
confirmation of the sheriff's sale dated October 9, 1943, of lots Nos. 784 sales. In some of the States of the American Union there are statutes
and 1146 of the cadastral survey of Concepcion, executed by the permitting the mortgagor to redeem after the foreclosure sale has been
Provincial Sheriff of Tarlac in favor of Bernardo Tiglao, pursuant to the confirmed. There is no such privilege extended to him by statute in the
order of execution entered herein, the said sale is hereby APPROVED." Philippine Islands. The right of the mortgagor and those claiming under
him to redeem for mortgagee is extinguished by the foreclosure when the
On May 7, 1948, the plaintiff filed with the Court of First Instance of same has been properly made. But, up to the time of confirmation the title
Tarlac a motion for the issuance of a writ of possession. The defendant remains in the mortgagor." In said case this Court held that a hearing "is
filed an opposition alleging (1) that the judgment of March 24, 1943, is a very essential part of those proceedings because the hearing gives the
interested parties an opportunity to lay before the court their reasons why latter filed it with the clerk of court in accordance with Rule 20 of the
the sale should or should not be confirmed, and it is the result of this Rules of Court of First Instance. What the creditor did was held sufficient,
hearing which diverts the title if the sale is confirmed." because if the debtors failed to receive the notice sent to their address
appearing in the record, it was their fault. The statement in said case,
In the case of Grimalt vs. Velasquez, 36 Phil., 936, 938, this Court, therefore, that lack of notice does not deprive the court of its jurisdiction
relying upon its decision in Raymundo vs. Sunico, supra, ruled that "in to approve a sheriff's sale, was purely an obiter dictum. Moreover, the
order that a foreclosure sale may be validly confirmed by the court, it is cases of So Chu vs. Nepomuceno, Jaranillo vs. Jacinto, Price vs. Sontua,
necessary that a hearing be given the interested parties at which they and National Investment Board vs. Peña, did not involve situations in
may have an opportunity to show cause why the sale should not be which confirmation of sheriff's sale was upheld although there was no
confirmed; that a failure to give notice is good cause for setting aside the notice or hearing. .
sale."
In the more recent case of Somera vs. Navarro, 42 Off. Gaz., 2106, it
In the cases of La Urbana vs. Belando, 54 Phil. 930, and Anderson vs. was contended that no 3-day notice of the motion for confirmation was
Reyes, 54 Phil. 944, it was held, following the decision in Grimalt vs. given, because the hearing of the motion was set for July 26, 1941, the
Velasquez, supra, that after the sale of mortgaged property and before its notice was mailed to the appellants on July 23 and was received by them
confirmation, the court may still grant the judgment debtor an opportunity on July 26, the appellants were present and at their instance said hearing
to pay the amount of the judgment. In other words, until a sheriff's sale is was postponed to August 9. Other postponements were conceded and
validly confirmed, the judgment debtor may exercise a right of the motion was not heard until December 4, 1942. This Court held:
redemption. "Resulta evidente, por tanto, que la regla sobre notificaciones se cumplio
substancialmente, y que toda discusion ahora sobre el particularveine a
Notice and hearing of motion for confirmation are therefore essential to ser meramente academica, porque, aun suponiendo que la primera
the validity of the order of confirmation, not only to enable the interested notificacion haya sido irregular, de ella no se siquio ningun perjuicio para
parties to resist the motion but also to inform them of the time when their los apelantes, toda vez que la mocion no se considero y resolvio sino
right of redemption is cut off. despues de varias transferencias, de los cuales aquellos habian sido
debidamente avisados." We have thus inferentially recognized the
essential need for notice of motion for confirmation of a sheriff's sale, for,
It is argued for the appellee that because section 3 of Rule 70 does not
on the contrary supposition. we would have summarily dismissed
carry the last part of section 257 of Act 190 to the effect that "should the
appellant's contention and held that notice and hearing were
court decline to confirm the sale, for good cause shown, and should set it
unnecessary.
aside, it shall order a resale in accordance with law," the cases
hereinabove cited are no longer efficacious. We disagree. The fact that
the present rules still require confirmation of the sheriff's sale implies the In the case at bar, the lower court undoubtedly had acquired jurisdiction
power of the court to either confirm the same or not, when asked. And the over the foreclosure proceedings but, in confirming the sheriff's sale
court may properly exercise its judgment on the matter only after hearing without the essential requisite as to notice of the motion for confirmation,
both parties. Indeed, there is reason to suppose that the omitted it exceeded its power, with the result that the order of confirmation is null
provision is superflous. and void. As stated by Mr. Justice Feria in Caluag et al.,*46 Off. Gaz.,
514. "a wrong, or for that matter a correct, decision is void, and may be
set aside either directly or collaterally, where the court exceeds its
The case of Commonwealth of the Philippines vs. Ching yap, 70 Phil.,
jurisdiction and power in rendering it." In Ang Lam vs. Rosillosa,** 47 Off.
116, citing So Chu vs. Nepomuceno, 29 Phil., 208, Jaranillo vs. Jacinto,
Gaz., Supp.(12), 103, it was held that "a void judgment may be assailed
43 Phil. 588, Price vs. Sontua, 60 Phil. 410, and National Investment
or impugned at any time either directly or collaterally, by means of a
Board vs. Peña, G.R. No. 46448, May 29, 1939, invoked by the appellee,
petition filed in the same case or by means of a separate action, or by
is obviously not controlling. In said case this Court found that notice of the
resisting such judgment in any action or proceeding wherein it is
motion for confirmation was sent to the judgment debtors at their address
invoked." Hence there is no merit in appellee's contention that the order
of record and when said notice was returned to the judgment creditor, the
of confirmation had become final and cannot be set aside after the 6-
month period provided in rule 38 of the Rules of Court, within which relief
could be asked, had expire.

The second contention of the appellant is that the trial court erred in not
suspending the proceedings because of the Moratorium Law (Republic
Act No. 342). This contention is untenable. The foreclosure judgment had
long become final. By his motion for confirmation of the sheriff's sale and
his motion for a writ of possession, the appellee sought to recover, not a
monetary obligation, but the properties sold to him at public auction. What
was held in Barrozo vs. Macaraeg, 46 Off. Gaz., 4932, is decisive against
appellant's position. "The debt moratorium merely prohibited the
enforcement by action of the debts therein included; and in this case no
one is attempting to force anybody to pay his debt. The judgment debtor
whose property has been sold is not in debt for the redemption money.
He could not be required by action to redeem. Hence, he is not entitled to
invoke the suspension."

Wherefore the order of March 22, 1944, confirming the sheriff's sale of
the mortgaged properties, being null and void, the order of June 30,
1948, granting appellee's motion for the issuance of a writ of possession
is hereby set aside, without prejudice to appellee's right to move anew for
the confirmation of the sheriff's sale in his favor, with due notice and
hearing. So ordered without costs.

Feria, Pablo, Bengzon, Padilla, Tuason, Reyes, Jugo and Bautista


Angelo, JJ., concur.

Вам также может понравиться