Академический Документы
Профессиональный Документы
Культура Документы
Abstract: The tied arch bridge system provides a unique solution to the several challenges associated with the construction of railroad
Downloaded from ascelibrary.org by University Of Ulster AT on 07/10/15. Copyright ASCE. For personal use only; all rights reserved.
overpasses and water crossings, such as restricted vertical clearance, undesirable or impractical arrangement for intermediate piers, and
extremely limited traffic control during construction. The paper presents the design and construction challenges pertinent to a novel
concrete-filled steel tubular tied arch system that was first introduced in the Ravenna viaduct (53 m) and applied later to the Columbus
viaduct (79 m). The main structural components of the Columbus viaduct are described in detail and the advantages of the system are
summarized. The detailed analysis of the system at different construction stages and design checks of main components and connections
under various loading conditions are discussed. Experimental investigations conducted on concrete-filled steel tubular arch and tie specimens
to validate their theoretical capacities are demonstrated. The three-dimensional nonlinear finite element model developed to analyze the tie-to-
arch connection and evaluate the lateral stability of arches is presented. Finally, the main construction procedures and challenges of the
three tied arches of the Columbus viaduct are highlighted. DOI: 10.1061/(ASCE)BE.1943-5592.0000205. © 2012 American Society of
Civil Engineers.
CE Database subject headings: Arch bridges; Concrete; Steel; Tubes; Design; Construction; Finite element method; Lateral stability;
Nebraska.
Author keywords: Arch; Bridges; Concrete; Steel; Tubes; Design; Construction; Finite-element analysis; Lateral stability.
Introduction steel and concrete materials and recognizing the enhanced strength
and ductility of concrete-filled steel tubes through synergistic in-
In recent years, the Nebraska Department of Roads (NDOR) has teractions of the steel tube and concrete in-fill.
adopted a novel tied arch bridge system in the construction of the The Ravenna viaduct spans a major route of the Burlington
Ravenna viaduct and Columbus viaduct in the state of Nebraska Northern Santa Fe Railroad. Because approximately 60 trains
(Tadros and Girgis 2006; Morcous et al. 2009). This system pro- per day pass on this route, there are very tight restrictions on
vides a unique solution to several of the challenges associated with the vertical clearance above the tracks, horizontal distance between
the construction of railroad overpasses and water crossings, such as piers, and time and duration of rail traffic interruptions. The bridge
restricted vertical clearance, undesirable or impractical arrange- was built in 2005 using two parallel arches that have a single span
ment for intermediate piers, and extremely limited traffic control of 53 m (174 ft) over six sets of rail tracks, two main lines, and four
during construction. In this system, the main components are pre- sidings. The structural depth below the existing road grade is
fabricated, assembled, and then placed on site, which accelerates 0.81 m (32 in.) to provide the required vertical clearance above
construction and eliminates constraints of working over live and the railroad tracks, and the total width is 17.22 m (56.5 ft) to ac-
major railroad routes. The structural efficiency and slenderness commodate three traffic lanes and one pedestrian lane. The con-
of the tied arch system is accomplished by using high performance struction of this bridge has shown that the tied arch system is a
very efficient and cost-effective system for a project with such
1
Associate Professor, Durham School of Architectural Engineering and constraints.
Construction, Univ. of Nebraska-Lincoln, 1110 S. 67th St., Omaha, NE The Columbus viaduct, located on U.S. 30 in Platte County,
68182 (corresponding author). E-mail: gmorcous2@unl.edu
2 Nebraska, has two spans—an arch span of 79 m (260 ft) and a beam
Project Engineer, Con-Fab California Corporation, 1910 E. Lathrop
Road, Lathrop, CA 95330; formerly, Post-Doctoral Fellow, Civil Engineer- span 29.26 m (96 ft). It has a structural depth below the road grade
ing, Univ. of Nebraska-Lincoln, 1110 S. 67th St., Omaha, NE 68182. of 1.12 m (44 in.) and a total width of approximately 25.60 m
E-mail: kromelh@confabca.com (84 ft). Three parallel tied arches are used to facilitate staging
3 of construction while replacing the old bridge. This project was
Ph.D. Candidate, Durham School of Architectural Engineering and
Construction, Univ. of Nebraska-Lincoln, 1110 S. 67th St., Omaha, NE completed in 2009 and has proven the feasibility of the tied arch
68182. E-mail: ydeng@mail.unomaha.edu system in applications where spans over 79 m (260 ft) are required
4
Leslie D. Martin Emeritus Professor, Civil Engineering, Univ. of and vertical clearance restrictions exist.
Nebraska-Lincoln, 1110 S. 67th St., Omaha, NE 68182-0178. E-mail: This paper presents the design and construction challenges
mtadros@mail.unomaha.edu
associated with the concrete-filled steel tubular tied arches of the
Note. This manuscript was submitted on August 25, 2010; approved on
November 29, 2010; published online on December 1, 2010. Discussion
Columbus viaduct. The paper is organized as follows: (1) the first
period open until June 1, 2012; separate discussions must be submitted section describes the main structural components in detail and sum-
for individual papers. This paper is part of the Journal of Bridge Engineer- marizes their unique advantages over conventional systems; (2) the
ing, Vol. 17, No. 1, January 1, 2012. ©ASCE, ISSN 1084-0702/2012/1- second section presents a detailed analysis of the system at different
107–116/$25.00. construction phases; (3) the third section discusses design checks of
cross section of the system are shown in Fig. 1(a)–1(c), respectively. efficient by providing a larger effective area to sustain the postten-
For the two outside arches, each arch consists of two 457-mm- sioning force. The compressive strength and ductility of the con-
(18-in.-) diameter by 12.7-mm- (0.5-in.-) thick concrete-filled steel crete core are increased by the lateral confinement provided by the
tubes. For the median arch, the arch consists of two 457-mm- steel tube, while the local buckling of the steel tube is restrained by
(18-in.-) diameter by 23.8-mm- (0.94-in.-) thick concrete-filled the concrete in-fill.
steel tubes. Although the arches are the primary compression mem- Hangers are made of 44.5-mm- (1¾-in.-) diameter threaded rods
bers in the system, no braces are provided to connect the parallel with minimum yield strength of 828 MPa (120 ksi). Hangers vary
arches, which is highly desirable for aesthetic reasons and for pro- in length along the arch and are used to connect the arch and tie at
viding unlimited overhead clearance. However, the two parallel 3.05-m (10-ft) spacing. Floor beams are 12.17 m (39 ft 11 in.) in
tubes of each arch are spaced at 914 mm (36 in.) on center to greatly length and simply supported on the ties at hanger locations. Floor
Fig. 1. (a) General plan of Columbus viaduct; (b) general elevation of Columbus viaduct; (c) cross section of Columbus viaduct
stress force 1,452.4 MPa (210:6 ksi ¼ 0:78 × 270 ksi) and an
anchorage set of 6.4 mm (0.25 in.). The resulting force after
Fig. 2. Plan and profile views of viaduct model (m) anchorage set is 182.4 kN (41 kips) per strand.
2. Vehicular live load is calculated in accordance with AASHTO
beams are W24 × 162 rolled sections with shear studs that are LRFD Section 3.6.1.2 (AASHTO 2007), which includes the
22.2 mm (7/8 in.) in diameter, 127-mm- (5-in.-) high, and spaced design truck in addition to a lane load of 9:34 kN=m
at 22.9 mm (9 in.) on center to provide the full composite action (0.64 klf) uniformly distributed over 3.05 m (10 ft) width. Mul-
with the deck. The composite deck is 20.3-mm- (8-in.-) thick and tiple presence factors are used based on the number of loaded
posttensioned longitudinally with 15.2-mm- (0.6-in.-) diameter lanes (maximum of four traffic lanes and two pedestrian lanes)
unbonded monostrands spaced at 305 mm (12 in.) on center. The according to AASHTO LRFD Section 3.6.1.1. A dynamic load
stay-in-place metal deck for concrete forming can be assembled allowance of 33% is used in accordance with AASHTO LRFD
with the floor beams before erection. Section 3.6.2.
The structural efficiency of this system is mainly because of 3. Pedestrian live load is calculated in accordance with AASHTO
(1) significant reduction in bending moments through the use of LRFD Section 3.6.1.6, which includes a uniform load of
arches and ties, (2) the effect of confinement on the concrete capac- 3:59 kN=m (0.075 ksf) over pedestrian lanes with no multiple
ity in compression members, (3) the use of posttensioning to elimi- presence factor or dynamic load allowance.
nate tensile stresses in the ties, and (4) composite action with a full 4. Fatigue load is calculated in accordance with AASHTO LRFD
width bridge deck to enhance the flexural capacity of the ties even Section 3.6.1.4, which includes a fatigue truck that has a 9.144-
without diaphragms. The economic efficiency of this system is m (30-ft) fixed distance between the two 220.7-kN (32-kips)
mainly because of (1) optimal use of different materials (e.g., steel axles. A load factor of 1.5 (0:75 × 2) is used for infinite life
and concrete), and (2) prefabrication of the tied arch and preassem- check. A dynamic load allowance of 15% is used in accor-
bly of the metal decking, which saves significantly on construction dance with AASHTO LRFD Section 3.6.2.
time and allows replacement projects to be completed with minimal Because of the proposed construction sequence of the Columbus
traffic disruption. Moreover, this system makes it possible to design viaduct, four analysis stages were performed as follows:
a superstructure that provides the required overhead clearance both 1. Stage I—Structure: Arches and ties (steel only) and
under and above the bridge and also improves the bridge aesthetics. floor beams;
Loads: Self-weight of arches, ties, floor beams, metal deck-
ing, and filling concrete.
System Analysis 2. Stage II—Structure: Arches and ties (filled with concrete) and
floor beams;
Structural analysis of the Columbus viaduct is performed using the Loads: Posttensioning of ties and self-weight of con-
structural analysis software SAP2000 v.10.1.3. The viaduct is crete deck.
3. Stage III—Structure: Arches and ties (filled with concrete), The effect of confinement on the compressive strength of the
floor beams, and 191-mm (7.5-in.) concrete deck composite concrete and its ultimate strain are considered according to Mander
with tie beams and cross beams; et al. (1988a, b) and Richart et al. (1928). These studies have in-
Loads: Posttensioning of deck. dicated a significant increase in the compressive capacity and duc-
4. Stage IV—Structure: Arches and ties (filled with concrete), tility of confined concrete. For the median arch, a confining
floor beams, and 191-mm (7.5-in.) concrete deck composite pressure of 7.6 MPa (1.1 ksi) results in an increase of compressive
with ties and floor beams strength of concrete from 55 MPa (8.0 ksi) to 86 MPa (12.5 ksi),
Loads: Railing, wearing surface, moving live load (truckþ and an increase of ultimate strain from 0.003 to 0.008.
impact and lane load), pedestrian load, and fatigue load.
Table 2 summarizes bending moment and axial force at the criti- Experimental Investigation
cal sections under different load cases and construction stages. The increase in the flexural capacity of a steel tube when filled with
concrete was estimated experimentally by Deng et al. (2011). Two
identical 6,100-mm- (20-ft-) long, 273-mm- (10.75-in.-) diameter
Design Challenges steel tubes, one filled with concrete, were simply supported with a
clear span of 5,510 mm (18.1 ft) and tested with point load at the
midspan. The hollow specimen sustained an ultimate load of
Arch Design 177 kN (39.79 kips) with a permanent deflection of 272 mm
Local Buckling (10.71 in.). Local buckling at the midspan on the compression side
For circular sections, a slenderness limit of λey equal to 125, is of the tube was noticeable. The concrete-filled specimen sustained
proposed by Bradford et al. (2002), where section slenderness 246 kN (55.31 kips) with a permanent deflection of 419 mm
λs is calculated as follows: (16.50 in.). It was noted that local buckling wave formation in
the steel tube was significantly restrained by the concrete in-fill.
λs ¼ ðD=tÞðf y =250Þ ≤ λey ¼ 125 ð1Þ By comparing load and deflection values of the two specimens,
it can be concluded that filling a steel tube with concrete increased
its flexural capacity and ductility approximately 39% and 54% re-
where f y = yield strength of steel tube (MPa); D = outer diameter of
spectively, as shown in Fig. 3. The predicted flexural capacity using
steel tube; and t = thickness of steel tube.
the theoretical sectional analysis, 288 kN-m (212.4 kip-ft), com-
Within this limit, the strength of postlocal buckling can be
pares well with that of the experimental result, 339 kN-m
considered to be no less than the yield strength of steel tube.
(250.1 kip-ft) (Deng et al. 2011).
All arch components of the Columbus viaduct satisfy this slender-
ness limit; therefore, no local buckling is considered in the design, Design Checks
and the ultimate strength of steel tubes is considered equal to the Theoretical sectional analysis is then performed to develop the in-
yield strength. teraction diagrams for strength design checks at the critical sections
in the arch. According to the structural analysis of the system, the
Confinement Effect median arch is more critical than the outside arch and is taken as an
The effect of confinement on concrete-filled steel tubular columns is example. For the median arch, Fig. 4(b) shows its cross section and
proposed by Fujimoto et al. (2004) as follows, based on Von Mises Fig. 4(a) shows the nominal strength and factored strength of P-M
yield criterion—hoop tensile strength in steel tube σsθ = 0:19f y ; lon- (axial force-moment) interaction diagram with and without effect of
gitudinal compressivestrength of steel tube = 0:89f y ;and longitudinal confinement.
tensile strength of steel tube = 1:08f y . The confining pressure for cir-
cular concrete-filled steel tubes is evaluated by the hoop stress as Tie Design
Local Buckling and Confinement Effect
2σsθ t
σr ¼ ð2Þ For rectangular sections, a slenderness limit for local buckling is pro-
ðD 2tÞ posed by Uy (1998) as the width-to-thickness ratio (b/t) = 80 and the
that are 12.7-mm- (0.5-in.-) thick. The top plate of the tube was
150
left off to facilitate the installation of the posttensioning hardware.
End plates had two holes that were 165 mm (6.5 in.) in diameter to
100 fit posttensioning anchorages. Posttensioning hardware, which in-
cludes wedge plates, wedges, anchorage plates, duct couplers,
50 ducts, and grouting accessories, were installed and properly fas-
tened in the steel tube. The 102-mm- (4-in.-) diameter ducts were
Downloaded from ascelibrary.org by University Of Ulster AT on 07/10/15. Copyright ASCE. For personal use only; all rights reserved.
installed so that the center of the ducts is 102 mm (4 in.) from the
0
0 50 100 150 200 250 300 350 400 bottom of the tube. Duct chairs were used to maintain a 51-mm
Deflection (mm) (2-in.) concrete cover below the duct, and bars were placed directly
on top of the ducts at 915-mm (3-ft) spacing to prevent the upward
Fig. 3. Load-deflection relationships of arch specimen and steel pipe movement of the ducts by buoyant forces when concrete is poured.
under bending The top plate was then welded to close the steel box. The top plate
has two 102-mm- (4-in.-) diameter holes at each end for concrete
pumping and 12 25.4-mm- (1-ft-) diameter holes spaced at 915 mm
for venting and quality assurance.
A self-consolidating concrete with a 762-mm (30-in.) spread
and a specified 28-day strength of 48.3 MPa (7,000 psi) was
pumped into the steel tube. Only 20 15.2-mm- (0.6-in.-) diameter
strands (10 per duct) were used and posttensioned at 1,396.6 MPa
(202.5 ksi) (0:75f pu ) using monostrand jack after the filling con-
crete strength has reached 27.6 MPa (4,000 psi). After all strands
were tensioned, lift-off tests were performed to determine the true
level of prestressing after initial losses. This was found to be aver-
aged at 1,175.9 MPa (170.5 ksi), which indicates 16% initial losses.
Following posttensioning, the two ducts were grouted using a very
simple grout consisting of Type I cement and water (w=c ¼ 0:44).
Toggle bolts and washers were used to block the nine additional
holes in the anchor plate (only 10 strands in a 19-strand plate)
and 50.8-mm- (2-in.-) diameter tube fitting were used to block
the grout access holes.
The specimen was tested in four point flexure using two
hydraulic jacks spaced 3.658 m (12 ft) from each other. The
span of the specimen from centerline to centerline was 11.963 m
(39.25 ft), and the loading points were located at 4.153 m (13.6 ft)
from each support, as shown in Fig. 5. The ultimate moment capac-
ity was 4,111 kN-m (3,032 kip-ft), and the ultimate deflection at the
midspan was 114 mm (4.49 in.), as shown in Fig. 6. This capacity is
very close to the value predicted using theoretical sectional analysis
(4,039 kN-m, 2,979 kip-ft).
Design Checks
Theoretical sectional analysis was then performed to develop the
Fig. 4. Median-arch: (a) the P-M interaction diagram; (b) cross interaction diagrams for four tie sections, i.e., midsection of the
section (m) outside tie, end-section of the outside tie, midsection of the median
tie, and end-section of the median tie. For each section, diagrams
plasticity limit for postlocal buckling to provide full yielding as were developed for two construction stages, i.e., noncomposite tie
b/t = 60. For the Columbus viaduct ties, most of the plates are for construction stage II and composite tie for construction stage
not subjected to compression; the tie acts as the primary tension III. Based on the results of an earlier experimental investigation
member of the arch. Because of bending effects, some plates will (Tadros and Girgis 2006), the effective deck width for composite
be subjected to compression stresses; however, the unsupported sections was taken as the distance between the centerlines of the
width-to-thickness ratio of these plates <60. Accordingly, the maxi- deck panels between ties, i.e., half-width of the deck for the outside
mum strength of steel in design equals the yield strength. tie and full width of the deck for the median tie. Fig. 7(a) shows the
As indicated by Fujimoto et al. (2004), the confinement effect of cross section of the composite median tie, and Fig. 7(b) demon-
rectangular concrete-filled steel tubes is much less efficient than strates the interaction diagram of the composite median tie with
that of circular ones. Therefore, confinement effects are conserva- 74 strands and the demand at critical sections. The design checks
tively neglected in theoretical sectional analysis for estimating the indicate that it is adequate to use 38 strands for the outside tie and
capacity of ties. 74 strands for the median tie.
2500
2000
1500
Load (kN)
1000
Fig. 7. Midsection of composite median tie: (a) cross section for com-
500
posite tie (m); (b) interaction diagram and the demand of critical section
0
0 20 40 60 80 100 120 140
Deflection (mm)
Arch-Tie Connection
The arch-tie connection of the median arch is considered the most
critical connection based on the analysis results presented earlier.
Thus, a detailed finite-element (FE) model of this connection was
developed using structural analysis program ANSYS v.11.0 to de-
termine the principle stresses at the weld locations. The loads ap-
plied to this connection were obtained from the 3D SAP model and
factored according to the 2007 AASHTO LRFD (AASHTO 2007).
These loads include dead load, posttensioning force, superimposed
dead load, and live loads. Fig. 8 shows the principle stresses at the
connection and welding locations. Based on the presented stress Fig. 8. FE model for arch-tie connection
contours, it was concluded that the average principle stresses be-
cause of factored loads at the weld location are less than 138 MPa
(20 ksi). About 75% of these stresses is a result of dead load and Lateral Stability
prestressing force, while only 25% results from transient loads.
Because fatigue load is only one truck without lane load and with Lateral stability analysis was performed to confirm the stability of
a 15% impact factor, the fatigue limit state was found to be uncriti- the three arches of the Columbus viaduct in the transverse direction
cal. Higher stress values up to 276 MPa (40 ksi) occur at very few when subjected to wind loads. Nonlinear static analysis (because
locations (i.e., the intersection of the tube and box) because of of geometric nonlinearity) was applied to the 3D SAP model to
stress concentrations. However, these stresses are still below the account for P-delta effects on the arch elements. Wind load was
ultimate strength of the steel section and the weld used, i.e., F y ¼ calculated according to AASHTO LRFD Section 3.8.1.2
317 MPa (46 ksi). (AASHTO 2007), which is 2:39 kN=m2 (0.50 ksf) in the windward
500
400
300
200
100
0
0 1 2 3 4 5
Downloaded from ascelibrary.org by University Of Ulster AT on 07/10/15. Copyright ASCE. For personal use only; all rights reserved.
Construction Challenges
of eccentrically loaded concrete-filled steel tubular columns.” J. Struct. Uy, B. (1998). “Local and post-local buckling of concrete filled steel
Eng., 130(2), 203–212. welded box columns.” J. Constr. Steel Res., 47(1–2), 47–72.