Вы находитесь на странице: 1из 13

Doc Number: HR-WTS01

Version: 1
Weekly Time Sheet Last Modified: 26.08.13
Department Internal

Name: V.VENGADASAMY Month: DECEMBER – 2018 Date: 25/11/2018 to 01/12/2018


U. ANAND BABU
Customer: M/s TATA INDIA LTD Site/Ref: 400/220 kV SUBSTATION, Jaongaon,Telungana.

Out Normal Over


S.No Date In time Job details
time hours Time

1. 25-11-18 - - - - -

2. 26-11-18 - - - - -

3. 27-11-18 - - - - -

4. 28-11-18 09:00 17:30 - -

5. 29-11-18 09:00 17:30 - -

6. 30-11-18 09:00 17:30 - -

Travel from Chennai to Warngal


7. 01-12-18 09:00 17:30 - -

For Period ___________ to ___________ Total normal hours charged: __________ Hours

For Period ___________ to ___________ Total over time hours charged: __________ Hours

ENGINEER SIGNATURE CUSTOMER APPROVAL

H.O : # 6/317, (New # 67), J.J Nagar, Mugappair East, Chennai – 600 037
Tel: +91 (044) 2656 0997
Mail: pdcs@vsnl.com / k.rangasamy@pdcsindia.com
Doc Number: HR-WTS01
Version: 1
Weekly Time Sheet Last Modified: 26.08.13
Department Internal

Name: V.VENGADASAMY Month: DECEMBER – 2018 Date: 02/12/2018 to 08/12/2018


U. ANAND BABU
Customer: M/s TATA INDIA LTD Site/Ref400/220 kV SUBSTATION, Jangaon,Telungana.

Out Normal Over


S.No Date In time Job details
time hours Time
Sunday
1. 02-12-18 - - - -

Bay 4-20 89A, 4-22 89L Isolator’s IR Testings has


2. 03-12-18 09:00 17:30 - - been done.

Bay 4-19 89L,4-19 89A,4-20 89A Iso’s IR Testings has


3. 04-12-18 09:00 17:30 - - been done

Bay (4-20 89A,4-23 89A, 4-23 89B,4-22 89L&89A, 4-


4. 05-12-18 09:00 17:30 - - 19 89L,4-19 89A) Iso’s IR Testing & Dia- 7 Panel Bus
wiring has been completed.
Bay 4-20 89B,4-21 89A,4-21 89,4-21 89T Iso R-Phase
5. 06-12-18 09:00 17:30 - - IR Testings and
Dia-8 Bus wiring has been completed.
Holyday (Telungana Election)
6. 07-12-18 09:00 17:30 - -

Bay 4-21 89T,4-24 89A,4-21 89T,4-24 89 BPI’s IR


7. 08-12-18 09:00 17:30 - - Testings has been done

For Period ___________ to ___________ Total normal hours charged: __________ Hours

For Period ___________ to ___________ Total over time hours charged: __________ Hours

ENGINEER SIGNATURE CUSTOMER APPROVAL

H.O : # 6/317, (New # 67), J.J Nagar, Mugappair East, Chennai – 600 037
Tel: +91 (044) 2656 0997
Mail: pdcs@vsnl.com / k.rangasamy@pdcsindia.com
Doc Number: HR-WTS01
Version: 1
Weekly Time Sheet Last Modified: 26.08.13
Department Internal

Name: V.VENGADASAMY Month: DECEMBER – 2018 Date: 09/12/2018 to 15/12/2018


U. ANAND BABU
Customer Customer: M/s TATA INDIA LTD Site/Ref400/220 kV SUBSTATION, Jaongaon,Telungana.

Out Normal Over


S.No Date In time Job details
time hours Time
Bay 4-23 89B,4-19 89L BPI’s IR Testings has been
1. 09-12-18 09:00 17:30 done and more 4-20 Tie Panel ferrules wiring has been
checked.
Bay 4-19 89A ,4-22 89,4-19 89,Bus Iso-1, Bus Iso-
2. 10-12-18 09:00 17:30 - - 2,and 4-22 BPI Bus side IR Testing has been done, Dia
7 Panel scheme checking started..
Bay 4-19LA,4-22 LA,4-21 LA & 4-21 89A P2 CT Side ,
3. 11-12-18 09:00 17:30 - - 4-19 89A CT P2 Side BPI’s IR Testing has been
completed.
Bay 4-20 89A CT P1 Side,4-19 Bus 1 side 89,4-19 89
male side bus-1, 4-19 89L female side ,4-22 89L male
4. 12-12-18 09:00 17:30 - - side,4-22 89L female side,4-22 89 female side,4-22 89
CT P2 side,4-23 89A male side BPI’s IR Testings and
4-20 BCT TAN DELTA Testing has been done.

5. 13-12-18 09:00 17:30 - - Bus 1&2 side BPI’s IR Testings has been done.

6. 14-12-18 09:00 17:30 - - Rain rained did not do anything.

Bay 4-19 CT,4-20 ACT’s IR Testings 4-19 CVT B-


Phase,4-22 CVT Y&B Phase Tan Delta Testing and
7. 15-12-18 09:00 17:30 - - more 4-19 CT R & B Phase CT Normal Testing has
been done.

For Period ___________ to ___________ Total normal hours charged: __________ Hours

For Period ___________ to ___________ Total over time hours charged: __________ Hours

ENGINEER SIGNATURE CUSTOMER APPROVAL

H.O : # 6/317, (New # 67), J.J Nagar, Mugappair East, Chennai – 600 037
Tel: +91 (044) 2656 0997
Mail: pdcs@vsnl.com / k.rangasamy@pdcsindia.com
Doc Number: HR-WTS01
Version: 1
Weekly Time Sheet Last Modified: 26.08.13
Department Internal

Name: V.VENGADASAMY Month: DECEMBER– 2018 Date: 16/12/2018 to 22/12/2018


U. ANAND BABU
Customer Customer: M/s TATA INDIA LTD Site/Ref400/220 kV SUBSTATION, Jaongaon,Telungana.

Out Normal Over


S.No Date In time Job details
time hours Time

1. 16-12-18 - - - - Sunday

2. 17-12-18 09:00 17:30 - - Safety Auditing.

Bay 4-20 BCT,4-21 CT’s IR Testing and


3. 18-12-18 09:00 17:30 - -
((( Normal testings has been done.
Bay 4-20 BCT IR Testings and 4-22 BCT ,Bus
1 CVT Y&B 4-19 LA,4-22 LA,4-21 LA Tan
4. 19-12-18 09:00 17:30 - -
Delta and more ((((CT’s Normal testings has
been done.
Bay 4-23 CT’s IR Testing CT Normal testing
5. 20-12-18 09:00 17:30 - -
and ISO to E/S Wiring has been checked.
Bay 4-19 CVT,4-22 CVT’s IR and Bus 1 CVT
6. 21-12-18 09:00 17:30 - - R-Phase & Bus 2 CVT’s TanDelta 4-22 CT 4-
23 CT’s Normal testings has been done.
Bay 4-01 LA’s R-Phase IR Testing and 4-05
7. 22-09-18 09:00 17:30 - - ACT,4-05 CT,4-06-R Phase Dan Delta Testing
has been done.

For Period ___________ to ___________ Total normal hours charged: __________ Hours

For Period ___________ to ___________ Total over time hours charged: __________ Hours

ENGINEER SIGNATURE CUSTOMER APPROVAL

H.O : # 6/317, (New # 67), J.J Nagar, Mugappair East, Chennai – 600 037
Tel: +91 (044) 2656 0997
Mail: pdcs@vsnl.com / k.rangasamy@pdcsindia.com
Doc Number: HR-WTS01
Version: 1
Weekly Time Sheet Last Modified: 26.08.13
Department Internal

Name: V.VENGADASAMY Month: DECEMBER – 2018 Date: 23/12/2018 to 29/12/2018


U. ANAND BABU
Customer: M/s TATA INDIA LTD Site/Ref400/220 kV SUBSTATION, Jaongaon,Telungana.

Out Normal Over


S.No Date In time Job details
time hours Time

1. 23-12-18 - - - - Sunday

12 no’s CT Tandelta and 1 set LA Testings has been


2. 24-12-18 09:00 17:30 - - done.

Dia-8 CRP Panel Scheme checking started and Bay


3. 25-12-18 09:00 17:30 - - 401& 404 LA’s Bay 404 CVT Tandelta Testings and
Bay 419 CB Continuty checked.
Bay 404 CVT Tandelta ,402 Isolator IR Testing, Bay
4. 26-12-18 09:00 17:30 - - 422 CB Continuty ,422 bay Line scheme checked and
ACDB Distribution board testings has been started.

5. 27-12-18 09:00 17:30 - - Bay 412 LA & 415 LA TanDelta testing has been done.

In ACDB Distribution Panel Bus Bar CRM & IR,CT’s


IR ,Normal testings ,Breaker IR ,CRM,Timer and
6. 28-12-18 09:00 17:30 - - operations ,Primary injection ,Bay 420 Breaker
interpole continuity checking has been done.

In Main ACDB Panel Busbar CRM ,IR, Scheme and


7. 29-12-18 09:00 17:30 - - interlock operations has been done.

For Period ___________ to ___________ Total normal hours charged: __________ Hours

For Period ___________ to ___________ Total over time hours charged: __________ Hours

ENGINEER SIGNATURE CUSTOMER APPROVAL

H.O : # 6/317, (New # 67), J.J Nagar, Mugappair East, Chennai – 600 037
Tel: +91 (044) 2656 0997
Mail: pdcs@vsnl.com / k.rangasamy@pdcsindia.com
Doc Number: HR-WTS01
Version: 1
Weekly Time Sheet Last Modified: 26.08.13
Department Internal

Name: V.VENGADASAMY Month: DECEMBER – 2018 Date: 01/12/2018 to 31/12/2018


U. ANAND BABU
Customer: M/s TATA INDIA LTD Site/Ref400/220 kV SUBSTATION, Jaongaon,Telungana.

Out Normal Over


S.No Date In time Job details
time hours Time

1. 30-12-18 - - - - Sunday

In Main ACDB Panel Bus Bar CRM & IR,CT’s IR


2. 31-12-18 09:00 17:30 - - ,Normal testings ,Breaker IR ,CRM, Timer and
operations ,Primary injection has been done.

3. - -

4. - -

5. - -

6. - -

7. - -

For Period ___________ to ___________ Total normal hours charged: __________ Hours

For Period ___________ to ___________ Total over time hours charged: __________ Hours

ENGINEER SIGNATURE CUSTOMER APPROVAL

H.O : # 6/317, (New # 67), J.J Nagar, Mugappair East, Chennai – 600 037
Tel: +91 (044) 2656 0997
Mail: pdcs@vsnl.com / k.rangasamy@pdcsindia.com
Doc Number: HR-WTS01
Version: 1
Weekly Time Sheet Last Modified: 26.08.13
Department Internal

Name: V.VENGADASAMY Month: SEPTEMBER – 2018 Date: 16/09/2018 to 22/09/2018


U. ANAND BABU
Customer: M/s GE T&D INDIA LTD Site/Ref400/220 kV SUBSTATION, Jaongaon,Telungana.

Out Normal Over


S.No Date In time Job details
time hours Time

1.

2.

3.

4.

5.

6.

7.

For Period ___________ to ___________ Total normal hours charged: __________ Hours

For Period ___________ to ___________ Total over time hours charged: __________ Hours

ENGINEER SIGNATURE CUSTOMER APPROVAL

H.O : # 6/317, (New # 67), J.J Nagar, Mugappair East, Chennai – 600 037
Tel: +91 (044) 2656 0997
Mail: pdcs@vsnl.com / k.rangasamy@pdcsindia.com
Doc Number: HR-WTS01
Version: 1
Weekly Time Sheet Last Modified: 26.08.13
Department Internal

Name: V.VENGADASAMY Month: SEPTEMBER – 2018 Date: 23/09/2018 to 29/09/2018


U. ANAND BABU
Customer: M/s GE T&D INDIA LTD Site/Ref400/220 kV SUBSTATION, Jaongaon,Telungana.

Out Normal Over


S.No Date In time Job details
time hours Time

1.

2.

3.

4.

5.

6.

7.

For Period ___________ to ___________ Total normal hours charged: __________ Hours

For Period ___________ to ___________ Total over time hours charged: __________ Hours

ENGINEER SIGNATURE CUSTOMER APPROVAL

Name: V.VENGADASAMY Month: OCTOBER – 2018 Date: 30/09/2018 to 06/10/2018

H.O : # 6/317, (New # 67), J.J Nagar, Mugappair East, Chennai – 600 037
Tel: +91 (044) 2656 0997
Mail: pdcs@vsnl.com / k.rangasamy@pdcsindia.com
Doc Number: HR-WTS01
Version: 1
Weekly Time Sheet Last Modified: 26.08.13
Department Internal

U. ANAND BABU
Customer: M/s GE T&D INDIA LTD Site/Ref400/220 kV SUBSTATION, Jaongaon,Telungana.

Out Normal Over


S.No Date In time Job details
time hours Time

1.

2.

3.

4.

5.

6.

7.

For Period ___________ to ___________ Total normal hours charged: __________ Hours

For Period ___________ to ___________ Total over time hours charged: __________ Hours

ENGINEER SIGNATURE CUSTOMER APPROVAL

Name: V.VENGADASAMY Month: OCTOBER – 2018 Date: 07/10/2018 to 13/10/2018

H.O : # 6/317, (New # 67), J.J Nagar, Mugappair East, Chennai – 600 037
Tel: +91 (044) 2656 0997
Mail: pdcs@vsnl.com / k.rangasamy@pdcsindia.com
Doc Number: HR-WTS01
Version: 1
Weekly Time Sheet Last Modified: 26.08.13
Department Internal

U. ANAND BABU
Customer: M/s GE T&D INDIA LTD Site/Ref400/220 kV SUBSTATION, Jaongaon,Telungana.

Out Normal Over


S.No Date In time Job details
time hours Time

1.

2.

3.

4.

5.

6.

7.

For Period ___________ to ___________ Total normal hours charged: __________ Hours

For Period ___________ to ___________ Total over time hours charged: __________ Hours

ENGINEER SIGNATURE CUSTOMER APPROVAL

Name: V.VENGADASAMY Month: OCTOBER – 2018 Date: 14/10/2018 to 20/10/2018

H.O : # 6/317, (New # 67), J.J Nagar, Mugappair East, Chennai – 600 037
Tel: +91 (044) 2656 0997
Mail: pdcs@vsnl.com / k.rangasamy@pdcsindia.com
Doc Number: HR-WTS01
Version: 1
Weekly Time Sheet Last Modified: 26.08.13
Department Internal

U. ANAND BABU
Customer: M/s GE T&D INDIA LTD Site/Ref400/220 kV SUBSTATION, Jaongaon,Telungana.

Out Normal Over


S.No Date In time Job details
time hours Time

1.

2.

3.

4.

5.

6.

7.

For Period ___________ to ___________ Total normal hours charged: __________ Hours

For Period ___________ to ___________ Total over time hours charged: __________ Hours

ENGINEER SIGNATURE CUSTOMER APPROVAL

Name: V.VENGADASAMY Month: OCTOBER – 2018 Date: 21/10/2018 to 27/10/2018

H.O : # 6/317, (New # 67), J.J Nagar, Mugappair East, Chennai – 600 037
Tel: +91 (044) 2656 0997
Mail: pdcs@vsnl.com / k.rangasamy@pdcsindia.com
Doc Number: HR-WTS01
Version: 1
Weekly Time Sheet Last Modified: 26.08.13
Department Internal

U. ANAND BABU
Customer: M/s GE T&D INDIA LTD Site/Ref400/220 kV SUBSTATION, Jaongaon,Telungana.

Out Normal Over


S.No Date In time Job details
time hours Time

1.

2.

3.

4.

5.

6.

7.

For Period ___________ to ___________ Total normal hours charged: __________ Hours

For Period ___________ to ___________ Total over time hours charged: __________ Hours

ENGINEER SIGNATURE CUSTOMER APPROVAL

Name: V.VENGADASAMY Month: OCTOBER – 2018 Date: 28/10/2018 to 03/11/2018

H.O : # 6/317, (New # 67), J.J Nagar, Mugappair East, Chennai – 600 037
Tel: +91 (044) 2656 0997
Mail: pdcs@vsnl.com / k.rangasamy@pdcsindia.com
Doc Number: HR-WTS01
Version: 1
Weekly Time Sheet Last Modified: 26.08.13
Department Internal

U. ANAND BABU
Customer: M/s GE T&D INDIA LTD Site/Ref400/220 kV SUBSTATION, Jaongaon,Telungana.

Out Normal Over


S.No Date In time Job details
time hours Time

1.

2.

3.

4.

5.

6.

7.

For Period ___________ to ___________ Total normal hours charged: __________ Hours

For Period ___________ to ___________ Total over time hours charged: __________ Hours

ENGINEER SIGNATURE CUSTOMER APPROVAL

H.O : # 6/317, (New # 67), J.J Nagar, Mugappair East, Chennai – 600 037
Tel: +91 (044) 2656 0997
Mail: pdcs@vsnl.com / k.rangasamy@pdcsindia.com

Вам также может понравиться