LOADING CHUTES FOR MAERSK TERMINAL IN PERU

Cimbria received an enquiry for loading chutes from one of our loading chutes was made up of four A650F/10s in AISI 304 with
Chinese dealers. The project company behind the enquiry was integrated 18 m2 filter and dual-purpose outlet (loading into
Nantong  Rainbow Heavy Machineries  Co. Ltd. (RHM China), trucks and loading onto conveyor). The chutes are approved
which explained that the project was being carried out on for handling food according to EU directive 1935/2004 and
behalf of Maersk for a terminal at the Port of Callao, Peru. are approved for ATEX zone 20/22. In addition, there are two
N500F/7s in AISI 304 with integrated 18 m2 filter for loading
The loading chutes were to be used for loading fertilizer into into open trucks. These chutes are also approved for ATEX
open trucks at a capacity of 800 t/h, and for loading grain zone 20/22. All the filters are supplied with an explosion relief
into open trucks and onto a band conveyor at a capacity of system as required by the customer.
915 t/h. The chutes were due to be installed under a mobile
hopper system used when unloading ships. The specifications The loading chutes were assembled, tested and readied
of the chutes were very strict, containing demands for all for shipment. Uniquely, the chutes were first shipped to
stainless steel execution, ATEX rating, and a rather complex China, where they were unpacked and pre-mounted on their
control/safety system which included a plug-in facility due to respective hoppers. After undergoing a functional (dry) test,
the mobile nature of the hoppers. the loading chutes were re-packed and shipped to the site in
Peru. After installation at the terminal, Cimbria was contacted
Following the initial enquiry, a process of clarification began, for commissioning of the loading chutes, which took place in
whereby the exact execution of the loading chutes was June 2015.
specified and the final contract was signed and stamped.
The final configuration of
the Moduflex