• Dugar HEP (236 MW)

Dugar Hydro Electric Project has been contemplated as a run of a river development
located in Pangi Valley near village Killar in Distt. Chamba of Himachal Pradesh. The
Project is situated between EL +/- 2105 m to EL +/- 2015 m. The Project comprises
construction of a diversion Barrage located downstream of the confluence of Mahal
Nallah with the river Chenab at EL +/- 2085 m with FRL at 2105 m, a 8.5 km long
head race tunnel to carry a design discharge of 346.15 cumecs and a power house
at EL +/- 2015 m housing 4 units of 59 MW to generate about 910 Gwh of energy in
90% dependable year.

• Purthi HEP (300 MW)


The proposed scheme has been conceived as an extension of Reoli HEP by utilizing
+/- cumecs discharge (design discharge of Reoli HEP) available at tail race outfall of
Reoli HEP. The proposal envisages the diversion of tail waters at Reoli HEP at tail
race outfall on the right bank at EL +/- 2333 m near Goma Kund, crossing the
Chenab river through aqueduct and then conveying water through +/- 11.3 km long
head race tunnel, surge shaft and a +/- 250 m long single pressure shaft to power
house proposed at EL+/- 2220 m on the left bank of Chenab river at about 500 m
d/s of Mujar Nallah confluence with river Chenab, D/s of village Purthi, utilizing a
gross head of +/-113m for generating 300 MW of power. The project shall generate
about 1190 Gwh of energy in 90% dependable year.

• Rashil HEP (130 MW)


Rashil Hydro Electric Project has been contemplated as a run of the river scheme
which is a downstream development of Tandi Hydro Electric Project, situated
between EL +/- 2770 m and +/- 2688m in Distt. Lahaul & Spiti of Himachal Pradesh.
The Project comprises construction of a diversion barrage located on Chenab River
near village Jabrang/Rashil at river bed EL +/- 2688 m on the left bank opposite
village Thirot. The Project is estimated to generate 541 Gwh of annual energy by
utilizing a gross head of 82m.

• Tandi HEP (104 MW)


Tandi Hydro Electric Project has been contemplated as a run of the river
development utilizing the water of river Chenab in Distt. Lahaul and Spiti of
Himachal Pradesh. This Project is situated between El +/- 2849m and FRL at 2849
m. The Project comprises of a diversion barrage just downstream of Village Tholung
at river bed El +/-2835m, a 7.4 km long head race tunnel and a power house
housing three units of 34.66 MW to generate 430 Gwh of annual energy by utilizing
a gross head of about 69 m.