MAPPEDU PRECAST FACTORY SITE BASEMENT LEVEL WORKING SCHEDULE


Sand filling & Back filling &
S.no Day day Excavation work P.c.c work Footing work Pedestal Consolidation Plinth Beam
1 1 11/04/19 Survey Marking
2 2 12/04/19 25% - - - - -
3 3 13/04/19 75% 10% - - - -
4 4 14/04/19 100% 50% - - - -
5 5 15/04/19 80% - - - -
6 7 16/04/19 100% - - - -
8 8 17/04/19 - - 30% - - -
9 9 18/04/19 - - - - - -
10 10 19/04/19 - - 70% 10% - -
11 11 20/04/19 - - 90% 40% 10% -
12 12 21/04/19 - - 100% 70% 40% -
13 13 22/04/19 - - 100% 70% 10%
14 14 23/04/19 - - 100% 50%
15 15 24/04/19 - - 80%
16 16 25/04/19 - - 100%
17 17 26/04/19 - -
18 18 27/04/19 - -
19 19 28/04/19 - -
20 20 29/04/19 - -
- -

Page 1
Sheet1

DULE

Basment column Earth Filling consolidation

- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
10% - -
50% 10%
80% 50%
100% 80% 30%
100% 60%
80%
100%