Additional Information:
• Feel free to forward this bulletin to people who might be interested.
HIGHLIGHTS ۩
IMPORTANT: before any eNodeB SW migration, please follow the secure upgrade process by initiating an initialization and
GO/NoGO meeting to ensure appropriate documentation and loads will be used
New KPIs included in Post Upgrade KPIs Report template and MOPs
- The global KPIs for upgrade must be provided 1 week after Post-upgrade monitoring phase.
- These KPIs will be filled by Upgrade Team and the Report sent within 2 weeks after committed Date for end of Operation.
18/05/2017 1/7 Nokia Internal Use © Nokia 2016
eNodeB lastest C5 (for Global Market) :
- LR16.2 FDD
Macro (Legacy BBUv1): LR16.2 CL2.2.1 (9412 ENB_LR1602_D0200_E00470 ) on 17W19.4
- LR16.1 FDD
Macro (Legacy BBUv1): LR16.1 CL1.2.6 (9412 ENB_LR1601_D0280_E01615) on 17W06.1
- LR16.1 TDD
Macro Legacy: LR16.1 CL2.2 (ENB_LR1601_D0302_E0748) on 17W11.3
Macro SoC: LR16.1 MNCL2.2 (ENB_LR1601_D0305_E0748) on 17W11.3
- LR15.1 FDD
Macro (Legacy BBUv1): LR15.1 CL3.6.3 (9412 ENB_LR1501_D0420_E01344) on 17W12.4
Macro (SoC/BBUv2): LR15.1 CL3.6 (9926 ENB_LR1501_D0304_E01312) on 16W38.5
Metro: LR15.1 CL3.3.0.4.4 ENB_LR1501_D0381_E01064) on 16W42.2
- LR15.1 TDD
Macro Legacy: LR15.1 MNCL1.2 (ENB_LR1501_D0302_E01416) on 17W10.3
Macro SoC: LR15.1 MNCL1.2 (ENB_LR1501_D0305_E01416) on 17W10.3
GENERAL TOPICS ۩
GDR technical bulletin for 4G eNodeB Secure Software Upgrade is available via OLCS alert “16-0032”
- If you don’t want to receive notification anymore, you need to remove your mail by yourself from the mailing list
This Mailing list should only be used for initialization and upgrade report emails.
Note: Do not use it for pre-checks, Go/No Go meetings, and any other email exchange.
- BEFORE each planned eNB SW upgrade activity, an initialization upgrade E-mail MUST be sent.
- AFTER each eNB SW upgrade, an upgrade report E-mail MUST be sent to the distribution list.
- WITHIN 2 WEEKS global KPIs post-upgrade report must be provided 1 week after Post-upgrade monitoring phase
eNodeB Secure Upgrade MOP : describes the process to manage the eNB upgrade https://mdms-ll.app.alcatel-
lucent.com/livelink/livelink.exe?func=ll&objId=68547237&objAction=browse&viewType=1
LR16.1
- LR16.1 FDD
Macro (Legacy BBUv1): LR16.1 CL1.2.6 (9412 ENB_LR1601_D0280_E01615) on 17W06.1
- LR16.1 TDD
Macro Legacy: LR16.1 CL2.2 (ENB_LR1601_D0302_E0748) on 17W11.3
Macro SoC: LR16.1 MNCL2.2 (ENB_LR1601_D0305_E0748) on 17W11.3
LR15.1
- LR15.1 FDD
Macro (Legacy BBUv1): LR15.1 CL3.6.3 (9412 ENB_LR1501_D0420_E01344) on 17W12.4
Macro (SoC/BBUv2): LR15.1 CL3.6 (9926 ENB_LR1501_D0304_E01312) on 16W38.5
Metro: LR15.1 CL3.3.0.4.4 ENB_LR1501_D0381_E01064) on 16W42.2
- LR15.1 TDD
Macro Legacy: LR15.1 MNCL1.2 (ENB_LR1501_D0302_E01416) on 17W10.3
Macro SoC: LR15.1 MNCL1.2 (ENB_LR1501_D0305_E01416) on 17W10.3
Check that all the O&M, tools equipments in front of are in lineup with the release.
- LR16.2.L SAM : 14.0 R5 P11 WPS : 6.1.9.1 NPO : 82D31 + EP1 NEM : LR16.2 D1.14
- LR16.1.L SAM : 14.0 R3 P1 WPS : 6.0.14 NPO : 81D18a + EP1 NEM : LR16.1 D1.22
- LR15.1.L SAM : 13.0 R5 P10 WPS : 5.0.15 NPO : 72D23 + EP3 NEM : LR15.1 D1.24
UPGRADE PATHS ۩
Official supported Macro & Metro products upgrade paths to LR16.1L:
Planned:
LR14.3 = LR14.3 FDD Legacy (BBU V1) -> End of Support planned eof June 2017
LR14.3s = LR14.3 FDD SOC (BBU V2) -> End of Support planned eof June 2017
TLR14.3 = LR14.3 TDD Legacy (BBU V1) -> End of Support planned eof June 2017
TLR14.3s = LR14.3 TDD SOC (BBU V2) -> End of Support planned eof June 2017
LR15.1 = LR15.1 FDD Legacy (BBU V1) -> End of Support planned eof Oct 2017
LR15.1s = LR15.1 FDD SOC (BBU V2) -> End of Support planned eof Oct 2017
TLR15.1 = LR15.1 TDD Legacy (BBU V1) -> End of Support planned eof June 2018
TLR15.1s = LR15.1 TDD SOC (BBU V2) -> End of Support planned eof June 2018
LR16.1 = LR16.1 FDD Legacy (BBU V1) -> End of Support planned eof June 2017
LR16.1s = LR16.1 FDD SOC (BBU V2) -> End of Support planned eof June 2017
TLR16.1 = LR16.1 TDD Legacy (BBU V1) -> End of Support planned eof Dec 2021
TLR16.1s = LR16.1 TDD SOC (BBU V2) -> End of Support planned eof Dec 2021
LR16.1 = LR16.1 FDD Legacy (BBU V1) -> End of Support planned eof June 2017
LR16.1s = LR16.1 FDD SOC (BBU V2) -> End of Support planned eof June 2017
TLR16.1 = LR16.1 TDD Legacy (BBU V1) -> End of Support planned eof Dec 2021
TLR16.1s = LR16.1 TDD SOC (BBU V2) -> End of Support planned eof Dec 2021
_ALERTS ۩
The onsite prime is responsible to check OLCS alerts website to ensure to have the latest bulletins/alerts available.
Onsite prime will check which of the listed bulletins inside the upgrade bulletin is applicable to or not (Crosscheck with Release
Letter needed). To receive OLCS alerts, please register at http://alerts.web.alcatel-lucent.com/alerts/?HomePage
17-0377 LR16.2.L No Yes LR16.2 After upgrading eNodeBs in the market to LR16.2L,CL1.1.6, about 0.3% cells have experienced KPI degrad
PH3
17-0374 LR16.2.L No Yes LR16.2 This alert applies to bCEM cards on LR16.2 which are unreachable or in rolling reboot.
Whenever a bCEM goes through a reset , the chance that it won't come into service is higher after software
17-0355 LR16.2.L No Yes N/A After the recent LR16.2 CL1.1.6 (ENB_LR1602_D0100_E00376) upgrade on the eNodeBs, the SAM GUI vi
and minElectricalTilt instead of the actual minimum and maximum electrical tilt values that is supposed to be
17-0325 LR15.1L, No Yes LR16.2.2, Description LR16.2 - After applying LR16.2 onone site, one RRH became Disabled Failed with IK4201029 S
LR16.1.L CL3
17-0282 LR16.1L, No Yes LR16.2.2 A 3dB increase in Cell Tx Power Max, counter 13704, is observed on some AWS and PCS cells when the e
LR16.2.L
17-0224 LR16.1L, Yes Yes LR16.2- A SW change in LR16.1 is causing repeated deletion/creation of X2link when all its associated neighbors ar
LR16.2.L CL2.2
17-0195 LR16.1.L Yes Yes LR15.1 eNodeBs in LR16.1 that cannot access the NTP server will reset every six hours.
17-0213 LR15.1.L No Yes LR15.1 A small percentage of WCS-RRH4x25-B30 (3JR41325AA) RRHs, whose AISG scan is enabled due to the p
CL3.6.3
Upgrade Procedure
eNodeB Macro and Metro product LR14.3.L/LR15.1.L to LR16.1.L Software Upgrade Procedure
https://infoproducts.alcatel-lucent.com/aces/cgi-bin/dbaccessfilename.cgi/9YZ068460118RJZZA_V1_LTE%20eNodeB%20Macro%20-
%20LR14.3.L%20and%20LR15.1.L%20to%20LR16.1.L%20Software%20Upgrade%20Procedure%20-%20LR16.1.L.pdf
LR15.1.L and LR16.1.L to LR16.2.L/LR16.2.2.L Software Upgrade Procedure
https://infoproducts.alcatel-lucent.com/aces/cgi-bin/dbaccessfilename.cgi/9YZ071380118RJZZA_V1_LTE%20eNodeB%20Macro%20-
%20LR15.1.L%20and%20LR16.1.L%20to%20LR16.2.LLR16.2.2.L%20Software%20Upgrade%20Procedure%20-%20LR16.2.L.pdf
For all Upgrade Procedure: Select your Product: 9412 eNodeB (Evolved Node B)
Release: LR16.x.L; Categorie: Upgrade
https://infoproducts.alcatel-lucent.com/aces/cgi-bin/au_doc_list.pl
LTE parameter evolution-LR14.x to LR15.x document:
https://wcdma-ll.app.alcatel-lucent.com/livelink/livelink.exe?func=ll&objId=67663512&objAction=browse&viewType=1
LR15.x.L Migration-QoS & Stability Monitoring Process
https://wcdma-ll.app.alcatel-lucent.com/livelink/livelink.exe?func=ll&objId=68469223&objAction=browse&viewType=1
KPI Investigation Methodology Tools Help LR14.3L
https://mdms-ll.app.alcatel-lucent.com/livelink/livelink.exe?func=ll&objId=68362389&objAction=browse&viewType=1
eNodeB Golden Parameter List (GPL) available from :
http://mobility.web.alcatel-lucent.com/~datadef/lte/enb_gpl/
Once GOLF request is validated, you will be allowed to download the SW on the following OLCS (ALED) web portal:
https://support.alcatel-lucent.com/portal/olcsHome.do
Go through the authentication. On the right side of the page, select My Products (in My support part).
Select your product (9412 eNodeB...)
Select “Downloads: Electronic Delivery” (in Documentation and Downloads part).
Select the item that you wish to download.