MECHANICAL – HVAC SERVICES

PROJECT:
Trade No.

QA /QC CHECKLIST FOR: Mechanical – DUCTWORK: ACCESSORIES


(Specify Trade / Description).

Location of Inspection: Date:

1. Post Award:
a. Shop Drawings: b. Submittals (Samples):

c. Mock Up: d. Location of Mock Up:

2. Fabrication Inspection (where applicable):


a. Fabrication (Fill in where applicable):

Item Acceptance Criteria Findings A/N*

DIFFUSERS,
REGISTERS & GRILLES

FIRE DAMPERS
VOLUME CONTROL
DAMPERS
NON RETURN
DAMPERS
DUCT ACCESS DOOR
PITOT TUBE OPENINGS
ADJUSTABLE
SPLITTER DAMPERS
TURNING VANES
FLEXIBLE DUCTS
VAV BOXES
DUCT

Page 1 of 4
MECHANICAL – HVAC SERVICES

Item Acceptance Criteria Findings A/N*

* A = Approve; N = Non Compliance (Corrective Action Required)

b. Test (where applicable):


Type of Test
Acceptance Criteria Findings** A/N*

*
** A = Approve; N = Non Compliance (Corrective Action Required)
Attach Test Report where applicable
c. Delivery:
Delivery Order
(Specify Equipment/Material Delivered)
Delivery
Handling / Storage Findings
Date

Page 2 of 4
MECHANICAL – HVAC SERVICES
3. Installation:
a. Work Statement: b. Date Submitted:
** Fill in Where Applicable

Item Acceptance Criteria** Findings** A/N*


DIFFUSERS, REGISTERS &
GRILLES

FIRE DAMPERS

Connection to Duct

ACCESS DOORS / OPENINGS

VCD, NRD, MVCD, VAV

PITOT TUBE OPENINGS

FLEXIBLE DUCTS

CONDENSATE DRAIN PIPES

* A = Approve; N = Non Compliance (Corrective Action Required)

Page 3 of 4
MECHANICAL – HVAC SERVICES
4. Post Installation:
Item Acceptance Criteria** Findings** A/N*
Minor damage during Installation
Leveling
Visual
Protection

* A = Approve; N = Non Compliance (Corrective Action Required)

5. General:
Item Site Observations General Comments AR / Date

Inspected By:

GC QAQC: ______________________ ______________________ ______________________


Name Signature Date

QAQC: ______________________ ______________________ ______________________


Name Signature Date

Page 4 of 4