Course
outline
Week 6 Assignment 6
The due date for submitting this assignment has passed.
How to access As per our records you have not submitted this Due on 2018-09-12, 23:59 IST.
the portal assignment.

Week 1 1) 1 point

Week 2

Week 3

Week 4

Week 5

Week 6

Lecture 27 :
Quantification
of Basic Events
for
Non-repairable
Components

Lecture 28 :
Quantification
of Basic Events
- Hazard Rate

Lecture 29 :
Quantification
of Basic Events
- Exponential
Distribution

Lecture 30 :
Quantification
of Basic Events
- Weibull The reliability and failure density of the equipment at time (t) = 6 months are
Distribution
i) 0.875, 0.833
Quiz : Week 6
Assignment 6 © 2014ii)NPTEL
0.125,- 0.075
Privacy & Terms - Honor Code - FAQs -
A project of
Feedback for In association with
iii) 0.075, 0.075
Week 6
iv) 0.6, 0.833
Week 7
No, the answer is incorrect. Funded by
Score: 0

1 of 4 Friday 09 November 2018 09:11 AM


Industrial Safety Engineering - - Unit 7 - Week 6 https://onlinecourses.nptel.ac.in/noc18_mg42/un...

Accepted Answers:
Powered by
Week 8
ii) 0.125, 0.075

Week 9 2) The unreliability and failure rate of the equipment at time (t) = 7 months are 1 point

Week 10 i) 0.05, 0.5

Week 11 ii) 0.95, 0.5

iii) 0.025, 0.075


Week 12
iv) 0.5, 0.5
Download
No, the answer is incorrect.
Videos
Score: 0

Assignment Accepted Answers:


Solution ii) 0.95, 0.5

3) Which of the following regions of the “bath tub curve” is represented by the exponential 1 point
failure rate?

i) Burn-in region

ii) wear-out region

iii) useful life region

iv) all of them

No, the answer is incorrect.


Score: 0
Accepted Answers:
iii) useful life region

4) Question 4 to 6 are based on the following description. 1 point


A device has a constant failure rate of λ = 10−5 failures per hour.

What is its reliability for an operating period of 1000 hour?

−3
i) 9.95 × 10

ii) 0.99

iii) 9.9 × 10−6

−5
iv)10

No, the answer is incorrect.


Score: 0
Accepted Answers:
ii) 0.99

5) If there are 1000 such devices, how many will fail in 1000 hour? 1 point

i) 1990

ii) 1000

iii) 990

iv) 10

No, the answer is incorrect.


Score: 0
Accepted Answers:

2 of 4 Friday 09 November 2018 09:11 AM


Industrial Safety Engineering - - Unit 7 - Week 6 https://onlinecourses.nptel.ac.in/noc18_mg42/un...

iv) 10

6) What is the reliability for an operating time equal to MTTF? 1 point

i) 2.72

ii) 7.39

iii) 0.36

iv) none of the above

No, the answer is incorrect.


Score: 0
Accepted Answers:
iii) 0.36

7) Which of the following regions of the “bath tub curve” are represented by Weibull failure 1 point
rate?

i) Burn-in region

ii) wear-out region

iii) useful life region

iv) all of them

No, the answer is incorrect.


Score: 0
Accepted Answers:
iv) all of them

8) Question 8 to 10 are based on the following description: 1 point


The random variable time to failure (TTF) follows Weibull distribution with scale and shape parameters
η=1.2 and β=0.5, respectively.

The mean time to failure (MTTF) of that random variable IS

i) 2.4

ii) 1.67

iii) 1.2

iv) None of the above

No, the answer is incorrect.


Score: 0
Accepted Answers:
ii) 1.67

9) The reliability and failure density at time (t) = 3 months are 1 point

i) 0.15, 0.047

ii) 0.25, 0.012

iii) 0.80, 0.22

iv) 0.95, 0.25

No, the answer is incorrect.


Score: 0
Accepted Answers:
i) 0.15, 0.047

10)The unreliability and failure rate at time (t) = 5 months are 1 point

3 of 4 Friday 09 November 2018 09:11 AM


Industrial Safety Engineering - - Unit 7 - Week 6 https://onlinecourses.nptel.ac.in/noc18_mg42/un...

i) 0.086, 0.245

ii) 0.914, 0.245

iii) 0.914, 0.97

iv) 0.56, 0.786

No, the answer is incorrect.


Score: 0
Accepted Answers:
ii) 0.914, 0.245