“Strategi Revolusioner Pengembangan Lapangan, Teknologi dan Kebijakan Migas Guna

Meningkatkan Ketahanan Energi Dalam Rangka Ketahanan Nasional”

An Advanced QAQC Strategy in Drilling Management to Anticipate


Contractor’s Efficient Survival Mode
Erwindo Tanjung
Premier Oil

Abstract
In survival mode due to low oil price situation, contractor drilling services modified their
personnel qualification, equipment standardization and tighten services leverage in order to
reduce the operational cost to be able to win the tender and keep utilization of the services,
personnel and equipment. The modification sometimes does not consider their existing
standard operation guidelines. The modification impacts significant low performance for their
reliable operation, onshore support, etc. which even could touch high operational risk for
Company. In the past, company normally just received the QAQC report from contractor’s
independent company, and limited only to equipment matters. However, in this recent
condition of the contractor, Company then must re-design and re-concept the mind set of
drilling operation management to prevent non-productive time (NPT) and operational risk.
QAQC is one of the most critical parts on drilling operation management for safe and reliable
operation. QAQC shall cover end to end drilling operation in relation to contractor’s
equipment, procedure, personnel, safety management, logistic, etc. starting from preparation,
transportation until execution and back to their shore base. All impacts related to contractor’s
failure will be company account; therefore QAQC supervision must cover all potential area
failure.
This paper contains a case history happened in the last drilling campaign PHE WMO about
contractor condition to survive which impacting their standard and performance, also PHE
WMO’s advanced strategy on QAQC to mitigate contractor’s condition in order to achieve
safe and reliable operation and the process of communication and placement of the strategy to
the contractor and all stake holders to ensure the smooth implementation. PHE WMO success
cut overall NPT 50% from the last previous campaign with no safety recordable case.

Keywords: Drilling QAQC, Drilling Operation Management

Equipment Problem, on both surface and


1. Introduction
downhole. This is the highest record of
PHE WMO started new drilling campaign in
contractor’s failure in history of the
Q4 2016. Eventhough during the period,
company.
price of oil was low; the campaign must be
continued as the EPCI was already in-placed.
In order to preserve economist drilling
2. Basic Theory
campaign, low cost unit of drilling services
PHE WMO found the overall NPT are
was strategized during tender process. This
mainly related to incompliance of
strategy was supported by contractor’s
contractor’s own QAQC standard and lack of
condition with much less demand/activity.
contractual clauses committment. These
The campaign covered 3 (three) development
condition happened quite massively in
wells and 1 (one) exploration well. During
almost all major contractors/services, and did
execution of the first well, PHE WMO
not happen in the past. PHE WMO suspected
suffered 240 hours NPT (15%), which 173
the condition are driven by tight profit
hours of them were related to Contractor’s
margin of the contractor. In other side, major

IATMI 18-011
1
contractor shall win the bid to keep the personnel, time for interview or come to
business cycle (i.e. preventing releasing an company’s office prior go to the rig site shall
equipment to others business unit, releasing inform clearly to the contractor as the
an experienced personnel), however due to personnel might be still working in other
low demand and PHE WMO’s driven of an operator. Ensuring the right personnel come
economist drilling campaign; the to the office is the critical part, as the
contractors/bidder must compete the personnel is coming directly from others
optimum lowest cost unit in high demand of operator which most of time does not have a
tender participant. PHE WMO then time to read and understand the background
reconstruct immediately the existing of company’s design, downhole condition
company’s QAQC system prior execution of and drilling program overall.
the 2nd well, named Advanced QAQC
Strategy. The advanced QAQC covered
people, plant/equipment and procedure. 4. Case Study and Discussion
Advance QAQC strategy is additional steps
of QAQC steps/proses that covers 3P
3. Methodology (People, Plant & Procedure) on top of
Commonly all equipment and personnel are common/existing QAQC procedure that
inspected in onshore yard before mobilize to already implementing in the company.
rig site. For equipment; prior to mobilize, Following are debrief advance QAQC of
company will receive and review those 3P:
contractor’s QAQC result to ensure to defect 4.1 People
or record from 3rd party independent 4.1.1 Personnel for routine
inspectior. Also for personnel, company shall activities/scopes such as wellhead
accept the SBTC (Safety Behaviour Training & tree, cementer, mud logger,
Competency) of each person prior to DD, mud engineer, etc must be
mobilize them. Following the increasing of consistent same/no change
significant NPT to sub-category of personnel. The contractor shall
equipment failure in the 1st (first) well; the also provide an experienced back
common QAQC practice is not sufficient to up personnel to anticipate any
prevent and not reliable to mitigate emergency call. If any changes is
unnecessary time and risk. Therefore, an proposing for long term period,
advanced QAQC strategy is established. then the proposed person by
Beside receive and review 3rd party contractor must be approved by
inspection document, company QAQC Company with 3 months notice
supervisor shall also visit and witness their period.
internal QAQC process to ensure meeting
4.1.2 For critical job, the personnel
company/manufacture’s guidelines. This
who will operate the equipment
advanced QAQC shall consider end to end
must come to company’s office to
process and coverage all circumstences
present specification of the tools,
operation of equipment, procedure, and
operational limitation, risk and
personnel. This advanced QAQC strategy
mitigation, report of QAQC from
shall be communicated to the contractor,
3rd party independent inspector,
about the objective, scope of the QAQC and
Valid Certificate of Conformity
also the schedule. Close communication and
(COC) and the agreed procedure.
good planning with the contractor, to prevent
The personnel who will go to rig
delay of inspection nor repair if any failure
site shall understood step by step
or any no-test result during the inspection
operating run procedure and risk
and testing of the equipment which may
cause late delivery to the field. About the

IATMI 18-011
2
register/matrix as the result of 4.2.3.1.4 Hydraulic integrity
risk & mitigation assessment. body and seal test
4.2 Plant 4.2.3.1.5 Make up torque
4.2.1 Reinforce implementation of witness
audit PJA (Pre-Job Activity), 4.2.3.1.6 Critical equipment
which part of CHESMS process dimension
to the contractor’s management 4.2.3.1.7 3rd Party
system. Independent
4.2.2 Randomly performing audit inspection report
minimum stock inventory of which covers NDT,
dedicated equipment as per load test and other
contractual. similar test
4.2.3 Lots of equipment stacked in the 4.2.3.2 Second, for critical
contractor’s shelf with no QAQC, equipment (i.e. high risk
no redress and no test yet. operation/scopes, high
However sometimes also NPT track record), on
happened the equipment was top of the first above;
available QAQC but validity was contractor shall also
too old (i.e. 1 (One) year ago). provide monthly
Company found some cases summary of failures
where the contractor does not from all areas of
comply their QAQC standard operation, and shall
from their own company, or even provide contractor’s
manufacture. There are 2 (two) management inspection
threats of advance QAQC policy/plan of the tools.
strategy. 4.3 Procedure
4.2.3.1 First, for non-critical 4.3.1 Additional procedure of QAQC
equipment will have shall be added on top of common
minimum QAQC existing ones. These additional
standards that meet are Pre-Mobilization Stage, Pre-
manufacture guideline Execution Stage and Prior
and reporting Execution Check List. These
requirement, also the QAQC procedures are gate
personnel qualification review stages prior to operate the
shall meets contractual equipment/services.
and pass interview. 4.3.1.1 Pre-Mobilization Stages
Additional of minimum are series of inspection
QAQC standars shall equipment prior to send
include but not limited the equipment to rig
to: site.
4.2.3.1.1 Function test 4.3.1.2 Pre-Execution Stages
mechanical and are series of assesstment
hydraulic system of the personnel
4.2.3.1.2 Function test competency and
electrical and operational procedures.
computerized Most of contractor’s
system operational procedures
4.2.3.1.3 Shear Pin Test are not valid and

IATMI 18-011
3
generic. Specific QAQC strategy shall be divided into major
procedure shall be and non-major services. This is basically to
generated and detail manage the concentration and manning for
specific procedure in optimum QAQC result.
relation to downhole
condition shall be added
4.3.1.3 Prior Execution Check 6. Recommendation
List is performed when - QAQC method shall be treated as a
the equipment and live strategy. The strategy will evolve
personnel are on board. in referring to a volatile operational
The personnel shall do concern.
final check list of the - The concern sometimes is more
equipment referring to related to contractor management (i.e.
contractor’s check list, gross neglicience), or equipment
report the check list to failure, or invalid procedure, etc.
the company - More number qualified QAQC
representatives prior to supervision – More available time
make up/operate the preparation are the ideal condition to
tool. do advance QAQC as comprehensive
Procedure for critical scope/equipment shall as possible, but most of time the ideal
be reviewed, and refreshed with all involved condition is not available, therefore a
parties including with rig site team thru sensitive and proactive decision is
teleconference. It is not enough a pre-spud required to define the focus of QAQC
meeting, several pre-phase meeting shall be strategy.
conducted as well to refresh the discussion.

5. Conclusion
An advanced QAQC strategy was
successfully reduce NPT significantly for
both equipment failure and downhole
problem, as shown in Figure 1. An advanced
QAQC will not just help to reduce
equipment failure, but also helpful to reduce
overall non-productive time as well as
improve safety process of engineering and
operation to optimize productive time.
Advanced QAQC will ask Company
involvement , focus and time to check,
review and agreed on Contractor’s Quality
Assurance Process since beginning of the
contract implementation, preparation until
execution; also Quality Control on both side
Company and Contractor.
Local within Indonesia and Overseas activity
shall be included into Contractor’s database
and shall be utilized by Company to review
statistical lesson and failure.

IATMI 18-011
4