Вы находитесь на странице: 1из 3

Wind power policy

Gujarat
Wind power policy 2013
 Preferential tariff:- Rs. 4.23/KWh
 The WTGs installed during the operative period will eligible for the incentive declared under this
policy for a period of 25 years.
 Wheeling of power to consumption site for captive consumer at 66KV voltage level and above
shall be allowed on payment of transmission charges and transmission losses applicable to
normal open access consumer. Wheeling of power to consumption site below 66 KV voltage
level shall be allowed on payment of transmission charges and transmission and wheeling
losses@10% of the energy fed to the grid. Wheeling for third party sale will be allowed at the
rate applicable for normal open access consumer
 The electricity generated from the WTGs shall be exempted from the payment of electricity
duty and wheeling of wind energy for third party and captive consumption shall be exempted
from cross subsidy surcharge.
 The electricity generated from WTGs may be sold to distribution licensee within the state at
rate of Rs. 4.15/unit of electricity and also distribution licensee may purchase surplus power
from captive consumer after adjustment of energy against consumption at recipient unit at a
rate of 85% of tariff applicable to WTGs.
 Third party sale of electricity from WTG is allowed.
 Metering point shall be at the 66KV pooling substation located at the wind farm site
 All wind power project should submit day ahead scheduled to SLDC but are kept out of the
preview of state ABT mechanism
 The drawl of reactive power shall be charged as per GERC order
 Banking of electricity generated by captive plant is allowed for a period of one month
 The evacuation facility within the range of 100 Km shall be erected by developer at their own
cost and beyond this limit GETCO shall erect the evacuation facilities
Maharashtra
New policy for power generation from non-conventional sources
 Preferential tariff:-
WPD 200-250:- Rs. 5.78/KWh
WPD 250-300:- Rs. 5.05/KWh
WPD 300-400:- Rs. 4.31/KWh
WPD >400 :- Rs. 3.88/KWh

 Private developer will undertake the erection of HV and EHV substation as well as transmission
and distribution lines required for the project
 The evacuation arrangement after commissioning will be transferred to MSECL/MSEDCL
company
 MEDA will reimburse 50% of the approved expenses on the evacuation arrangement to
developer/ promoter from green energy fund
 100% expenditure needed for approach road shall be payable as subsidy from green energy
fund
 Electricity generated from WTAG are exempted from electricity duty ]
 A subsidy of 11% of the total share capital of the project shall be paid green energy fund for
wind power project installed and commission by co-operative institutions
 100% refund of octroi tax/entry tax for equipment of wind power project will be through green
energy fund
Karnataka
Renewable energy policy
 Preferential tariff:- Rs. 3.70/KWh
 Renewable energy development is to be classified as an industry. Land is therefore to be made
available to the developers by the commerce and industries department single window system
 A green energy cess at Rs. 0.05/unit on commercial and industrial consumer to generate Rs. 55
crore annually, out of which Rs. 50 crore will be set aside for renewable energy project financing
and strengthing the evacuation system
 Year wise proposed capacity addition for wind
o 2009-10: 630 MW
o 2010-11: 680 MW
o 2011-12: 530 MW
o 2012-13: 530 MW
o 2013-14: 599 MW
 Provision of single window service for technical consultation, source of finance and project
clearances
 Under this policy it is obligation to sell the electricity generated from the renewable energy
projects commission to the respective geographical ESCOM in which the project is located at the
tariff determined by KERC under a long term power purchase agreement
 Target for wind power capacity addition by 2014 will be 4337MW
 The barren government lands, reserved as per industrial planning for industrial use at declared
renewable energy sites. 10% of such lands will be kept at the disposal at KREDL for developing
the land to set up the renewable energy power projects
 The identified revenue private and forest lands will be developed by KREDL to facilitate setting
up of various renewable energy projects in an efficient manner
 Various statutory clearances that are essential for the development and commissioning of the
renewable energy project will be dealt by the KREDL with the concerned department and
agencies
 10% of lands will be set apart for renewable energy project in all future SEZ to be identified
under industrial policy 2009 and also in the approved SEZ
 Establish renewable energy SEZ under the provision of the industrial policy 2009
 A state level empowered committee with the Chief Secretary Government of Karnataka as
chairman will provide single window clearances for developing the renewable energy source
power plant
 Respective renewable energy project developer will bear the cost of transmission lines from the
project site to the substation as per grid norms
 Wheeling charges @ 5% will be applicable subject to the KERC norms
 Exemption of demand cut to the extent of 50% of the installed capacity assigned for the captive
use purpose will be allowed
 Revised value added tax on various renewable energy equipment and instruments
 Letter of credit to the developer for realizing payment in scheduled period for the renewable
energy power sold to the ESCOM
 To avoid locking of huge capacities the wind power project allotment will be restricted to 59
MW at a given area each time. The government waste land in windy location identified for
industrial use development will be offer to set up wind projects
 The capacity of the earlier commissioned wind turbine which are more than 10 year old will be
considered for augmentation by replacing with efficient higher capacity WTG
Rajasthan
 Preferential tariff:- Rs. 5.73/KWh
 The state will promote setting up of wind power plants for direct sale to DISCOM of Rajasthan in
the tariff determined through competitive bidding process for the year 2013-14 onwards.
o 2013-14: 300 MW
o 2014-15: 400 MW
o 2015-16: 500 MW
 To promote wind power plant of unlimited capacity for capacity for captive use or sale to third
party sale
 Pooling substation shall be developed and maintained by developers
 For creating a proper facility for receiving power at the receiving substation , the developer shall
pay grid connectivity charges
 The power injection beyond the nominal voltage range of 97%-103% may attract reactive power
charges as per the relevant grid code
 Electricity generated from WTG for captive use are exempted from electricity duty
 The government land required for wind power developers at concessional rate of 10% of the
DLC rate
 For setting up of wind power project maximum allotment of land to the developer shall be 5
Hectare/MW
 Open access for third party sale is allowed
Tamil Nadu
 Preferential tariff: Rs. 3.51/KWh
 Wheeling charge is 5% of total wheeled energy
 Banking charge is 5% of energy
 Unutilized banked energy as on 31st March permitted for sale @ 75% of purchase rate to the
distribution company
 The cost of grid integration up to interconnection point shall be borne by the generator but the
work shall be executed by STU/ Distribution licensee. But in case of sale of entire power to the
distribution licensee by any new and renewable resource based generators, the cost of
interfacing line up to interconnection point shall be have to borne only by STU/distribution
licensee
 The tariff determined by the commission in the tariff order shall be applicable for the power
purchase agreement period 20 years

Вам также может понравиться