Вы находитесь на странице: 1из 6

T ECHNICAL A RTICLE

The Estimate Review and


Validation Process of detail and diligence used during the
estimate review cycle will vary both with
the strategic importance, total value, and
purpose of the particular estimate. These
Larry Dysert, CCC, and Bruce G. Elliott, CCC steps can be easily adapted on a fit-for-use
basis. Note that this article is focused on
ABSTRACT: This article focuses on the application of a fit-for-use methodology to the reviewing and validating an estimate—it
process of performing estimate review and validation and covers the contractor’s and does not discuss bidding strategies, which
owner’s points of view. The major steps of the estimate review and estimate validation can involve many other factors and deci-
cycle are examined. How good is your estimate? These are the first words that we, as sions.
estimators, normally hear upon presenting our estimates to our management or to our
customers; and they are the same words we ask when first receiving an estimate pre-
pared by others. We, of course, would like to think that any estimate we prepare is of Estimate Review Cycles
high quality (although not necessarily highly accurate), but how can we be sure that The principal purpose of an estimate
this is the case? This article will focus on a methodology for the process of reviewing review process is to present information
and validating capital cost estimates—either those we prepare ourselves or those pre- about both the estimate and the project in
pared by others. The major steps of the estimate review and validation process will be a way that allows the reviewer to evaluate
examined, and we will discuss the realistic goals of an estimate review process. that the estimate is of sufficient quality to
meet its intended purpose. The estimate
KEY WORDS: Cost, estimating, deliverables, planning, review, risk, and validation review process is usually comprised of a
series of estimate reviews, beginning with
he cost estimate is of paramount cost control of projects. The estimate not internal estimating department reviews,

T importance to the success of a


project. The capital cost of a
proposed project is one of the
key determinants in evaluating the finan-
cial viability and business case of the new
only establishes a project budget, but plays
an equally important role in monitoring
the budget during project execution. It is
the relationship between estimating,
scheduling, and cost control, which is typ-
engineering reviews, project team reviews,
and continuing with reviews by various
levels of management, depending on the
importance of the project.

investment. From the owner’s perspective, ically identified by the term cost engineer-
if the cost estimate is not accurate, the ing, that serves as a driver for successful Estimating Team/Estimating
financial return from the capital invest- and cost-effective projects. Thus, an effec- Department Review
ment may not be realized; and com- tive estimate must not only establish a real- The first review of the estimate
pounding this problem is the fact that istic budget, but must also provide accu- should, of course, be conducted by the
other deserving projects may not have rate information to allow for scheduling, estimating team that prepared the capital
been funded. It is obvious that estimating cost monitoring, and progress measure- cost estimate. This is essentially a screen-
is critical for the economic and optimal ment of a project during execution. ing review to ensure that the math is cor-
use of an owner’s limited capital budget. Since we have established that an esti- rect (i.e., extensions of pricing are correct,
From the contractor’s perspective, mate is of critical importance to a project’s summaries add up properly, etc.), that the
accurate estimating is just as important. In success, it makes sense that the estimate estimate is documented correctly and
a lump-sum bidding situation, the profit should undergo a rigorous review process. includes a comprehensive basis of esti-
margin of the contractor is dependent on The estimate should be evaluated not only mate document, and that it adheres to esti-
the accuracy of his or her estimate. If the for its quality or accuracy, but also to mating department guidelines. Typically,
project is exceptionally large, the loss from ensure that it contains all of the required the lead estimator conducts this review
an inaccurate estimate on a lump-sum bid information and is presented in a way that with the members of his or her estimating
can potentially put a contractor out of is understandable to all project team team. On very large projects or those of
business. For cost-plus projects, the con- members and client personnel. A struc- significant importance, this review may be
tractor will face less direct economic risk tured estimate review process should be a conducted by the estimating department
from an inaccurate estimate, but the dam- standard practice for all estimating depart- manager or supervisor.
age to the contractor’s reputation can be ments.
severe. The following sequence of steps will
The cost estimate, however, serves discuss a formal review process for an Check the Math
other purposes besides establishing the internally prepared appropriation grade The first step of the review is to ensure
budget for a project. It also serves as a tool estimate, which is an estimate submitted that all of the math used in the estimate is
or resource used for both scheduling and for capital budget authorization. The level correct. With today’s computerized esti-
Cost Engineering Vol. 44/No. 1 JANUARY 2002 17
mating systems, this is much less of a con- schedule and key milestone dates affecting neering documents and deliverables avail-
cern than 20 years ago when estimates the estimate. able to create the estimate.
were primarily prepared by hand using • Cost Basis—The source of all pricing • Confirm that the estimate summary
simple calculators. However, math errors used in the estimate should be document- and details are organized and presented in
can still occur. This can be a major con- ed in this section of the BOE. This would the proper format. The estimate should
cern when using an electronic spread- include the source of all bulk material follow the project work breakdown struc-
sheet, such as Excel, for preparing the esti- pricing, the pricing of major equipment ture and code of accounts. Also, the esti-
mate. Surprisingly, it is very easy to make a (referencing quotes or purchase orders if mate format needs to be consistent with
formula error in a spreadsheet, such as used), and all labor rates including office, the intended purpose of the estimate, and
inserting a row or column that does not get engineering, fabrication, and construc- provide sufficient detail to meet this pur-
included in a subtotal. All spreadsheet for- tion. The source of all labor workhours pose.
mulas, subtotals, and totals should be should be documented, along with any • Ensure that all estimate backup infor-
examined carefully for correctness. From a assumptions regarding labor productivi- mation is organized properly. Can all val-
client’s point of view, nothing will help to ties. All allowances included in the esti- ues on the summary page of the estimate
lose credibility in the entire estimate faster mate should also be clearly identified. It is be traced to the estimate detail pages, and
than a finding a math error that went also important to document the time basis can all information on the estimate detail
undetected. of the estimate, and the basis for cost esca- pages be traced to the estimate backup or
lation included in the estimate. source documents?
• Risk Basis—Since, by definition, • Verify that all allowances and factors
Basis of Estimate every estimate is a prediction of probable are appropriate for the type of estimate
The comprehensive basis of estimate costs, it is clear that every estimate involves being prepared, and are consistent with
(BOE) document should be reviewed uncertainty and risk. Contingency is typi- comparable projects and estimates.
carefully to ensure that it is both correct cally included in an estimate to cover the
and complete. The BOE is an extremely costs associated with this uncertainty. This This level of estimate review helps to
important document. The dollar amount section of the BOE should document how ensure that all estimates prepared by the
indicated on an estimate is meaningless the contingency was determined, and department are using established guide-
without knowing the parameters, or what identify key areas of risk and opportunity lines, and are presented in a consistent
is included and not included in the esti- in the cost estimate. manner from project to project.
mate. The BOE serves to clearly define
the design basis, planning basis, cost basis, It is important to ensure that the basis
and risk basis of the estimate. of estimate is clear and easily understood, Engineering/Design Review
and to verify that all information and fac- The next level of estimate review
• Design Basis—The overall scope of tors documented in the BOE have been should be held with the engineering team,
the project should be summarized, with consistently applied throughout the esti- and should evaluate the estimate in terms
additional detail provided for each mate, including such items as wage rates, of accurately representing the project
area/unit/work package of the project. labor productivities, material and subcon- scope. The core members of the engineer-
Specific inclusions, and even more impor- tract pricing, etc. Again, the estimate can ing team are key participants in this
tantly, specific exclusions of items or facil- lose credibility if different pricing or labor review, along with the lead estimator and
ities, should be documented. All assump- rates have been used for the same item estimating team.
tions regarding project scope should be within the estimate detail.
documented. If available, equipment lists
should be attached or referenced, and a Completeness of Engineering
listing of all drawings, sketches, and speci- Estimating Department Guidelines Deliverables
fications used in the preparation of the A careful review should be done to One of the first items to review is the
estimate should be documented, includ- verify that the cost estimate follows stan- listing of all drawings, sketches, specifica-
ing drawing revision date and number. dard estimating guidelines for the depart- tions, and other engineering deliverables
• Planning Basis—This portion of the ment. This would include a review to ver- used in preparing the estimate to ensure
BOE should document important infor- ify that standard estimating procedures that it is complete (see design basis above).
mation from the integrated project plan were followed regarding estimate format, The lead engineers need to cross-refer-
that affects the estimate. It should include cost coding, presentation and documenta- ence this listing against their own engi-
specific information about any contracting tion. This would include items such as the neering drawing and deliverables lists to
strategies for engineering, design, procure- following. make sure that all relevant information
ment, fabrication, and construction. It was passed on to the estimating team. The
should include information about resourc- • Verify that the proper estimating revision numbers of drawings should be
ing and project execution plans such as methods, techniques and procedures were checked to ensure that they match the
the length of the workweek, use of over- used that match the stage of project com- intended revision for the estimate. If late
time, number of shifts, etc. It should also pleteness. In other words, different esti- changes to the engineering drawings have
include information about the project mating techniques will be used depending occurred, and are intended to be incorpo-
on the type and completeness of the engi- rated into the estimate, this needs to be

18 Cost Engineering Vol. 44/No. 1 JANUARY 2002


checked to ensure that all late changes should be of particular interest to the engi- responsibility of the estimating team, the
have been included. neering team, and concurrence sought. scope related costs should also be reviewed
As mentioned, the goal of this portion by the rest of the project team to gain con-
Equipment List of the estimate review is to make sure that sensus.
The equipment list and equipment the scope of the project as understood by In particular, the following areas
pricing should be double-checked by the engineering is reflected in the estimate. At should be discussed:
engineering team for completeness and the end of the engineering review, the esti-
accuracy. Equipment is often one of the mate should have the full support of the • Verify that the latest project schedule
key drivers of cost and scope, and needs to engineering team during subsequent agrees with the estimate, particularly
be checked carefully for completeness and reviews. as it relates to escalation.
accuracy. • Examine the project administration,
and other home office related costs for
Project Manager/Project Team Review reasonableness.
Design Basis of Estimate Once the estimating and engineering • Conduct a final constructability
The engineers should review the basis teams have reviewed the estimate closely, review to ensure that the methods of
of estimate and summary of project scope it is ready for review by the project manag- installation and construction assumed
carefully to verify and correlate their er and the rest of the project team. The in the estimate are reasonable and
understanding of the project scope with objective now is to gain the entire project cost effective.
that expressed in the estimate. All exclu- team’s support of the estimate, and espe- • Review the construction indirect costs
sions expressed in the BOE should be cially that of the project manager. This is (field staff, temporary facilities, tem-
agreed to; and all allowances and assump- also the first point where the estimate porary services, construction equip-
tions verified. If there have been any ques- should be able to pass overall validation ment and services, construction tools
tions about interpretation of the drawings tests, in addition to a quality review. and consumables, etc.) to make sure
or engineering deliverables, now is the they are reasonable.
time to discuss the estimator’s interpreta- • Ensure that all required start-up and
tion with the engineers, and to make sure Estimate Documentation commissioning materials are includ-
that the project scope is accurately reflect- The first part of this review should be ed, if required. This is often an area of
ed in the estimate. All drawings used for the examination of the estimate documen- cost that is overlooked.
the estimate should be available during tation by the project team and project • For international projects, there may
this review. Sometimes it can help to have manager. This includes the basis of esti- be many more items of cost that
the estimator explain how each drawing mate, as well as the estimate summary and should be carefully reviewed. These
was used in the preparation of the esti- estimate detail pages. The purpose is to may include such items as interna-
mate. For example, the estimator may ensure that the estimate is presented in an tional labor adjustments for produc-
describe whether particular quantities understandable manner. If standard esti- tivities and wage rates, adjustments for
were obtained from a detailed takeoff mating guidelines have been followed (as workweek variations, material cost
using isometric drawings, or if the quanti- discussed above), all estimates should be adjustments for both local and global-
ties were derived from a P&ID and plot presented in a consistent and understand- ly sourced materials, international
plan. able style. It is very important that the proj- freight costs, international duties and
ect manager fully understand how the esti- taxes, labor camp costs, premiums for
mate is prepared because he/she often expatriate costs, etc.
Engineering/Design Costs becomes the person responsible for pre-
The engineering team should also senting, and sometimes defending, the
review the assumptions and costs associat- estimate to upper management, and later Estimate Validation
ed with the engineering and design por- to the eventual customer. The entire proj- In most organizations, the project
tion of the estimate. The engineering ect team should also understand the entire manager is ultimately held responsible for
team needs to feel comfortable that the estimate package, format and contents. the execution of the project. Therefore,
amount of money included in the estimate the project manager has a vested interest
for engineering, design, and support is in performing “sanity checks” or otherwise
adequate for the level of effort expected to Cost Review validating the estimate as reasonable. Most
be expended on the project. Engineering should have already experienced project managers will have
reviewed the engineering, design, and various “rules-of-thumb” that they will
associated support costs. Now is the time want to use to verify against the estimate.
Risk Basis of Estimate for the other key members of the project Regardless, the estimate should include an
Last, the engineering team should team (project manager, project controls, estimate review metrics report that sum-
review the risk basis of the estimate, and be procurement, construction manager, com- marizes and compares several key bench-
in position to agree with the analysis of missioning manager, etc.) to examine their mark ratios and factors versus historical
cost risk associated with the estimate. The respective costs that are included in the values from similar projects. If sufficient
level of risk associated with scope defini- estimate, and to obtain agreement that historical data from completed projects is
tion, and with engineering/design costs they are correct. Although primarily the not available, information from other

Cost Engineering Vol. 44/No. 1 JANUARY 2002 19


trusted estimates may need to be substitut- estimates. This is an important, but often were to be built according to any other
ed. overlooked, aspect to the overall estimate defined alternatives, what would they cost?
The goal is to ensure that key metrics review process. The current estimate can Usually, the recommended alternative for
from the estimate are in line with the same gain credibility by comparing it with earli- project scope has long since been deter-
metrics from similar projects. If there is a er estimates, and clearly explaining the dif- mined and agreed to by the project team,
large discrepancy, it must be explainable ferences and reasons for the differences. and the engineering deliverables created
by the particular circumstances of the esti- The reconciliation can usually be present- for preparing the estimate have been
mated project versus the similar complet- ed at a high level, without excessive detail, focused on a single design alternative.
ed projects. Such comparison metrics may but the backup should be available in case However, many times management will
include values such as percent of adminis- it is required during the review. start asking questions concerning other
tration (home office) costs, percent of alternative scopes or designs. One of the
engineering/design costs, equipment to certainties is that management will always
total field cost ratios, equipment to total Management Reviews think the project cost is too high, and will
project cost ratios, cost per piece of equip- The last series of reviews is usually now be probing to determine if there are
ment, labor hours per piece of equipment, held by various levels of corporate man- lower cost options. Therefore, it is impor-
and cost to plant capacity ratios ($/BBL, agement. The number of upper manage- tant to have available for the management
$/SF). Sometimes the metrics will be gen- ment reviews, and the level of manage- reviews any earlier design/cost alternatives,
erated down to the discipline level where ment they are presented to, typically varies and the decision tree leading to the select-
you may look at ratios such as cost per with the strategic importance and/or total ed design.
diameter inch of piping, cost per cubic estimated cost of the particular project. The effectiveness of an estimate
yard of concrete, and cost per ton of steel. These reviews are typically conducted at a review relies on the information that is
In addition to examining key bench- very high level of analysis, and usually do presented, and the manner in which it is
mark metrics and ratios, another form of not involve the details of the estimate. presented. The above discussion has con-
estimate validation may involve preparing Upper management reviews often focus centrated on how to structure a sequence
a quick check estimate using order of mag- on substantiating the overall adequacy of of estimate reviews for internally prepared
nitude estimating methods. Again, any the estimate in regards to its intended use. estimates to ensure that estimates are well
large discrepancies between the estimates In other words, can management be documented, consistent, reliable, and
should be able to be explained by the assured that the level of detail available for appropriate for their intended use. After
peculiarities of the project. the estimate, the estimating methods this review cycle, the level of estimate
Estimate validation is a very impor- employed, and the skills of the estimating accuracy should be apparent, reflective of
tant activity during the project review and project teams support their decision- the scope information available for prepar-
cycle, and the proper tools need to be in making process on whether to proceed? ing the estimate, and capable of support-
place to allow this to occur. As with the project manager review, ing the required decision making process
Benchmarking key estimate ratios and estimate validation is a key element of the for the project. Next, we will discuss tech-
metrics depends upon having a project upper management reviews. It is impor- niques for reviewing estimates prepared by
history database in place to collect, ana- tant to be able to explain and demonstrate others.
lyze and present the required information. that metrics for the current estimate are in
Similarly, the capability to provide quick line with data from other similar proj-
check estimates depends on having the ects—i.e., that the estimate is reasonable. Reviewing Estimates Prepared By Others
correct strategic and conceptual estimat- It is also important to show where the met- The foregoing discussion has focused
ing information and tools ready for use. rics may be substantially different from on structuring an estimate review process
other projects, and provide explanations for the estimates that we internally prepare
for the differences. to ensure that the estimate is of a high
Risk Basis of Estimate Management will also be interested quality and supports the decision making
The project manager and project in the cost risk assessment. It is important process of our management. Often, we
team should again review the risk basis of to clearly and concisely explain how the may also find ourselves in a position to
the estimate, and agree with the analysis of contingency amount was developed, and review and/or approve estimates prepared
cost risk associated with the project. The what the levels of risk are. It is then up to by others, and that may or may not have
project manager, in particular, should management to accept the level of risk gone through a rigorous internal review
agree with the risk assessment and contin- indicated, or change the amount of con- cycle as described above. When reviewing
gency amounts, and be able to defend it in tingency and accept more or less risk for estimates by others, we always want to
subsequent review to upper or corporate the project. When reviewing the risk keep in mind the basic fundamentals pre-
management. analysis, it is always important to discuss viously described. Complicating the mat-
the areas of high risk, and what is being ter, however, is the problem that many
done to mitigate those risks. times the amount of time allowed for a
Reconciliation to Past Estimates Up until the management reviews, complete estimate review is very short.
Last, the project manager will usually the estimate review will have typically con- Thus, the review of an estimate prepared
be interested in reconciliation of the cur- centrated on the project as defined by the by others is usually accomplished by a crit-
rent estimate to the preceding estimate or project scope documents. If the project ical assessment of the estimate and its doc-

20 Cost Engineering Vol. 44/No. 1 JANUARY 2002


umentation, and a series of questions to Estimate Documentation You should examine the estimate summa-
assist in evaluating the level of diligence Is the estimate documented clearly? Is ry and detail pages closely to ascertain
used in preparing the estimate. The fol- the estimate summary and detail pages which aspects of the estimate you may
lowing discussion centers on guidelines well organized, and presented at an appro- want to examine in closer detail. Basically,
that we can use to efficiently review esti- priate level of detail? Is every cost appear- you should examine in detail those items
mates prepared by others. ing on the estimate summary traceable to of the estimate that will have the most sig-
the estimate detail and other estimate nificant cost effect if estimated incorrectly.
backup? One review technique, which is often
Basis of Estimate employed, is to thoroughly examine and
The first thing to assess is the basis of review the estimating steps that were used
estimate. Is it well organized and com- Estimate Validation for a particular part of the estimate. Select
plete? Does it provide the required infor- Hopefully, the estimate for review will an area of the estimate, and ask how the
mation regarding the design basis, plan- include a metrics report showing key esti- quantities were derived. Don’t just take
ning basis, cost basis, and risk basis of the mating metrics and benchmark ratios for their word for it, however. Ask the estima-
estimate? Does the design basis clearly the estimate and similar past projects. You tors to show you the drawings from which
document the scope of the project, and should review this report, and question the quantities were generated. Perform a
have all engineering deliverables used in any significant differences. You should quick takeoff to see if the quantities can be
developing the estimate been identified? also have your own set of metrics and sta- verified. Ask what the basis was for the unit
Have all scope assumptions been acknowl- tistics from your own project history to material price and labor workhours. Have
edged? Is the planning basis, which compare against. these been consistent throughout the esti-
includes the schedule, resource plan, and At this point, you may also develop mate? What adjustments were made and
construction plan, reasonable? Are the your own quick check estimate for com- why? If the answers to your questions are
material prices, labor rates, and labor pro- parison purposes, typically using concep- evasive, it may call into question the cred-
ductivities reasonable, in line with expec- tual estimating techniques. This is always ibility of the entire estimate, and a more
tations, and consistently applied through- a good practice to see if the estimate being thorough review of the complete estimate
out the estimate? Has the risk basis been reviewed is reasonable. If there is a signifi- may be necessary. If your questions are
clearly defined, and is it reasonable for the cant difference, then question the estima- answered confidently, and the answers can
level of information available to prepare tor and listen to his or her explanations be verified against the engineering deliver-
the estimate? and opinions for the deltas. Significant dif- ables and scope information, then you
ferences between the check estimate and may decide to check the rest of the esti-
the estimate being reviewed may indicate mate details in a more cursory fashion.
Estimating Personnel Used the need for taking a more thorough Typically in this situation, once you
Next, you will want to know who pre- examination of the estimate detail. have shown the wherewithal to compel
pared the estimate, and their level of esti- the estimator to back up any claims or
mating experience. Do they have estab- explanations, he/she will discover they
lished estimating procedures and guide- Estimate Detail can’t just, “pull the wool over your eyes.”
lines? Was the estimate checked and If the preceding inquiry, or should we From that point forward, you will usually
reviewed before publication? say interrogation, has gone well, and you find that you are getting honest answers to
are confident that the estimate appears to your questions.
have been prepared in a professional man-
Estimating Methodology and ner, you are ready to delve into some of
Procedures the estimate details to verify estimate qual- he goal of an estimate is to pre-
What estimating methods, techniques
and procedures were used in preparing the
estimate? Are they appropriate for the level
of information available and project type?
Were different estimating methods used
ity. The goal is to check that selected areas
of the estimate can withstand further
scrutiny. The key here is to not get too
deep into the details, and lose sight of the
forest for the trees.
T dict the probable cost of a
project. The goal of an estimate
review is to determine that a
high quality and sufficiently accurate esti-
mate has been prepared. The review
for different parts of the estimate? Is the An important point to remember here should ensure that the proper estimating
level of detail in the estimate sufficient for is the “80/20 rule”. This principle general- methods, procedures, techniques, data,
the purpose of the estimate? Were parts of izes that 80 percent of the cost will come and guidelines have been employed in the
the project difficult to estimate, and why? from 20 percent of the estimate line items. preparation of the estimate. The use of a
Was sufficient time available to prepare For any particular estimate, the significant structured estimate review process and
the estimate? What adjustments were cost drivers may vary. Sometimes, the estimating review techniques will help to
made to the estimate for location, com- main cost driver may be a particular ensure that quality estimates are consis-
plexity, etc., and are they reasonable? Was process unit of the project; other times it tently prepared which effectively support
the estimate prepared using a code of may be the type of process equipment or the decision-making process by manage-
account structure? machinery throughout the project, and ment.
still other times it may be the overall bulk
material quantities or labor manhours.

Cost Engineering Vol. 44/No. 1 JANUARY 2002 21


Larry Dysert, CCC, is
senior project estimator
for Eastman Kodak Co.
(1669 Lake Ave.,
Rochester, NY 14652-
439; Phone: 716-722-
Meet AACE International
7115; Fax: 716-722-
1100; E-mail:
larry.dysert@kodak.com), where he is
responsible for the preparation of conceptu-
al and detailed project cost estimates at the
domestic and international levels. Dysert
has 21 years of project consulting experi-
ence in the chemical process, petroleum
refining and construction industries. He is
an active member of AACE International,
serves as chairman of the technical board,
A.K. Varma, CCE
has spoken at numerous AACE
International conferences, and has taught
project estimation at the Rochester Institute
nil Kumar Varma was born in Kerala, India, and is a graduate in mechanical engi-

A
of Technology (N.Y.). Dysert has a B.S. in
neering from the University of Calicut, India.Certified by the Project Management
economics from the Univ. of Calif. in San Institute (PMI) as a Project Management Professional (PMP) and by AACE
Diego and an advanced-graduate degree in International as a Certified Cost Engineer (CCE). Anil’s professional career began
economics from the Univ. of Calif. at Santa with FACT Engineering and Design Organization (FEDO) where he worked as a field piping
Barbara. engineer for two years starting from 1984. He then joined Bharat Petroleum Corporation, India
in their Refinery Major Projects Division and worked on various grassroot refinery projects as
project engineer, senior project control engineer, Dy Manager (Projects), etc.
Bruce G. Elliott, Anil later joined Petrochemical Corporation in Singapore in 1995 for their PCS II 1.0 billion
CCC, is the estimating US$ Ethylene Cracker Project, as a project engineer and subsequently as construction engineer,
department supervisor Field Project Control and subcontracts engineer.
at the Eastman Kodak
Presently working with Abu Dhabi National Oil Company (ADNOC) in Abu Dhabi, United
Company in Rochester,
Arab Emirates as a senior mechanical engineer/projects engineer, Anil has extensive experience
NY. He holds a B.S. in in various refinery, petrochemical and oil and gas projects, which include complex plants like
economics from Cal FCCU, Hydrocracker, Delayed Coker, Methanol, Ethylene Cracker, HDPE/LDPE etc. He is
Poly San Luis Obispo, also experienced in the project execution of cross-country pipelines.
and a B.S. in industrial technology from
Cal State Long Beach. He has 27 years of Anil is an expert in project control, project management, and contract management of large
value projects, and his accomplishments include developing project control and execution pro-
project estimating and management con-
cedures for different types of projects. Anil’s personal areas of interest are the pragmatic use of
trols experience in the engineering and con- earned value techniques and the development of risk-based cost estimating techniques. He is
struction industry for both owner and con- active with the Arabian Gulf Section of both AACE International and PMI and is presently
tractor organizations. He is an active mem- undertaking a NVQ Level 4 certification in project control from the United Kingdom.
ber of the Genesee Valley Section of AACE
International. Anil and his wife, Priya, have two children, Rohan (9-years-old) and Varun (4-years-old) and live
in Abu Dhabi.

You may contact Anil on 971-2-6266083/6027327 or varmaak@emirates.net.ae.◆


This manuscript was first presented at
the 2000 AACE International Annual
Meeting and 2nd World Congress of Cost
Engineering, Project Management, and
Quantity Surveying at Calgary, Alberta,
Canada, and is a part of the 2000 AACE The staff of AACE International
International Transactions. ◆
would like to wish all of our members
a happy new year.

22 Cost Engineering Vol. 44/No. 1 JANUARY 2002

Вам также может понравиться