Академический Документы
Профессиональный Документы
Культура Документы
IN TELECOM COMPANIES
By
Anna Peter
2017
0
CERTIFICATION
I, the undersigned, certify that I have read and hereby recommend for acceptance by the
in Tanzania in partial fulfillment of the requirements for award of the Degree of Master
_________________________
Dr. George Mwaluko
(Supervisor)
Date:____________________
I, Anna Peter, declare that this thesis is my original work and that it has not been
presented and will not be presented to any other university for a similar or any other
degree award.
i
Signature:______________________
©This dissertation is a copyright material protected under the Berne Convention, the
Copyright Act 1999 and other international and national enactments, in that behalf, on
intellectual property. It may not be reproduced by any means in full or in part, except for
short extracts in fair dealings, for research or private study, critical scholarly review or
discourse with an acknowledgement, without the written permission of the University of
Dar es Salaam on behalf of the author.
ACKNOWLEDGEMENTS
First and foremost, all praise and gratefulness is due to Almighty God who endowed me
with strength, health, patience, and knowledge to complete this work. Secondly, I would
like to express my profound gratitude and special thanks to my supervisor Dr. George
Mwaluko of the University of Dar es Salaam who, despite being busy with his other
ii
duties, took time out to guide and support me academically throughout the study. His
Thirdly, I am thankful to all respondents, particularly all directors and managers from
would also like to express my sincere gratitude and appreciation to all my fellow
postgraduate students with whom I studied and held discussions. I am thankful for their
encouragement, moral and academic support. The sleepless nights we worked together
during studies, and all the fun we had in the class will always be honored and
remembered.
Lastly but not the least, my heartfelt thanks should go to my husband for his moral and
material support. Since it is not possible to mention everyone who helped individually, I
thank all those who in one way or another contributed to the successful completion of
DEDICATION
iii
TABLE OF CONTENTS
CERTIFICATION i
ACKNOWLEDGEMENTS iii
DEDICATION iv
TABLE OF CONTENTS v
LIST OF FIGURES x
iv
LIST OF ABBREVIATIONS xi
CHAPTER ONE 1
INTRODUCTION 1
1.3 Objectives 5
CHAPTER TWO 8
LITERATURE REVIEW 8
2.1 Introduction 8
v
2.6 Telecom Projects Status Africa and Tanzania 1990-201510
STUDY METHODOLOGY 20
3.1 Introduction 20
3.7.1 Questionnaires 25
3.7.2 Interviews 26
vi
3.11 Qualitative Data Analysis 27
CHAPTER FOUR 30
4.1 Introduction 30
CHAPTER FIVE 68
5.1 Introduction 68
5.2 Summary 68
vii
5.3 Recommendation 70
REFFERENCES 72
Appendix I: QUESTIONN 79
LIST OF TABLES
viii
Table 4.5: Strategies for Successful Implementation of Telecommunication Projects…57
LIST OF FIGURES
ix
Figure 4.6: Strategies to Successful Implementation of Projects....................................64
LIST OF ABBREVIATIONS
HR - Human Resource
MS - Mobile Station
x
CIs - Confidence Intervals
CN - Core Network
UE - User Equipment
xi
CHAPTER ONE
INTRODUCTION
electronic means. The simplest form of telecommunications takes place between two
network, and the Internet is the largest example. Telecommunication sector comprises of
six major segments; Mobile Sector, Fixed Line Sector, Wireless Sector, Payphone
In earlier times, telecommunications involved the use of visual signals, such as beacons,
smoke signals, semaphore telegraphs, signal flags, and optical heliographs, or audio
messages such as coded drumbeats, lung-blown horns, and loud whistles. In modern
times, telecommunications involves the use of electrical devices such as the telegraph,
of fiber optics and their associated electronics, orbiting satellites and the Internet.
deliver a set of voice, data, and broadband services using wire line or wired
Telecom is the fifth largest and fastest growing industry in the world, playing an
half of the world’s population had at least one mobile subscription, totaling over 3.6
billion unique mobile subscribers. Developed markets are growing more slowly as
penetration rates approach levels close to saturation. For example, in Europe and North
America, unique subscriber growth was below 1% in 2014. At the other end, Africa is
still the world’s most under-penetrated region with subscriber growth at nearly 12%
industry till 2015 had contributed to 4% of world economy as compared to 2014 where it
was 3.8%. This clearly shows the remarkable growth of sector (GSMA, 2015).
the market have compelled telecom companies to expand their networks so as to acquire
wider coverage and large share in the market. The telecom market share in Africa has
Tanzania forms the second largest telecom market in East Africa, behind Kenya and
currently has a mobile penetration level of 67% which is slightly below the Sub Saharan
region’s average of 71.1%, according to the World Bank. The two leading mobile
operators in the country are Vodacom and Tigo, which account for 69.3% of total
telecom service revenue in 2015 (Pyramid Research, 2015). The sector contribution to
The driver of this phenomenal growth has been the mobile sector, which since the entry
of the first mobile operator in 1994 has transformed the communications landscape. The
government too has played its part with competition picking up due to the liberalization
2
of the market and the introduction of a progressive licensing framework. Operators
continue to invest in the expansion of their mobile networks in rural areas and ensure
adequate quality of service to increase and maintain their subscriber market share.
The report form World Bank (2015) shows the highlights form the project database that
until the end of 2014 the telecom sector was the leading sector for projects
projects, Vodacom Ltd being the leading company investing about 1,257 million US
dollars.
31,862,656 which is approximately 10 times more than what is shown in TCRA 2005
This supports the World Bank report that more projects are being implemented to expand
their networks so as to meet the growing demands of its customers. However, the
network project encounters several challenges that hinder the project’s performance.
The study in Tanzania has shown that the implementation of telecom project suffers in
the investment costs. Out of 25 projects implemented in telecom sector, at least 4 are
cancelled due different factors. This accounts for 1% of total investment costs
(World Bank, 2015). More studies have been conducted on other telecom companies in
Africa. The telecom in Nigeria also confirmed failure of many projects being in cost and
schedule overruns. Moorage and Radford (2006) reported that the cost of projects in
Nigeria escalated by 14% (the minimum average percentage) and the period of projects
3
in Nigeria escalated by 188% (the minimum average percentage). So it was the aim of
the study to discuss the factors critical to the successful implementation of projects in
Tanzania as it is to other organizations where project works are frequently adopted. The
not fulfill expectations due to some sorts of external influence, unexpected events, ever-
al., (1997) reported the findings from various studies, which were conducted in different
developing countries of Nigeria, Saudi Arabia, Malaysia and Indonesia. They confirmed
that all of the projects implemented in these countries suffered from significant
construction cost and time overruns. Tanzania telecom companies also have many
projects experiencing failures. These are such as CVBS, MNP and RAN projects in
TTCL Company (TTCL, 2014). Furthermore, the World Bank (2014), in its report about
telecom project performance across African countries shows that in Tanzania about
28.9% of projects implemented during that period underperformed in terms of cost and
schedule. This suggests that the more projects are implemented the more the failures if
4
steps are not taken to manage them effectively and efficiently (Suhaiza, 2007). Despite
the findings from various literatures about the success factors for projects performance,
few literatures exists on factors affecting the performance of projects in telecom industry
in Tanzania with specific network projects. Since network projects are being widely
implemented in the telecom industry in Tanzania, its prominence and the persisting
challenges facing this industry in managing these projects today are the driving force
for carrying out research on identifying the success factors crucial to the performance of
1.3 Objectives
The main objective of this study is to assess the factors affecting projects
companies;
telecom companies.
5
1.4 Research Questions
telecom companies?
This study is significant for practical pursuits. Projects are widely implemented and
increasing due to the demands for network expansions among the TCs. This makes it
factors affecting project performance. The findings of the study provide knowledge on
the efficiency and effectiveness of the adoption of better strategies to ensure projects
success outcomes among TCs. The findings also add useful information to the existing
herein are of practical importance to stakeholders such as project fund donors and
academic institutions. Lastly, this study may be used as a reference point to scholars who
TIGO ,TTCL and HUAWEI as their respective vendors in their headquarters in Dar es
Salaam Region The choice for the above companies is due to their long existence in the
6
telecom industry in Tanzania. They have experienced a lot in managing their network
projects and so they are better placed to acquire the desired research data. The study only
network projects.
7
8
CHAPTER TWO
LITERATURE REVIEW
2.1 Introduction
This chapter is divided into different sections covering all the important aspects of the
research subjects. It explains the concepts of project and project management, it gives an
overview of the project status among TCs, explains the challenges facing the
management of the telecom projects, and discusses the factors crucial to the successful
The term project has been discussed through various literatures. The PMI (2008) defines
with results, output or product, complexity with normally interrelated activities and a
large number of different tasks, uncertainty as it has element of risks, temporary with its
well defined beginning and end, and lastly it operates in a life cycle as emphasis and
resource needs change during the life of the project (Asihuza, 2007).
Telecommunication projects are highly exposed to risks due to its intensive capital
9
sector, management and sponsors must as much as possible adopt the best project
Desmon (2016) says that some of the challenges encountered during the implementation
customer, not enough resources (people, cash, lab space, spare circuits, Changes to scope
keep interfering (regulatory, customer, demands, related project off track) Conflicts
staffs),Committing to unrealistic dates ,Clear roles and responsibilities, and Not clear
A project management consultant firm in America (AMA) has identified major failure
factors for projects which include lack of project management skills, scope creep, poorly
defined objectives, high staff turnover, insufficient resources, poor follow up,
management methods adopted in the project team. This clearly shows that if projects are
applied and steps are not taken in order to manage them effectively and efficiently, the
This section reviews the status of telecom projects both worldwide, Africa and
10
2.5 Telecom Projects Status Worldwide
investments both in Africa and Tanzania which invested a total of 3898 and 114303
million dollars representing 68% and 88% investment share for Africa and Tanzania
natural gas, railroads, seaports, telecom, water and sewerage) was 4728 million and 162
685 million dollars in Tanzania and Africa respectively. Despite its high investment in
projects it still suffers from failures due different factors including financial. The reports
show only 11 and 208 projects were successfully completed for Tanzania and Africa
11
respectively. The project status both for Africa and Tanzania is illustrated by the figures
below.
12
COMPANY TOTAL COMPLETED PROJECT S EQUIVALENT
PROJECTS INVESTMENT PROJECTS UNDERPRFOMED LOSS IN ( MIL
(IN MIL $) $)
3 TIGO 11 746 9 2 8
4 ZANTEL 8 624 5 3 6.2
5 TTCL 10 190 4 6 19
2.7 Project Success Measurement Criteria (Indicators)
Defining what project success is, how do we define project success and design
performance measures that allow us to recognize the degree of success, has been a great
deal written over the years. However, none has given the final definition of project
success since it varies depending on the project criteria. In general project success
involves two main components which are Project success criteria and project success
factors, for the project to be implemented successfully the criteria and factors for project
The measurement criteria for project success differ from one project to the other. In early
times the evaluation of projects success was mainly based on the three criteria known as
“the iron triangle” which are time, cost and quality. Any project that was implemented
outside the timeframe, out the budget and outcome does not meet the pre-determined
consider only three criteria and criticized by several authors (e.g. Pinto and slevin, 1998;
Atkinson, 1999; Barcca, 1999). New other criteria were then established.
13
Kerzner (1998) identified 5 criteria that can be used to measure project success. The
criteria are completed in time, within budget, completed at the desired level of quality,
accepted by the customer and resulted in customers allowing the contractor to use them
project success to include client perception in contrast to the early literature where
emphasis was given to cost quality and time during the project management.
Shenhar (1997) classified project success criteria into two dimensions. The first one is
the efficiency which is not limited by the dimension of time, cost and quality but can be
efficiency and yield, efficiency of purchase order and safety measures. The second
dimension is the impact on the customer or end user, followed by the third dimension,
which is impact on the organization. Lastly the success of the project need to be
measured by the way it helps the organization to move and prepare for the future.
Similary Masoud (2014) identifies 5 critical successes, which are meeting schedule,
within budget, customer satisfaction, commercial success, reaching scope and preparing
for the future. Preparing for the future scored 5.657 indicating that it was the most
important indicator of the project success. It was revealed that studying the projects
carefully and narrating the project lessons learned can play a very significant role on
project success. The commercial success scored 5.342, which also shows the second
level of importance as project success indicators based on the response received. The
respondents also agreed on staying within the budget with a mean of 5.285 being the 3rd
and Masoud (2014) reveal that these 5 items are the most important factors related to
project success.
scholars, it is important to note that projects are operated under different environments,
contexts and have different objectives; hence they require different indicators for
projects refer to meeting budget, meeting schedule, scope control, archiving commercial
This area of research is not a new concept. Several studies have been conducted
concerning the factors affecting performance of the projects, even though these factors
may not be similar to all projects and organizations (Belassi & Tukel, 1996).
Pinto (1988) mentions 10 factors critical to the project performance and categorizes
these factors into two main categories. The first one includes top management support,
project plan or schedule, and project mission. These three were grouped as strategic. The
second group consists of seven factors namely client consultation, personnel, technical
are classified as tactical. He proceeds by specializing the factors into different stages of
project cycle. The strategic factors occur during the early planning phase of project, and
15
Belassi and Tukel (1996) group success factors into organization factors, environmental
factors and factors related to project management and team. The study was conducted in
respect to the criteria for success (cost, time, quality and client satisfaction, the
organizational structure and project size). In their study availability of resources ranked
as the top, followed by top management support, the third most important factor was
Availability of resources and top management support were the dominant factors. The
study was conducted in manufacturing industry and not telecom industry as this study
seeks to address.
Albert et al (2004) have five major groups of independent variables, namely project-
and external environment. These are identified as crucial to project success. However,
there are no information about the relationship between them, hence the study suggests
further study on the key performance indicators (KPIs) and how it relates to the CSFs.
The identified relation will provide useful piece of information to implement a project
successfully.
Tsun (2008), studying the critical success factors of agile software development projects
using quantitative approach, finds that for each of the four project success categories
(quality, scope, time, and cost) only 3 out of 12 factors are identified as critical success
factors for agile software development project. These factors were (a) delivery strategy,
(b) agile software engineering techniques, and (c) team capability. Again the study does
16
not reveal the relationship between the success factors and the mentioned group of
success criteria.
Desmon (2006) discovered few factors for successful project implementation in telecom
which are (i) good people (ii) clear objectives (iii) team work (iv) clearly defined
deliverables (v) good planning (vi) strong change control. However, these were more
common and generalized for all telecom projects not for specific projects as this study
seeks to address.
The study conducted by Oko et al (2010) investigated potential causes to cost overruns
related factors were top the list of categories that cause cost overruns in
overruns and are ranked in their order of importance: the lack of contractor experience
on the telecommunication projects, the high cost of imported materials and the
fluctuation in the prices of materials that are necessary for the telecommunication
projects. Again this study was conducted for general telecom projects not specific types
The study conducted by Hamoud (2014) on the influence of EMV on project success
project success. In his study he evaluated a total of 12 telecom projects across Africa
and found 0.833% of EMV components including a clear definition of project scope
accelerates the project success. However in this study the factors were evaluated as a
17
component of EMV (not as an independent component) and it was limited to projects
implemented by Nokia contractors only, contrary to this study which seeks to evaluate
the extent to which each one affects the project performance. This study will specifically
access to the provisioned radio channel and shuttle the data packets to and from the
user’s device. In fact, this is the component controlled and mediated by the Radio
machine, and provides connection with its core network (CN). Depending on the
standard, mobile phones and other wireless connected devices are varyingly known as
user equipment (UE), terminal equipment, mobile station (MS), etc. As the demand for
implemented hence the need to assess the performance factors is more imperative.
From the survey conducted RAN projects are characterized by the following
performance criteria (i) better coverage, (ii) low cost, (ii) high quality, (vi) high
capacity, (v) time saving, (vi) preparing for future expansions. Hence for RAN projects
to be successful all of the above mentioned performance criteria should be met. Another
18
influencing the performance. From the literature review and survey conducted in
telecom companies and respective Huawei vendors, the factors below were the most
failing in RAN projects implementations. These are (i) lack of proper planning, (ii) lack
of coordination between vendors and clients, (iii) lack of training, (iv) lack of top
management supports, (v) technology complexity, (vi) resource availability, (vii) scope
not defined clearly. Hence from the literature review the researcher seek to assess the
success factors for RAN projects performance. However, the criteria that were
measured: cost, time, scope of the projects and preparing for the future. These were
measures against the factors derived from Pinto’s model of project success factors after
verifying them from the survey that they fit for this study.
19
2.10 Literature Gaps
In the reviewed literatures, the study on the success factors for project performance is
Furthermore the factors identified were not explained how they related to the specified
measurement criteria. In addition to the above literature gaps more studies were
conducted in developed countries with few studies in least developing countries like
Tanzania.
CHAPTER THREE
STUDY METHODOLOGY
3.1 Introduction
constitutes the blueprints for the collection, measurement and analysis of data (Kothari,
problems, collecting and analyzing data that answers research questions and critically
draws conclusions on the research problem being investigated (Kombo et al., 2006).
This chapter presents various research methods and procedures, which were employed in
conducting the study in accordance with the research questions and objectives. It
20
provides detailed explanations on the research design, area of the study, population and
sampling methods and instruments for data collection, analysis and presentation.
The study has made use of document analysis, interview and questionnaires as data
collection methods. Although there were some difficulties in getting company statistical
between the success factors and project performance variables and quantitative as it
verify the relationship between the variables. This approach is mainly applicable in
collection of and analysis of data in a manner that aims to combine relevance with the
constitutes the blue print for the collection, measurement and analysis of data.
This research was concern factors affecting project success among telecom companies,
with the specific objectives of finding the extent of failure of telecom projects, the
21
implementation of these projects by the telecom operators. All these helped to achieve
the main objective and specific objectives. The information was collected using
questionnaires and checklists distributed to the TCs and Huawei vendors’ employees,
one to one interviews with project managers of the Huawei and TCs, interview with
network engineering and operation team of TCs. A case study of RAN projects in both
companies was employed using both qualitative and quantitative methods to assess the
factors crucial to the success of projects using dependent and independent variables.
Where each item of information in the survey represents one variable, a measure by
which varies in response could be established. The objective of the case study design
was to determine respondents’ opinions about the success factors for project
performance in telecom industry. Saunders et al (2003) confirms that case study design
is the best method used to gain a wider knowledge of the context of the research and
Webster (1995) defines sampling as set of respondents selected from a large population
for the purpose of a survey. This study used a sample size of 42 respondents, using
Furthermore, random sampling technique was used to select the respondents for the
A researcher needs to select a specific area for the study because only specific locations
are ideal and suitable to test particular theories (Develeux & Hoddlinot, 1992). This
research was conducted at the headquarters of telecom companies in Dar es Salaam, due
to time constraint and the readily availability of telecom firms in Dar es Salaam.
The target population for this study was management and staff of telecom companies,
and telecom vendors. A study made by Alan Barrett (2008) suggests that it is so difficult
to study the entire population due to some limitation for example time, fund and
administration, data collection and analysis. In this study stratified sampling was applied
in order to obtain representative sample. Under stratified sampling, the population was
divided into several sub-populations that individually more homogeneous than total
population. The different sub-populations are called strata. Then we select items from
23
Strata were formed on the basis of common characteristics of the items to be put in each
stratum. This means that various strata were formed in such a way as to ensure elements
were most homogeneous within each stratum and most heterogeneous between
different strata. In this case stratum items were staffs of each company and strata items
were companies involved in this research: Tanzania Telecom Company Ltd, Vodacom
Tanzania ltd, Tigo (T) Ltd, Airtel Tanzania Ltd and Huawei Ltd.
Simple random sampling was used to select Item from each stratum. Proportional
allocation was applied, whereby the sizes of the samples from different strata were kept
population included in stratum i and n represents the total sample size, the number of
For the case of this research, I selected sample size n = 42 from the population of staffs
with size N = 420, which was divided into four strata with size N1 =104; N2 = 94;
N3=84 and N4 = 74, and N5=64 covered Vodacom, Airtel, Tigo, Huawei and TTCL
respectively.
In order to get sample size from each strata the following calculation was used:
Where Pi=Ni/N
24
ii) For strata with N2 = 94; then P2 = 94/420
N4=nP4; 42x74/420=7.4
Table 3.1 summarizes the distribution of questionnaires relative to the samples of the
study’s population.
Both primary data and secondary data collection methods were employed in this study.
Primary data including both qualitative and quantitative data was derived from
questionnaires; checklist, questions for observation and personal interviews but mostly
using questionnaires.
25
3.7.1 Questionnaires
because researchers can gather information fairly easily and the questionnaire responses
are easily coded. Questionnaire was used to collect quantitative data and it was divided
into 5 sections. The first section’s aim is to collect personal details and organization
experience in project management. The third section evaluated the extent of failures of
telecom projects followed by the most important section which aims to find out what
the factors that influence the success in project performance, which is adopted from
Pinto’s Project Management Profile (PIP). And lastly, the study went to find out the
3.7.2 Interviews
Interview can be structured or unstructured. Due to the nature of this study, the
researcher used both structured and unstructured interviews for data collection. This kind
perceptions on the factors affecting projects performance for instance, their perceptions
vendors reactions when projects underperform and the extent of project failures in their
respect companies. Questions were in English since the respondents were expected to be
fluent in that language although there was a room for using either English or Swahili
during discussion between the researcher and respondents. The researcher conducted
26
interviews with PMs and heads of network departments face to face interviews were
conducted in the offices of the respondents, and recorded by a tape recorder and by way
Secondary data were sourced from various documents, those which have been written by
other persons and processed, but can further be used for other researches. Also, project
Data analysis refers to examining what has been collected and making deductions and
inferences from it (Kombo & Tromp, 2006). The method used for data analysis depends
on whether the study is qualitative or quantitative. In this study the researcher adopted
The Statistical Packages and Software for Social Sciences (SPSS) version 21 was used
determine significance level of variables. Quantitative data were presented in tables and
data for objective one and two, extent to which projects performance affected were
27
3.11 Qualitative Data Analysis
Qualitative data were also analyzed using Dedoose software, which is most effective
tool for qualitative data analysis. This involved coding of data into variables and
descriptors (fields). Responses were presented into percentages and response quotes.
After successful completion of data entry, the researcher presented both qualitative and
quantitative data under themes and sub-themes reflecting the objectives of the study and
Kitchen and Tate (2000) argue that validity and reliability are two factors that make a
final touch and provide green light for piloting research instruments.
Validity refers to the degree to which any inferences a researcher makes, based on the
& Wallen, 2000). On the other hand, reliability is concerned with the extent to which
data collection process yields consistent results. To ensure validity and reliability, a
questionnaire was reviewed by lecturers and fellow Masters Students at the College of
researcher solicited comments for improving on research questions and data collections
tools. In addition, a pilot study was conducted involving 10 network engineers form 3
TCs prior to the field. Lessons from the pilot study helped the researcher to well design
data collection tools and choose the best approach and data collection method.
28
3.13 Ethical Issues and Considerations
Ethical issues are crucial in research since they guide the researcher on what is
permissible and what is not, and thus are mandatory for the researcher to observe.
Morrison (1993) stipulates that ethical principles in the conduct of research include
acquiring research clearance and the informed consent of the participants as well as
maintaining confidentiality. Hence this study adhered to all ethical issues before
interviews and filling in of the questionnaires the researcher fully explained the
objectives of the study to all the respondents. In addition to that, their consent was
sought and their right to confidentiality was assured. Furthermore, the researcher fully
addition, research clearance was obtained from the University of Dar es Salaam.
29
CHAPTER FOUR
4.1 Introduction
This chapter is the core part of this study as it consists of research findings obtained
respondents, the result and analysis of the study done on the assessment of the
with specific objectives which were to examine the extent performance level of
companies.
shown in Table 4.1, where by total of 42 individuals from five different telecom
The results (Table 4.1) show that the number of male respondents was 36 (85.7%) which
is higher than number of female respondents, which was 6 (14.3%). It can be assumed
to females. However, since the study collected information from both male and female,
30
it can be said that the study had views of both male and female and there was no
selection bias.
31
Figure 4.2.1: Gender of Respondents
32
Figure 4.2.3: Working Position of Respondents
33
The table continues to show that a total of 34(81%) respondents were holding bachelor
degree, followed by 6 (14.3%) respondents who were holding master degree and 2
(4.8%) respondents who had diploma level of education. This shows that information in
this study was from intellectual people and therefore they can be reliable. Respondents
were working as project managers presented 5.6% of all respondents, while those who
were working as network engineers presented 94.4% of all respondents. Hence the study
projects for the period of 1-5 years, while 6 (14.3%) respondents had working
experience of 6-10 years, 6 (14.4%) respondents had working experience of more than
This part explains and provides answers for the specific research questions. Moreover,
the part indicates analysis methods used in each of the study objective. During analysis
stage I used mean scores, standard deviation and p-values to explain the results of
specific objectives of the study. It must be noted that the mean is the average value of
response for each item on the Likert scale. This is simply the sum of the values divided
by the number of values. The implication is that the item with the highest mean is the
one which most respondents chose or rated highly and vice versa. The mean disclosure
34
Where Sum of different observation
N = Number of observation
Standard deviation is however a measure of variation. This uses all the observations, and
is defined in terms of the deviation (xi-μ) of the observations from the mean. The
variation is small if the observations are bunched closely about their mean, and large if
they are scattered over considerable distances. The following formula is used to get the
N = Number of observations
35
4.3.1 Performance Level of Telecommunication Projects
The first objective of the study was to examine performance level of telecom projects.
Accordingly, three variables of the project performance dimensions were used to reach
to the conclusion of this objective. These include project implementation time, planned
budget and quality expected of the project. Three questions were prepared using the
presented their perception as regard to the performance level of telecom projects in their
capture perceptions of the respondents concerned thereof. The scale ranged from 1=very
low extent, 2=low extent, 3= moderate extent, 4=high extent, and 5= very high extent.
To analyze the results, I used descriptive analysis in which the mean scores and standard
deviation were calculated and used in the interpretation of the results. The factor with
the highest mean was the one that most respondents thought was very highly considered
and the variable with the smallest mean was the least considered. Meanwhile, the
standard deviation greater than 1.5 is an indication that respondents had greatly
diverging opinions. The results and interpretations have been given in the table 4.2
below:
36
Table 4.2: Performance Level of Telecommunication Projects
Generally, the results show that performance level of the telecommunication projects
After presenting the results of this objective the researcher carried out discussion of
these results. It should be understood that the discussion material are the results of the
findings obtained from the analysis of the study findings, ideas contributed by
respondents during interviews, ideas of researcher and other people who showed interest
in this study and contributed their views in one way or another. Also, findings of other
researchers in this area were included to justify the results of present study.
It was argued that telecommunication companies have tried hard to meet expected
quality in their projects. However, it was important to narrate here what quality means.
Quality refers to the extent to which product meet the standard. It can be also defined as
the degree of excellence (Agbor, 2011). According to Nathan (2011) quality is the extent
is that the projects have ensured availability of Internet and network services in the
country. It was also added that cyber security has been highly ensured which make the
38
wall industry reliable to the consumers. As the results customers have been satisfied by
the services offered by the telecommunication projects. According to Zhen (2010) signal
since customers’ satisfaction base on the speed and accuracy with which their
telecommunication services was not much considered in this present study hence other
establishment of new projects. This means that the newly executive telecommunication
telecommunication industry has been improved day after day. It was argued that all
telecommunication companies have been adopting new hybrid technologies which have
become advantageous to the managers, operation officers and users. The new
technological devices are durable and cost savers. One of the of the respondents put it:
Box 1:
In the past it was common to face telecom service outages but today such
thing is not common except in the deep rural areas where telecom masks
are very few and their operation depend much on the electric from national
grid which is not stable…but in towns, especially in the cities like Dar es
Salaam, operation of telecommunication companies use various source of
energy such as oil and gas in generators, solar and electricity from
national grid. These entire sources ensure maximum availability of electric
power needed for telecommunication operations.
companies in the country. There is substantial empirical evidence that use of quality
material is among the factors that influence the best performance in engineering projects.
At this point, it becomes clearer that engineers must understand the quality of the
the best performance. In line with this the researcher stressed this in order for the
The results continued to show that telecommunication companies have also performed
better in terms of meeting their planned budgets. It was believed that good performance
in financial matters associated with telecommunication projects has been attained as the
results of good accountabilities whereas project operators are accountable for their
40
decisions and actions toward project operations and submit themselves to whatever
scrutiny is appropriate to their duties. Apart from that, financial departments have
managed with the skilled personnel with technological accounting devices (both soft and
Moreover, it was argued that all project implementers (engineers, technicians, financial
officers and managers) in the telecommunication projects have been working together as
a team to make sure projects are done in sequence order and ensure that each project is
done within the budgeted cost. In case of selecting consultants, the companies have been
using proper tendering procedures in order to get qualified and trustworthy consultants
Concerning time performance, it was discovered that the projects were performing
somehow better. According to the established interpretation scale in this study, it was
characterized by moderate performance. This was due to the fact that some projects have
been facing time overrun and failed to be completed within budgeted time. More
directly, time management in engineering projects has become a reason for concern
basing on the fact that it has an impact towards economic development of the country.
41
African countries (Yakubu & Sun, 2009). This has largely been attributed by failure to
adhere to the principles and practices of project time management which has made it so
difficult for the engineers to accomplish the work allocated to them within the planned
period of time, hence leading to delay of the project. Aibinu and Jagboro (2002) cited in
has to a smaller extent been attained. According to them the main causes of unfavorable
redesign, weakness in design and additional work, adverse weather condition, financial
It is also important to understand that time management is the act or process of planning
and exercising conscious control over the amount of time spent on specific activities,
Time management may be aided by a range of skills, tools, and techniques used to
manage time when accomplishing specific tasks, projects, and goals complying with a
due date. From one to attain proper time management, he or she must create conducive
environment to effectively, set priorities, carry out activities around those priorities and
Project time prediction is very important in determining the funds needed for the
accomplishment of the project through forecasting on the different changes that may
create an impact towards the development of the project. The study also emphasized that
for successful project time prediction. There is the need to have enough information
regarding availability, accessibility and usability of all resources and/or materials needed
42
in carrying out the project. The study noted that improper estimate of projects duration
It was noted that one of the greatest reasons for time overrun in the telecommunication
projects performed by visited companies was design change. The study indicates that
design changes were attributed to increased complexity with the degree of resource
scarcity following the alteration of the previous plan. Design changes could also
attribute to the change in the technology where by new equipment could be used in
carrying out the re-planned activities. According to Beach (2008) there is overwhelming
evidence in the literature in support of the poor performances of the project following
changes in early design. These poor performances occur in terms of cost incurred, time
The second specific objective was to identify factors affecting success of telecom
presented to the respondents who were asked to give their opinions. The same five
points Likert scale model of response which range from 1=very low extent to 5=very
high extent was adopted. Descriptive analysis was first employed followed by t-test.
The results of descriptive analysis have been given in the Table 4.3 below, whereby
mean score, standard deviation was used to rank the results according to the descending
43
order of their importance. The variables with highest mean are the ones voted to have
The results in Table 4.3 revealed that respondents of this study suggested almost all the
variables analyzed had high effect in the success of telecommunication projects in the
country. This is because the mean values were ranging from 3.41 to 4.2, which implies
that the variables had high effects in the success of telecommunication projects. Except
for the size of the project and number of the project undertaken per year; the two were
According to the descending order of importance (i.e. decrease effect) the factors have
been presented as follow: project fund (mean=4.05), clearly defined roles and
top management support (mean= 3.81), project team motivation (mean=3.81), training
the human resources (mean= 3.76), availability of adequate resources (mean= 3.71),
consultation (mean= 3.71), employees involvement within the project (mean= 3.62),
monitoring and evaluation (mean= 3.57), competent project team members (mean=
3.57), technical expertise (mean= 3.52), project size (mean= 3.10) and lastly, number of
44
Table 4.3: Factors Affecting Success of Telecommunication Projects-Descriptive
45
The results were subjected to one sample t-test in order to determine which
chosen since it is used when an investigator wants to know whether the mean of the
score/variable from which the sample is drawn is the same as the hypothesized mean (or
average mean of the scores). Hence, mean of each identified individual criterion was
tested against the average mean; the average mean was calculated and found to be 3.67.
But since this is non-parametric test and the results based on the people/respondents
perceptions, therefore, in interpreting the results of t-test let us neglect the observed
negative signs of t-values and that of Confidence Intervals (CIs) and concentrate on the
meaning of p-values. These negative values are the results of the effects of the mean
difference, which was obtained after subtracting the value of average mean from the
actual mean of the given variable. Now, the results of such t-test have been shown in
Table 4.4.
The results of t-test indicate that factors that have significant power to predict success of
telecommunication projects are project size (p<0.001), number of the project undertaken
per year (p<0.001), clearly defined roles and responsibilities (p=0.026) and project funds
explained below:
46
Table 4.4: Factors Affecting Success of Telecommunication Projects T-test
47
Figure 4.4: Factors Affecting Success of Projects
Project Funds
It was noted that funds is the main factor affecting almost all projects, including
telecommunication projects. Certainly, project fund has been seen to be the biggest factor
that affects success of telecom projects among telecom companies. Availability of enough
funds to perform all required activities of the project was mentioned to associate with better
performance of the project, while lack of enough budget disappoints project performance.
48
One of the respondents from TTCL network engineering said that sometime they fail to
It has also been pinpointed by Belassi and Tukelo (2016) that lack of enough budget is
the number one challenge to the Uganda Telecom Company to expand its services in
authors consider shortage of funds to be the most important hindering factors in African
projects and other third world countries. Therefore, due to that the companies, especially
telecom companies, must make sure that enough budget is allocated to the important
Box 3:
…if the purchasing budget is not enough to buy all required material then
the project has to wait and that make the activities to take more time than
expected.
The second factor affecting performance of telecom project was mentioned to be clearly
defined roles and responsibilities among project executors. The study argued that in
49
Accurate Schedule and Plans
According to the descending order of priority, accurate schedule and plans were
mentioned to be the third factor with high effect in the performance of telecom projects.
It was noted that project time prediction is very important in determining the funds
needed for the accomplishment of the project through forecasting on the different
changes that may create an impact towards development of the project. The study also
emphasized that for successful project time prediction; there is the need to having
and/or materials needed in carrying out the project. Further, it was argued that improper
which is one of the tools/techniques used by management in all productive projects for
productivity measurement, and obtaining information about the time spent on productive
and non-productive activities by workers. In trying to know what could be the cause of
delay in telecom project; the researcher got the chance to chat with one of project
Box 3:
50
Project Management Techniques
However, the researcher also narrated that successful projects time evaluation is
out the project through the use of technical experts with experience on what activities
can easily affect cost performance of telecom projects. However, weak management of
the project can be observed if project is at the hands of managers with low management
skills this is because a misunderstanding will exist between project workers. On other
hand, lazy manager is not able to keep detailed and accurate records of expenses, hence
stimulate misuse of the funds. Jackson (2012) proclaimed that many uncertainties in
engineering projects, include financial uncertainty, stems from the complexity of the
The study shows that top management support is among the factors that highly affect the
success of project among telecom companies. It can be said that top managers provided
strong support to their team so as to implement those projects at the time required. It
revealed that in the visited telecom companies there was the good relationship between
top management and other staff from middle and lower class, and the hierarchy of power
is clearly defined. The top management can provide fund and other materials so as to
implement their projects at the time required by setting objectives for each activities to
51
However, it was discussed that weak management of any project can results to the over
budgeting, time overrun, abandonment or collapse of the project, the phenomena which
signify poor performance. In an interview with respondents it was noted that if a project
is at the hands of managers with low management skills as regard engineering work,
misunderstanding will exist between project workers. As a result of this, some part of
construction funds as well as time will be lost in solving disputes. On the other hand, a
lazy manager is not able to keep detailed and accurate records of expenses, hence
stimulate misuse of the funds. Jackson (2012) proclaimed that many uncertainties in
engineering projects, including financial uncertainty, stems from the complexity of the
members and resolve the situation. One of the engineering consultants, who introduced
Box 3:
The researcher of this study was in support of the Eng. Mwelele’s views and
supplemented them by stating that good managerial skills to the project managers;
52
arise. These skills keep their resumes up- to- date so they can respond quickly respond to
constraints as they arise in the course of the project before they will bring difficulties in
the project.
Team member or staff motivation refers to both internal and external factors that
stimulate the energy and desire in people to become more commitment to their jobs so as
to attain a set goal (Iyer &and Jha, 2015). Internal factors are those within the
development among others while external factors political stability within the area, costs
driving force that causes a change from desire to will in life (Chang, 2012). In short, it
can be summarized that motivation is the way of apprising employees to work towards
In this study it was highly accepted that team motivation has high effect in the
was discovered that there were motivations for the team members within the project that
encouraged and motivated them to perform their duties effectively. The companies had
introduced some incentives for the technological staff to trigger their zeal for working
53
There is high relationship between better performance and availability and accessibility
of required resources. In this study it was accepted that availability of materials for
telecom projects has been getting easy due to the increase of utilization of telecom
services. Although most of the required material and/or equipment are imported but
there are a large number of producers of these materials/equipment required for telecom
materials/equipment production has even led to the decrease of purchasing cost. It was
part in improving the cost performance through facilitating the accomplishment of the
activities within the stipulated time depending on the level of “know-how” to use the
available equipment.
Also, most of telecom companies had enough financial and information resources to
implement their specific goals and objectives. In the study conducted by Cheng, et al
(2012) concerns construction projects in the republic of South Africa it was commented
However, to have the best engineering projects in the country, there is a need of proper
proper use of the modern equipment. It was also mentioned that availability of human
resources (i.e. experts in telecom field) is not so pressing in the country due to the fact
that there are many university leavers who can perform many telecommunication chores.
54
On top of that, it was narrated that nowadays university and colleges in this country has
been able to produce skillful people in the engineering and technological arena.
It was accepted that most of the locally available technicians and engineers in electrical
and telecommunication industry have enough skills to perform their jobs well. They also
tend to utilize their skills to the maximum in order to win market competition. One of
the respondents said that “some of engineering projects in this country fail not because
there is no skilled people to perform them; rather, it is because of lack of financial and
material resources.” It was also added that managers and leaders in engineering projects
have skills relating to the engineering works but they lack management skills which is
also virtual for the project to perform better. The overwhelming evidence available in
supporting the idea that management skill is very important in performance of any
project is the ability to organize team in proper manner so as to implement the designed
project successfully.
On the other side, inadequate project management skills and miscalculations are the
bigger contributors of construction delays. This has been also reported by various
research reports from different scholars and researchers who conducted their studies in
engineering related projects. Oluwoye (2003) reported that poor supervision is a major
problem facing the Ghana water and electricity supply projects. Enshassi et al (2009)
added that inadequate supervision is the source of endemic project delay in Ghana and
Nigeria, and their economic and social impact is often discussed. Nonetheless, some
55
studies (Adrian, 2002; Howell, 1981, among others) indicate that workers on a
construction project are unproductive for 50 percent of their time on site and this is due
to the poor management’s control. For that reason, it can be understood that improving
management skills and practices in engineering industry can therefore reduce poor
performance significantly, which in turn leads to the economic and social growth of the
country.
Employee involvement or engagement was also voted to have high effect in the
project can be brought by clearly defined responsibilities to each staff that might lead to
clear implementation of the project. In this study it was noted that there was moderate
participation of technical staffs within the telecom projects due to the moderate
relationship that existed among staff and managements. Engaged employees are those
who give full discretionary effort at work, and are highly vigorous and dedicated to their
job, while disengaged employees are those who are motivationally disconnected from
work, who do not have the energy to work hard and who are not enthusiastic at work
(Towers, 2009). Many researchers have shown the positive effect of employee
al (2008), there are at least four reasons why engaged employees perform better than
health. Third, engaged employees create their own job resources and personal resources.
community but has been heavily promoted by consulting companies (Knight, 2011). It
can be defined as the harnessing of organizational members selves to their work roles
where people express themselves physically, cognitively, and emotionally during role
performances. In order to be engaged, an individual has to think, feel and act on their
job. In other words, this mental state constitutes a driving force which requires physical,
cognitive and emotional resources. The concept has also been defined as an individual’s
involvement, satisfaction and enthusiasm for work (Harter, et al., 2012). Knight (2011)
added that top management must be able to analyze the integration of concept of
aligned with job satisfaction, is all about employees’ connection and commitment to
need to win over the minds (rational commitment) and the hearts (emotional
commitment) of employee in ways that lead to extraordinary effort. When employees are
involved in making decision on some issues concerning their organization, they feel
proud to be part of that particular organization and once they are proud they will be in a
During discussion the study argued that through proper designing of project activities
while taking into account of the unknown disparities, the project management can
57
reorganize and figure out the possible impacts of disparities in the project; and at the end
employee engagement which usually help in solving management problems that can cost
the project. The researcher suggested that for the proper close monitoring of the project
performance there is the need of fully involvement of all key players from the beginning
It was discussed that insufficient detailed evaluation is one of the greater roots for poor
performance in telecom project and even other non-telecom projects. Detailed evaluation
is termed as process that critically examines a project that involved collection and
analysis of information about a project activities, characteristics, and outcomes with the
main aim of making judgments about the project in order to improve its effectiveness.
Olawale and Van (2011) attested that detailed evaluation is dependant of the different
evaluation and impact evaluation. Chang (2002) and Mwandosya (2008) noted that
ultimately help in the realization of project goals more effectively. In the context of cost
overrun, it was argued that insufficient detailed evaluation of the project prior to
58
Competent Project Team Members
Involvement of competent (enough skilled) staff in telecom project is one of the aspects
of good performance. It was argued that presence of enough skilled and knowledgeable
staff in telecom companies ensures good performances of the telecom projects in the
country. This is because the project teams are aware of what is supposed to be done and
the right time to do the task. They can also understand quick ways of solving the
emergency telecommunication problems. The study continued that it is very difficult for
the telecom company without experienced technical staff to perform well in terms of
technological advancement. This is the reason why the respondents of this study asserted
that in order for the telecom company to work effectively and perform their duties well,
there must be enough number of personals with skills and knowledge on engineering
The study argued that no organization or institution which can perform successful
without having skilled manpower. The presence of enough skilled technical staff within
the technological company, such as telecom companies, can also give the management
confidence to believe that the company has ability to continue providing service to the
client since all core duties can be performed well and in time. Therefore, telecom
companies must be filled with enough technological skilled staff. Additionally, it should
be understood that the presence of enough skilled staff in telecom companies does not
59
only mean the person with high level of education and qualification but also the
professional approach to the technological activities. The work force must be adequately
effectively.
Faniran (2009) has explained the problem of lacking proper knowledge and skills in the
technological companies by saying that the shortage of skills and capacity has been
identified as the single greatest impediment to the success and development of modern
technology in many sub-Sahara countries. This clearly means that in order for successful
technological industry in the country, there is the need of having enough personnel with
skills and knowledge on procurement activities. At this point, it becomes clearer that
investigation of all job applicants in order to ensure the companies are equipped with
technologically skilled people. The companies should also provide regular refreshment
trainings to those who are ready employed. The refreshment trainings will enable
employees to learn new ways of performing their duties which are used in other
countries.
Project Size
Another factor that can affect performance of a telecom company is the size of the
project. It was said that when the project is bigger than the ability of the work force, the
project will experience poor performance. Feng et al (2010) put it that project size
60
management has become a major challenge face some engineering projects. These may
be due to increasing design complexity, more rigorous federal and state regulations, as
Lastly, about sixteen factors were analyzed in this study to affect performance of
telecom companies. But there must be some other factors affecting performance of
telecom projects and therefore, researcher suggested that another study to be conducted
while analyzing other factors apart from these which can also have an impact in telecom
projects.
This is the third specific objectives of the study and was looking for strategic factors to
Different variables were prepared and presented to the respondents in order to give their
opinions on which variables should be considered as the best ways of attaining good
form of short sentences with response mode of five Likert scale points that range from
1=strongly disagree to 5=strongly agree. Data collected were subjected to the descriptive
analysis in which mean and STD were considered in drawing conclusion. In the
interpretation of the results after conducting descriptive analysis of the findings the
mean scores of 1.00-2.32 have been taken to present variables which were
score of 2.33-3.65 have been taken to represent variables that were “fairly important”
61
and the mean scores of 3.66-5.00 have been taken to present variables that were “very
important” in the success of telecom projects. The results have been presented in Table
4.5.
According to the opinions of the respondents it can be said that for the telecom project to
be successful there is the need for the telecom companies to make regular meetings and
share information within and across the companies (mean 4.14), conduct regular project
monitoring (mean 4.05), should also use proper technological tools to monitor cost and
scheduling the progress of the project (mean 3.95), together with consulting project
management experts before beginning the project (mean 3.93). Also, it was accepted that
adhering to the policy and legislation pertain to technology may influence success and/or
62
Source: Field Data (2017)
It was argued that having regular meetings and manner of information sharing helps in
sharing act as the means of ensuring all activities are in line with the planned time and
budget. In line with the concept of regular meetings and information sharing, it was
agreed that early delays can be recovered through improved communication, addition or
63
reduction on the amount of resources depending on the need, resolving of problematic
authors say that through proper communication within different department in the
This is because proper communication between key players called for share of
knowledge within the project and this may, in turn, lead to the proper utilization of
available resources.
For the successful telecom project there is the need of establishing effective project
monitoring and valuation using recognized and accepted methodologies. This has been
argued that managers should be capable of providing effective planning and monitoring
of all activities in and outside the project. Gunaydın and Dogan (2004) also noted that
increased project cost performance has been attained through the use of a project
planning, organizing, leading and controlling the use of project resources. It was further
argued that through proper monitoring; it is possible for project managers to identify the
performance of the projects so as to attain the best results regarding utilization of the
allocated resources. A number of researchers such as Hwang and Lim (2012) have
indicated that there is a close relationship between cost performances of the projects and
project monitoring activities. The researcher of this present study is in support of this
close relationship. This is because monitoring help to ensure that objective activities are
64
met within an estimated budget and time, identifying successes, identifying problems
and weakness so they can be rectified before they cause harm to the entire project.
For the proper monitoring of project there is the need of preparing a checklist. It was
accepted with respondents that in determining cost performance of complex project such
effectively considered in almost all visited companies in this study. One of respondents
said:
Box 4:
completeness in carrying out a task with an example of “to do list.” Therefore, improper
checklist preparation can lead to the misuse of the funds. This being the fact the study
concluded that proper preparation of check can assist in monitoring project activities for
the better performance; since it bringing out the best picture of how the project should be
managed.
projects is a widely used financial and economic appraisal tool for attaining value for
65
many. It is particularly useful when making choice in implementation of project
activities and when the project is complex and involved a stream cost overrun. Sound
and developing a baseline plan representing the budgeted cost of work scheduled. The
baseline plan allowed the preparation of a cumulative spending curve and daily, weekly
as well as monthly cost histogram for both project design and implementation activities.
The researcher was in support of the above and suggested that improvement of manner
The use of proper technological tools to monitor cost and scheduling the progress of the
project was also voted to be important factor for successful telecom project
implementation. It was said that in carrying out telecom projects implementers usually
look on the ways of increase project simplicity by doing several activities such as
adopting use of modern equipment. The modern equipment work faster and therefore
help to speedup project implementation processes while reducing inputs such as number
of labourers who need to be paid for their labour. According to Abraham (2013) the new
that, this has also contributed to the reduction on the rate of accidents in the engineering
sites. It should be noted that accidents reduce project funds since a victim has to be
compensated with the money which was not initially estimated in the budget. There is no
66
doubt that modern technological equipment (i.e. computerized machines) simplifies
67
CHAPTER FIVE
5.1 Introduction
This chapter provides summary of the findings, conclusions and recommendations to the
main findings presented in Chapter Four by relating them to the specific objectives of
the study while reflecting on the methods used to obtain and analyze data. The chapter
5.2 Summary
The study posed three research questions to be answered and the questions were: what is
the performance level of telecom projects? What are the factors affecting
questions were answered and here are the summary of the findings relating to them.
Studying performance level of telecom project was the first aim of this study. Various
variables were analyzed in order to understand thereof. Descriptive statistic was the only
analysis performed on the data pertains to this objective. The study found that visited
telecom companies had performed better on meeting expected qualities of their telecom
projects, control cost overrun and time overrun. Generally, the results show that
performance level of the telecom projects among selected telecom companies was high.
68
5.2.2 Factors Affecting Success of Telecommunication Projects
The second specific objective was to analyze factors affecting success of telecom
projects in which the researcher conducted descriptive analysis and t-test to reach to the
conclusion of this objective. According to the descending order of importance, the study
found that factors affecting performance/success of telecom projects were the following:
project fund, clearly defined roles and responsibilities, accurate schedule and plans,
support, project team motivation, training the human resources, availability of adequate
competent project team members, technical expertise, project size and number of
projects undertaken per year. The results of t-test have shown that project size, number
of the project undertaken per year, clearly defined roles and responsibilities and project
projects.
The last specific objective called for the strategies for successful implementation of
telecom project. It was noted that for successful implementation of telecom projects
there is the need for the telecom companies to make regular meetings and share
information within and across the companies, conduct regular project monitoring, use
proper technological tools to monitor cost and scheduling the progress of the project,
69
consulting project management experts before beginning the project as well as adhering
5.3 Recommendation
Based on the findings of the study the following recommendations have been identified
for the purpose of increasing performance of telecom projects in the country. These are
as follows:
The study recommends for the more proper planning of activities in telecom
projects through the use of proper managerial and technical skills. This will help
simplicity and recovery early delays among others. Hence better cost, time and
making process. This will help in good project screening, risk identification and
70
measures in order to meet the required performances in all aspect of the telecom
projects.
Actually the study focused on the factors affecting performance of telecom projects in
Tanzania while focusing on the projects carried out in Dar es Salaam. Therefore, there is
the need for other researchers to conduct other related studies but focusing on telecom
projects carried out in other regions in order to get the full picture of factors affecting
other studied on telecom project performance that include other variables such as
customers’ satisfaction with the telecom services in the country, and return of the
REFFERENCES
71
Azhar, O., Gaddis, P. (2008). The project manager. Harvard Business Review , Vol 37(3),
pp 89.
Bakker, A., and Schaufeli E (2008) Towards a model of work engagement. Career
Chang S. (2012). Reasons for cost schedule increases for engineering design projects.
Cheng, R., Meredith, J., and Mantel, S. (2010). Project Management A Managerial
72
Enshassi, A., Mohamed, S. and Abushaban, S. (2009). Factors affecting the performance
Feng, G., Slevin, D. and Pinto, J. (2010). The project implementation profile: New tool
Fraenkel, J. R., and Wallen, W. E. (2000). How to design and evaluate educational
research.
Gunaydın and Dogan. (2004). Project success index for capital facility construction
21-39.
Psychology pp 268-279.
Hwang, B., and Lim, E. (2012). Critical Success Factors for Key Project Players and
73
Iyer, K,. and Jha, K. (2015). Factors affecting cost performance: evidence from Indian
Jackson, S. (2012). Project cost overruns and risk management. The University of
Reading.
Sons
Management, 38(2), 30 – 40
Kressler, H (2003) Motivate and Reward: Performance Appraisal and Incentive System
Kombo, D. K., and Tromp, D. L. (2006). Proposal and thesis writing: An introduction.
Kothari, C.R (2004). Research Methodology; Methods and Techniques, 2nd Ed, New
74
Kaming, P. Olomolaiye,P., Holt, G and Harris, F. (1997). Factors influencing
Masoud, A. (2014) Earned value Management and Telecom projects success page
Omoregie, A., and Radford, D. (2006). Infrastructure delays and cost escalation:
3rd-7thApril 2006
Oko J. Aliu A. and Koleola T. (2010). Significant Factors Causing Cost Overruns
Olawale, O and Van, A. (2011). Constraints to credit access by new SMEs in South
75
Management Institute, Inc., 2008),6.
Russell W. Darnall, The World’s Greatest Project (Newtown Square, PA: Project
Sekaran Uma (2003). Research Methods for Business, 4th edition. John Wiley and Sons,
2003.
Shenhar, A. J., Levy, O. and Dvir, D. (1997). Mapping the dimensions of project success.
Tsun C. (2008). A survey study of critical success factors in agile software projects
Wateridge, J. (1998). How can IS/IT projects be measured for success? International
Webster, P., (1995). The annual cycle and the predictability of the tropical coupled
76
Yakubu, A and Sun, M. (2009). Cost Time Control Construction Projects: A Survey of
Zhen, Z. (2010). Application of innovative Critical Chain Method for project planning
5-13.
Websites
http://www.mst.go.tz/index.php/arrrchieve/78-news/130-hotuba-ya-bajeti-2015-16
http://www.gsmamobileeconomy.com/GSMA_Global_Mobile_Economy_Report_2015.
https://www2.deloitte.com/content/dam/Deloitte/fpc/Documents/secteurs/technologies-
medias-et-telecommunications/deloitte_the-future-of-telecoms-in
africa_2014.pdf
https://www.tcra.go.tz/index.php/quarterly-telecommunications-statistics#2014-
https://www.tcra.go.tz/index.php/quarterly-telecommunications-statistics#2014-
http://www.slideshare.net/djadja/imt-lecture-managing-telecommunication-project-
77
http://ppi.worldbank.org/snapshots/country/tanzania
APPENDICES
78
Appendix I: QUESTIONNAIRES
(Questionnaire)
The aim of this questionnaire is to collect the information about the factors
affecting telecom projects performance in Tanzania. It requires to be filled with facts as
relevant as possible. All data obtained through this questionnaire will be used only for
academic research and will be strictly confidential. After the data being analyzed and
presented the interested participants for this study will be given the feedback.
SUBMITTED BY ………………………………….
SUPERVISED BY ………………………………………
2. Company name……………….
Masters ( ) PhD ( )
Project manager ( )
Network engineer ( )
Finance manager ( )
Procurement manager ( )
6. How many years have you been involved in network projects implementations?
80
16 –20 years ( ) above 21 years ( )
8. To what extent are the network projects implemented in your organization meet time
schedule
very high extent ( ) high extent () moderate () low extent () very low extent ()
very high extent ( ) high extent () moderate () low extent () very low extent ()
10. To what extent do the projects implemented meet the quality expected?
very high extent ( ) high extent () moderate () low extent () very low extent ()
9. Below are factors affecting telecom projects performance. From your experience
express your own opinions by putting (tick) on each of the following factors to show
the extent at which they have affected the performance of telecom projects in your
organization.
81
FACTORS 5=very 4=high 3=moderate 2=low 1=very
high extent extent low
extent extent
Availability of adequate
resources
Project size
Technical expertise
Client/vendors consultation
Project fund
82
11. Based on your experience in telecom projects management, what are the other
factors affecting the performance of telecom projects in your organization?
i. ………………………………………………………………………..
ii. …………………………………………………………………………
iii. ……………………………………………………………………………..
11. Below are some of the strategies that can be used by telecom operators to ensure
successful project implementation. Please provide your own opinions on these
strategies by putting a tick on each strategy.
budgets
Applying software
scheduling the
progress of the
project
Regular project
83
monitoring
Consulting project
management
experts before
beginning the
project
Have regular
update meetings
and share
information
12. Please in your own opinions based on your experience in projects management and
the experience gained from being involved in projects, what else can be adopted in
telecommunication industries in order to promote successfully implementations of
telecommunication projects?
i. ……………………………………………………………………………………..
ii. ……………………………………………………………………………………..
iii. ……………………………………………………………………………………
iv. ……………………………………………………………………………………
v. ……………………………………………………………………………………
84
85