WORK SCHEDULE FOR EXCAVATION ANG TRENCHING

MAHANAGDONG GEOTHERMAL POWERPLANT B

ABOVE GROUND FIRE WATER LOOP

EXCAVATION AND TRENCHING


C/S DESCRIPTION NO. OF DAYS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
1 EXCAVATION WORKS
1.1 Clearing and Grubbing
1.2 Setting Out
1.3 Excavation
1.4 Backfilling and disposal of surplus earth
2 REBAR WORKS
2.1 Fabrication of Reinforcement for Trench
2.2 Fabrication of Reinforcement for Trench Cover
2.3 Rebar Installation and Alignment
3 FORMS AND SHUTTERING
3.1 Formworks alignment and bracing
3.2 Formworks for trench cover
3.2 Stripping of forms
4 CONCRETING
4.1 Casting of lean concrete
4.2 Casting of concrete on bottom slab
4.3 Casting of concrete on perimeter walls
4.4 Casting of concrete on trench covers
4.5 Concrete repairs and finishes
4.6 Concrete curing
5 PIPE INSTALLATION
5.1 Pipe support fabrication
5.2 Alignment and Installation
6 INSPECTION
6.1 Punchlists correction
6.2 Placement of trench cover
`
Prepared by:

Engr. Ramces M. Soliman


Project Engineer
ASISI SYSTEMS CORP.