Rohan abuilders (India) Pvt.

Ltd
Project :-Sussen Asia Pvt.Ltd.Shirtwal
Job Hazard Analysis Sheet No. 2…... of ……1..

PROJECT / TASK: Shuttring And De-Shuttring CONTRACTOR: RBIPL JOB No.:

nd
SUPERVISOR: Mr.Sunil Shinde LOCATION: 2 Expansion Main Plant. DATE:

JOB STEP HAZARDS Control Measure ACTION


Break the job into steps. List the hazard or type of harm List the necessary control measures to be Person who will
Listing work which may be hazardous. identified with each step followed to eliminate the identified hazards ensure this
happens

Handling of wooden planks and 1. Injury due to sharp 1. Avoid handling the material with
supports edges/nails in old sharp edge side.
materials, Fall of 2. Remove nails before reuse.
material, Tripping 3. Secure the pieces properly in a
hazard stack. Mr.Murugan
4. Maintain good Housekeeping.
5. Use Proper PPE’S
Cutting wood/ply to required 1. Defective cutting 1. Check for proper operation all the
size. machine/tools tools & cutting machine before
causing injury, start of the job.
2. Guard moving parts of the
machines.
3. Wear safety goggles/shoes.

Preparation of shuttering parts 1. Flying nails while 1. Wear safety goggles/shoes.


hammering. 2. Do not allow crowding near the
work place.
3. Drive the nail with full
concentration and maintain
hammer centre on the nail.
shuttering 1. Fall of shuttering, Fall 1. Provide proper access to the
of workers ,Cut work place.
Injury, Eye Injury 2. Use proper PPE’S (Hand Gloves,
Safety Shoes, Hard Hat, Goggle).
3. Proper Supervision
De-shuttering 1. Falling Hazards, 1. Observe all precautions relevant
Hand Injury. to the used lifting device.
2. Keep other workers away from
the de-shuttering area.
3. Do not throw shuttering material
rather lower it slowly
4. Inspect for protruding nails.
5. After 2 mtr height required full
2. Injury by nails. body safety harness or life line.
1. Removing nails wherever holding
the shuttering.
2. Collect and dispose used nails at
the ground level and maintain
good housekeeping.
Job Hazard Analysis Attendees: Mr. Dhake , Mr.MURUGAN , Mr.Vinod Narkhede
Name Signature Date
Written by: Safety Officer RBIPL Mr. Dhake
Site Engineer: Mr.MURUGAN
Reviewed by: Project Manager Mr.Vinod Narkhede
RBIPL
SAPL Officer / Engineer: